Resource scheduling involves either time-limited or resource-limited scheduling. Time-limited scheduling aims to make resources available as needed to meet deadlines, while resource-limited scheduling adjusts timelines based on fixed resource levels. Parallel scheduling starts eligible activities simultaneously based on available resources. For a project with limited staff, parallel scheduling showed it would take 32 weeks to complete within a 4-person resource limit, compared to the original 5-person, 32-week plan.