Resource Scheduling
• Time Limited
Scheduling
• Resource Limited
Scheduling
The Need for Resource Scheduling:
• The previous Project Scheduling methods that
we have covered have not considered the
constraint of resources.

• Generally, there are two types of projects…..
1. Projects that MUST meet a certain deadline
and have ‘unlimited’ resources in order to
meet this. This would use Time Limited
Scheduling.
2. Projects that have limited availability of the
required resources, however the project
deadline is more flexible. The would use
Resource Limited Scheduling.
Note: if a project has both limited time and
resources, the project manager must initially
assume that one or the other is flexible. OR,
renegotiations will need to take place.
Time Limited Scheduling
Objectives:
• To determine exactly what resources the
project requires, and make these resources
available for when they are needed.
• To use each resource as efficiently as possible
– Resource Smoothing: this defines the act of
maximising resources efficiency. Despite having
‘umlimited’ resorurces, it is still necessary to try to
keep costs down as much as possible.
The Resources Loading Chart:
Consider the following example which is adapted from Field & Keller ‘Project
Management’ 1998:

Activity

Description

Staff

Duration

Earliest Start
Time

Float

Latest Finish
Time

A

Prepare offices

2

12

0

0

12

B

Procure equipment

2

8

0

4

12

C

Design tests

1

5

0

17

22

D

Install equiptment

4

10

12

0

22

E

Test system

3

10

22

0

32

F

Train users

1

5

12

15

32
• We will build the previous information into a
‘Resource Loading Chart’
Observations:
• From the previous slide’s graph we can
immediately tell how many staff are needed at
any one time.

• For example – in week 10, we can identify that
only 2 staff members are required. Whereas in
week 14 there are 5 staff members required.
• Note: The bottom row of the graph could also
be described as the ‘critical path’. Each of
these items as Float=0. This row can be
described as the Base Line.

• The method of creating this chart, by
positioning one activity at a time, is called
Serial Scheduling.
Resource Levelling:
• As identified in the previous slides, our chart
contains ‘extreme peaks’. For example, weeks
1-5.
• Resource levelling helps to avoid this.
• As we have several activities which contain
float, we can try to move these activities to
‘level’ out the staff distribution:
• Obviously the below still isn’t ideal as we still
have a ‘peak’ during week 13. However we
have levelled s much as possible, and in turn
we have reduced costs.
Resource Limited Scheduling
Objectives:
• To adjust the project’s time to adapt to fixed
level of resources.
• In the previous example, we realised it would
take 5 staff to create the office in 32 weeks.
• Now, let’s consider how long it would take if
the staff level were fixed at 4.
Parallel Scheduling:
Definition: Starting at the beginning of a project
and considering all the eligible activities, in a
parallel manner.
An eligible activity would be one which could be
started if the resources were available.
Let’s re-consider the example….
Activity

Dependency

Staff

Duration Latest Start Time Float Latest Finish Time

A

N/A

2

12

0

0

12

B

N/A

2

8

4

4

12

C

N/A

1

5

17

17

22

D

A and B

4

10

12

0

22

E

C and D

3

10

22

0

32

F

A and B

1

5

27

15

32
Have a go at plotting the chart with
the strict resource limit of 4:
The Result…..
Further Reading:
– Time Limited Scheduling

• Field & Keller Chapter 3.4, ‘Project
Management’
• Moder et al (1983)
– Resource Limited Scheduling

• Kerzner Chapter 12
•

More Related Content

PDF
Fire Fighting System
PPTX
Summer Internship project presentation
PPTX
Bata Case Study
PPTX
Cryptographic algorithms
PPTX
Budget and cost control slide share
PDF
Project scheduling and resource levelling_Construction Management
PDF
Indian logistics
PPTX
UNIT 1.pptx
Fire Fighting System
Summer Internship project presentation
Bata Case Study
Cryptographic algorithms
Budget and cost control slide share
Project scheduling and resource levelling_Construction Management
Indian logistics
UNIT 1.pptx

What's hot (20)

PPT
Project management tools and techniques
PPTX
Project cost control
PPTX
03 Construction Project Planning and Scheduling
PPT
crashing of project
PPTX
PROJECT SCHEDULE
PPT
Project planning and Scheduling
PPTX
Pert & cpm project management
PPTX
Construction Project Management
PPTX
Project management techniques
PPT
Earned Value Analysis
PPTX
project management concepts
ODP
Critical path method
PPTX
6.5 Resource Leveling and Resource Smoothing
PPTX
Earned value analysis (1)
PPT
Construction scheduling & Cost control
PDF
time cost trade off
PDF
Lecture 1. general introduction to project management
PDF
Construction Planing & Schedule
PPTX
Project Time Management
PPTX
Pert and CPM
Project management tools and techniques
Project cost control
03 Construction Project Planning and Scheduling
crashing of project
PROJECT SCHEDULE
Project planning and Scheduling
Pert & cpm project management
Construction Project Management
Project management techniques
Earned Value Analysis
project management concepts
Critical path method
6.5 Resource Leveling and Resource Smoothing
Earned value analysis (1)
Construction scheduling & Cost control
time cost trade off
Lecture 1. general introduction to project management
Construction Planing & Schedule
Project Time Management
Pert and CPM
Ad

Viewers also liked (6)

PPTX
Service sectors ppt
PPT
Waiting Line Management
PDF
Machine Learning for Dummies
PPT
Planning, scheduling and resource allocation
PPT
Resource allocation
PPTX
Chapter 3: Front Office Operations
Service sectors ppt
Waiting Line Management
Machine Learning for Dummies
Planning, scheduling and resource allocation
Resource allocation
Chapter 3: Front Office Operations
Ad

Similar to Resource Scheduling (20)

PPTX
Resource Scheduling
PPTX
Allocating resources
PPTX
Ch09 (1).pptx
PPT
Chap008.ppt
PDF
Project-Time-Line.pdf
PDF
PPT
project_management and its adoption_10.ppt
PPT
Module :-5 project scheduling and resource levelling
PPTX
Resource planning and resource allocation
PPT
PM Session 6
PDF
SPM chapter 06 - Activity Planning by Bob Hughes
PDF
789669510-SPM-Unit-2-3-Activity-Planning.pdf
PPT
Resource Planning
PPTX
PPT
4.1 Scheduling.ppt
PDF
Project Management Notes 3
PDF
Scheduling resources and costs is a crucial aspect of project management that...
PPTX
Lecture-8-Scheduling-Resources-and-Cost.pptx
PDF
Project management Financing software.pdf
PPT
Scheduling-Resources-and-Costs.ppt
Resource Scheduling
Allocating resources
Ch09 (1).pptx
Chap008.ppt
Project-Time-Line.pdf
project_management and its adoption_10.ppt
Module :-5 project scheduling and resource levelling
Resource planning and resource allocation
PM Session 6
SPM chapter 06 - Activity Planning by Bob Hughes
789669510-SPM-Unit-2-3-Activity-Planning.pdf
Resource Planning
4.1 Scheduling.ppt
Project Management Notes 3
Scheduling resources and costs is a crucial aspect of project management that...
Lecture-8-Scheduling-Resources-and-Cost.pptx
Project management Financing software.pdf
Scheduling-Resources-and-Costs.ppt

More from Nicola2903 (12)

PPTX
Network diagrams
PPTX
Estimating
PPTX
Critical path method
PPTX
Work breakdown Structure
PPTX
The gantt Chart
PPTX
Work breakdown structure
PPTX
Network Diagrams
PPTX
Estimating
PPTX
Estimating in Project Scheduling
PPTX
The Critical Path Method
PPTX
The Critical Path Method
PPTX
The Gantt Chart
Network diagrams
Estimating
Critical path method
Work breakdown Structure
The gantt Chart
Work breakdown structure
Network Diagrams
Estimating
Estimating in Project Scheduling
The Critical Path Method
The Critical Path Method
The Gantt Chart

Recently uploaded (20)

PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
Electronic commerce courselecture one. Pdf
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
PDF
Network Security Unit 5.pdf for BCA BBA.
PPTX
Big Data Technologies - Introduction.pptx
PDF
Unlocking AI with Model Context Protocol (MCP)
PDF
MIND Revenue Release Quarter 2 2025 Press Release
PPTX
Spectroscopy.pptx food analysis technology
DOCX
The AUB Centre for AI in Media Proposal.docx
PPTX
Cloud computing and distributed systems.
PPTX
sap open course for s4hana steps from ECC to s4
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PDF
Reach Out and Touch Someone: Haptics and Empathic Computing
PDF
cuic standard and advanced reporting.pdf
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PDF
Encapsulation theory and applications.pdf
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
Agricultural_Statistics_at_a_Glance_2022_0.pdf
Electronic commerce courselecture one. Pdf
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
Network Security Unit 5.pdf for BCA BBA.
Big Data Technologies - Introduction.pptx
Unlocking AI with Model Context Protocol (MCP)
MIND Revenue Release Quarter 2 2025 Press Release
Spectroscopy.pptx food analysis technology
The AUB Centre for AI in Media Proposal.docx
Cloud computing and distributed systems.
sap open course for s4hana steps from ECC to s4
Advanced methodologies resolving dimensionality complications for autism neur...
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
Reach Out and Touch Someone: Haptics and Empathic Computing
cuic standard and advanced reporting.pdf
Diabetes mellitus diagnosis method based random forest with bat algorithm
Encapsulation theory and applications.pdf
Building Integrated photovoltaic BIPV_UPV.pdf

Resource Scheduling

  • 1. Resource Scheduling • Time Limited Scheduling • Resource Limited Scheduling
  • 2. The Need for Resource Scheduling: • The previous Project Scheduling methods that we have covered have not considered the constraint of resources. • Generally, there are two types of projects…..
  • 3. 1. Projects that MUST meet a certain deadline and have ‘unlimited’ resources in order to meet this. This would use Time Limited Scheduling. 2. Projects that have limited availability of the required resources, however the project deadline is more flexible. The would use Resource Limited Scheduling. Note: if a project has both limited time and resources, the project manager must initially assume that one or the other is flexible. OR, renegotiations will need to take place.
  • 5. Objectives: • To determine exactly what resources the project requires, and make these resources available for when they are needed. • To use each resource as efficiently as possible – Resource Smoothing: this defines the act of maximising resources efficiency. Despite having ‘umlimited’ resorurces, it is still necessary to try to keep costs down as much as possible.
  • 6. The Resources Loading Chart: Consider the following example which is adapted from Field & Keller ‘Project Management’ 1998: Activity Description Staff Duration Earliest Start Time Float Latest Finish Time A Prepare offices 2 12 0 0 12 B Procure equipment 2 8 0 4 12 C Design tests 1 5 0 17 22 D Install equiptment 4 10 12 0 22 E Test system 3 10 22 0 32 F Train users 1 5 12 15 32
  • 7. • We will build the previous information into a ‘Resource Loading Chart’
  • 8. Observations: • From the previous slide’s graph we can immediately tell how many staff are needed at any one time. • For example – in week 10, we can identify that only 2 staff members are required. Whereas in week 14 there are 5 staff members required.
  • 9. • Note: The bottom row of the graph could also be described as the ‘critical path’. Each of these items as Float=0. This row can be described as the Base Line. • The method of creating this chart, by positioning one activity at a time, is called Serial Scheduling.
  • 10. Resource Levelling: • As identified in the previous slides, our chart contains ‘extreme peaks’. For example, weeks 1-5. • Resource levelling helps to avoid this. • As we have several activities which contain float, we can try to move these activities to ‘level’ out the staff distribution:
  • 11. • Obviously the below still isn’t ideal as we still have a ‘peak’ during week 13. However we have levelled s much as possible, and in turn we have reduced costs.
  • 13. Objectives: • To adjust the project’s time to adapt to fixed level of resources. • In the previous example, we realised it would take 5 staff to create the office in 32 weeks. • Now, let’s consider how long it would take if the staff level were fixed at 4.
  • 14. Parallel Scheduling: Definition: Starting at the beginning of a project and considering all the eligible activities, in a parallel manner. An eligible activity would be one which could be started if the resources were available. Let’s re-consider the example….
  • 15. Activity Dependency Staff Duration Latest Start Time Float Latest Finish Time A N/A 2 12 0 0 12 B N/A 2 8 4 4 12 C N/A 1 5 17 17 22 D A and B 4 10 12 0 22 E C and D 3 10 22 0 32 F A and B 1 5 27 15 32
  • 16. Have a go at plotting the chart with the strict resource limit of 4:
  • 18. Further Reading: – Time Limited Scheduling • Field & Keller Chapter 3.4, ‘Project Management’ • Moder et al (1983) – Resource Limited Scheduling • Kerzner Chapter 12 •