Project Management Session 6 Scheduling Resources
Session Outcomes Following the session the delegates should have a basic understanding of the typical resource scheduling problems for time as well as resources constrained projects. In addition the delegate should be able to show how free slack can be used to effect resource leveling.
Preamble
The Resource Problem After staff and other resources have been allocated the project manager still need to answer the following questions: Will the  resources be adequate and available  when needed; Will  outside contractors  have to be used; Will unforeseen resource dependencies exist  – will there be a new critical path; How much  flexibility do we  have in using resources; Are original  deadlines realistic.
The Resource Problem Resources and Priorities: Project sequencing and scheduling deals poorly with resource availability and utilization ; Project network times are not a schedule until resources have been assigned: The implicit  assumption is that resources will be available  in the required amounts when needed; Adding new projects requires making realistic judgments of  resource availability  and project durations; Resources may be adequate but  demand can vary  – then resource leveling or smoothing is required; or  Resources  may not be adequate to meet peak resource requirements , the late start date of certain activities will have to be delayed and project duration be increased – this is referred to as resource constrained scheduling.
Types of Project Constraints Technical or Logic Constraints: Constraints related to the networked sequence in which project activities must occur – example, dig trenches, pour cement, then lay bricks for walls… Physical Constraints: Activities that cannot occur in parallel or are affected by contractual or environmental conditions – ship renovation, one person allowed in confined space… Resource Constraints: The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities- example, normally you have 3 people to do three activities in parallel, but because you only have one person you have to schedule them in series – NB!! Resource dependency takes priority but cannot violate technical dependencies.
Constraint Examples
Kinds of Resource Constraints People; Materials; Equipment; Working Capital.
Classification of A Scheduling Problem Classification of Problem: Using a priority matrix will help determine if the project is time or resource constrained; Time Constrained Project: A project that must be completed by an  imposed date ; Time is fixed , resources are flexible: additional resources are required to ensure project meets schedule Resource Constrained Project: A project in which the  level of resources available cannot be exceeded: Resources are fixed , time is flexible: inadequate resources will delay the project.
Resource Allocation Methods Resource allocation is based on the following assumptions: Splitting activities is not allowed —once an activity is start, it is carried to completion; Level of resource used for an activity cannot be changed ; Activities with the  most slack pose the least risk ; Reduction of flexibility does not increase risk ; The  nature of an activity (easy, complex) doesn’t increase risk .
Resource Allocation Methods Time-Constrained Projects: Projects that must be completed by an imposed date;  Require the use of  leveling techniques  that focus on  balancing or smoothing resource demand  by  using positive slack (delaying noncritical activities ) to manage resource utilization over the duration of the project with the following result: Peak resource demands are reduced; Resource demand over the life of the project are reduced; Fluctuation in resource demand is minimized.
Botanical Garden 1 2 3 4 5
Botanical Garden
Botanical Garden 1 2 3 4 5
Botanical Garden Using the slack of irrigation to start 3 days late 1 2 3 4 5
Botanical Garden Using the slack of fence and walls to start 3 days late 1 2 3 4 5
Botanical Garden
Resource Allocation Methods Resource Demand Leveling Techniques for Time-Constrained Projects: Advantages: Peak resource demands are reduced; Resources  demand  over the life of the project are reduced; Fluctuation in resource demand is minimized; Disadvantages: Loss of flexibility  that occurs from reducing slack; Increases  in the criticality  of all activities.
Resource Allocation Methods Resource-Constrained Projects: Projects that involve resources that are limited in quantity or by their availability’ Scheduling of activities requires the use of heuristics (rules-of-thumb) that focus on: Minimum slack; Smallest (least) duration; Lowest activity identification number. The parallel method is used to apply heuristics: An iterative process that starts at the first time period of the project and schedules period-by-period any activities scheduled to start using the three priority rules.
Resource Allocation Methods
The Impacts of Resource-Constrained Scheduling Reduces delay but reduces flexibility; Increases criticality of events; Increases scheduling complexity; May make traditional critical path no longer meaningful; Can break sequence of events; May cause parallel activities to become sequential and critical activities with slack to become noncritical.b
CPM includes a way of relating the project schedule to the level of physical resources allocated to the project; This allows the project manager to trade time for cost, or vice versa; In CPM, two activity times and two costs are specified, if appropriate for each activity. Resource Management
The first time/cost combination is called  normal,  and the second set is referred to as  crash ; Normal assumes time and resources in normal conditions – although there is a “technical” way to calculate it;  Crash result from an attempt to expedite the activity by the application of additional resources. Resource Management
Careful planning is critical when attempting to expedite (crash) a project; Expediting tends to create problems, and the solution to one problem often creates several more problems that require solutions. Resource Management
Another way to expedite a project is known as  “fast-tracking”; Mostly construction  but term also used on other projects; It refers to  overlapping the design and build phases  of a project; Because design is usually completed before construction starts, overlapping the two activities will result in shortening the project duration; Could however also lead to increased number of  change orders,  and therefore increased cost and loss of time – however generally feasible. Resource Management
 

More Related Content

PPTX
Evolution of project management
PPT
Scheduling-Resources-and-Costs.ppt
PPTX
project management
PPT
Challenges Of Project Management
PDF
Project Management:Life Cycle & Phases.
PDF
Zarządzanie projektami metodą łańcucha krytycznego
PPT
Lecture5---Gantt Chart
PPT
Project life cycle
Evolution of project management
Scheduling-Resources-and-Costs.ppt
project management
Challenges Of Project Management
Project Management:Life Cycle & Phases.
Zarządzanie projektami metodą łańcucha krytycznego
Lecture5---Gantt Chart
Project life cycle

What's hot (20)

PDF
01 pmp introduct to project management exam
PDF
Chapter 05 Software effort estimation PartII_final
PDF
Project Deliverables Powerpoint Presentation Slides
PDF
Lecture 2. project management – Description (1)
PPTX
Project management fundamentals
PPTX
Project Scheduling
PPTX
Project Management using MS Project 2010
PDF
Primavera - Tutorial
PPTX
Project management case study
PPTX
Brief introduction to project management and project management tools
PDF
Work Breakdown Structure
PPTX
Project recovery
PDF
Project Monitoring And Controlling
ODP
Agile Project Management
PDF
Resource allocation and smoothing
PPTX
RESOURCE LEVELLING (MS PROJECT)
PPTX
Lean Agile Metrics And KPIs
PPTX
Project management
PDF
Agile Project Management for PMP's
01 pmp introduct to project management exam
Chapter 05 Software effort estimation PartII_final
Project Deliverables Powerpoint Presentation Slides
Lecture 2. project management – Description (1)
Project management fundamentals
Project Scheduling
Project Management using MS Project 2010
Primavera - Tutorial
Project management case study
Brief introduction to project management and project management tools
Work Breakdown Structure
Project recovery
Project Monitoring And Controlling
Agile Project Management
Resource allocation and smoothing
RESOURCE LEVELLING (MS PROJECT)
Lean Agile Metrics And KPIs
Project management
Agile Project Management for PMP's
Ad

Viewers also liked (20)

PPT
PDF
Contingency Plan WAK BANKS ATM
PDF
Project Management Constraints
PPTX
Business software packages
PPTX
Quality of software
PPT
Capability maturity model cmm lecture 8
PPTX
Monitoring the control
PDF
160155061 project-monitoring-control
PPTX
How to close a project
PPT
Ch 9 project monitoring & control updated
PPTX
Project closure and audit
PDF
Modern Software Productivity Measurement: The Pragmatic Guide
PPSX
Project Closing Process
PPT
Configuration Management in Software Engineering - SE29
PPTX
Understanding and improving software productivity
PPT
Software configuration management
PDF
Lecture 8 monitoring & controlling (1)
PPT
PPT
Project audit & closure
DOCX
Project Management
Contingency Plan WAK BANKS ATM
Project Management Constraints
Business software packages
Quality of software
Capability maturity model cmm lecture 8
Monitoring the control
160155061 project-monitoring-control
How to close a project
Ch 9 project monitoring & control updated
Project closure and audit
Modern Software Productivity Measurement: The Pragmatic Guide
Project Closing Process
Configuration Management in Software Engineering - SE29
Understanding and improving software productivity
Software configuration management
Lecture 8 monitoring & controlling (1)
Project audit & closure
Project Management
Ad

Similar to PM Session 6 (20)

PPTX
Lecture-8-Scheduling-Resources-and-Cost.pptx
PDF
Scheduling resources and costs is a crucial aspect of project management that...
PPT
Chap008.ppt
PPTX
PM-Chapter8-1.pptx
PPT
Chapter-8-Post-Mid.ppt
PPT
Resource-Allocation.ppt
PPT
Module :-5 project scheduling and resource levelling
PPT
ch09s.ppt
PPTX
Larson2024_Ch08_PowerPoint_Accessible.pptx
PPTX
Resource planning and resource allocation
DOCX
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
PPTX
Allocating resources
PDF
Best Project Scheduling Techniques.
PDF
PPTX
Ch09 (1).pptx
PPT
-PM-09-7.ppt
PDF
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
DOCX
Chapter EightScheduling Resources and Costs8–1Copyright
PPTX
Pert,cpm, resource allocation and gert
PDF
Project Management in Practice 6th Edition Meredith Solutions Manual
Lecture-8-Scheduling-Resources-and-Cost.pptx
Scheduling resources and costs is a crucial aspect of project management that...
Chap008.ppt
PM-Chapter8-1.pptx
Chapter-8-Post-Mid.ppt
Resource-Allocation.ppt
Module :-5 project scheduling and resource levelling
ch09s.ppt
Larson2024_Ch08_PowerPoint_Accessible.pptx
Resource planning and resource allocation
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
Allocating resources
Best Project Scheduling Techniques.
Ch09 (1).pptx
-PM-09-7.ppt
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
Chapter EightScheduling Resources and Costs8–1Copyright
Pert,cpm, resource allocation and gert
Project Management in Practice 6th Edition Meredith Solutions Manual

More from dmdk12 (20)

PPTX
The Case for Change
PPTX
Framework for Project Layout Meeting
PPT
Change Presented ad A Project Roadmap: Infographic Template
PPT
The Change Project As an Archetypal Journey
PPT
Change Journey as an Individual Quest
PPT
Infographic Template for Developing a Project Journey
PPT
The People Management Story
PPTX
Infographic - Steering Committee Purpose, Role, Requirements, Metrics
PPTX
The HR Career in South Africa
PPTX
LEadership Theories Snap Shot
PPTX
ROI on People Management Interventions - It is Possible!!
PPTX
The People Management Story
PPTX
Model for Merger Management - This is a work in progress!!
PPTX
ROI For HR Practice Toolkit
PPTX
Coaching Toolkit
PPT
Focus on CPM and Resp Matrix
PPTX
Iron Triangle
PPTX
The Project Cycle Revisited
PPTX
Projects- The Three Artifacts
PPT
Organization Design 2 - Focus on Strategy
The Case for Change
Framework for Project Layout Meeting
Change Presented ad A Project Roadmap: Infographic Template
The Change Project As an Archetypal Journey
Change Journey as an Individual Quest
Infographic Template for Developing a Project Journey
The People Management Story
Infographic - Steering Committee Purpose, Role, Requirements, Metrics
The HR Career in South Africa
LEadership Theories Snap Shot
ROI on People Management Interventions - It is Possible!!
The People Management Story
Model for Merger Management - This is a work in progress!!
ROI For HR Practice Toolkit
Coaching Toolkit
Focus on CPM and Resp Matrix
Iron Triangle
The Project Cycle Revisited
Projects- The Three Artifacts
Organization Design 2 - Focus on Strategy

Recently uploaded (20)

PDF
Roadmap Map-digital Banking feature MB,IB,AB
PPTX
5 Stages of group development guide.pptx
PPTX
Probability Distribution, binomial distribution, poisson distribution
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PDF
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
PPTX
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
PDF
Chapter 5_Foreign Exchange Market in .pdf
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PDF
Unit 1 Cost Accounting - Cost sheet
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PDF
MSPs in 10 Words - Created by US MSP Network
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PDF
Business model innovation report 2022.pdf
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PPT
Chapter four Project-Preparation material
Roadmap Map-digital Banking feature MB,IB,AB
5 Stages of group development guide.pptx
Probability Distribution, binomial distribution, poisson distribution
Reconciliation AND MEMORANDUM RECONCILATION
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
Chapter 5_Foreign Exchange Market in .pdf
DOC-20250806-WA0002._20250806_112011_0000.pdf
Ôn tập tiếng anh trong kinh doanh nâng cao
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
New Microsoft PowerPoint Presentation - Copy.pptx
Unit 1 Cost Accounting - Cost sheet
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
340036916-American-Literature-Literary-Period-Overview.ppt
MSPs in 10 Words - Created by US MSP Network
unit 1 COST ACCOUNTING AND COST SHEET
Business model innovation report 2022.pdf
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
Chapter four Project-Preparation material

PM Session 6

  • 1. Project Management Session 6 Scheduling Resources
  • 2. Session Outcomes Following the session the delegates should have a basic understanding of the typical resource scheduling problems for time as well as resources constrained projects. In addition the delegate should be able to show how free slack can be used to effect resource leveling.
  • 4. The Resource Problem After staff and other resources have been allocated the project manager still need to answer the following questions: Will the resources be adequate and available when needed; Will outside contractors have to be used; Will unforeseen resource dependencies exist – will there be a new critical path; How much flexibility do we have in using resources; Are original deadlines realistic.
  • 5. The Resource Problem Resources and Priorities: Project sequencing and scheduling deals poorly with resource availability and utilization ; Project network times are not a schedule until resources have been assigned: The implicit assumption is that resources will be available in the required amounts when needed; Adding new projects requires making realistic judgments of resource availability and project durations; Resources may be adequate but demand can vary – then resource leveling or smoothing is required; or Resources may not be adequate to meet peak resource requirements , the late start date of certain activities will have to be delayed and project duration be increased – this is referred to as resource constrained scheduling.
  • 6. Types of Project Constraints Technical or Logic Constraints: Constraints related to the networked sequence in which project activities must occur – example, dig trenches, pour cement, then lay bricks for walls… Physical Constraints: Activities that cannot occur in parallel or are affected by contractual or environmental conditions – ship renovation, one person allowed in confined space… Resource Constraints: The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities- example, normally you have 3 people to do three activities in parallel, but because you only have one person you have to schedule them in series – NB!! Resource dependency takes priority but cannot violate technical dependencies.
  • 8. Kinds of Resource Constraints People; Materials; Equipment; Working Capital.
  • 9. Classification of A Scheduling Problem Classification of Problem: Using a priority matrix will help determine if the project is time or resource constrained; Time Constrained Project: A project that must be completed by an imposed date ; Time is fixed , resources are flexible: additional resources are required to ensure project meets schedule Resource Constrained Project: A project in which the level of resources available cannot be exceeded: Resources are fixed , time is flexible: inadequate resources will delay the project.
  • 10. Resource Allocation Methods Resource allocation is based on the following assumptions: Splitting activities is not allowed —once an activity is start, it is carried to completion; Level of resource used for an activity cannot be changed ; Activities with the most slack pose the least risk ; Reduction of flexibility does not increase risk ; The nature of an activity (easy, complex) doesn’t increase risk .
  • 11. Resource Allocation Methods Time-Constrained Projects: Projects that must be completed by an imposed date; Require the use of leveling techniques that focus on balancing or smoothing resource demand by using positive slack (delaying noncritical activities ) to manage resource utilization over the duration of the project with the following result: Peak resource demands are reduced; Resource demand over the life of the project are reduced; Fluctuation in resource demand is minimized.
  • 15. Botanical Garden Using the slack of irrigation to start 3 days late 1 2 3 4 5
  • 16. Botanical Garden Using the slack of fence and walls to start 3 days late 1 2 3 4 5
  • 18. Resource Allocation Methods Resource Demand Leveling Techniques for Time-Constrained Projects: Advantages: Peak resource demands are reduced; Resources demand over the life of the project are reduced; Fluctuation in resource demand is minimized; Disadvantages: Loss of flexibility that occurs from reducing slack; Increases in the criticality of all activities.
  • 19. Resource Allocation Methods Resource-Constrained Projects: Projects that involve resources that are limited in quantity or by their availability’ Scheduling of activities requires the use of heuristics (rules-of-thumb) that focus on: Minimum slack; Smallest (least) duration; Lowest activity identification number. The parallel method is used to apply heuristics: An iterative process that starts at the first time period of the project and schedules period-by-period any activities scheduled to start using the three priority rules.
  • 21. The Impacts of Resource-Constrained Scheduling Reduces delay but reduces flexibility; Increases criticality of events; Increases scheduling complexity; May make traditional critical path no longer meaningful; Can break sequence of events; May cause parallel activities to become sequential and critical activities with slack to become noncritical.b
  • 22. CPM includes a way of relating the project schedule to the level of physical resources allocated to the project; This allows the project manager to trade time for cost, or vice versa; In CPM, two activity times and two costs are specified, if appropriate for each activity. Resource Management
  • 23. The first time/cost combination is called normal, and the second set is referred to as crash ; Normal assumes time and resources in normal conditions – although there is a “technical” way to calculate it; Crash result from an attempt to expedite the activity by the application of additional resources. Resource Management
  • 24. Careful planning is critical when attempting to expedite (crash) a project; Expediting tends to create problems, and the solution to one problem often creates several more problems that require solutions. Resource Management
  • 25. Another way to expedite a project is known as “fast-tracking”; Mostly construction but term also used on other projects; It refers to overlapping the design and build phases of a project; Because design is usually completed before construction starts, overlapping the two activities will result in shortening the project duration; Could however also lead to increased number of change orders, and therefore increased cost and loss of time – however generally feasible. Resource Management
  • 26.