SlideShare a Scribd company logo
Scheduling
Resources
and Costs
CHAPTER EIGHT
Copyright © 2011 by The McGraw-Hill Companies, Inc. All
rights reserved.
McGraw-Hill/Irwin
8–3
The Resource Problem
• Resources and Priorities
–Project network times are not a schedule
until resources have been assigned.
• The implicit assumption is that resources will be available
in the required amounts when needed.
• Adding new projects requires making realistic judgments
of resource availability and project durations.
–Cost estimates are not a budget
until they have been time-phased.
8–4
Project Planning Process
FIGURE 8.1
8–5
The Resource Problem (cont’d)
• Resource Smoothing (or Leveling)
–Involves attempting to even out varying demands
on resources by using slack (delaying noncritical
activities) to manage resource utilization when
resources are adequate over the life of the project.
• Resource-Constrained Scheduling
–The duration of a project may be increased by
delaying the late start of some of its activities if
resources are not adequate to meet peak demands.
8–6
Types of Project Constraints
• Technical or Logic Constraints
– Constraints related to the networked sequence
in which project activities must occur.
• Physical Constraints
– Activities that cannot occur in parallel or are affected by
contractual or environmental conditions.
• Resource Constraints
– The absence, shortage, or unique interrelationship and
interaction characteristics of resources that require a particular
sequencing of project activities
• Kinds of Resource Constraints
– People, materials, equipment
8–7
Constraint Examples
FIGURE 8.2
8–8
Classification of A Scheduling Problem
• Classification of Problem
–Using a priority matrix will help determine if
the project is time or resource constrained.
• Time-Constrained Project
–Must be completed by an imposed date.
• Time is fixed, resources are flexible: additional resources
are required to ensure project meets schedule.
• Resource-Constrained Project
–Is one in which the level of resources available
cannot be exceeded.
• Resources are fixed, time is flexible: inadequate resources
will delay the project.
8–9
Resource Allocation Methods
• Limiting Assumptions
–Splitting activities is not allowed—once an
activity is started, it is carried to completion.
–Level of resources used for an activity cannot
be changed.
• Risk Assumptions
–Reduction of flexibility does not increase risk.
–The nature of an activity (easy, complex)
doesn’t increase risk.
8–10
Resource Allocation Methods (cont’d)
• Time-Constrained Projects
–Must be completed by an imposed date.
–Require use of leveling techniques that focus
on balancing or smoothing resource demands.
–Use positive slack (delaying noncritical activities)
to manage resource utilization over the duration
of the project.
• Peak resource demands are reduced.
• Resources over the life of the project are reduced.
• Fluctuation in resource demand is minimized.
8–11
Resource Allocation Methods (cont’d)
• Resource Demand Leveling Techniques
for Time-Constrained Projects
–Advantages
• Peak resource demands are reduced.
• Resources over the life of the project are reduced.
• Fluctuation in resource demand is minimized.
–Disadvantages
• Loss of flexibility that occurs from reducing slack.
• Increases in the criticality of all activities.
8–12
Resource Allocation Methods (cont’d)
• Resource-Constrained Projects
– Resources are limited in quantity or availability.
– Activities are scheduled using heuristics
(rules-of-thumb) that focus on:
1. Minimum slack
2. Smallest (least) duration
3. Lowest activity identification number
8–13
The Impacts of Resource-Constrained
Scheduling
• Reduces delay but reduces flexibility.
• Increases criticality of events.
• Increases scheduling complexity.
• May make the traditional critical path
no longer meaningful.
• Can break sequence of events.
• May cause parallel activities to become
sequential and critical activities with slack
to become noncritical.
8–14
Splitting
• Splitting
– A scheduling technique use to get a better project
schedule and/or increase resource utilization.
• Involves interrupting work on an activity to employ the
resource on another activity, then returning the resource
to finish the interrupted work.
• Is feasible when startup and shutdown costs are low.
• Is considered the major reason why projects fail to meet
schedule.
8–15
Splitting Activities
FIGURE 8.11
8–16
Benefits of Scheduling Resources
• Leaves time for consideration
of reasonable alternatives:
–Cost-time tradeoffs
–Changes in priorities
• Provides information for time-phased
work package budgets to assess:
–Impact of unforeseen events
–Amount of flexibility in available resources
8–17
Multiproject Resource Schedules
• Multiproject Scheduling Problems
1. Overall project slippage
• Delay on one project create delays for other projects
2. Inefficient resource application
• The peaks and valleys of resource demands create
scheduling problems and delays for projects.
3. Resource bottlenecks
• Shortages of critical resources required for multiple
projects cause delays and schedule extensions.
8–18
Multiproject Resource Schedules (cont’d)
• Managing Multiproject Scheduling:
–Create project offices or departments to oversee
the scheduling of resources across projects.
–Use a project priority queuing system: first come,
first served for resources.
–Centralize project management: treat all projects
as a part of a “megaproject.”
–Outsource projects to reduce the number
of projects handled internally.

More Related Content

PPT
Chap008.ppt
PPTX
PM-Chapter8-1.pptx
PDF
Scheduling resources and costs is a crucial aspect of project management that...
PPTX
Lecture-8-Scheduling-Resources-and-Cost.pptx
PPT
Scheduling-Resources-and-Costs.ppt
PPTX
Larson2024_Ch08_PowerPoint_Accessible.pptx
PDF
Allocating Resources To The Project
PPT
PM Session 6
Chap008.ppt
PM-Chapter8-1.pptx
Scheduling resources and costs is a crucial aspect of project management that...
Lecture-8-Scheduling-Resources-and-Cost.pptx
Scheduling-Resources-and-Costs.ppt
Larson2024_Ch08_PowerPoint_Accessible.pptx
Allocating Resources To The Project
PM Session 6

Similar to Chapter-8-Post-Mid.ppt (20)

DOCX
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
PPT
PPTX
Allocating resources
PPTX
Ch09 (1).pptx
PPT
Resource allocation
PPT
PPTX
Spm chapter 8
PPT
Spm chapter 8
PPT
software management project: resource allocation
PPT
ch09s.ppt
PDF
PMI-ACP Domain V: Adaptive Planning v1.0
PPT
-PM-09-7.ppt
PDF
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
PPTX
IT PROJECT MANAGEMENT FOR AUTONOMOUS STUDENTS FOR ANNA UNIVERSITY
PPT
Software project management notes of resource allocation
PPTX
Resource planning and resource allocation
PPT
Software Engineering (Project Scheduling)
PPT
lecture8-190719030939.ppthjtyuiytiytiyti
PPTX
Pert,cpm, resource allocation and gert
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
Allocating resources
Ch09 (1).pptx
Resource allocation
Spm chapter 8
Spm chapter 8
software management project: resource allocation
ch09s.ppt
PMI-ACP Domain V: Adaptive Planning v1.0
-PM-09-7.ppt
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
IT PROJECT MANAGEMENT FOR AUTONOMOUS STUDENTS FOR ANNA UNIVERSITY
Software project management notes of resource allocation
Resource planning and resource allocation
Software Engineering (Project Scheduling)
lecture8-190719030939.ppthjtyuiytiytiyti
Pert,cpm, resource allocation and gert
Ad

More from TecnicoItca (20)

PDF
tipos-de-organizacion-empresarial.pdf
PPT
-Interes-Simple.ppt
PPTX
Tesis-de-gerencia-de-proyectos (1).pptx
PPT
Gestion-Financiera-Semestre-2016-0-ppt.ppt
PPT
08-Project-Control-ppt.ppt
PPTX
Project-Progress-Presentation.pptx
PPT
-Project-Management.ppt
PPT
Telsys-Case-International-Management.ppt
PPTX
Project-Management.pptx
PPT
Project-Management.ppt
PPTX
PROJECT-SCHEDULING-pptx.pptx
PPT
Project-Management-Introduction.ppt
PPT
Project-Manager.ppt
PPT
ch10s.ppt
PPT
Resource-Allocation.ppt
PPT
Chapter-5-Scheduling-and-Resource-Allocation.ppt
PPT
Clases-de-Bonos-matematica.ppt
PPTX
Valoracion-de-Bonos.pptx
PPT
Bonos-Clase.ppt
PPT
Valuacion-de-Bonos-3.ppt
tipos-de-organizacion-empresarial.pdf
-Interes-Simple.ppt
Tesis-de-gerencia-de-proyectos (1).pptx
Gestion-Financiera-Semestre-2016-0-ppt.ppt
08-Project-Control-ppt.ppt
Project-Progress-Presentation.pptx
-Project-Management.ppt
Telsys-Case-International-Management.ppt
Project-Management.pptx
Project-Management.ppt
PROJECT-SCHEDULING-pptx.pptx
Project-Management-Introduction.ppt
Project-Manager.ppt
ch10s.ppt
Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Clases-de-Bonos-matematica.ppt
Valoracion-de-Bonos.pptx
Bonos-Clase.ppt
Valuacion-de-Bonos-3.ppt
Ad

Recently uploaded (20)

PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
web development for engineering and engineering
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Construction Project Organization Group 2.pptx
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PPTX
Lecture Notes Electrical Wiring System Components
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
Geodesy 1.pptx...............................................
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
web development for engineering and engineering
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Construction Project Organization Group 2.pptx
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Automation-in-Manufacturing-Chapter-Introduction.pdf
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
Lecture Notes Electrical Wiring System Components
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Internet of Things (IOT) - A guide to understanding
Model Code of Practice - Construction Work - 21102022 .pdf
Geodesy 1.pptx...............................................
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
Embodied AI: Ushering in the Next Era of Intelligent Systems
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
UNIT 4 Total Quality Management .pptx
UNIT-1 - COAL BASED THERMAL POWER PLANTS

Chapter-8-Post-Mid.ppt

  • 1. Scheduling Resources and Costs CHAPTER EIGHT Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin
  • 2. 8–3 The Resource Problem • Resources and Priorities –Project network times are not a schedule until resources have been assigned. • The implicit assumption is that resources will be available in the required amounts when needed. • Adding new projects requires making realistic judgments of resource availability and project durations. –Cost estimates are not a budget until they have been time-phased.
  • 4. 8–5 The Resource Problem (cont’d) • Resource Smoothing (or Leveling) –Involves attempting to even out varying demands on resources by using slack (delaying noncritical activities) to manage resource utilization when resources are adequate over the life of the project. • Resource-Constrained Scheduling –The duration of a project may be increased by delaying the late start of some of its activities if resources are not adequate to meet peak demands.
  • 5. 8–6 Types of Project Constraints • Technical or Logic Constraints – Constraints related to the networked sequence in which project activities must occur. • Physical Constraints – Activities that cannot occur in parallel or are affected by contractual or environmental conditions. • Resource Constraints – The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities • Kinds of Resource Constraints – People, materials, equipment
  • 7. 8–8 Classification of A Scheduling Problem • Classification of Problem –Using a priority matrix will help determine if the project is time or resource constrained. • Time-Constrained Project –Must be completed by an imposed date. • Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule. • Resource-Constrained Project –Is one in which the level of resources available cannot be exceeded. • Resources are fixed, time is flexible: inadequate resources will delay the project.
  • 8. 8–9 Resource Allocation Methods • Limiting Assumptions –Splitting activities is not allowed—once an activity is started, it is carried to completion. –Level of resources used for an activity cannot be changed. • Risk Assumptions –Reduction of flexibility does not increase risk. –The nature of an activity (easy, complex) doesn’t increase risk.
  • 9. 8–10 Resource Allocation Methods (cont’d) • Time-Constrained Projects –Must be completed by an imposed date. –Require use of leveling techniques that focus on balancing or smoothing resource demands. –Use positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project. • Peak resource demands are reduced. • Resources over the life of the project are reduced. • Fluctuation in resource demand is minimized.
  • 10. 8–11 Resource Allocation Methods (cont’d) • Resource Demand Leveling Techniques for Time-Constrained Projects –Advantages • Peak resource demands are reduced. • Resources over the life of the project are reduced. • Fluctuation in resource demand is minimized. –Disadvantages • Loss of flexibility that occurs from reducing slack. • Increases in the criticality of all activities.
  • 11. 8–12 Resource Allocation Methods (cont’d) • Resource-Constrained Projects – Resources are limited in quantity or availability. – Activities are scheduled using heuristics (rules-of-thumb) that focus on: 1. Minimum slack 2. Smallest (least) duration 3. Lowest activity identification number
  • 12. 8–13 The Impacts of Resource-Constrained Scheduling • Reduces delay but reduces flexibility. • Increases criticality of events. • Increases scheduling complexity. • May make the traditional critical path no longer meaningful. • Can break sequence of events. • May cause parallel activities to become sequential and critical activities with slack to become noncritical.
  • 13. 8–14 Splitting • Splitting – A scheduling technique use to get a better project schedule and/or increase resource utilization. • Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work. • Is feasible when startup and shutdown costs are low. • Is considered the major reason why projects fail to meet schedule.
  • 15. 8–16 Benefits of Scheduling Resources • Leaves time for consideration of reasonable alternatives: –Cost-time tradeoffs –Changes in priorities • Provides information for time-phased work package budgets to assess: –Impact of unforeseen events –Amount of flexibility in available resources
  • 16. 8–17 Multiproject Resource Schedules • Multiproject Scheduling Problems 1. Overall project slippage • Delay on one project create delays for other projects 2. Inefficient resource application • The peaks and valleys of resource demands create scheduling problems and delays for projects. 3. Resource bottlenecks • Shortages of critical resources required for multiple projects cause delays and schedule extensions.
  • 17. 8–18 Multiproject Resource Schedules (cont’d) • Managing Multiproject Scheduling: –Create project offices or departments to oversee the scheduling of resources across projects. –Use a project priority queuing system: first come, first served for resources. –Centralize project management: treat all projects as a part of a “megaproject.” –Outsource projects to reduce the number of projects handled internally.