Agile Scheduling and Release
Planning
Michael Geiser
What Do We Want to Accomplish?
• This presentation proposes (within an Agile SDLC)
• How to estimate a code complete date for development to plan a software
release date.
• How to track progress towards the code complete date
• Present examples Executive Sponsor statuses slides so you can provide a clear
concise status that communicates your message to Senior Management
• Use the same artifacts to clearly see that you are on-track or off-track and
how the project is trending so we can see if a mitigation plan is needed
Assumptions/Facts
• Scrum, as codified in the Agile Manifesto, is one of the most
successful Software Development approaches/methodologies for
small independent teams and can be scaled to large distributed
teams.
• Leaders in the field (Scott Ambler, Mike Cottmeyer, VersionOne,
Thoughtworks…) recognize that the Agile Manifesto has limitations
when applied to “Large Scale” Agile development efforts
• Having many scrum teams in an enterprise does not mean you are doing
Enterprise Agile
• Single Team-level Agile practices are different from multiple-team Agile
practices at scale
• Agile at scale requires a broader set of tools and techniques
Project Timeline Slides and Missed Schedule Milestones
• Changes in scope are inevitable (not referring to scope creep which is controllable). Agile
addresses fact of life FAR better than any other SDLC.
Inaccurate Effort and Capacity Estimates
• Estimates made before work started are often an order of magnitude off and need to you
constantly consider the effect Scope changes.
• Completed work and informed revised estimates should continually revise code complete
estimates.
Inability to Objectively and Independently assess project status
• Tracking software development in MS Project is problematic and relies on how he Percent
Complete entries are made.
• This often leads to Executive Sponsors getting an overly-optimistic view of progress
PMO Basics
• If we’re not continually and meaningfully measuring the actual status of the project, how
do we know we’re on track or need a mitigation plan?
• We should use templates across projects and with all Executive Sponsors to that we
consistently report and minimize the effort to report and maximize transparency
Agile Project Management Pain Points
Waterfall and Scrum Differences
• In Waterfall SDLCs, SOP is that schedules and scope are defined often
with little Development input and Development is told to “work
longer to get just the work done”.
• We know how well that worked out in the past…
• Scrum (“Textbook Orthodox Scrum” not SAFe or others) swings the
pendulum too far in the opposite direction.
• “It’s done when it’s done” and “You can’t have release dates” are just as or
even more unrealistic
• The organization doesn’t exist to server Development (as nice as that sounds)
• It’s also very “anti-Agile” because it doesn’t meet the needs of stakeholders
Release Tracking Chart
Release Tracking Chart
The Release Tracking Chart tracks the Scope, Development Plan, Sprint Plan, and Actual Work completed on a single chart
that is always available and always reviewed in Executive Sponsor Status Meetings
Scope:
• The Scope and the effort to complete scope constantly changes during a project; normally some scope is added or removed and progressive
elaboration gives us increasing more precise estimations of total effort and code complete dates.
• Good Change Management processes for scope is stile vital in Agile; embracing change in Agile does not mean accepting any change without
understanding and recognizing the impact of the change. Scope should reflect accepted changes by the product owner.
• Agile teams should communicate scope and scope changes to recognize schedule risks so they can take action early enough when needed.
Development Plan:
• Estimated project work that can be completed according to Staffing Plan is charted to compare to Scope and to project a code complete date.
Sprint Plan:
• This should track to the Development Plan but reflects the actual Staff capacity and highlights immediately when the Development plan is or is
not being met so remediation plans can be implemented early when needed
Actual Work:
• Shows work completed against Scope, the Development and Sprint Plans. It is transparently communicated when Actual Work completed and
total scope are not on plan to met for the target code complete date
Release Tracking Chart
• Take care that the chart and table are consistent across all Status meetings
• Include 3 slides in the Executive Sponsor Status Meeting deck:
• Last meeting’s actual status
• This meeting’s actual status
• Next meeting’s plan
• Being able to move between these three slides and see the change over 6
weeks is an extremely effective way to present this information.
• I sometimes put the current slide in the main Status section and put the three in
Appendix Material (know your audience)
• The next 7 slides demonstrate this concept.
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13
Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul
Scope +25% 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75
Scope 775 775 775 775 775 775 775 775 775 775 775 775 775
Scope -25% 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25
Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645
Iteration Plan
Actual
Completed 0 0 0 0 0 0 0 0 0 0 0 0 0
Notes
• Your Development Plan must
overshoot your Scope in the last few
sprints to account for backlog scarcity
near the end of the project and project
closeout activities. This Dev Plan
doesn’t even come close to that goal.
• I would put the Project Schedule at
Yellow trending Red at this point.
Sprint 1 - Start
Actual numbers in
Black, projected
numbers in red
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13
Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul
Scope +25% 958.75 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25
Scope 775 725 725 725 725 725 725 725 725 725 725 725 725
Scope -25% 591.25 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75
Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645
Iteration Plan 45 100
Actual 40 85
Completed 40 80 80 80 80 80 80 80 80 80 80 80 80
Notes
• Scope Refinement reduces Schedule
Risk moderately but Schedule is still
Yellow. I would eliminate the Trending
Red modifier but to early to say
Trending Green
Sprint 2 - End
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13
Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul
Scope +25% 958.75 886.25 813.75 803.75 760 760 760 760 760 760 760 760 760
Scope 775 725 675 675 650 650 650 650 650 650 650 650 650
Scope -25% 591.25 563.75 536.25 546.25 540 540 540 540 540 540 540 540 540
Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645
Iteration Plan 45 100 150 185 220
Actual 40 85 120 160 210
Completed 40 80 120 160 210 210 210 210 210 210 210 210 210
Notes
• Schedule almost Green but Iteration
Plan and Actual Work Completed is not
Meeting Plan; Mitigation Plan still
needed.
Observe the “Uncertainty Range” of the
Scope is getting progressively narrow.
Completed Scope has an uncertainty of
0%; you know exactly how long it took to
complete. Uncertainty ranges show the
complexity range of uncompleted work.
Sprint 5 - End
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13
Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul
Scope +25% 958.75 886.25 813.75 803.75 760 790 742.5 742.5 742.5 742.5 742.5 742.5 742.5
Scope 775 725 675 675 650 680 650 650 650 650 650 650 650
Scope -25% 591.25 563.75 536.25 546.25 540 570 557.5 557.5 557.5 557.5 557.5 557.5 557.5
Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645
Iteration Plan 45 100 150 185 220 265 315
Actual 40 85 120 160 210 240 280
Completed 40 80 120 160 210 240 280 280 280 280 280 280 280
Notes
• Sprint Velocity is predictable but less
than Development Plan. Schedule is
Yellow Trending Red.
• Corrective Action must be taken or
project will fail to meet schedule: A
decision must be made to reduce
Scope, lengthen Schedule or add
Resources to finish by June 1.
Decision Made: Current Scope is needed
for MVP and Schedule will be kept;
Resources will be added to balance
Sprint 7 - End
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13
Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul
Scope +25% 958.75 886.25 813.75 803.75 760 790 742.5 733.75 718.75 718.75 718.75 718.75 718.75
Scope 775 725 675 675 650 680 650 655 660 660 660 660 660
Scope -25% 591.25 563.75 536.25 546.25 540 570 557.5 576.25 601.25 601.25 601.25 601.25 601.25
Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645
Iteration Plan 45 100 150 185 220 265 315 370 440
Actual 40 85 120 160 210 240 280 340 425
Completed 40 80 120 160 210 240 280 340 425 425 425 425 425
Notes
• Velocity increases as additional
Resources engage and begin
“norming” with the team.
Sprint 9 - End
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13
Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul
Scope +25% 958.75 886.25 813.75 803.75 760 790 742.5 733.75 718.75 698.75 690 690 690
Scope 775 725 675 675 650 680 650 655 660 660 670 670 670
Scope -25% 591.25 563.75 536.25 546.25 540 570 557.5 576.25 601.25 621.25 650 650 650
Dev Plan 45 95 145 195 245 295 345 395 445 505 565 625 685
Iteration Plan 45 100 150 185 220 265 315 370 440 510 580
Actual 40 85 120 160 210 240 280 340 425 505 590
Completed 40 80 120 160 210 240 280 340 425 505 590 590 590
Notes
• Development Plan updated to reflect
increased Velocity and Scope changes
(The “Dev Plan” line bends upward)
• Schedule Yellow Trending Green or
Green Trending Yellow; Development
Plan must overshoot Total Scope in the
last few sprints to account for Backlog
scarcity near the end of the project
and project closeout activities (there’s
the real world creeping into your Dev
Plan again!)
Sprint 11 - End
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13
Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul
Scope +25% 958.75 886.25 813.75 803.75 760 790 742.5 733.75 718.75 698.75 690 675 665
Scope 775 725 675 675 650 680 650 655 660 660 670 670 665
Scope -25% 591.25 563.75 536.25 546.25 540 570 557.5 576.25 601.25 621.25 650 665 665
Dev Plan 45 95 145 195 245 295 345 395 445 505 565 625 685
Iteration Plan 45 100 150 185 220 265 315 370 440 510 580 650 720
Actual 40 85 120 160 210 240 280 340 425 505 590 650 665
Completed 40 80 120 160 210 240 280 340 425 505 590 650 665
Notes
• It is recommended to plan on a
“Hardening Sprint”, which would be
Sprint 14 in this example, to finish and
refactor as needed and to finalized
non-functional requirements like
performance and other “end-to-end”
testing that are hard or impossible to
do until code complete
Sprint 13 - End
Release Timeline Estimation
Classic Cone of Uncertainty
• What is the “Cone of Uncertainty”?
• The cumulative uncertainty of the scope and effort for a project and it’s
reduction over the course of a project
• In most common definitions, it is an artifact of the Waterfall project
start up approach
• Relatively course-grained estimates are done based on knowledge of scope
and capacity during early planning
• These rough estimates are often used to determine a target release date
• The development window is determined either from backing into the release
date or based on historical data of development pace
• The project timeline is locked down using these estimates
Classic Cone of Uncertainty Diagram
Problems with the Classic Cone of Uncertain
Diagram
• The over/under on the Accuracy of Estimates is interesting but we need to know while the project is in flight
how the accuracy of estimates affects when the work will actually be done.
• The “Classic” Cone of Uncertainty diagram is (IMHO) a seriously flawed representation of the concept and
not useful at all.
• The 1.00x level of Accuracy of Estimates on the y axis is reached at the end of the project. The graph gives the
impression we had the estimate dead on at the start and are just eliminating the buffer.
• The x axis needs to show when the project will be done as the metric of interest.
• Completing work, Progressive Elaboration and Rolling Wave Planning over a project lifetime narrows the range of
estimation uncertainty; it is a continual process not the event based changes shown in the diagram.
This diagram has no useful
information or value
Code Complete Date Refinement – Improved
• The useful Project Management graph is a Target Code Complete Date “Cone of Uncertainty“
• This graph allows action to be taken to affect the target completion date (remove scope, add resources) or to accurately set
expectation of shareholders and downstream teams (Release Management)
• Graph the right (actionable) information
• A useful graph for in-flight projects needs to show the impact of Change Requests, refinement, velocity and total scope on the finish
date
• Mitigation plans can only be implemented if you know there is a likelihood and impact of risk to the target date
• The right graph needs the right axes
• The x axis is time
• The y axis is total scope
• Need to know Velocity
• The estimated speed of development per iteration is needed
• Collect the data at the right time
• Update the graph at the end of each iteration or on key events (i.e. Scope Changes, staff crises)
• Overlay the estimated completion date range (the uncertainty of the date)
• Like managing risk, the uncertainty needs to decrease over time and reach a single target date as soon as possible
Code Complete Date Chart
Q: “Why have this chart too when I have the excellent Release Tracking
Chart?”
A: Complexity and Clarity
• These two charts have two entirely different purposes and combining them would be confusing
• The x-intercept of the Code Complete Chart is a key feature of the chart, you wouldn’t get the same clear
picture from a combined chart
• The Release Tracking Chart does give you a Code Complete date, but this chart vital for reporting results of
Change Control Meetings whereas the Release Tracking Chart would not be useful.
Code Complete Date Chart
• Take care that the chart and table are consistent across all Status meetings
• Include 3 slides in the Executive Sponsor Status Meeting deck:
• Last meeting’s actual status
• This meeting’s actual status
• Next meeting’s plan
• Being able to move between these three slides and see the change over 6
weeks is an extremely effective way to present this information.
• I sometimes put the current slide in the main Status section and put the three in
Appendix Material (know your audience)
• The next 6 slides demonstrate how to use this tool.
Notes
• Initial Scope (with uncertainty) is between
581 and 969 Story Point and will take
between 9 and 14 Sprints
• Initial Target Code Complete date is 17
June. This date is very much “At Risk”.
Sprint 1 - Start
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul
Est Scope +25% 968.75 893.75 818.75 743.75 668.75 593.75 518.75 443.75 368.75 293.75 218.75 143.75 68.75 -6.25
Est Scope Remaining 775 700 625 550 475 400 325 250 175 100 25 -50 -125 -200
Est Scope -25% 581.25 506.25 431.25 356.25 281.25 206.25 131.25 56.25 -18.75 0 0 0 0 0
Velocity 75 75 75 75 75 75 75 75 75 75 75 75 75 75
Approved Scope change 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Notes
• Velocity in Sprints 2 and 3 were less than
Sprint 1 and below the initial estimate
• Scope changes can be from PO changes to
the Backlog, the elimination of duplicate
User Stories or refinement of User Story
estimates
• Range of Code Complete has reduced but
17 June Code Complete date is still At-Risk
Sprint 3 - End
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul
Est Scope +25% 968.75 843.75 768.75 708.75 633.75 558.75 483.75 408.75 333.75 258.75 183.75 108.75 33.75 -41.25
Est Scope Remaining 775 675 615 555 480 405 330 255 180 105 30 -45 -120 -195
Est Scope -25% 581.25 506.25 461.25 401.25 326.25 251.25 176.25 101.25 26.25 0 0 0 0 0
Velocity 75 70 60 75 75 75 75 75 75 75 75 75 75 75
Approved Scope change -25 10 0 0 0 0 0 0 0 0 0 0 0 0
Notes
• Velocity is on average close to estimate in
Burndown in this example
• The Code Complete date range is now
much more narrow
• Target Code Complete of 17 June is now
after the range of Code Complete dates
(but there is still no buffer)
• Code Complete estimated date is
between 20 May and 17 June (3 June is
most likely based on graph)
Sprint 6 - End
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul
Est Scope +25% 968.75 843.75 768.75 693.75 531.25 437.5 367.5 292.5 217.5 142.5 67.5 -7.5 -82.5 -157.5
Est Scope Remaining 775 675 615 555 425 350 272 197 122 47 -28 -103 -178 -253
Est Scope -25% 581.25 506.25 461.25 416.25 318.75 262.5 192.5 117.5 42.5 0 0 0 0 0
Velocity 75 70 60 80 70 70 75 75 75 75 75 75 75 75
Approved Scope change -25 10 0 -50 -5 -8 0 0 0 0 0 0 0 0
Notes
• The uncertainty of Code Complete is
minimal and there is almost an entire
sprint buffer between the latest Code
Compete date and the 17 June target
• Almost certain that Code Complete will be
the end of the 3 June Sprint at this point
Sprint 9 - End
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul
Est Scope +25% 968.75 843.75 768.75 693.75 531.25 425 327.5 246.25 156.25 81.25 6.25 -68.75 -143.75 -218.75
Est Scope Remaining 775 675 615 555 425 340 262 197 125 50 -25 -100 -175 -250
Est Scope -25% 581.25 506.25 461.25 416.25 318.75 255 196.5 147.75 93.75 18.75 0 0 0 0
Velocity 75 70 60 80 80 70 80 80 75 75 75 75 75 75
Approved Scope change -25 10 0 -50 -5 -8 15 8 0 0 0 0 0 0
Notes
• It is an important principle of Agile that
we be open to change in scope at any
time. This doesn’t mean that the Product
Owner and Stakeholders have free reign
to make any changes with consequences;
the “Iron Triangle” concepts still apply.
• The effect of the change at this point on
the Release Date is obvious: If the scope
change is accepted, the schedule change
of adding two additional Sprints also must
be accepted (at this late stage, it is
unlikely we could add resources to cover
the scope change).
Sprint 9 – What if we add another 100 days of scope at the start of Sprint 9?
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul
Est Scope +25% 968.75 843.75 768.75 693.75 531.25 425 327.5 246.25 277.5 202.5 127.5 52.5 -22.5 -97.5
Est Scope Remaining 775 675 615 555 425 340 262 197 222 147 72 -3 -78 -153
Est Scope -25% 581.25 506.25 461.25 416.25 318.75 255 196.5 147.75 166.5 91.5 16.5 -58.5 -133.5 -208.5
Velocity 75 70 60 80 80 70 80 80 75 75 75 75 75 75
Approved Scope change -25 10 0 -50 -5 -8 15 108 0 0 0 0 0 0
Notes
Code Complete
Sprint 11 – End (Code Complete)
Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul
Est Scope +25% 968.75 843.75 768.75 693.75 531.25 425 327.5 246.25 156.25 81.25 0 0 0 0
Est Scope Remaining 775 675 615 555 425 340 262 197 125 50 0 0 0 0
Est Scope -25% 581.25 506.25 461.25 416.25 318.75 255 196.5 147.75 93.75 18.75 0 0 0 0
Velocity 75 70 60 80 80 70 80 80 75 80 0 0 0 0
Approved Scope change -25 10 0 -50 -5 -8 15 8 0 5 0 0 0 0

More Related Content

PPTX
Agile Release Planning
PPTX
CI / CD Roles, Processes and Supporting Tools
PPT
Release planning
PPTX
Release Planning. For Agile Teams. A Quick Overview
PDF
Release planning in Scrum
PDF
Agile Metrics
PDF
Agile Lesson
PPTX
Agile Workshop: Agile Metrics
Agile Release Planning
CI / CD Roles, Processes and Supporting Tools
Release planning
Release Planning. For Agile Teams. A Quick Overview
Release planning in Scrum
Agile Metrics
Agile Lesson
Agile Workshop: Agile Metrics

What's hot (20)

PPTX
Agile project management with scrum
PDF
Agile metrics - Measure and Improve
PPTX
Seven Key Metrics to Improve Agile Performance
PPTX
Agile Metrics
PPT
Agile Metrics
PDF
Agile quiz answers
PPTX
Project Management
PPT
Agile Project Management
PDF
Agile user-stories
PDF
The Role of Quality Assurance in the World of Agile Development and Scrum
PPTX
Agile Metrics...That Matter
PPTX
The Essence of Sprint Planning : Presented by Sprint Planning
PPTX
Introduction to Scrum.ppt
PPT
Agile Executive Briefing - Situational Assessment + 50k Ft View
PDF
Agile Delivery Powerpoint Presentation Slides
PDF
Agile metrics
PPT
Agile Metrics V6
PPTX
Agile planning
PPTX
How smooth is your agile ride
PDF
Big Apple Scrum Day 2015 - Advanced Scrum Metrics Presentation
Agile project management with scrum
Agile metrics - Measure and Improve
Seven Key Metrics to Improve Agile Performance
Agile Metrics
Agile Metrics
Agile quiz answers
Project Management
Agile Project Management
Agile user-stories
The Role of Quality Assurance in the World of Agile Development and Scrum
Agile Metrics...That Matter
The Essence of Sprint Planning : Presented by Sprint Planning
Introduction to Scrum.ppt
Agile Executive Briefing - Situational Assessment + 50k Ft View
Agile Delivery Powerpoint Presentation Slides
Agile metrics
Agile Metrics V6
Agile planning
How smooth is your agile ride
Big Apple Scrum Day 2015 - Advanced Scrum Metrics Presentation
Ad

Viewers also liked (16)

PDF
Ateala Management Inc Product Marketing For An Agile World
DOCX
Really useful linux commands
PPTX
Scrum Training
PDF
Keeping up with Agilists
PPTX
High output product managers
PDF
Forecast it - Agile in distributed teams - AgilityLab
PDF
Forecasting Accurately with Salesforce Forecasting
PPTX
AgileChina 2015: Agile Estimation Workshop
PPTX
Agile Release & Iteration Planning
PPTX
Agile Release Planning
PPT
Release Management
PPTX
Tying Roadmap Strategy to Agile Planning
PPTX
Understanding the Agile Release and Sprint Planning Process
PDF
Stop coding start testing
PPTX
Développement distribué agile
PPTX
Release Management: Successful Software Releases Start with a Plan
Ateala Management Inc Product Marketing For An Agile World
Really useful linux commands
Scrum Training
Keeping up with Agilists
High output product managers
Forecast it - Agile in distributed teams - AgilityLab
Forecasting Accurately with Salesforce Forecasting
AgileChina 2015: Agile Estimation Workshop
Agile Release & Iteration Planning
Agile Release Planning
Release Management
Tying Roadmap Strategy to Agile Planning
Understanding the Agile Release and Sprint Planning Process
Stop coding start testing
Développement distribué agile
Release Management: Successful Software Releases Start with a Plan
Ad

Similar to Agile Progress Tracking and Code Complete Date Estimation (20)

PPTX
KANBAN AT SCALE: A SIEMENS HEALTH SERVICES CASE STUDY (BENNET VALLET & DAN VA...
DOCX
Introduction to SAFeMSIS CoreFall 2019Scenario –.docx
PPTX
A kanban scrum mashup to deliver fp projects
PPTX
How do develop Tminus maps for Software development
PPTX
"Making Scrum "More" Effective : What can we learn from Other Body of Knowled...
PPTX
Oct 2012 Presentation for Agile NJ
PPTX
Scaling lean agile agile prage 2014 (armani)
PDF
IMPLEMENTATION OF SCALED AGILE AND DEVOPS
PPTX
PMI-ACP Domain 1 Agile Principles and Mindset
PPTX
Large Scale Agile Transformation in Government: Field report
PDF
Lean - Tight Oil Design & Construction
PPT
Kristian Fischer - Put Test in the Driver's Seat
PDF
Scrum, Kanban, and DevOps Sitting in a Tree… - Big Apple Scrum Day 2018
PPT
SAP Cutover Strategy with details becomes Cutover Kickoff)
PPTX
Scaling Agile with Subwaymapping
PPTX
Introduction to Scaling agile and a Subwaymap
PDF
The Kanban Retrospective
PDF
Project Management Controlling And Monitoring PowerPoint Presentation Slides
PDF
Elective Care Conference: using the IST capacity and demand tool
PDF
Project Management Controlling And Monitoring Powerpoint Presentation Slides
KANBAN AT SCALE: A SIEMENS HEALTH SERVICES CASE STUDY (BENNET VALLET & DAN VA...
Introduction to SAFeMSIS CoreFall 2019Scenario –.docx
A kanban scrum mashup to deliver fp projects
How do develop Tminus maps for Software development
"Making Scrum "More" Effective : What can we learn from Other Body of Knowled...
Oct 2012 Presentation for Agile NJ
Scaling lean agile agile prage 2014 (armani)
IMPLEMENTATION OF SCALED AGILE AND DEVOPS
PMI-ACP Domain 1 Agile Principles and Mindset
Large Scale Agile Transformation in Government: Field report
Lean - Tight Oil Design & Construction
Kristian Fischer - Put Test in the Driver's Seat
Scrum, Kanban, and DevOps Sitting in a Tree… - Big Apple Scrum Day 2018
SAP Cutover Strategy with details becomes Cutover Kickoff)
Scaling Agile with Subwaymapping
Introduction to Scaling agile and a Subwaymap
The Kanban Retrospective
Project Management Controlling And Monitoring PowerPoint Presentation Slides
Elective Care Conference: using the IST capacity and demand tool
Project Management Controlling And Monitoring Powerpoint Presentation Slides

More from Michael J Geiser (16)

PPTX
AWS Cost Reduction and Management Plan
PPTX
2018 staffing strategy
DOCX
Response on Proposal for Converting to a Gated Community
DOCX
Skeptical Inquirer Content Problems
DOCX
Problems with Password Change Lockout Periods in Password Policies
PPTX
1967 lincoln continental convertible restoration v4
DOCX
Minimum Viable Product (MVP) – “Like This / Not Like This” Redux (MVP) – “Lik...
PPTX
Agile humor for slides
DOCX
Choosing an IdM User Store technology
PPTX
Maturing Agile SDLC & workflow improvements
PPTX
Introduction to the WSO2 Identity Server &Contributing to an OS Project
PPTX
Jira workflow for documentation issue types agile edition
PPTX
Apigee dc failover
PPTX
Using JIRA to Manage Project Management Risks and Issues
PPTX
Approvals in jira
PDF
Girl Scout Cookie Sale Posters
AWS Cost Reduction and Management Plan
2018 staffing strategy
Response on Proposal for Converting to a Gated Community
Skeptical Inquirer Content Problems
Problems with Password Change Lockout Periods in Password Policies
1967 lincoln continental convertible restoration v4
Minimum Viable Product (MVP) – “Like This / Not Like This” Redux (MVP) – “Lik...
Agile humor for slides
Choosing an IdM User Store technology
Maturing Agile SDLC & workflow improvements
Introduction to the WSO2 Identity Server &Contributing to an OS Project
Jira workflow for documentation issue types agile edition
Apigee dc failover
Using JIRA to Manage Project Management Risks and Issues
Approvals in jira
Girl Scout Cookie Sale Posters

Recently uploaded (20)

PPTX
artificial intelligence overview of it and more
PPTX
Introuction about WHO-FIC in ICD-10.pptx
PDF
Slides PDF The World Game (s) Eco Economic Epochs.pdf
PPTX
Mathew Digital SEO Checklist Guidlines 2025
PPTX
PptxGenJS_Demo_Chart_20250317130215833.pptx
PDF
An introduction to the IFRS (ISSB) Stndards.pdf
PPT
Design_with_Watersergyerge45hrbgre4top (1).ppt
PPTX
June-4-Sermon-Powerpoint.pptx USE THIS FOR YOUR MOTIVATION
PPT
FIRE PREVENTION AND CONTROL PLAN- LUS.FM.MQ.OM.UTM.PLN.00014.ppt
PDF
Best Practices for Testing and Debugging Shopify Third-Party API Integrations...
PDF
The New Creative Director: How AI Tools for Social Media Content Creation Are...
PPTX
Job_Card_System_Styled_lorem_ipsum_.pptx
PPT
isotopes_sddsadsaadasdasdasdasdsa1213.ppt
PDF
Smart Home Technology for Health Monitoring (www.kiu.ac.ug)
PDF
Introduction to the IoT system, how the IoT system works
PDF
WebRTC in SignalWire - troubleshooting media negotiation
PPTX
presentation_pfe-universite-molay-seltan.pptx
PPTX
Slides PPTX World Game (s) Eco Economic Epochs.pptx
PPTX
E -tech empowerment technologies PowerPoint
PPTX
SAP Ariba Sourcing PPT for learning material
artificial intelligence overview of it and more
Introuction about WHO-FIC in ICD-10.pptx
Slides PDF The World Game (s) Eco Economic Epochs.pdf
Mathew Digital SEO Checklist Guidlines 2025
PptxGenJS_Demo_Chart_20250317130215833.pptx
An introduction to the IFRS (ISSB) Stndards.pdf
Design_with_Watersergyerge45hrbgre4top (1).ppt
June-4-Sermon-Powerpoint.pptx USE THIS FOR YOUR MOTIVATION
FIRE PREVENTION AND CONTROL PLAN- LUS.FM.MQ.OM.UTM.PLN.00014.ppt
Best Practices for Testing and Debugging Shopify Third-Party API Integrations...
The New Creative Director: How AI Tools for Social Media Content Creation Are...
Job_Card_System_Styled_lorem_ipsum_.pptx
isotopes_sddsadsaadasdasdasdasdsa1213.ppt
Smart Home Technology for Health Monitoring (www.kiu.ac.ug)
Introduction to the IoT system, how the IoT system works
WebRTC in SignalWire - troubleshooting media negotiation
presentation_pfe-universite-molay-seltan.pptx
Slides PPTX World Game (s) Eco Economic Epochs.pptx
E -tech empowerment technologies PowerPoint
SAP Ariba Sourcing PPT for learning material

Agile Progress Tracking and Code Complete Date Estimation

  • 1. Agile Scheduling and Release Planning Michael Geiser
  • 2. What Do We Want to Accomplish? • This presentation proposes (within an Agile SDLC) • How to estimate a code complete date for development to plan a software release date. • How to track progress towards the code complete date • Present examples Executive Sponsor statuses slides so you can provide a clear concise status that communicates your message to Senior Management • Use the same artifacts to clearly see that you are on-track or off-track and how the project is trending so we can see if a mitigation plan is needed
  • 3. Assumptions/Facts • Scrum, as codified in the Agile Manifesto, is one of the most successful Software Development approaches/methodologies for small independent teams and can be scaled to large distributed teams. • Leaders in the field (Scott Ambler, Mike Cottmeyer, VersionOne, Thoughtworks…) recognize that the Agile Manifesto has limitations when applied to “Large Scale” Agile development efforts • Having many scrum teams in an enterprise does not mean you are doing Enterprise Agile • Single Team-level Agile practices are different from multiple-team Agile practices at scale • Agile at scale requires a broader set of tools and techniques
  • 4. Project Timeline Slides and Missed Schedule Milestones • Changes in scope are inevitable (not referring to scope creep which is controllable). Agile addresses fact of life FAR better than any other SDLC. Inaccurate Effort and Capacity Estimates • Estimates made before work started are often an order of magnitude off and need to you constantly consider the effect Scope changes. • Completed work and informed revised estimates should continually revise code complete estimates. Inability to Objectively and Independently assess project status • Tracking software development in MS Project is problematic and relies on how he Percent Complete entries are made. • This often leads to Executive Sponsors getting an overly-optimistic view of progress PMO Basics • If we’re not continually and meaningfully measuring the actual status of the project, how do we know we’re on track or need a mitigation plan? • We should use templates across projects and with all Executive Sponsors to that we consistently report and minimize the effort to report and maximize transparency Agile Project Management Pain Points
  • 5. Waterfall and Scrum Differences • In Waterfall SDLCs, SOP is that schedules and scope are defined often with little Development input and Development is told to “work longer to get just the work done”. • We know how well that worked out in the past… • Scrum (“Textbook Orthodox Scrum” not SAFe or others) swings the pendulum too far in the opposite direction. • “It’s done when it’s done” and “You can’t have release dates” are just as or even more unrealistic • The organization doesn’t exist to server Development (as nice as that sounds) • It’s also very “anti-Agile” because it doesn’t meet the needs of stakeholders
  • 7. Release Tracking Chart The Release Tracking Chart tracks the Scope, Development Plan, Sprint Plan, and Actual Work completed on a single chart that is always available and always reviewed in Executive Sponsor Status Meetings Scope: • The Scope and the effort to complete scope constantly changes during a project; normally some scope is added or removed and progressive elaboration gives us increasing more precise estimations of total effort and code complete dates. • Good Change Management processes for scope is stile vital in Agile; embracing change in Agile does not mean accepting any change without understanding and recognizing the impact of the change. Scope should reflect accepted changes by the product owner. • Agile teams should communicate scope and scope changes to recognize schedule risks so they can take action early enough when needed. Development Plan: • Estimated project work that can be completed according to Staffing Plan is charted to compare to Scope and to project a code complete date. Sprint Plan: • This should track to the Development Plan but reflects the actual Staff capacity and highlights immediately when the Development plan is or is not being met so remediation plans can be implemented early when needed Actual Work: • Shows work completed against Scope, the Development and Sprint Plans. It is transparently communicated when Actual Work completed and total scope are not on plan to met for the target code complete date
  • 8. Release Tracking Chart • Take care that the chart and table are consistent across all Status meetings • Include 3 slides in the Executive Sponsor Status Meeting deck: • Last meeting’s actual status • This meeting’s actual status • Next meeting’s plan • Being able to move between these three slides and see the change over 6 weeks is an extremely effective way to present this information. • I sometimes put the current slide in the main Status section and put the three in Appendix Material (know your audience) • The next 7 slides demonstrate this concept.
  • 9. Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul Scope +25% 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 968.75 Scope 775 775 775 775 775 775 775 775 775 775 775 775 775 Scope -25% 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 581.25 Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645 Iteration Plan Actual Completed 0 0 0 0 0 0 0 0 0 0 0 0 0 Notes • Your Development Plan must overshoot your Scope in the last few sprints to account for backlog scarcity near the end of the project and project closeout activities. This Dev Plan doesn’t even come close to that goal. • I would put the Project Schedule at Yellow trending Red at this point. Sprint 1 - Start Actual numbers in Black, projected numbers in red
  • 10. Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul Scope +25% 958.75 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25 886.25 Scope 775 725 725 725 725 725 725 725 725 725 725 725 725 Scope -25% 591.25 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75 563.75 Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645 Iteration Plan 45 100 Actual 40 85 Completed 40 80 80 80 80 80 80 80 80 80 80 80 80 Notes • Scope Refinement reduces Schedule Risk moderately but Schedule is still Yellow. I would eliminate the Trending Red modifier but to early to say Trending Green Sprint 2 - End
  • 11. Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul Scope +25% 958.75 886.25 813.75 803.75 760 760 760 760 760 760 760 760 760 Scope 775 725 675 675 650 650 650 650 650 650 650 650 650 Scope -25% 591.25 563.75 536.25 546.25 540 540 540 540 540 540 540 540 540 Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645 Iteration Plan 45 100 150 185 220 Actual 40 85 120 160 210 Completed 40 80 120 160 210 210 210 210 210 210 210 210 210 Notes • Schedule almost Green but Iteration Plan and Actual Work Completed is not Meeting Plan; Mitigation Plan still needed. Observe the “Uncertainty Range” of the Scope is getting progressively narrow. Completed Scope has an uncertainty of 0%; you know exactly how long it took to complete. Uncertainty ranges show the complexity range of uncompleted work. Sprint 5 - End
  • 12. Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul Scope +25% 958.75 886.25 813.75 803.75 760 790 742.5 742.5 742.5 742.5 742.5 742.5 742.5 Scope 775 725 675 675 650 680 650 650 650 650 650 650 650 Scope -25% 591.25 563.75 536.25 546.25 540 570 557.5 557.5 557.5 557.5 557.5 557.5 557.5 Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645 Iteration Plan 45 100 150 185 220 265 315 Actual 40 85 120 160 210 240 280 Completed 40 80 120 160 210 240 280 280 280 280 280 280 280 Notes • Sprint Velocity is predictable but less than Development Plan. Schedule is Yellow Trending Red. • Corrective Action must be taken or project will fail to meet schedule: A decision must be made to reduce Scope, lengthen Schedule or add Resources to finish by June 1. Decision Made: Current Scope is needed for MVP and Schedule will be kept; Resources will be added to balance Sprint 7 - End
  • 13. Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul Scope +25% 958.75 886.25 813.75 803.75 760 790 742.5 733.75 718.75 718.75 718.75 718.75 718.75 Scope 775 725 675 675 650 680 650 655 660 660 660 660 660 Scope -25% 591.25 563.75 536.25 546.25 540 570 557.5 576.25 601.25 601.25 601.25 601.25 601.25 Dev Plan 45 95 145 195 245 295 345 395 445 495 545 595 645 Iteration Plan 45 100 150 185 220 265 315 370 440 Actual 40 85 120 160 210 240 280 340 425 Completed 40 80 120 160 210 240 280 340 425 425 425 425 425 Notes • Velocity increases as additional Resources engage and begin “norming” with the team. Sprint 9 - End
  • 14. Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 Sprint Close 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul Scope +25% 958.75 886.25 813.75 803.75 760 790 742.5 733.75 718.75 698.75 690 690 690 Scope 775 725 675 675 650 680 650 655 660 660 670 670 670 Scope -25% 591.25 563.75 536.25 546.25 540 570 557.5 576.25 601.25 621.25 650 650 650 Dev Plan 45 95 145 195 245 295 345 395 445 505 565 625 685 Iteration Plan 45 100 150 185 220 265 315 370 440 510 580 Actual 40 85 120 160 210 240 280 340 425 505 590 Completed 40 80 120 160 210 240 280 340 425 505 590 590 590 Notes • Development Plan updated to reflect increased Velocity and Scope changes (The “Dev Plan” line bends upward) • Schedule Yellow Trending Green or Green Trending Yellow; Development Plan must overshoot Total Scope in the last few sprints to account for Backlog scarcity near the end of the project and project closeout activities (there’s the real world creeping into your Dev Plan again!) Sprint 11 - End
  • 15. Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul Scope +25% 958.75 886.25 813.75 803.75 760 790 742.5 733.75 718.75 698.75 690 675 665 Scope 775 725 675 675 650 680 650 655 660 660 670 670 665 Scope -25% 591.25 563.75 536.25 546.25 540 570 557.5 576.25 601.25 621.25 650 665 665 Dev Plan 45 95 145 195 245 295 345 395 445 505 565 625 685 Iteration Plan 45 100 150 185 220 265 315 370 440 510 580 650 720 Actual 40 85 120 160 210 240 280 340 425 505 590 650 665 Completed 40 80 120 160 210 240 280 340 425 505 590 650 665 Notes • It is recommended to plan on a “Hardening Sprint”, which would be Sprint 14 in this example, to finish and refactor as needed and to finalized non-functional requirements like performance and other “end-to-end” testing that are hard or impossible to do until code complete Sprint 13 - End
  • 17. Classic Cone of Uncertainty • What is the “Cone of Uncertainty”? • The cumulative uncertainty of the scope and effort for a project and it’s reduction over the course of a project • In most common definitions, it is an artifact of the Waterfall project start up approach • Relatively course-grained estimates are done based on knowledge of scope and capacity during early planning • These rough estimates are often used to determine a target release date • The development window is determined either from backing into the release date or based on historical data of development pace • The project timeline is locked down using these estimates
  • 18. Classic Cone of Uncertainty Diagram
  • 19. Problems with the Classic Cone of Uncertain Diagram • The over/under on the Accuracy of Estimates is interesting but we need to know while the project is in flight how the accuracy of estimates affects when the work will actually be done. • The “Classic” Cone of Uncertainty diagram is (IMHO) a seriously flawed representation of the concept and not useful at all. • The 1.00x level of Accuracy of Estimates on the y axis is reached at the end of the project. The graph gives the impression we had the estimate dead on at the start and are just eliminating the buffer. • The x axis needs to show when the project will be done as the metric of interest. • Completing work, Progressive Elaboration and Rolling Wave Planning over a project lifetime narrows the range of estimation uncertainty; it is a continual process not the event based changes shown in the diagram. This diagram has no useful information or value
  • 20. Code Complete Date Refinement – Improved • The useful Project Management graph is a Target Code Complete Date “Cone of Uncertainty“ • This graph allows action to be taken to affect the target completion date (remove scope, add resources) or to accurately set expectation of shareholders and downstream teams (Release Management) • Graph the right (actionable) information • A useful graph for in-flight projects needs to show the impact of Change Requests, refinement, velocity and total scope on the finish date • Mitigation plans can only be implemented if you know there is a likelihood and impact of risk to the target date • The right graph needs the right axes • The x axis is time • The y axis is total scope • Need to know Velocity • The estimated speed of development per iteration is needed • Collect the data at the right time • Update the graph at the end of each iteration or on key events (i.e. Scope Changes, staff crises) • Overlay the estimated completion date range (the uncertainty of the date) • Like managing risk, the uncertainty needs to decrease over time and reach a single target date as soon as possible
  • 21. Code Complete Date Chart Q: “Why have this chart too when I have the excellent Release Tracking Chart?” A: Complexity and Clarity • These two charts have two entirely different purposes and combining them would be confusing • The x-intercept of the Code Complete Chart is a key feature of the chart, you wouldn’t get the same clear picture from a combined chart • The Release Tracking Chart does give you a Code Complete date, but this chart vital for reporting results of Change Control Meetings whereas the Release Tracking Chart would not be useful.
  • 22. Code Complete Date Chart • Take care that the chart and table are consistent across all Status meetings • Include 3 slides in the Executive Sponsor Status Meeting deck: • Last meeting’s actual status • This meeting’s actual status • Next meeting’s plan • Being able to move between these three slides and see the change over 6 weeks is an extremely effective way to present this information. • I sometimes put the current slide in the main Status section and put the three in Appendix Material (know your audience) • The next 6 slides demonstrate how to use this tool.
  • 23. Notes • Initial Scope (with uncertainty) is between 581 and 969 Story Point and will take between 9 and 14 Sprints • Initial Target Code Complete date is 17 June. This date is very much “At Risk”. Sprint 1 - Start Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul Est Scope +25% 968.75 893.75 818.75 743.75 668.75 593.75 518.75 443.75 368.75 293.75 218.75 143.75 68.75 -6.25 Est Scope Remaining 775 700 625 550 475 400 325 250 175 100 25 -50 -125 -200 Est Scope -25% 581.25 506.25 431.25 356.25 281.25 206.25 131.25 56.25 -18.75 0 0 0 0 0 Velocity 75 75 75 75 75 75 75 75 75 75 75 75 75 75 Approved Scope change 0 0 0 0 0 0 0 0 0 0 0 0 0 0
  • 24. Notes • Velocity in Sprints 2 and 3 were less than Sprint 1 and below the initial estimate • Scope changes can be from PO changes to the Backlog, the elimination of duplicate User Stories or refinement of User Story estimates • Range of Code Complete has reduced but 17 June Code Complete date is still At-Risk Sprint 3 - End Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul Est Scope +25% 968.75 843.75 768.75 708.75 633.75 558.75 483.75 408.75 333.75 258.75 183.75 108.75 33.75 -41.25 Est Scope Remaining 775 675 615 555 480 405 330 255 180 105 30 -45 -120 -195 Est Scope -25% 581.25 506.25 461.25 401.25 326.25 251.25 176.25 101.25 26.25 0 0 0 0 0 Velocity 75 70 60 75 75 75 75 75 75 75 75 75 75 75 Approved Scope change -25 10 0 0 0 0 0 0 0 0 0 0 0 0
  • 25. Notes • Velocity is on average close to estimate in Burndown in this example • The Code Complete date range is now much more narrow • Target Code Complete of 17 June is now after the range of Code Complete dates (but there is still no buffer) • Code Complete estimated date is between 20 May and 17 June (3 June is most likely based on graph) Sprint 6 - End Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul Est Scope +25% 968.75 843.75 768.75 693.75 531.25 437.5 367.5 292.5 217.5 142.5 67.5 -7.5 -82.5 -157.5 Est Scope Remaining 775 675 615 555 425 350 272 197 122 47 -28 -103 -178 -253 Est Scope -25% 581.25 506.25 461.25 416.25 318.75 262.5 192.5 117.5 42.5 0 0 0 0 0 Velocity 75 70 60 80 70 70 75 75 75 75 75 75 75 75 Approved Scope change -25 10 0 -50 -5 -8 0 0 0 0 0 0 0 0
  • 26. Notes • The uncertainty of Code Complete is minimal and there is almost an entire sprint buffer between the latest Code Compete date and the 17 June target • Almost certain that Code Complete will be the end of the 3 June Sprint at this point Sprint 9 - End Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul Est Scope +25% 968.75 843.75 768.75 693.75 531.25 425 327.5 246.25 156.25 81.25 6.25 -68.75 -143.75 -218.75 Est Scope Remaining 775 675 615 555 425 340 262 197 125 50 -25 -100 -175 -250 Est Scope -25% 581.25 506.25 461.25 416.25 318.75 255 196.5 147.75 93.75 18.75 0 0 0 0 Velocity 75 70 60 80 80 70 80 80 75 75 75 75 75 75 Approved Scope change -25 10 0 -50 -5 -8 15 8 0 0 0 0 0 0
  • 27. Notes • It is an important principle of Agile that we be open to change in scope at any time. This doesn’t mean that the Product Owner and Stakeholders have free reign to make any changes with consequences; the “Iron Triangle” concepts still apply. • The effect of the change at this point on the Release Date is obvious: If the scope change is accepted, the schedule change of adding two additional Sprints also must be accepted (at this late stage, it is unlikely we could add resources to cover the scope change). Sprint 9 – What if we add another 100 days of scope at the start of Sprint 9? Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul Est Scope +25% 968.75 843.75 768.75 693.75 531.25 425 327.5 246.25 277.5 202.5 127.5 52.5 -22.5 -97.5 Est Scope Remaining 775 675 615 555 425 340 262 197 222 147 72 -3 -78 -153 Est Scope -25% 581.25 506.25 461.25 416.25 318.75 255 196.5 147.75 166.5 91.5 16.5 -58.5 -133.5 -208.5 Velocity 75 70 60 80 80 70 80 80 75 75 75 75 75 75 Approved Scope change -25 10 0 -50 -5 -8 15 108 0 0 0 0 0 0
  • 28. Notes Code Complete Sprint 11 – End (Code Complete) Sprint 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Sprint Close Date 14-Jan 28-Jan 11-Feb 25-Feb 11-Mar 25-Mar 8-Apr 22-Apr 6-May 20-May 3-Jun 17-Jun 1-Jul 15-Jul Est Scope +25% 968.75 843.75 768.75 693.75 531.25 425 327.5 246.25 156.25 81.25 0 0 0 0 Est Scope Remaining 775 675 615 555 425 340 262 197 125 50 0 0 0 0 Est Scope -25% 581.25 506.25 461.25 416.25 318.75 255 196.5 147.75 93.75 18.75 0 0 0 0 Velocity 75 70 60 80 80 70 80 80 75 80 0 0 0 0 Approved Scope change -25 10 0 -50 -5 -8 15 8 0 5 0 0 0 0