Air quality control system: De-Sox Projects & De-Nox Projects
1. AIR QUALITY
CONTROL
SYSTEM (AQCS)
PROJECT STORIES
De-Sox Projects
De-Nox Projects
1. Orot Rabin Unit 5 & 6 FGD Add-on (Israel)
2. Yongheung Unit 1 & 2 FGD Add-on (Korea)
3. Shinboryeong Unit 1 & 2 FGD Add-on (Korea)
4. ShinSeochon FGD Add-on (Korea)
1. Castle Peak TPP Emission Control (Hong Kong)
1.1 Summary
1.2 Detailed Scope of Work
1.3 Field Work
2. Ratcliffe SCR Add-on (UK)
2.1 Summary
2.2 Detailed Scope of Work
2.3 Field Work
Copyright by Doosan Heavy Industries & Construction Co., Ltd. All Rights Reserved.
2. DOOSAN POWER SERVICES
PROJECT STORIES DE-SOX PROJECTS
1.0 Orot Rabin Unit 5 & 6 FGD Add-on (Israel)
PROJECT OVERVIEW
PLANT LOCATION
Hadera, Israel
Plant
Information
∙ Plant Type
∙ Capacity
∙ Fuel
Subcritical
575MW x 2
Coal (1.12% Sulfur)
∙
FGD on a turn-key basis with equipment as follows:
- Absorbers island
- Reagent preparation system, WWTP
- Limestone gypsum handling system
- Gypsum dewatering system
- Electrical, instrumentation and control
- Flue gas ductwork, piping
∙ FGD specifications
Scrubbing reagent Limestone
Capacity 2,887,896Am3
/h
Inlet SO2 785ppm
SO2 removal efficiency
95.55%
SO2: 100mg/Nm3
No. of absorber 1 per boiler
No. of spray level 3+1
Scope of
Supply
PJT title
Orot Rabin Unit 5 6 FGD Add-on
Client
IEC (Israel Electric Corporation)
Contract year
2010
Installation
3. DOOSAN POWER SERVICES
PROJECT STORIES DE-SOX PROJECTS
2.0 Yongheung Unit 1 2 FGD Add-on (Korea)
PROJECT OVERVIEW
PLANT LOCATION
Yongheung, Korea
Plant
Information
∙ Plant Type
∙ Capacity
∙ Fuel
Subcritical
800MW x 2
Coal (1.0% Sulfur)
∙
FGD on a turn-key basis with equipment as follows:
- Absorber, GGH
- Limestone gypsum handling, WWTP
- Reagent preparation gypsum dewatering
- Electrical, Instrumentation and control
- Buildings
∙ FGD specifications
Scrubbing reagent Limestone
Capacity 3,667,200Am3
/h
Inlet SO2 429ppm
SO2 removal efficiency
94.5%
Dust: 20mg/Sm3, SOx: 25ppm
No. of absorber 1 per boiler
No. of spray level 3+1
Scope of
Supply
PJT title
Yongheung Unit 1 2 FGD Add-on
Client
KOSEP
Contract year
2002
Installation
4. DOOSAN POWER SERVICES
PROJECT STORIES DE-SOX PROJECTS
3.0 Shinboryeong Unit 1 2 FGD Add-on (Korea)
PROJECT OVERVIEW
PLANT LOCATION
Shinboryeong, Korea
Installation
Plant
Information
∙ Plant Type
∙ Capacity
∙ Fuel
Ultra supercritical
1,000MW x 2
Coal (1.3% Sulfur)
∙
FGD on a turn-key basis with equipment as follows:
- Absorber, GGH
- Limestone gypsum handling, WWTP
- Reagent preparation gypsum dewatering
- Electrical, instrumentation and control
- Buildings
∙ FGD specifications
Scrubbing Reagent Limestone
Capacity 5,329,786Am3
/h
Inlet SOx 1,114ppm
SOx Removal Efficiency
95.5%
Dust: 15mg/Sm3, SOx: 50ppm
No. of Absorber 1 per boiler
No. of Spray level 4+1
Scope of
Supply
PJT title
Shinboryeong Unit 1, 2 FGD Add-on
Client
KOMIPO
Contract year
2013
5. DOOSAN POWER SERVICES
PROJECT STORIES DE-SOX PROJECTS
4.0 ShinSeochon FGD Add-on (Korea)
PROJECT OVERVIEW
PLANT LOCATION
ShinSeochon, Korea
Installation
Plant
Information
∙ Plant Type
∙ Capacity
∙ Fuel
Ultra supercritical
1,000MW x 1
Coal (1.01% Sulfur)
∙ FGD on a turn-key basis with equipment as follows:
- Absorber, non-leakage GGH
- Limestone gypsum handling, WWTP
- Reagent preparation gypsum dewatering
- Electrical, instrumentation and control
- Buildings
∙ FGD specification
Scrubbing Reagent Limestone
Capacity 5,489,880Am3
/h
Inlet SOx 1,191ppm
SOx Removal Efficiency
98.7%
Dust: 3mg/Sm3, SOx: 15ppm
No. of Absorber 1 per boiler
No. of Spray level 4+1
Scope of
Supply
PJT title
ShinSeochon FGD Add-on
Client
KOMIPO
Contract year
2018
6. DOOSAN POWER SERVICES
PROJECT STORIES DE-NOX PROJECTS | CASTLE PEAK TPP EMISSION CONTROL (HONG KONG)
5.1 Castle PeakTPP Emission Control (Hong Kong)
PROJECT OVERVIEW
PLANT LOCATION
PJT title
CP Emission Control Project
Client
China Light Power (CLP)
Contract year
2007
PJT period
2007-2010
Tuen Mun NT, Hong Kong
Plant
Information
∙ Contractor
∙ Boiler OEM
∙ Plant Type
∙ Capacity
∙ Boiler
∙ COD
Doosan Babcock
BPL
Coal-fired
660MWe x 4 (B Station)
Subcritical, wall-fired PC boiler
1986
∙ Emission reduction (NOx)
∙ Life extension
Customer
Needs
∙
Boosted over fired air (BOFA) for all four units on an EPC basis
(330m of duct, 600t additional steel)
∙
Optimized selective catalytic reduction (OSCR) for all four units on an
EPC basis
- SCR civils
- SCR mechanical
- SCR ECI
- Ammonia injection grid
- Urea storage system
- Feed water piping modifications
- Air heater cold end element upgrade and new sealing system
∙
Reducing NOX emissions by 75% through the combination of BOFA and
OSCR
∙
Extending lifetime of existing plants
Scope of
Supply
Customer
Benefits
7. DOOSAN POWER SERVICES
PROJECT STORIES DE-NOX PROJECTS | CASTLE PEAK TPP EMISSION CONTROL (HONG KONG)
5.2 DetailedScope of Work
Project Objectives
Detailed Work Scope
•NOx emissions reduction of 75%
•High availability and flexibility of operations
•Proven technology and robust design
•No losses of boiler efficiency
•EPC for boosted over fire air (BOFA) system
- Design, fabrication, installation and construction
- BOFA fans including civils
- BOFA ducting
- BOFA ports and pressure part modifications
- Upgrade to DCS
•EPC for selective catalytic reduction (SCR)
- Design, fabrication and installation of an in-duct
- Civil for support structure
- SCR mechanical work
- ECI for SCR
- Ammonia injection grid
- Urea storage system
- Feedwater piping modifications
•Air heater cold end element upgrade and new sealing system
•Economizer outlet flue gas ducting retrofit
BOX DUCTING DESIGN
ECONOMIZER GAS OUTLET DUCT DESIGN
Inlet
AIG
Expansion vanes
Straightening vanes
AH flange
Catalyst
GSG
Mixer
Turning vanes
Lower tubes
8. DOOSAN POWER SERVICES
PROJECT STORIES DE-NOX PROJECTS | CASTLE PEAK TPP EMISSION CONTROL (HONG KONG)
5.3 Field Work
∙Removal of cladding and lagging
∙ Dismantling of the horizontal section of the economizer outlet by
removing panels
∙ The dismantling of the economizer outlet downward leg began with
panel removal at the top flange of the heat exchanger, then working on
the upward leg
∙ Corner sections of the ducting were kept in place until all the panel had
been removed
∙ Cross member and stiffener removal throughout
∙Installation of a new SCR support beam
∙Removal of the structural I beam
∙Relocation (750mm) of the structural I beam
∙ Fabricated and installed associated bracings
1 Dismantling of the Economizer Outlet 2 Modification of the Structural Beam
Relocation of
economizer outlet
beam (750mm)
New SCR
supporting beam
Position of removed
structural beam
Bracing removal
Panel removal
9. DOOSAN POWER SERVICES
PROJECT STORIES DE-NOX PROJECTS | CASTLE PEAK TPP EMISSION CONTROL (HONG KONG)
5.3 Field Work
∙ 12 expansion vanes were erected
from both ‘A’ and ‘B’ sides
∙ Held in position by using expansion
vane support tubes
∙ 3 sections were erected separately,
then welded into position
∙Installed before the inlet roof panels
∙ Lifted into place using runway beams,
with a crane on standby
∙ Panels were erected from both ‘A’ and
‘B’ sides
∙ Commenced after intermediate
beams were erected
∙ The process began at the lower levels,
then progressed upwards
∙ Alignment and seal welding were
required
3 Expansion Vanes 4 Static Mixer 5 Erection of the Reactor Panel
1st section of
the static mixer
Temporary
guide beams
Panel 1
10. DOOSAN POWER SERVICES
PROJECT STORIES DE-NOX PROJECTS | CASTLE PEAK TPP EMISSION CONTROL (HONG KONG)
5.3 Field Work
∙ 1 section of economizer outlet rear was removed to enable the
turning vanes to be lifted in
∙5 sonic horns for each reactor
∙Relatively inexpensive compared to soot blowers
- Lower OM costs
-
The capital costs for sonic horns are 25% of those for
soot blowers
∙ Horns which can be operated on standard plant
compressed air
∙Small bore piping is rated for standard 70 to 90 psi
∙Frequent cycle keeps catalyst clean
6 Turning Vanes Ammonia Injection Grid (AIG) 7 Sonic Horns
11. DOOSAN POWER SERVICES
PROJECT STORIES DE-NOX PROJECTS | CASTLE PEAK TPP EMISSION CONTROL (HONG KONG)
5.3 Field Work
∙ Capacity: 120m3
∙ In order to ensure stability while the
facility was being erected, the urea
solutionizer tank, made of stainless
steel, was half-filled with water to
lower the center of gravity
∙ Supported by 8 load cells which
determine the concentration of urea
∙ Capacity: 114m3
each
∙Positioned with crane
∙ In order to ensure stability before the
steel support was being erected, the
urea solution storage tanks were half-
filled with water to lower the center of
gravity
∙ 2 2'' pipes from the tank farm
∙ Stainless steel
∙ Carries urea to and from the
decomposition chamber
8 AIG Storage: Urea Solutionizer Tank 9 AIGStorage:UreaSolutionStorageTanks 10 Ammonia Injection Grid (AIG)
12. DOOSAN POWER SERVICES
PROJECT STORIES DE-NOX PROJECTS | RATCLIFFE SCR ADD-ON (UK)
6.1 Ratcliffe SCR Add-on (UK)
PROJECT OVERVIEW
PLANT LOCATION
PJT title
Ratcliffe SCR Add-on
Client
E.ON / UK Plc
Contract year
2008
PJT period
5 years
Nottinghamshire, UK
Plant
Information
∙ Plant Type
∙ Capacity
∙ Boiler
∙ Turbine
∙ COD
Coal-fired
500MW x 4 Units
Subcritical, conventional drum type
TC3F – 3 Casings
1967
∙ Emission reduction (NOx)
∙ High availability and flexibility
Customer
Needs
∙
On-site service team
∙
Supplying new SCR to all four 500MW subcritical units
∙
Partial replacement of boiler pressure parts
∙
Supplying an air pollution control system
∙
Technical support by highly skilled service engineers – approximately
4,000 people on site – working in confined operational areas
∙
Annual installation completed during unit shutdown while other 3 units
being fully operational, without loss of boiler efficiency
∙
Building a strong, open contractual relationship which minimizes risk
on challenging retrofit project
∙
Achieving NOx emissions limit of 100mg/NM3 in steady state condition
∙
Extending the plant life for continuing operations at the power station
until the late 2020s
Scope of
Supply
Customer
Benefits
13. DOOSAN POWER SERVICES
PROJECT STORIES DE-NOX PROJECTS | RATCLIFFE SCR ADD-ON (UK)
6.2 DetailedScope of Work
Project Objectives
Detailed Work Scope
•Achieving NOx emissions limit of 100mg/NM3 in steady state condition.
•Achieving high availability and flexibility of operations at SCR units over 15 years
•No losses of boiler efficiency
•
All design, fabrication and construction work for 4 SCR units (8 reactor vessels)
at Ratcliffe Power Station including:
- Ammonia plant
- Fans, motors, damper and ductwork
- Ducting reactors (6,500 tons)
- SCR economizer pressure parts (1,600 tons)
- Piping valves (22,000m)
- Structural steel (7,500 tons)
- Dampers, expansion joints replacement
-
ID fan replacement, air heater modifications, ash handling system
modifications, insulation, sonic horns
- Specialist heavy lift crane
- Civil work (2,500m3
concrete)
- ECI work (Cabling 450km)
FLUES, REACTOR AND BYPASS DESIGN
14. DOOSAN POWER SERVICES
PROJECT STORIES DE-NOX PROJECTS | RATCLIFFE SCR ADD-ON (UK)
6.3 Field Work
∙ Design based on tied connection to the existing boiler house
structure
1 SCR Supporting Structure 2 Installation Work