Guidance to Bidders Asian Development Bank Procurement Guidelines
Asian Development Bank Procurement GuidelinesPurpose
Purpose Para 1. This appendix provides guidance to potential bidders wishing to participate in ADB-financed procurement.
Asian Development Bank Procurement GuidelinesResponsibility for Procurement
Responsibility for Procurement Para 2. The responsibility for the implementation of the project, and therefore for the payment of goods, works, and services under the project, rests solely with the borrower. ADB, for its part, is required by its Charter to ensure that funds are paid from ADB financing only as expenditures are incurred. Disbursements are made only at the borrower’s request.Supporting evidence that the funds are used in accordance with the financing agreement and/or the procurement plan shall be submitted with the borrower’s withdrawal application.
Responsibility for Procurement Para 2. Payment may be made to reimburse the borrower for payment(s) already made from its own resources, directly to a third party (usually to a supplier or contractor), orto a commercial bank for expenditures against a Commitment Letter covering a commercial bank’s letter of credit.As emphasized in paragraph 1.2 of the Guidelines, the borrower is legally responsible for the procurement. It invites, receives, and evaluates bids, and awards the contract. The contract is between the borrower and the supplier or contractor. ADB is not a party to the contract.
Asian Development Bank Procurement GuidelinesADB’s Role
ADB’s Role Para 3. As stated in paragraph 1.11 of the Guidelines, ADB reviews the procurement procedures, documents, bid evaluations, award recommendations, and the contract to ensure that the process is carried out in accordance with agreed procedures, as required in the financing agreement. In the case of major contracts, the documents are reviewed by ADB prior to their issue, as described in Appendix 1. Also, if, at any time in the procurement process (even after the award of contract), ADB concludes that the agreed procedures were not followed in any material respect, ADB may declare misprocurement, as described in paragraph 1.12.
ADB’s Role Para 3. However, if a borrower has awarded a contract after obtaining ADB’s “no objection,” ADB will declare misprocurement only if the “no objection” was issued on the basis of incomplete, inaccurate, or misleading information furnished by the borrower.Furthermore, if ADB determines that corrupt or fraudulent practices were engaged in by representatives of the borrower or of the bidder, ADB may impose the applicable sanctions set forth in paragraph 1.14 of the Guidelines.
ADB’s Role Para 4. ADB has published Standard Bidding Documents (SBDs) for various types of procurement. As stated in paragraph 2.12 of the Guidelines, it is mandatory for the borrower to use these documents, with minimum changes to address country- and project-specific issues. The prequalification and bidding documents are finalized and issued by the borrower.
Asian Development Bank Procurement GuidelinesInformation on Bidding
Information on Bidding Para 5. Information on bidding opportunities under ICB may be obtained from the general procurement notice and the specific procurement notices as described in paragraphs 2.7 and 2.8 of the Guidelines. General guidance on participation, as well as advance information on business opportunities in upcoming projects, may be obtained from the ADB website.
Asian Development Bank Procurement GuidelinesBidder’s Role
Bidder’s Role Para 6Once a bidder receives the prequalification or bidding document, the bidder should study the documents carefully to decide if it can meet the technical, commercial, and contractual conditions, and if so, proceed to prepare its bid. The bidder should then critically review the documents to see if there is any ambiguity, omission, or internal contradiction, or any feature of specifications or other conditions which are unclear or appear discriminatory or restrictive; if so, it should seek clarification from the borrower, in writing, within the time period specified in the bidding documents for seeking clarifications.
Bidder’s Role Para 7The criteria and methodology for selection of the successful bidder are outlined in the bidding documents, generally under Instructions to Bidders and Specifications. If these are not clear, clarification should be similarly sought from the borrower.
Bidder’s Role Para 8In this connection it should be emphasized that the specific bidding documents issued by the borrower govern each procurement, as stated in paragraph 1.1 of the Guidelines. If a bidder feels that any of the provisions in the documents are inconsistent with the Guidelines, it should also raise this with the borrower.
Bidder’s Role Para 9It is the responsibility of the bidder to raise any issue of ambiguity, contradiction, omission, etc., prior to the submission of its bid, to assure submission of a fully responsive and compliant bid, including all the supporting documents requested in the bidding documents. Noncompliance with critical (technical and commercial) requirements will result in rejection of the bid. If a bidder wishes to propose deviations to a noncritical requirement, or propose an alternative solution, the bidder should quote the price for the fully compliant bid and then separately indicate the adjustment in price that can be offered if the deviation is accepted. Alternative solutions should be offered only when authorized in the bidding documents. Once bids are received and publicly opened, bidders will not be required or permitted to change the price or substance of a bid.
Asian Development Bank Procurement GuidelinesConfidentiality
ConfidentialityPara 10As stated in paragraph 2.47 of the Guidelines, the process of bid evaluation shall be confidential until the publication of contract award. This is essential to enable the borrower and ADB reviewers to avoid either the reality or perception of improper interference. If at this stage a bidder wishes to bring additional information to the notice of the borrower, ADB, or both, it should do so in writing.
Asian Development Bank Procurement GuidelinesAction by ADB
Action by ADB Para 11Bidders are free to send copies of their communications on issues and questions with the borrower to ADB or to write to ADB directly, when borrowers do not respond promptly, or the communication is a complaint against the borrower. All such communications should be addressed to the project officer for the project, with a copy to the Principal Director, Central Operations Services Office.
Action by ADB Para 12References received by ADB from potential bidders, prior to the closing date for submission of the bids, will, if appropriate, be referred to the borrower with ADB’s comments and advice, for action or response.
Action by ADB Para 13Communication received from bidders after the opening of the bids, will be handled as follows. In the case of contracts not subject to prior review by ADB, the communication will be sent to the borrower for due consideration and appropriate action, if any, and these will be reviewed during subsequent supervision of the project by ADB staff. In the cases of contracts subject to the prior review process, the communication will be examined by ADB, in consultation with the borrower. If additional data is required to complete this process, these will be obtained from the borrower.
Action by ADB Para 13If additional information or clarification is required from the bidder, ADB will ask the borrower to obtain it and comment or incorporate it, as appropriate, in the evaluation report. ADB’s review will not be completed until the communication is fully examined and considered.
Action by ADB Para 14Except for acknowledgment, ADB will not normally enter into discussion or correspondence with any bidder during the evaluation and review process of the procurement, until award of the contract is published. Notwithstanding paragraph 14(a) above, ADB may enter into discussion where it deems necessary to conduct investigations, audit, evaluation or other assessments of the procurement process.
Asian Development Bank Procurement GuidelinesDebriefing
DebriefingPara 15As stated in paragraph 2.65, if, after notification of award, a bidder wishes to ascertain the grounds on which its bid was not selected, it should address its request to the borrower. If the bidder is not satisfied with the explanation given and wishes to seek a meeting with ADB, it may do so by writing the Principal Director, Central Operations Services Office, who will arrange a meeting at the appropriate level and with the relevant staff. In this discussion, only the bidder’s bid can be discussed and not the bids of competitors.
Appendix 3   guidance to bidders

More Related Content

PPTX
Wb appendix 3 guidance to bidders
PPTX
Adb procurement guidelines introduction1
PPTX
Wb consultant 1b
PPTX
Wb consultant 1a
PPTX
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
PPTX
Adb procurement guidelines icb-b1
PDF
Instructions to bidders
PPTX
Appendix 1 adb review of procurement decisions
Wb appendix 3 guidance to bidders
Adb procurement guidelines introduction1
Wb consultant 1b
Wb consultant 1a
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Adb procurement guidelines icb-b1
Instructions to bidders
Appendix 1 adb review of procurement decisions

What's hot (20)

PDF
Hitachi RFP for Janitorial FINAL
PPTX
Wb procurement icb c2
PPTX
Wb procurement icb a
PDF
Bid document for Solar in Himachal Pradesh
PDF
16 tender document khawaja fareed university 09112017
PDF
4. international procurement guideline
DOC
!Rfq 9119 13-7035 final draft for approval (jan 30)
PPTX
Tendering and Procurement Basics
PDF
The Law of Tendering
PPTX
Contemporary issues of banking law ppt
PDF
Ipds volume i.35-39
PDF
Business laws
PPTX
Procurement and Subcontractors
PDF
Tender and Bidding in Construction Projects
PDF
8287494393-DLF THE CREST - PAYMENT PLAN , SITE PLAN,FLOOR PLAN,EXTRA CHARGES
PPT
Law of contract introduction
PPT
Sbd procurement of goods section vii general conditions-2
PPT
Sbd procurement of goods section vii general conditions-1
DOCX
Report(1)
PPTX
Tendering & Procurement Overview
Hitachi RFP for Janitorial FINAL
Wb procurement icb c2
Wb procurement icb a
Bid document for Solar in Himachal Pradesh
16 tender document khawaja fareed university 09112017
4. international procurement guideline
!Rfq 9119 13-7035 final draft for approval (jan 30)
Tendering and Procurement Basics
The Law of Tendering
Contemporary issues of banking law ppt
Ipds volume i.35-39
Business laws
Procurement and Subcontractors
Tender and Bidding in Construction Projects
8287494393-DLF THE CREST - PAYMENT PLAN , SITE PLAN,FLOOR PLAN,EXTRA CHARGES
Law of contract introduction
Sbd procurement of goods section vii general conditions-2
Sbd procurement of goods section vii general conditions-1
Report(1)
Tendering & Procurement Overview
Ad

Viewers also liked (12)

DOC
Resume 2016
PPTX
Lviv GameDev Mixer Данило Сиротинський "Практичний досвід синхронізації ігор ...
ODP
Location
PPTX
Wb consultant 2a
PPTX
PDF
Introduction to Parasitology
PPTX
Experience from the FEW Workshop
PDF
Key innovative market trends for your policy administrative system
PPTX
Automation in clinical hematology
PDF
Πανελλήνιος Διαγωνισμός Φυσικής Α΄ Λυκείου 2005/ Θέματα και Λύσεις
PDF
Strategi i Sosiale medier for bedrift
PPTX
BMW Risk Management
Resume 2016
Lviv GameDev Mixer Данило Сиротинський "Практичний досвід синхронізації ігор ...
Location
Wb consultant 2a
Introduction to Parasitology
Experience from the FEW Workshop
Key innovative market trends for your policy administrative system
Automation in clinical hematology
Πανελλήνιος Διαγωνισμός Φυσικής Α΄ Λυκείου 2005/ Θέματα και Λύσεις
Strategi i Sosiale medier for bedrift
BMW Risk Management
Ad

Similar to Appendix 3 guidance to bidders (20)

PPTX
Adb procurement guidelines icb-c2
PPTX
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
PPTX
Adb procurement guidelines icb-b3
PPTX
Adb procurement guidelines icb-c1
PPT
Procurement operation delivery optimization
PPTX
Adb procurement guidelines introduction2
PPTX
Wb consultants 8
PPTX
Adb procurement guidelines icb-a
PPTX
Wb procurement icb b1
PPTX
3 other methods of procurement
PPTX
Adb procurement guidelines icb-d
PDF
procurement-price-adjustment.pdf
PPTX
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
DOC
BID DOCUMENT.doc
PPTX
Wb procurement other method-1
DOC
Pbd.goods
PPTX
Adb procurement guidelines icb-b2
PPTX
Wb appendix 1 review by the bank
PPTX
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
PDF
adb-bos-procurement-presentation-03-dec-20192.pdf
Adb procurement guidelines icb-c2
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Adb procurement guidelines icb-b3
Adb procurement guidelines icb-c1
Procurement operation delivery optimization
Adb procurement guidelines introduction2
Wb consultants 8
Adb procurement guidelines icb-a
Wb procurement icb b1
3 other methods of procurement
Adb procurement guidelines icb-d
procurement-price-adjustment.pdf
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
BID DOCUMENT.doc
Wb procurement other method-1
Pbd.goods
Adb procurement guidelines icb-b2
Wb appendix 1 review by the bank
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
adb-bos-procurement-presentation-03-dec-20192.pdf

More from Joy Irman (20)

PDF
Penjelasan atas peraturan presiden nomor 54 tahun 2010
PDF
Penjelasan atas peraturan presiden nomor 54 tahun 2010
PDF
Lampiran iv b jasa konsultansi - perorangan
PDF
Lampiran iv a jasa konsultansi - badan usaha
PDF
Consulting Services Operation Manual, Asian Development Bank
PDF
Guidelines for the Use of Consultants under Islamic Development Bank Financing
PDF
Guidelines for the Employment of Consultants under Japanese ODA Loans
PDF
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
PPT
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
PPT
12 konsep ramah lingkungan
PPT
13 pengadaan secara elektronik
PPT
6 1 persiapan dan perencanaan pengadaan
PPT
3 1 organisasi pengadaan
PPT
4 rencana umum pengadaan barang
PPT
5 2 pelaksanaan swakelola
PPT
5 1 ketentuan umum swakelola
PPT
3 7 penyedia barang jasa
PPT
3 6 pejabat penerima hasil pekerjaan
PPT
3 5 ulp pejabat pengadaan
PPT
3 4 pejabat pembuat komitmen
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv a jasa konsultansi - badan usaha
Consulting Services Operation Manual, Asian Development Bank
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
12 konsep ramah lingkungan
13 pengadaan secara elektronik
6 1 persiapan dan perencanaan pengadaan
3 1 organisasi pengadaan
4 rencana umum pengadaan barang
5 2 pelaksanaan swakelola
5 1 ketentuan umum swakelola
3 7 penyedia barang jasa
3 6 pejabat penerima hasil pekerjaan
3 5 ulp pejabat pengadaan
3 4 pejabat pembuat komitmen

Recently uploaded (20)

PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PDF
A Brief Introduction About Julia Allison
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
DOCX
Business Management - unit 1 and 2
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
IFRS Notes in your pocket for study all the time
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PPTX
Amazon (Business Studies) management studies
PDF
Laughter Yoga Basic Learning Workshop Manual
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
How to Get Business Funding for Small Business Fast
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
WRN_Investor_Presentation_August 2025.pdf
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
A Brief Introduction About Julia Allison
New Microsoft PowerPoint Presentation - Copy.pptx
Business Management - unit 1 and 2
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
IFRS Notes in your pocket for study all the time
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
Reconciliation AND MEMORANDUM RECONCILATION
DOC-20250806-WA0002._20250806_112011_0000.pdf
Principles of Marketing, Industrial, Consumers,
COST SHEET- Tender and Quotation unit 2.pdf
ICG2025_ICG 6th steering committee 30-8-24.pptx
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
Amazon (Business Studies) management studies
Laughter Yoga Basic Learning Workshop Manual
Belch_12e_PPT_Ch18_Accessible_university.pptx
How to Get Business Funding for Small Business Fast
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
WRN_Investor_Presentation_August 2025.pdf

Appendix 3 guidance to bidders

  • 1. Guidance to Bidders Asian Development Bank Procurement Guidelines
  • 2. Asian Development Bank Procurement GuidelinesPurpose
  • 3. Purpose Para 1. This appendix provides guidance to potential bidders wishing to participate in ADB-financed procurement.
  • 4. Asian Development Bank Procurement GuidelinesResponsibility for Procurement
  • 5. Responsibility for Procurement Para 2. The responsibility for the implementation of the project, and therefore for the payment of goods, works, and services under the project, rests solely with the borrower. ADB, for its part, is required by its Charter to ensure that funds are paid from ADB financing only as expenditures are incurred. Disbursements are made only at the borrower’s request.Supporting evidence that the funds are used in accordance with the financing agreement and/or the procurement plan shall be submitted with the borrower’s withdrawal application.
  • 6. Responsibility for Procurement Para 2. Payment may be made to reimburse the borrower for payment(s) already made from its own resources, directly to a third party (usually to a supplier or contractor), orto a commercial bank for expenditures against a Commitment Letter covering a commercial bank’s letter of credit.As emphasized in paragraph 1.2 of the Guidelines, the borrower is legally responsible for the procurement. It invites, receives, and evaluates bids, and awards the contract. The contract is between the borrower and the supplier or contractor. ADB is not a party to the contract.
  • 7. Asian Development Bank Procurement GuidelinesADB’s Role
  • 8. ADB’s Role Para 3. As stated in paragraph 1.11 of the Guidelines, ADB reviews the procurement procedures, documents, bid evaluations, award recommendations, and the contract to ensure that the process is carried out in accordance with agreed procedures, as required in the financing agreement. In the case of major contracts, the documents are reviewed by ADB prior to their issue, as described in Appendix 1. Also, if, at any time in the procurement process (even after the award of contract), ADB concludes that the agreed procedures were not followed in any material respect, ADB may declare misprocurement, as described in paragraph 1.12.
  • 9. ADB’s Role Para 3. However, if a borrower has awarded a contract after obtaining ADB’s “no objection,” ADB will declare misprocurement only if the “no objection” was issued on the basis of incomplete, inaccurate, or misleading information furnished by the borrower.Furthermore, if ADB determines that corrupt or fraudulent practices were engaged in by representatives of the borrower or of the bidder, ADB may impose the applicable sanctions set forth in paragraph 1.14 of the Guidelines.
  • 10. ADB’s Role Para 4. ADB has published Standard Bidding Documents (SBDs) for various types of procurement. As stated in paragraph 2.12 of the Guidelines, it is mandatory for the borrower to use these documents, with minimum changes to address country- and project-specific issues. The prequalification and bidding documents are finalized and issued by the borrower.
  • 11. Asian Development Bank Procurement GuidelinesInformation on Bidding
  • 12. Information on Bidding Para 5. Information on bidding opportunities under ICB may be obtained from the general procurement notice and the specific procurement notices as described in paragraphs 2.7 and 2.8 of the Guidelines. General guidance on participation, as well as advance information on business opportunities in upcoming projects, may be obtained from the ADB website.
  • 13. Asian Development Bank Procurement GuidelinesBidder’s Role
  • 14. Bidder’s Role Para 6Once a bidder receives the prequalification or bidding document, the bidder should study the documents carefully to decide if it can meet the technical, commercial, and contractual conditions, and if so, proceed to prepare its bid. The bidder should then critically review the documents to see if there is any ambiguity, omission, or internal contradiction, or any feature of specifications or other conditions which are unclear or appear discriminatory or restrictive; if so, it should seek clarification from the borrower, in writing, within the time period specified in the bidding documents for seeking clarifications.
  • 15. Bidder’s Role Para 7The criteria and methodology for selection of the successful bidder are outlined in the bidding documents, generally under Instructions to Bidders and Specifications. If these are not clear, clarification should be similarly sought from the borrower.
  • 16. Bidder’s Role Para 8In this connection it should be emphasized that the specific bidding documents issued by the borrower govern each procurement, as stated in paragraph 1.1 of the Guidelines. If a bidder feels that any of the provisions in the documents are inconsistent with the Guidelines, it should also raise this with the borrower.
  • 17. Bidder’s Role Para 9It is the responsibility of the bidder to raise any issue of ambiguity, contradiction, omission, etc., prior to the submission of its bid, to assure submission of a fully responsive and compliant bid, including all the supporting documents requested in the bidding documents. Noncompliance with critical (technical and commercial) requirements will result in rejection of the bid. If a bidder wishes to propose deviations to a noncritical requirement, or propose an alternative solution, the bidder should quote the price for the fully compliant bid and then separately indicate the adjustment in price that can be offered if the deviation is accepted. Alternative solutions should be offered only when authorized in the bidding documents. Once bids are received and publicly opened, bidders will not be required or permitted to change the price or substance of a bid.
  • 18. Asian Development Bank Procurement GuidelinesConfidentiality
  • 19. ConfidentialityPara 10As stated in paragraph 2.47 of the Guidelines, the process of bid evaluation shall be confidential until the publication of contract award. This is essential to enable the borrower and ADB reviewers to avoid either the reality or perception of improper interference. If at this stage a bidder wishes to bring additional information to the notice of the borrower, ADB, or both, it should do so in writing.
  • 20. Asian Development Bank Procurement GuidelinesAction by ADB
  • 21. Action by ADB Para 11Bidders are free to send copies of their communications on issues and questions with the borrower to ADB or to write to ADB directly, when borrowers do not respond promptly, or the communication is a complaint against the borrower. All such communications should be addressed to the project officer for the project, with a copy to the Principal Director, Central Operations Services Office.
  • 22. Action by ADB Para 12References received by ADB from potential bidders, prior to the closing date for submission of the bids, will, if appropriate, be referred to the borrower with ADB’s comments and advice, for action or response.
  • 23. Action by ADB Para 13Communication received from bidders after the opening of the bids, will be handled as follows. In the case of contracts not subject to prior review by ADB, the communication will be sent to the borrower for due consideration and appropriate action, if any, and these will be reviewed during subsequent supervision of the project by ADB staff. In the cases of contracts subject to the prior review process, the communication will be examined by ADB, in consultation with the borrower. If additional data is required to complete this process, these will be obtained from the borrower.
  • 24. Action by ADB Para 13If additional information or clarification is required from the bidder, ADB will ask the borrower to obtain it and comment or incorporate it, as appropriate, in the evaluation report. ADB’s review will not be completed until the communication is fully examined and considered.
  • 25. Action by ADB Para 14Except for acknowledgment, ADB will not normally enter into discussion or correspondence with any bidder during the evaluation and review process of the procurement, until award of the contract is published. Notwithstanding paragraph 14(a) above, ADB may enter into discussion where it deems necessary to conduct investigations, audit, evaluation or other assessments of the procurement process.
  • 26. Asian Development Bank Procurement GuidelinesDebriefing
  • 27. DebriefingPara 15As stated in paragraph 2.65, if, after notification of award, a bidder wishes to ascertain the grounds on which its bid was not selected, it should address its request to the borrower. If the bidder is not satisfied with the explanation given and wishes to seek a meeting with ADB, it may do so by writing the Principal Director, Central Operations Services Office, who will arrange a meeting at the appropriate level and with the relevant staff. In this discussion, only the bidder’s bid can be discussed and not the bids of competitors.