Basic A&I
Application & Installation of Generators
Jessica Treadway - February 2017
Page2
Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
What is A&I?
CATERPILLAR CONFIDENTIAL:GREEN
“A&I” is Application and
Installation engineering
technical support…
Page3
CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
Agenda
Page4
CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
• Engine RoomDesign
• Air IntakeSystems
• CoolingSystems
• ExhaustSystems
• FuelSystems
• Engine RoomVentilation
• Foundations &Isolation
Page5
Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN
CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
Engine Room Design
Engine Room Design Considerations
• Single or Multiple Use Facility
• Single or Multiple Generators
• Prime Power or Standby
• Ventilation Requirements
• Cooling Requirements
• Serviceability
• Clearances
• Access
Single or Multiple Use Facility
Single Use Facility
This room is primarily dedicated to generators.
Multiple Use Facility
The multi use facility would not only have generator sets, but also auxiliary equipment such as
boiler units, compressors, etc.
•Location
Prime or Standby
Serviceability
Service Convenience
• Compressed Air
• Ventilation Air
• Water
• Emergency Wash Station
• Fire Suppression System
• Cable Routing
• Load Testing
Clearances
• Lifting Capabilities
• Overhead Clearances
• Side Clearances
• Front and Rear
Clearances
• Underneath Clearance
• Electrical Connections
Access
• DoorWidth
• Access forRoutine
Maintenance
• MajorRepair
• ServiceElevator
Several Other Considerations
• Emergency/Rental Generator
• Expansion (future genset)
• Installation Considerations - Lift Points
• Total Package Weight
• Engine Storage
• Removing Moisture in Generators
• Flooring Considerations
• Rooftop Installations
• Fire & Explosion Prevention
• Lines, Tubes & Hoses
Page14
Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
Air Intake Systems
• Dirt and debris ingested into the engine are a major source of wear on
moving engine parts.
• The air intake is a significant path for dirt and debris to enter the
engine.
• Sources of dirt and debris in the air intake include:
– Materials left from initial fabrication and assembly of ducts
– Filter changes
– Air intake duct leaks
– Environment
Air Cleanliness
Particles in Intake Air
• Particles under 0.001mm (1 micron) diameter have little
effect and will pass out through the exhaust
• Particles from 0.001 – 0.01mm (1-10 microns) diameter have
a measurable effect on the engine
– The average human hair is 0.08mm (80 microns) in diameter
• One teaspoon of 0.125mm (125 microns) diameter dust per
hour will create catastrophic failure of an engine in 24 hours
Air Cleaner Configurations
• Engine mounted
• Remote mounted
• Multiple element
• Multi-stage (Precleaners)
• May be a requirement of the site configuration
• Best practice to leave engine-mounted air cleaners on the engine and
route ducts from them
• For remote-mounted air cleaners,
ducts must be completely sealed
to ensure all intake air is drawn
through the filter elements
Air Intake Ducts
• Varies according to engine model,
rating and fuel
• Provided on technical data sheet in
both volumetric and mass flow terms
• Establishes total flow
requirement for use in
design of the site air
intake system
• Used in restriction
calculations
Combustion Air Flow Requirements
Page20
Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
Cooling Systems
Engine Heat Balance
Internal Heat
~ 25% - 35%
Mechanical Work
30%-40%
Exhaust Energy
~ 30%-35%
Radiation ~ 5%
Review of the Basics
Internal heat is removed by:
– Jacket water
– Oil cooler
– Aftercooler
Oil cooler heat load is included in the jacket water heat load on
diesel engines and in the aftercooler heat load on most gas
engines.
Review of the Basics
Cooling system is defined by how the aftercooler heat
is handled:
– JWAC jacket water aftercooled
– SCAC separate circuit aftercooled
– ATAAC air to air aftercooled
– Two stage aftercooler (JWAC+SCAC)
Radiators
Installed Remote
Radiator Height Limits
If more than 57ft vertical
distance from JW pump to
highest point in cooling circuit,
a hot well or heat exchanger is needed to
keep static head pressure below seal limits.
– Try to design room to ½”
H2O restriction
– Plan cooling at ¾” H2O
restriction
• Walls at the air exit
should be 2 fan
diameters or more
away from the radiator
• Louvers typically
require an additional
25-95% opening,
heavy duty bird screen
material, 20-40%
Radiator Air Flow
Radiator Sizing
Need to Know:
– Heat rejection to JW and AC
– Radiant heat added to room
– Room air restriction (if installed radiator)
– Line loss and pump flow rate (if remote radiator)
– Site altitude
– Max ambient temperature
Heat Rise
• Heat Rise - Potential temp rise as intake air moves across gen-set
Example for Caterpillar Diesel Engines:
– Tier 2 engine in a power room: 4oC heat rise
– Tier 4 engine with CEM in a power room: 6oC heat rise
– Tier 2 engine in an enclosure: 7oC heat rise
• THESE ARE MINIMUM VALUES
• When specifying, make sure to
clarify location of ambient temp
or specify cooling
system capability including
heat rise.
Line Restriction
– Always keep external restriction between the
limits shown for the pump in technical
information
– Too much restriction
• Too little flow to cool the engine
• Cavitation that ruins the pump
– Too little restriction
• Too much velocity erodes the cooling system
Venting
– Vent lines or air release valves are needed at every air trap point.
– Vent lines need to be constantly rising until they reach the highest point in the system.
– Air release valves use a float and spring to keep the system closed until steam builds
up in a cavity.
Page31
Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
Exhaust Systems
Exhaust System Considerations
• Minimize back pressure
• Reduce noise
• Provide adequate clearance
• Ensure proper mounting
Back Pressure
• Target – Half the maximum allowable systemback
pressure
• CommonCulprits
– Exhaust pipe diameter
– Sharp bends
– Exhaust pipe length
– Silencer resistance
• Calculate andMeasure
Noise Reduction
• Determine AttenuationLevel
– Residential
– Critical
– Supercritical
• Selecting aSilencer
– Balance sound attenuation with back pressure
– Space, Cost, Appearance
Clearance and Mounting
•Clearance
– Overhead cranes
– Minimum 9 inches from combustible materials
– Air intake
•Mounting
– Flexible connections
– Weight support
Page36
Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
Fuel Systems
Diesel Fuel Supply System
• Fuel StorageSystem
• Fuel TransferSystem
• Fuel FiltrationSystem
Fuel Storage System
• Main Tank
– Sizing Rule of Thumb:
Fuel Consumption Rate x Hours Between Refills
» (at 100% load factor depending on application)
– 660 Rule
• Day Tank
– Required when main fuel tank is:
• Same level, > 50 ft away
• > 12 ft below engine
• Above engine fuel injectors
Fuel Transfer System
• Fuel Pump Capability and DesignConsiderations
– Vertical distance from tank to pump
– Internal piping system losses
– Elevation
•Routing
– Avoid hot surfaces
– Avoid formation of traps
– Low to the ground
Fuel Filtration System
• Engine fuel filters must never be removedor
bypassed
• Removal of water andsediment
– Water separator
– Coalescing filter
– Centrifuge
Page41
Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
Engine Room Ventilation
Ventilation
• Remove Radiant and Convection Heat
– Genset and Switchgear performance
– Adequate conditions for personnel
• Engine Room Temperature Rise
– 8.5oC to 12.5oC
– Never exceed 49oC
• Air Velocity
– 1.5 m/s in working areas
Ventilation Considerations
• Direction
– Cool, dry, clean air
– Low entry
– Horizontal air flow
– Generator first
Ventilation Considerations
• Routing
– Entry as far and low as possible
– Discharge as high as possible
– Do not blow cool air toward hot engine components
Type 1 Ventilation
Type 2 Ventilation
Type 3 Ventilation
Type 4 Ventilation
Incorrect Flow Single Engine
Multiple Engine Arrangement
Incorrect Ventilation
Required Air Flow
– Engine room ventilation
can be estimated by the
following formula,
assuming 38oC (100oF)
ambient air temperature:
Page53
Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN
Electric Power | Marine | Oil & Gas
Foundations & Isolation
Functional Requirements for Foundations
• Support total weight (mass) & dynamic loading of
equipment, accessory equipment and fluids (coolant, oil
and fuel)
• Maintain alignment between engine, driven equipment, and
accessory equipment
• Isolate equipment vibration from surrounding structures
Base Material
• Material supporting the foundation must carrythe
total weight
– Firm level soil, gravel, or rock
– Fine clay, loose sand, or sand near ground water level
• Seasonalchanges
– Extend foundations below the frost line
Concrete Foundations
• Avoid excessively thick bases
• For paralleled units foundation must
withstand twice the weight
• Minimum 12 inch edge clearance
• Mass no less than mass of
equipment
• Depth to attain minimum weight
𝐹𝐷 = 𝑊 ÷ (𝐷 × 𝐵 × 𝐿)
FD = Foundation Depth
W = Total Weight of Equipment
D = Density of Concrete
B = Foundation Width
L = Foundation Length
Functional Requirements for Package
Isolators
• Limit vibrations transmitted from genset to foundation
• Ensure that package rigid body vibration modes stay clear of
engine excitation frequencies
• Correct for small variations in foundation surface flatness
– Generally, isolators used on electric power gensets can not correct
for foundation flexure under dynamic loads!
Isolators
• Manytypes
– Rubber
– Gravel or Sand (Bulk Isolation)
– Spring
Summary
• Engine RoomDesign
• Air IntakeSystems
• CoolingSystems
• ExhaustSystems
• FuelSystems
• Engine RoomVentilation
• Foundations &Isolation
Questions ?

More Related Content

PPT
Komatsu pc1250 8 sales presentation
PDF
Engine_Application_and_Start_Up_Presentation.pdf
PDF
Vacon NXP Liquid Cooled
PPT
Cpg 2010
PDF
Services Shop
DOCX
PPTX
PROJECT PRESENTATION-1.pptx hhdhcdubddubb
Komatsu pc1250 8 sales presentation
Engine_Application_and_Start_Up_Presentation.pdf
Vacon NXP Liquid Cooled
Cpg 2010
Services Shop
PROJECT PRESENTATION-1.pptx hhdhcdubddubb

Similar to Application Installation of Generators.pdf (20)

PPTX
3. remote cooling applications
PDF
Tyler Rack Installation Manual
PDF
The Role of HVAC in Marine Engine Room Safety
PPTX
Energy uses in vehicle assembly plant
PPT
Engine systems diesel engine analyst - parte 3
PDF
Old Generation Rotary Screw Air Compressor - Operating Instructions
PDF
Compresor kaeser-csd100-ingl.
PPTX
PPTX
MARINE DIESEL ENGINES & Engine in DSV.pptx
PDF
Cookbook
PPT
Methods Of Cooling Of Rotating Electrical Machines
PPS
Saba Power Plant
DOC
M.Reda CV
DOC
M.reda cv
DOC
M.reda cv
PDF
Hussman Rack Installation Manual
PPT
Partes de Control Automático de Motobomba.ppt
PDF
Fundamentals of fluid machineries and Fluid mechanics
PDF
Gaspack vge vgi (en) light
PDF
Industry Brochure - Mining
3. remote cooling applications
Tyler Rack Installation Manual
The Role of HVAC in Marine Engine Room Safety
Energy uses in vehicle assembly plant
Engine systems diesel engine analyst - parte 3
Old Generation Rotary Screw Air Compressor - Operating Instructions
Compresor kaeser-csd100-ingl.
MARINE DIESEL ENGINES & Engine in DSV.pptx
Cookbook
Methods Of Cooling Of Rotating Electrical Machines
Saba Power Plant
M.Reda CV
M.reda cv
M.reda cv
Hussman Rack Installation Manual
Partes de Control Automático de Motobomba.ppt
Fundamentals of fluid machineries and Fluid mechanics
Gaspack vge vgi (en) light
Industry Brochure - Mining
Ad

Recently uploaded (20)

PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PDF
Visual Aids for Exploratory Data Analysis.pdf
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PDF
distributed database system" (DDBS) is often used to refer to both the distri...
PPTX
tack Data Structure with Array and Linked List Implementation, Push and Pop O...
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PDF
ChapteR012372321DFGDSFGDFGDFSGDFGDFGDFGSDFGDFGFD
PPTX
Amdahl’s law is explained in the above power point presentations
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PPTX
communication and presentation skills 01
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PDF
Improvement effect of pyrolyzed agro-food biochar on the properties of.pdf
PPTX
introduction to high performance computing
PDF
Abrasive, erosive and cavitation wear.pdf
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
Soil Improvement Techniques Note - Rabbi
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
Visual Aids for Exploratory Data Analysis.pdf
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
distributed database system" (DDBS) is often used to refer to both the distri...
tack Data Structure with Array and Linked List Implementation, Push and Pop O...
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
III.4.1.2_The_Space_Environment.p pdffdf
Fundamentals of safety and accident prevention -final (1).pptx
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
ChapteR012372321DFGDSFGDFGDFSGDFGDFGDFGSDFGDFGFD
Amdahl’s law is explained in the above power point presentations
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
communication and presentation skills 01
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
Improvement effect of pyrolyzed agro-food biochar on the properties of.pdf
introduction to high performance computing
Abrasive, erosive and cavitation wear.pdf
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
Soil Improvement Techniques Note - Rabbi
Ad

Application Installation of Generators.pdf

  • 1. Page1 Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN Basic A&I Application & Installation of Generators Jessica Treadway - February 2017
  • 2. Page2 Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas What is A&I? CATERPILLAR CONFIDENTIAL:GREEN
  • 3. “A&I” is Application and Installation engineering technical support… Page3 CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas
  • 4. Agenda Page4 CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas • Engine RoomDesign • Air IntakeSystems • CoolingSystems • ExhaustSystems • FuelSystems • Engine RoomVentilation • Foundations &Isolation
  • 5. Page5 Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas Engine Room Design
  • 6. Engine Room Design Considerations • Single or Multiple Use Facility • Single or Multiple Generators • Prime Power or Standby • Ventilation Requirements • Cooling Requirements • Serviceability • Clearances • Access
  • 7. Single or Multiple Use Facility Single Use Facility This room is primarily dedicated to generators. Multiple Use Facility The multi use facility would not only have generator sets, but also auxiliary equipment such as boiler units, compressors, etc.
  • 10. Service Convenience • Compressed Air • Ventilation Air • Water • Emergency Wash Station • Fire Suppression System • Cable Routing • Load Testing
  • 11. Clearances • Lifting Capabilities • Overhead Clearances • Side Clearances • Front and Rear Clearances • Underneath Clearance • Electrical Connections
  • 12. Access • DoorWidth • Access forRoutine Maintenance • MajorRepair • ServiceElevator
  • 13. Several Other Considerations • Emergency/Rental Generator • Expansion (future genset) • Installation Considerations - Lift Points • Total Package Weight • Engine Storage • Removing Moisture in Generators • Flooring Considerations • Rooftop Installations • Fire & Explosion Prevention • Lines, Tubes & Hoses
  • 14. Page14 Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas Air Intake Systems
  • 15. • Dirt and debris ingested into the engine are a major source of wear on moving engine parts. • The air intake is a significant path for dirt and debris to enter the engine. • Sources of dirt and debris in the air intake include: – Materials left from initial fabrication and assembly of ducts – Filter changes – Air intake duct leaks – Environment Air Cleanliness
  • 16. Particles in Intake Air • Particles under 0.001mm (1 micron) diameter have little effect and will pass out through the exhaust • Particles from 0.001 – 0.01mm (1-10 microns) diameter have a measurable effect on the engine – The average human hair is 0.08mm (80 microns) in diameter • One teaspoon of 0.125mm (125 microns) diameter dust per hour will create catastrophic failure of an engine in 24 hours
  • 17. Air Cleaner Configurations • Engine mounted • Remote mounted • Multiple element • Multi-stage (Precleaners)
  • 18. • May be a requirement of the site configuration • Best practice to leave engine-mounted air cleaners on the engine and route ducts from them • For remote-mounted air cleaners, ducts must be completely sealed to ensure all intake air is drawn through the filter elements Air Intake Ducts
  • 19. • Varies according to engine model, rating and fuel • Provided on technical data sheet in both volumetric and mass flow terms • Establishes total flow requirement for use in design of the site air intake system • Used in restriction calculations Combustion Air Flow Requirements
  • 20. Page20 Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas Cooling Systems
  • 21. Engine Heat Balance Internal Heat ~ 25% - 35% Mechanical Work 30%-40% Exhaust Energy ~ 30%-35% Radiation ~ 5%
  • 22. Review of the Basics Internal heat is removed by: – Jacket water – Oil cooler – Aftercooler Oil cooler heat load is included in the jacket water heat load on diesel engines and in the aftercooler heat load on most gas engines.
  • 23. Review of the Basics Cooling system is defined by how the aftercooler heat is handled: – JWAC jacket water aftercooled – SCAC separate circuit aftercooled – ATAAC air to air aftercooled – Two stage aftercooler (JWAC+SCAC)
  • 25. Radiator Height Limits If more than 57ft vertical distance from JW pump to highest point in cooling circuit, a hot well or heat exchanger is needed to keep static head pressure below seal limits.
  • 26. – Try to design room to ½” H2O restriction – Plan cooling at ¾” H2O restriction • Walls at the air exit should be 2 fan diameters or more away from the radiator • Louvers typically require an additional 25-95% opening, heavy duty bird screen material, 20-40% Radiator Air Flow
  • 27. Radiator Sizing Need to Know: – Heat rejection to JW and AC – Radiant heat added to room – Room air restriction (if installed radiator) – Line loss and pump flow rate (if remote radiator) – Site altitude – Max ambient temperature
  • 28. Heat Rise • Heat Rise - Potential temp rise as intake air moves across gen-set Example for Caterpillar Diesel Engines: – Tier 2 engine in a power room: 4oC heat rise – Tier 4 engine with CEM in a power room: 6oC heat rise – Tier 2 engine in an enclosure: 7oC heat rise • THESE ARE MINIMUM VALUES • When specifying, make sure to clarify location of ambient temp or specify cooling system capability including heat rise.
  • 29. Line Restriction – Always keep external restriction between the limits shown for the pump in technical information – Too much restriction • Too little flow to cool the engine • Cavitation that ruins the pump – Too little restriction • Too much velocity erodes the cooling system
  • 30. Venting – Vent lines or air release valves are needed at every air trap point. – Vent lines need to be constantly rising until they reach the highest point in the system. – Air release valves use a float and spring to keep the system closed until steam builds up in a cavity.
  • 31. Page31 Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas Exhaust Systems
  • 32. Exhaust System Considerations • Minimize back pressure • Reduce noise • Provide adequate clearance • Ensure proper mounting
  • 33. Back Pressure • Target – Half the maximum allowable systemback pressure • CommonCulprits – Exhaust pipe diameter – Sharp bends – Exhaust pipe length – Silencer resistance • Calculate andMeasure
  • 34. Noise Reduction • Determine AttenuationLevel – Residential – Critical – Supercritical • Selecting aSilencer – Balance sound attenuation with back pressure – Space, Cost, Appearance
  • 35. Clearance and Mounting •Clearance – Overhead cranes – Minimum 9 inches from combustible materials – Air intake •Mounting – Flexible connections – Weight support
  • 36. Page36 Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas Fuel Systems
  • 37. Diesel Fuel Supply System • Fuel StorageSystem • Fuel TransferSystem • Fuel FiltrationSystem
  • 38. Fuel Storage System • Main Tank – Sizing Rule of Thumb: Fuel Consumption Rate x Hours Between Refills » (at 100% load factor depending on application) – 660 Rule • Day Tank – Required when main fuel tank is: • Same level, > 50 ft away • > 12 ft below engine • Above engine fuel injectors
  • 39. Fuel Transfer System • Fuel Pump Capability and DesignConsiderations – Vertical distance from tank to pump – Internal piping system losses – Elevation •Routing – Avoid hot surfaces – Avoid formation of traps – Low to the ground
  • 40. Fuel Filtration System • Engine fuel filters must never be removedor bypassed • Removal of water andsediment – Water separator – Coalescing filter – Centrifuge
  • 41. Page41 Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas Engine Room Ventilation
  • 42. Ventilation • Remove Radiant and Convection Heat – Genset and Switchgear performance – Adequate conditions for personnel • Engine Room Temperature Rise – 8.5oC to 12.5oC – Never exceed 49oC • Air Velocity – 1.5 m/s in working areas
  • 43. Ventilation Considerations • Direction – Cool, dry, clean air – Low entry – Horizontal air flow – Generator first
  • 44. Ventilation Considerations • Routing – Entry as far and low as possible – Discharge as high as possible – Do not blow cool air toward hot engine components
  • 52. Required Air Flow – Engine room ventilation can be estimated by the following formula, assuming 38oC (100oF) ambient air temperature:
  • 53. Page53 Electric Power | Marine | Oil & Gas CATERPILLAR CONFIDENTIAL:GREEN Electric Power | Marine | Oil & Gas Foundations & Isolation
  • 54. Functional Requirements for Foundations • Support total weight (mass) & dynamic loading of equipment, accessory equipment and fluids (coolant, oil and fuel) • Maintain alignment between engine, driven equipment, and accessory equipment • Isolate equipment vibration from surrounding structures
  • 55. Base Material • Material supporting the foundation must carrythe total weight – Firm level soil, gravel, or rock – Fine clay, loose sand, or sand near ground water level • Seasonalchanges – Extend foundations below the frost line
  • 56. Concrete Foundations • Avoid excessively thick bases • For paralleled units foundation must withstand twice the weight • Minimum 12 inch edge clearance • Mass no less than mass of equipment • Depth to attain minimum weight 𝐹𝐷 = 𝑊 ÷ (𝐷 × 𝐵 × 𝐿) FD = Foundation Depth W = Total Weight of Equipment D = Density of Concrete B = Foundation Width L = Foundation Length
  • 57. Functional Requirements for Package Isolators • Limit vibrations transmitted from genset to foundation • Ensure that package rigid body vibration modes stay clear of engine excitation frequencies • Correct for small variations in foundation surface flatness – Generally, isolators used on electric power gensets can not correct for foundation flexure under dynamic loads!
  • 58. Isolators • Manytypes – Rubber – Gravel or Sand (Bulk Isolation) – Spring
  • 59. Summary • Engine RoomDesign • Air IntakeSystems • CoolingSystems • ExhaustSystems • FuelSystems • Engine RoomVentilation • Foundations &Isolation