TIME AND COST EFFICIENCY
OF COMPUTER ASSEMBLY
BUSINESS
AppliedMathematics
Josh De Freitas
Upper Six II
SchoolBased Assessment
HillviewCollege
1 | P a g e
Contents
Introduction...................................................................................................................................2
Method of Data Collection ..............................................................................................................3
Critical Path Analysis.......................................................................................................................4
Hungarian Algorithm.......................................................................................................................8
Discussion ....................................................................................................................................13
Limitations ...................................................................................................................................14
Recommendations........................................................................................................................15
Conclusion....................................................................................................................................16
2 | P a g e
Introduction
Delta’s Electronics is a popular computer store in the community. They specializein the assembly
of desktop computers from parts and this often requires trips to various computer parts retail
stores who often sell all the parts but for different prices. Due to the rise in demand for
computers and country-wide recession, Delta’s Electronics have decided to increase production
and minimize cost as well. Therefore they have enlisted the help of the researcher, whom is a
great acquaintance to help achieve this task.
This project plans to optimize the assemblyof a desktop computer, and minimize the cost of parts
to be used to assemble such computers. One of the main objectives is to minimize the amount
of time taken to completely assemblea desktop computer by presenting the order of tasks which
must be completed. This will be achieved by investigating the various steps done in assembling a
computer. Another objective is to minimize the amount of money spent on parts to keep the
business running in harsh economic times.
3 | P a g e
Method of Data Collection
Data was collected through an interview with the employees who build the computers and the
employees who retrieve the parts necessary for assembling the computer. They were asked the
procedure in assembly and the costs for each part from the various stores. The information gave
insight into the process and the steps taken which were used in the critical path analysis. The
employees also stated the price, in 5 stores, for the parts, which include: motherboard,
processor, heat sink, power supply, sata cables, fans, case, and screws, RAM chips and hard
drives. These prices were used to conduct the Hungarian algorithm.
4 | P a g e
Critical Path Analysis
Critical Path analysis or Critical Path method is the string of activities that, if the
durations are added, is longer than any other path through the network. Therefore a delay in
one of the critical path activities will cause the entire project to be delayed. This is a very
important tool used by businesses and project managers to keep projects on track and prepare
for emergency or unplanned situations.
In this case the critical path would be found for the assembly of a computer tower with
the various computer parts provided.
With the aid of a precedence diagram, each node is replaced with a square divided into
small squares as represented below.
Activity Activityduration
Precededby
EarliestStartTime (EST) LatestStart Time (LST)
Each processof the computerassemblyisrepresentedbyaletterandits respective durationtime in
minutesinthe table below.
Description of Activity Task Preceded by Duration (minutes)
Install Powersupplyoncase A - 10
Install motherboard B A 11
Place processoronboard C B 9
Attach heatsink D B, C 13
Install R.A.M.chips E B 10
Install harddrive F D, E 13
Install graphicscard G B 12
Connectsata cablestopowersupply H F, G, E 10
Assemble case withfansandscrews I H 11
5 | P a g e
An activity network diagram is necessary to form the critical path. An activity network algorithm
will be used to make such diagram.
A B CEG D F H
A A B B C C D D F F H H I I
B B C C D D F F H H I I
C C D D E E H H I I
D D E E F F I I
E E F F G G
F F G G H H
G G H H I I
H H I I
I I
6 | P a g e
7 | P a g e
Table 1 showing activity tasks and their earliest start times and latest start times and float
times.
Activity Task Earliest Start Time Latest StartTime Float Time
A 0 0 0
B 10 10 0
C 21 21 0
D 30 30 0
E 21 46 25
F 43 43 0
G 21 44 23
H 56 56 0
I 66 66 0
The Critical Path: Start A, B, C, D, F, H, I End
From the diagram it can be seen that the minimum time to assemble a computer to sell would
be 77 minutes.
8 | P a g e
Hungarian Algorithm
The Hungarian Algorithm is used to minimize costs of allocating resources. The steps for
conducting a Hungarian algorithm is as follows:
1. Draw a cost matrix
2. Subtract the smallest number in each row from all the numbers in that row
3. Subtract the smallest number in each column from all the numbers in that column
4. Draw a horizontal or vertical lines to cover all the zeroes. If the minimum number of
such lines is equal to the number of columns then you have finished. The answer is given
by selecting one zero in each row and column. There may be more than one minimum
cost.
5. If there are less horizontal or vertical lines to cover all the zeroes than there are columns
then subtract the smallest uncovered number from all the uncovered numbers and add
it to where the lines cross. Start again from step 4.
9 | P a g e
In this case, the Hungarian algorithm would be used to determine which of 5 stores would be
suitable to purchase each part/group of parts. To retrieve the parts there is one static proof
electronic-safe box that can only carry one part/ group and the work day and path only allows
for one trip to each store to get parts.
The table below shows the cost matrix.
PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5
PowerSupply $228 $252 $200 $264 $295
Motherboard $600 $650 $725 $732 $700
Processor+
Heat sink
$655 $622 $622 $600 $646
RAM+
Hard drives
$783 $777 $783 $790 $722
Sata cables+
Case + Fans+
Screws
$200 $225 $200 $197 $272
10 | P a g e
The minima fromeach row is subtracted fromeach row
PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5 Subtracting row
minimum
PowerSupply $28 $52 $0 $64 $95 (-200)
Motherboard $0 $50 $125 $132 $100 (-600)
Processor+
Heat sink
$55 $22 $22 $0 $46 (-600)
RAM+
Hard drives
$61 $55 $61 $68 $0 (-722)
Sata cables+
Case + Fans+
Screws
$3 $6 $3 $0 $75 (-197)
The minima fromeach column is subtracted fromeach column
PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5
PowerSupply $28 $52 $0 $64 $95
Motherboard $0 $50 $125 $132 $100
Processor+
Heat sink
$55 $0 $22 $0 $46
RAM+
Hard drives
$61 $55 $61 $68 $0
Sata cables+
Case + Fans+
Screws
$3 $6 $3 $0 $75
Subtracting
column
maximum
-0 (-22) -0 -0 -0
11 | P a g e
Covering all zeros with minimum number of lines.
PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5
PowerSupply $28 $52 $0 $64 $95
Motherboard $0 $50 $125 $132 $100
Processor+
Heat sink
$55 $0 $22 $0 $46
RAM+
Hard drives
$61 $55 $61 $68 $0
Sata cables+
Case + Fans+
Screws
$3 $6 $3 $0 $75
The number of lines match number of columns therefore the zeros cover an
optimal assignmentwhich correspond to the optimal assignmentof the cost
matrix.
The optimal cost for parts would be $2341
PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5
PowerSupply $228 $252 $200 $264 $295
Motherboard $600 $650 $725 $732 $700
Processor+
Heat sink
$655 $622 $622 $600 $646
RAM+
Hard drives
$783 $777 $783 $790 $722
Sata cables+
Case + Fans+
Screws
$200 $225 $200 $197 $272
12 | P a g e
Therefore the following allocation for parts would minimize cost
STORE 1: Motherboard
STORE 2: Processor +heat sink
STORE 3: Power supply
STORE 4: Sata cables +case + fans + screws
STORE 5: RAM + Hard drives
The minimum costwould be: $2341
13 | P a g e
Discussion
In this research two tests were conducted to improve upon the time and cost efficiency of the
assembly of computers by Delta’s Electronics. The tests were a critical path analysis and a
Hungarian algorithm. The criticalpath analysis was used to determine the minimum time needed
for the completion of the assembly of the computer system in order to determine float times.
This is done so that individual tasks can be delayed without causing a delay to the project
completion. An activity network diagram was used to help conduct the critical path analysis.
The critical path for the assembly of the computer was found to be Start A, B, C, D, F, H, I End
Where each letter represents the specific task that is path of the critical path. Using this critical
path, from the activity network diagram was found that the minimum time to assemble a
computer to sell would be 77 minutes. Therefore efficiency of assembly can be improved upon
if the employees of Delta’s Electronics assemble the desktop computer within 77 minutes.
The second test that was conducted was the Hungarian algorithm. This was done to allocate
various parts necessary for the assembly of the computer to the different stores so that the
least amount of money is spent to buy each part. The cost matrix was tabulated and through
row and column elimination the following optimal assignment was found:
Therefore the following allocation for parts would minimize cost
STORE 1: Motherboard
STORE 2: Processor + heat sink
STORE 3: Power supply
STORE 4: Sata cables +case + fans + screws
STORE 5: RAM + Hard drives
Therefore Delta’s Electronics would spend the least money by following the previous allocation
inn purchasing its parts from each store. The Hungarian algorithm also showing that the
optimal cost for parts would be $2341.
From these results Delta’s Electronics can now assemble desktop computers in a time and cost
efficient way.
14 | P a g e
Limitations
There were manylimitationsthatmaybe consideredinthe researchconducted.Firstlythe various
storeswhere partscan be obtainedare subjecttoprice changes andmay vary accordingly.Secondly,the
cost of transport and fuel tothe differentstoresmaybe more that othersbecause theirlocationmaybe
closeror furtherthanDelta’sElectronics.Thirdly,partsmaybe faultyandcostsmay vary unexpectedly
to account forthis.Finally the real world events were not accounted for when taking the duration
into consideration as these factors could affect duration and hence the critical path.
15 | P a g e
Recommendations
The methodusedinconductingthisresearchmayhavenot beenidealandrecommendationscanbe made
to improve this. More tests could be done to further maximize efficiency and account for human error.
The tasksinthe critical pathwere simplifiedanda more detailedanalysiscouldbe done toachieve more
accurate results in time efficiency.
16 | P a g e
Conclusion
In conclusion the critical path analysis conducted highlighted the crucial steps and the minimum
amount of time taken to assemble a desktop computer by Delta’s Electronics which means they
would be able to assemble computers more efficiently and save time. The Hungarian algorithm
in this research showed optical assignment for stores and parts to be purchased to minimize
costs. The Hungarian algorithm also showed the least amount of money necessary to assemble a
desktop computer. With this information, Delta’s Electronics would be able to save money in
assembling the computers.
17 | P a g e
Bibliography
CPM- Critical PathMethod.(n.d.).Retrievedfromhttp://www.netmba.com/operations/project/cpm/
Critical PathMethod (CPM).(n.d.).RetrievedfromUniversityof SouthCarolina:
http://hspm.sph.sc.edu/Courses/J716/CPM/CPM.html
Howto use Hungarian Algorithm.(n.d.).RetrievedfromWikiHow:http://www.wikihow.com/Use-the-
Hungarian-Algorithm
Hungarian Algorithm .(n.d.).Retrievedfromhttp://hungarianalgorithm.com/

More Related Content

DOCX
Communication studies school based assessment, SBA
DOCX
CAPE Caribbean Studies Internal Assessment
DOCX
Cape Economics SBA
DOCX
CAPE Caribbean Studies IA
DOCX
Caribbean Studies - CAPE Unit 2 - Internal Assignment/IA 2017
DOCX
Unemployment IA by Erica Dacas
DOCX
Economics SBA
DOCX
Cape Communication Studies Sba Unit 1
Communication studies school based assessment, SBA
CAPE Caribbean Studies Internal Assessment
Cape Economics SBA
CAPE Caribbean Studies IA
Caribbean Studies - CAPE Unit 2 - Internal Assignment/IA 2017
Unemployment IA by Erica Dacas
Economics SBA
Cape Communication Studies Sba Unit 1

What's hot (20)

DOCX
Management if Business IA (MOB)
DOCX
Communication studies i.a.
DOCX
COMMUNICATION STUDIES iA ON LGBTQI
DOCX
Cape Applied Math SBA
DOCX
Communication studies Basic Exposition piece
DOC
Caribbean Studies Internal Assessment (Sample)
DOCX
CAPE Communication Studies IA
DOC
CAPE Economics, June 2005, Unit 2, Paper 2 suggested answer by Edward Bahaw
DOC
CAPE Economics, July 2nd, Unit 1, Paper 2 suggested answer by Edward Bahaw
DOCX
Sociology IA
DOCX
Sample 21Communication studies I.A / S.B.A
PDF
Cape Caribbean Studies: 2006-2016 past-papers
DOC
Sociology Unit 1 Internal Assessment Sample
DOCX
CAPE Caribbean Studies Unit 2 - Sample SBA
DOCX
Caribbean studies internal assessment
DOCX
CAPE Sociology Unit 1 IA
DOCX
CAPE Communication Studies SBA
DOCX
CAPE Tourism Unit 1 SBA
DOC
Mob sba guidelines
DOC
June 2010 unit 2 paper 2 answer
Management if Business IA (MOB)
Communication studies i.a.
COMMUNICATION STUDIES iA ON LGBTQI
Cape Applied Math SBA
Communication studies Basic Exposition piece
Caribbean Studies Internal Assessment (Sample)
CAPE Communication Studies IA
CAPE Economics, June 2005, Unit 2, Paper 2 suggested answer by Edward Bahaw
CAPE Economics, July 2nd, Unit 1, Paper 2 suggested answer by Edward Bahaw
Sociology IA
Sample 21Communication studies I.A / S.B.A
Cape Caribbean Studies: 2006-2016 past-papers
Sociology Unit 1 Internal Assessment Sample
CAPE Caribbean Studies Unit 2 - Sample SBA
Caribbean studies internal assessment
CAPE Sociology Unit 1 IA
CAPE Communication Studies SBA
CAPE Tourism Unit 1 SBA
Mob sba guidelines
June 2010 unit 2 paper 2 answer
Ad

Similar to Applied Mathematics Unit 2SBA (20)

PPT
Lecture01 algorithm analysis
PPTX
Design & Analysis of Algorithm course .pptx
PPT
Introduction to Algorithms
PDF
Analysis of Algorithms
PDF
Design & Analysis of Algorithms Lecture Notes
PDF
Lecture 2 role of algorithms in computing
PPT
CS3114_09212011.ppt
PDF
Advanced Datastructures and algorithms CP4151unit1b.pdf
PPTX
AoA Lec Design of algorithm spresentation
PDF
Algorithm Design and Analysis
PPT
Data Structure and Algorithms Department of Computer Science
PPSX
Ds03 part i algorithms by jyoti lakhani
PPTX
CH-1.1 Introduction (1).pptx
PDF
Data Structure - Lecture 1 - Introduction.pdf
PDF
PPTX
Introduction to Basics C Programming.pptx
PPTX
DATA STRUCTURES unit 1.pptx
PDF
geekgap.io webinar #1
PPTX
Design and Analysis of Algorithm for II year Computer science and Engineering...
Lecture01 algorithm analysis
Design & Analysis of Algorithm course .pptx
Introduction to Algorithms
Analysis of Algorithms
Design & Analysis of Algorithms Lecture Notes
Lecture 2 role of algorithms in computing
CS3114_09212011.ppt
Advanced Datastructures and algorithms CP4151unit1b.pdf
AoA Lec Design of algorithm spresentation
Algorithm Design and Analysis
Data Structure and Algorithms Department of Computer Science
Ds03 part i algorithms by jyoti lakhani
CH-1.1 Introduction (1).pptx
Data Structure - Lecture 1 - Introduction.pdf
Introduction to Basics C Programming.pptx
DATA STRUCTURES unit 1.pptx
geekgap.io webinar #1
Design and Analysis of Algorithm for II year Computer science and Engineering...
Ad

Recently uploaded (20)

PDF
TR - Agricultural Crops Production NC III.pdf
PPTX
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PDF
Microbial disease of the cardiovascular and lymphatic systems
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PPTX
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PDF
01-Introduction-to-Information-Management.pdf
PDF
Complications of Minimal Access Surgery at WLH
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PPTX
Cell Types and Its function , kingdom of life
PDF
VCE English Exam - Section C Student Revision Booklet
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
Pre independence Education in Inndia.pdf
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
TR - Agricultural Crops Production NC III.pdf
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
Pharmacology of Heart Failure /Pharmacotherapy of CHF
Microbial disease of the cardiovascular and lymphatic systems
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
01-Introduction-to-Information-Management.pdf
Complications of Minimal Access Surgery at WLH
STATICS OF THE RIGID BODIES Hibbelers.pdf
Anesthesia in Laparoscopic Surgery in India
FourierSeries-QuestionsWithAnswers(Part-A).pdf
Cell Types and Its function , kingdom of life
VCE English Exam - Section C Student Revision Booklet
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
Module 4: Burden of Disease Tutorial Slides S2 2025
Pre independence Education in Inndia.pdf
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Renaissance Architecture: A Journey from Faith to Humanism

Applied Mathematics Unit 2SBA

  • 1. TIME AND COST EFFICIENCY OF COMPUTER ASSEMBLY BUSINESS AppliedMathematics Josh De Freitas Upper Six II SchoolBased Assessment HillviewCollege
  • 2. 1 | P a g e Contents Introduction...................................................................................................................................2 Method of Data Collection ..............................................................................................................3 Critical Path Analysis.......................................................................................................................4 Hungarian Algorithm.......................................................................................................................8 Discussion ....................................................................................................................................13 Limitations ...................................................................................................................................14 Recommendations........................................................................................................................15 Conclusion....................................................................................................................................16
  • 3. 2 | P a g e Introduction Delta’s Electronics is a popular computer store in the community. They specializein the assembly of desktop computers from parts and this often requires trips to various computer parts retail stores who often sell all the parts but for different prices. Due to the rise in demand for computers and country-wide recession, Delta’s Electronics have decided to increase production and minimize cost as well. Therefore they have enlisted the help of the researcher, whom is a great acquaintance to help achieve this task. This project plans to optimize the assemblyof a desktop computer, and minimize the cost of parts to be used to assemble such computers. One of the main objectives is to minimize the amount of time taken to completely assemblea desktop computer by presenting the order of tasks which must be completed. This will be achieved by investigating the various steps done in assembling a computer. Another objective is to minimize the amount of money spent on parts to keep the business running in harsh economic times.
  • 4. 3 | P a g e Method of Data Collection Data was collected through an interview with the employees who build the computers and the employees who retrieve the parts necessary for assembling the computer. They were asked the procedure in assembly and the costs for each part from the various stores. The information gave insight into the process and the steps taken which were used in the critical path analysis. The employees also stated the price, in 5 stores, for the parts, which include: motherboard, processor, heat sink, power supply, sata cables, fans, case, and screws, RAM chips and hard drives. These prices were used to conduct the Hungarian algorithm.
  • 5. 4 | P a g e Critical Path Analysis Critical Path analysis or Critical Path method is the string of activities that, if the durations are added, is longer than any other path through the network. Therefore a delay in one of the critical path activities will cause the entire project to be delayed. This is a very important tool used by businesses and project managers to keep projects on track and prepare for emergency or unplanned situations. In this case the critical path would be found for the assembly of a computer tower with the various computer parts provided. With the aid of a precedence diagram, each node is replaced with a square divided into small squares as represented below. Activity Activityduration Precededby EarliestStartTime (EST) LatestStart Time (LST) Each processof the computerassemblyisrepresentedbyaletterandits respective durationtime in minutesinthe table below. Description of Activity Task Preceded by Duration (minutes) Install Powersupplyoncase A - 10 Install motherboard B A 11 Place processoronboard C B 9 Attach heatsink D B, C 13 Install R.A.M.chips E B 10 Install harddrive F D, E 13 Install graphicscard G B 12 Connectsata cablestopowersupply H F, G, E 10 Assemble case withfansandscrews I H 11
  • 6. 5 | P a g e An activity network diagram is necessary to form the critical path. An activity network algorithm will be used to make such diagram. A B CEG D F H A A B B C C D D F F H H I I B B C C D D F F H H I I C C D D E E H H I I D D E E F F I I E E F F G G F F G G H H G G H H I I H H I I I I
  • 7. 6 | P a g e
  • 8. 7 | P a g e Table 1 showing activity tasks and their earliest start times and latest start times and float times. Activity Task Earliest Start Time Latest StartTime Float Time A 0 0 0 B 10 10 0 C 21 21 0 D 30 30 0 E 21 46 25 F 43 43 0 G 21 44 23 H 56 56 0 I 66 66 0 The Critical Path: Start A, B, C, D, F, H, I End From the diagram it can be seen that the minimum time to assemble a computer to sell would be 77 minutes.
  • 9. 8 | P a g e Hungarian Algorithm The Hungarian Algorithm is used to minimize costs of allocating resources. The steps for conducting a Hungarian algorithm is as follows: 1. Draw a cost matrix 2. Subtract the smallest number in each row from all the numbers in that row 3. Subtract the smallest number in each column from all the numbers in that column 4. Draw a horizontal or vertical lines to cover all the zeroes. If the minimum number of such lines is equal to the number of columns then you have finished. The answer is given by selecting one zero in each row and column. There may be more than one minimum cost. 5. If there are less horizontal or vertical lines to cover all the zeroes than there are columns then subtract the smallest uncovered number from all the uncovered numbers and add it to where the lines cross. Start again from step 4.
  • 10. 9 | P a g e In this case, the Hungarian algorithm would be used to determine which of 5 stores would be suitable to purchase each part/group of parts. To retrieve the parts there is one static proof electronic-safe box that can only carry one part/ group and the work day and path only allows for one trip to each store to get parts. The table below shows the cost matrix. PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5 PowerSupply $228 $252 $200 $264 $295 Motherboard $600 $650 $725 $732 $700 Processor+ Heat sink $655 $622 $622 $600 $646 RAM+ Hard drives $783 $777 $783 $790 $722 Sata cables+ Case + Fans+ Screws $200 $225 $200 $197 $272
  • 11. 10 | P a g e The minima fromeach row is subtracted fromeach row PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5 Subtracting row minimum PowerSupply $28 $52 $0 $64 $95 (-200) Motherboard $0 $50 $125 $132 $100 (-600) Processor+ Heat sink $55 $22 $22 $0 $46 (-600) RAM+ Hard drives $61 $55 $61 $68 $0 (-722) Sata cables+ Case + Fans+ Screws $3 $6 $3 $0 $75 (-197) The minima fromeach column is subtracted fromeach column PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5 PowerSupply $28 $52 $0 $64 $95 Motherboard $0 $50 $125 $132 $100 Processor+ Heat sink $55 $0 $22 $0 $46 RAM+ Hard drives $61 $55 $61 $68 $0 Sata cables+ Case + Fans+ Screws $3 $6 $3 $0 $75 Subtracting column maximum -0 (-22) -0 -0 -0
  • 12. 11 | P a g e Covering all zeros with minimum number of lines. PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5 PowerSupply $28 $52 $0 $64 $95 Motherboard $0 $50 $125 $132 $100 Processor+ Heat sink $55 $0 $22 $0 $46 RAM+ Hard drives $61 $55 $61 $68 $0 Sata cables+ Case + Fans+ Screws $3 $6 $3 $0 $75 The number of lines match number of columns therefore the zeros cover an optimal assignmentwhich correspond to the optimal assignmentof the cost matrix. The optimal cost for parts would be $2341 PARTS STORE 1 STORE 2 STORE 3 STORE 4 STORE 5 PowerSupply $228 $252 $200 $264 $295 Motherboard $600 $650 $725 $732 $700 Processor+ Heat sink $655 $622 $622 $600 $646 RAM+ Hard drives $783 $777 $783 $790 $722 Sata cables+ Case + Fans+ Screws $200 $225 $200 $197 $272
  • 13. 12 | P a g e Therefore the following allocation for parts would minimize cost STORE 1: Motherboard STORE 2: Processor +heat sink STORE 3: Power supply STORE 4: Sata cables +case + fans + screws STORE 5: RAM + Hard drives The minimum costwould be: $2341
  • 14. 13 | P a g e Discussion In this research two tests were conducted to improve upon the time and cost efficiency of the assembly of computers by Delta’s Electronics. The tests were a critical path analysis and a Hungarian algorithm. The criticalpath analysis was used to determine the minimum time needed for the completion of the assembly of the computer system in order to determine float times. This is done so that individual tasks can be delayed without causing a delay to the project completion. An activity network diagram was used to help conduct the critical path analysis. The critical path for the assembly of the computer was found to be Start A, B, C, D, F, H, I End Where each letter represents the specific task that is path of the critical path. Using this critical path, from the activity network diagram was found that the minimum time to assemble a computer to sell would be 77 minutes. Therefore efficiency of assembly can be improved upon if the employees of Delta’s Electronics assemble the desktop computer within 77 minutes. The second test that was conducted was the Hungarian algorithm. This was done to allocate various parts necessary for the assembly of the computer to the different stores so that the least amount of money is spent to buy each part. The cost matrix was tabulated and through row and column elimination the following optimal assignment was found: Therefore the following allocation for parts would minimize cost STORE 1: Motherboard STORE 2: Processor + heat sink STORE 3: Power supply STORE 4: Sata cables +case + fans + screws STORE 5: RAM + Hard drives Therefore Delta’s Electronics would spend the least money by following the previous allocation inn purchasing its parts from each store. The Hungarian algorithm also showing that the optimal cost for parts would be $2341. From these results Delta’s Electronics can now assemble desktop computers in a time and cost efficient way.
  • 15. 14 | P a g e Limitations There were manylimitationsthatmaybe consideredinthe researchconducted.Firstlythe various storeswhere partscan be obtainedare subjecttoprice changes andmay vary accordingly.Secondly,the cost of transport and fuel tothe differentstoresmaybe more that othersbecause theirlocationmaybe closeror furtherthanDelta’sElectronics.Thirdly,partsmaybe faultyandcostsmay vary unexpectedly to account forthis.Finally the real world events were not accounted for when taking the duration into consideration as these factors could affect duration and hence the critical path.
  • 16. 15 | P a g e Recommendations The methodusedinconductingthisresearchmayhavenot beenidealandrecommendationscanbe made to improve this. More tests could be done to further maximize efficiency and account for human error. The tasksinthe critical pathwere simplifiedanda more detailedanalysiscouldbe done toachieve more accurate results in time efficiency.
  • 17. 16 | P a g e Conclusion In conclusion the critical path analysis conducted highlighted the crucial steps and the minimum amount of time taken to assemble a desktop computer by Delta’s Electronics which means they would be able to assemble computers more efficiently and save time. The Hungarian algorithm in this research showed optical assignment for stores and parts to be purchased to minimize costs. The Hungarian algorithm also showed the least amount of money necessary to assemble a desktop computer. With this information, Delta’s Electronics would be able to save money in assembling the computers.
  • 18. 17 | P a g e Bibliography CPM- Critical PathMethod.(n.d.).Retrievedfromhttp://www.netmba.com/operations/project/cpm/ Critical PathMethod (CPM).(n.d.).RetrievedfromUniversityof SouthCarolina: http://hspm.sph.sc.edu/Courses/J716/CPM/CPM.html Howto use Hungarian Algorithm.(n.d.).RetrievedfromWikiHow:http://www.wikihow.com/Use-the- Hungarian-Algorithm Hungarian Algorithm .(n.d.).Retrievedfromhttp://hungarianalgorithm.com/