AUTODESK® CONSULTING




Customer Case Study


The Customer: Army Corps of Engineers                                                              HIGHLIGHTS
The U.S. Army Corps of Engineers (USACE) is composed of 39,000
                                                                                                   Autodesk
dedicated civilians and soldiers delivering engineering services in more than
                                                                                                   Consulting joined
90 countries worldwide. The USACE is responsible for building and                                  with the USACE in
maintaining America’s infrastructure and providing military facilities wherever                    its first attempt to
U.S. service personnel train, work, and live.                                                      model and analyze
                                                                                                   an existing military
In recent years, terrorist attacks, actions by hostile political regimes, and
                                                                                                   installation for the
                                                                                                   purpose of
other factors have underscored the grave danger of leaving U.S. military
                                                                                                   achieving “net
installations dependent on outside suppliers for water, oil, gasoline and other                    zero” at all U.S.
resources a military unit requires to function.                                                    military
                                                                                                   installations..
In 2009, President Obama issued Executive Order 13514, requiring that “all
                                                                                                   Ecotect Analysis,
new Federal buildings, entering the design phase in 2020 or later, are
                                                                                                   Revit Architecture,
designed to achieve zero net energy by 2030.”                                                      3ds Max and
                                                                                                   Project Vasari
To achieve “net zero” a building or installation must be able to generate the                      Implementation
services necessary to supply energy, water, and dispose of waste internally,                       were used to
without relying on outside resources or services.
                                                                                                   deconstruct,
                                                                                                   analyze, and
                                                                                                   model energy
As Katherine Hammack, Assistant Secretary of the Army for Installations,
                                                                                                   usage and
Energy & Environment, explained:                                                                   savings.

“Addressing energy security and sustainability is operationally necessary,                         This process will
financially prudent, and essential to mission accomplishment…We are                                be applied to other
                                                                                                   facilities as work
creating a culture that recognizes the value of sustainability measured not just
                                                                                                   continues to make
in terms of financial benefits, but benefits to maintaining mission capability,                    all military
quality of life, relationships with local communities, and the preservation of                     installations self-
options for the Army's future.”*                                                                   sustaining by
                                                                                                   2030. .

* Hammack, K. (2010). Office of the Assistant Secretary of the Army. Retrieved 12 15, 2010, from
 http://www.asaie.army.mil/public/IE




Autodesk Internal – Do Not Distribute                                                              1/4
Case Study: United States Army Corps of Engineers                                           AC AEC




 The Project
 In 2009, the USACE hired the National Renewable Energy Laboratory and
 the Construction Engineering Research Laboratory to analyze the energy
 footprints of five standard designs currently used for U.S. military buildings
 and determine what changes could be made to reduce the buildings’ energy
 usage.


 The study focused specifically on passive design strategies, and reported
 that, while it was possible to reduce the energy consumption of these facilities
 by approximately 20-30%, achieving the mandated reductions of 65% and
 higher at existing facilities was not possible.

 In the autumn of 2010, the USACE began work to create a process for
 renovating, retrofitting, and designing military installations that would use only
 internally available resources and be completely self-sustaining or “net zero.”

 The decision was made to select one existing installation, analyze its specific
 site and climactic conditions, and develop an integrated design that could be
 applied to infrastructure, water, and waste treatment/disposal at all U.S.
 military installations.

 In January of 2011, 16 Army installations were asked to apply to become the
 first “net zero” site for energy, water, and waste by 2030. The installation
 selected was Fort Leonard Wood in Missouri.

 Developing a plan to make Fort Leonard Wood self-sustaining was more than
 a challenge; it was an imperative. The cost of supplying Fort Leonard Wood
 with power had risen 55% in the previous year. Now, the supplier was about
 to disappear entirely.


 The Challenges
 The team was tasked with developing comprehensive, synergistic solutions
 for providing water to the base, handling its waste and reducing energy
 consumption. These solutions would also need to be transferable to other
 installations. Achieving this required creating a digital, simulated model
 baseline for a “net zero” installation.


 The first step involved deconstructing the installation’s master plan, design,
 and the orientation of its facilities. The base’s specific needs and problems
 were analyzed in light of the new self-sustaining imperative, which meant
 challenging deeply ingrained beliefs and conventions. The orientation of
 buildings, the placement of windows, building systems, and many other
 factors had to be studied simultaneously to assess the feasibility of the
 changes proposed.


 The 26-person project team was highly diverse, multidisciplinary, and located
 around the globe. The program sought to elicit conceptual thinking and


                                                                                      2/4
Case Study: United States Army Corps of Engineers                                         AC AEC


 innovative solutions, and only employees who had been employed by USACE
 for two years of les were selected for the team. The budget for the entire
 project had been pared to the point where crucial analyses could be
 conducted on only a small sample of the installation’s buildings.


 The Solution
 The program employed an iterative design process, and was completed in a
 short time in a predominantly virtual environment.

 The programs used in this project were Autodesk® Ecotect® Analysis,
 Autodesk® Revit® Architecture, Autodesk® 3ds Max®, Autodesk ® Project
 Vasari Implementation.


 Ecotect was used to determine the best orientation for buildings, the amount
 of direct solar radiation available to the site, and whether available wind
 power was a viable source of renewable energy. It generated and critical
 performance data regarding shading, solar path, insulation, radiation, and
 glazing that was used to weigh and prioritize proposed options.


 Vasari & Revit Architecture’s Conceptual Energy Analysis (CEA) functionality,
 used in conjunction with the Green Building Studio (GBS) web service,
 allowed building information to be restacked and rearranged to produce
 simulated design alternatives, which were then compared to find the most
 energy-efficient results.


 3DS Max produced qualitative and quantitative data about natural lighting.


 Throughout the four-month project, Autodesk Customer Success Manager,
 Mike Juros, an architect and Senior Technical Specialist, provided online “train
 the trainer” coaching and phone support to USACE Architect and Technical
 Designer, Jennifer Ramirez, USACE for Vasari, Revit , and GBS.

 AC provided the team with whitepapers, videos and guides to help facilitate
 learning before formal training was mobilized. Key Architects and Engineers
 from the Construction Engineering Research Laboratory (CERL) received
 special training.

 ELA provided design and analysis software and ensured accessibility and
 consistent performance.

 The benefits of involving key stakeholders from the start became increasingly
 clear as the project progressed. Engineers, local contractors, and the
 construction manager were part of the team from the schematic design
 phase.


 During the process, many factors came to light. For example, it was
 discovered that when soldiers’ barracks are empty, the lack of body heat
 increases the disparity between the side of the building in the sun and the
 side in shadow which, in turn, creates a lop-sided cooling/heating demand
 that puts additional strain on the HVAC system. This knowledge led to a

                                                                                    3/4
Case Study: United States Army Corps of Engineers                                                                                                                    AC AEC


   reorientation of the building on the site, and reduced the energy demand
   without moving any interior walls.

   The Results
   The project was presented to the installation and was well received.


   The USACE intends to develop the processes used in the Fort Leonard Wood
   study, and apply the same strategies to other installations that have similar
   utilities issues. Based on the findings and success of this study, funding for
   the planning of two more area developments has been secured, and these
   projects are currently in progress.


   Following the Ft. Leonard Wood pilot project period, AC conducted three
   Sustainable Design sessions to train 36 people at locations in Omaha, NE,
   Norfolk, VA, and Vicksburg, MS.

   Autodesk AC and software played a key role in developing solutions that
   demonstrate how U.S. military installations can dramatically reduce their
   energy consumption. The data generated by the project provides good
   reason to believe that, with continued research and study, the “net zero” goal
   set by President Obama for 2030 may be achievable.



     The Contacts
     Xxxxxxxxxx
     Customer Success Manager
     Global Services, Autodesk Consulting
     Direct: Xxx-xxx-xxxx
     Email: xxxxxxxxxxxxxxxxx

     White House press release for Executive Order 13514:
     http://www.whitehouse.gov/the_press_office/President-
     Obama-signs-an-Executive-Order-Focused-on-Federal-
     Leadership-in-Environmental-Energy-and-Economic-
     Performance/

     FedCenter site providing informational links
     http://www.fedcenter.gov/programs/eo13514/




Autodesk, Building Information Modeling (BIM), Revit, 3ds max, are registered trademarks or trademarks of Autodesk, Inc., and/or its subsidiaries and/or affiliates in the
USA and/or other countries. All other brand names, product names, or trademarks belong to their respective holders. Autodesk reserves the right to alter product and
services offerings, and specifications and pricing at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document.
© 2010 Autodesk, Inc. All rights reserved.




                                                                                                                                                    4/4

More Related Content

PDF
Encouraging Sustainability: Use of LEED to Enhance Focus on Sustainability
PDF
IDGA's Military Construction Summit 2010
PDF
Military Construction Summit 2010
PPTX
Jonathan coles residential 2013
PDF
Chase visamobile self-mailer_non-student.pdf
PPT
RUS: Конкурентная разведка для транснациональных компаний
PPT
RUS: Система инновационной и технологической разведки (Ver.2.0)
PPT
RUS: Система раннего предупреждения рискограф
Encouraging Sustainability: Use of LEED to Enhance Focus on Sustainability
IDGA's Military Construction Summit 2010
Military Construction Summit 2010
Jonathan coles residential 2013
Chase visamobile self-mailer_non-student.pdf
RUS: Конкурентная разведка для транснациональных компаний
RUS: Система инновационной и технологической разведки (Ver.2.0)
RUS: Система раннего предупреждения рискограф

Viewers also liked (10)

PPTX
Presentacion de conceptos de web. 2.0-slidershaare
PPTX
wave boarden
PDF
Recent works March 2015
DOCX
Fenton webb interview
PPTX
waveboard
PDF
Jonathan coles overview 2013
PDF
White paper for WFB Private Clients
PPTX
Susan Fry Portfolio
PPT
RUS: Безопасность детей в социальных сетях
PPT
Nicolas jimenez
Presentacion de conceptos de web. 2.0-slidershaare
wave boarden
Recent works March 2015
Fenton webb interview
waveboard
Jonathan coles overview 2013
White paper for WFB Private Clients
Susan Fry Portfolio
RUS: Безопасность детей в социальных сетях
Nicolas jimenez
Ad

Similar to Autodesk case study: US Army Corp of Engineers (20)

PPTX
2012 Reenergize the Americas Keynote: Richard G. Kidd
PDF
PPT
Roundtable 3: NetZero Energy Installations and Facilities
PDF
PDF
2011 Environmental Symposium- Roundtable 1
PPTX
Vernon Fox, Head Of IS - Offshore at Mainstream Renewable Power - Sustainable...
PDF
Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...
PDF
NewsCastle - October 2012
PDF
12032011 nolan for fleet v3 web
PDF
Infrastructure and Investment Opportunities for Energy Efficiency in Buildings
PDF
Ict4s_conference_ireen_project_page_blöchle
PDF
인문기술융합창작소 미래예측방법론 교육원고 (2012)
PDF
Future of the U.S. Energy Grid
PDF
Chu National Press Club112910
PDF
Public Works Digest sept-oct11
PPTX
Doug waters army presentation
PDF
Hoyt diana
PDF
Global Geothermal Summit, Oct. 12, 2011
PPTX
660 presentation final
PDF
Susd0001 Nicolas Carbone Individual Assignment (2)
2012 Reenergize the Americas Keynote: Richard G. Kidd
Roundtable 3: NetZero Energy Installations and Facilities
2011 Environmental Symposium- Roundtable 1
Vernon Fox, Head Of IS - Offshore at Mainstream Renewable Power - Sustainable...
Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...
NewsCastle - October 2012
12032011 nolan for fleet v3 web
Infrastructure and Investment Opportunities for Energy Efficiency in Buildings
Ict4s_conference_ireen_project_page_blöchle
인문기술융합창작소 미래예측방법론 교육원고 (2012)
Future of the U.S. Energy Grid
Chu National Press Club112910
Public Works Digest sept-oct11
Doug waters army presentation
Hoyt diana
Global Geothermal Summit, Oct. 12, 2011
660 presentation final
Susd0001 Nicolas Carbone Individual Assignment (2)
Ad

Recently uploaded (20)

PDF
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
PDF
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
PDF
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
PDF
A novel scalable deep ensemble learning framework for big data classification...
PDF
A comparative study of natural language inference in Swahili using monolingua...
PDF
NewMind AI Weekly Chronicles – August ’25 Week III
PDF
Hybrid model detection and classification of lung cancer
PPT
What is a Computer? Input Devices /output devices
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PDF
STKI Israel Market Study 2025 version august
PDF
Zenith AI: Advanced Artificial Intelligence
PDF
Web App vs Mobile App What Should You Build First.pdf
PDF
NewMind AI Weekly Chronicles - August'25-Week II
PDF
DP Operators-handbook-extract for the Mautical Institute
PDF
Enhancing emotion recognition model for a student engagement use case through...
PPTX
Final SEM Unit 1 for mit wpu at pune .pptx
PDF
Univ-Connecticut-ChatGPT-Presentaion.pdf
PDF
Architecture types and enterprise applications.pdf
PPTX
Group 1 Presentation -Planning and Decision Making .pptx
PPTX
Chapter 5: Probability Theory and Statistics
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
A novel scalable deep ensemble learning framework for big data classification...
A comparative study of natural language inference in Swahili using monolingua...
NewMind AI Weekly Chronicles – August ’25 Week III
Hybrid model detection and classification of lung cancer
What is a Computer? Input Devices /output devices
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
STKI Israel Market Study 2025 version august
Zenith AI: Advanced Artificial Intelligence
Web App vs Mobile App What Should You Build First.pdf
NewMind AI Weekly Chronicles - August'25-Week II
DP Operators-handbook-extract for the Mautical Institute
Enhancing emotion recognition model for a student engagement use case through...
Final SEM Unit 1 for mit wpu at pune .pptx
Univ-Connecticut-ChatGPT-Presentaion.pdf
Architecture types and enterprise applications.pdf
Group 1 Presentation -Planning and Decision Making .pptx
Chapter 5: Probability Theory and Statistics

Autodesk case study: US Army Corp of Engineers

  • 1. AUTODESK® CONSULTING Customer Case Study The Customer: Army Corps of Engineers HIGHLIGHTS The U.S. Army Corps of Engineers (USACE) is composed of 39,000 Autodesk dedicated civilians and soldiers delivering engineering services in more than Consulting joined 90 countries worldwide. The USACE is responsible for building and with the USACE in maintaining America’s infrastructure and providing military facilities wherever its first attempt to U.S. service personnel train, work, and live. model and analyze an existing military In recent years, terrorist attacks, actions by hostile political regimes, and installation for the purpose of other factors have underscored the grave danger of leaving U.S. military achieving “net installations dependent on outside suppliers for water, oil, gasoline and other zero” at all U.S. resources a military unit requires to function. military installations.. In 2009, President Obama issued Executive Order 13514, requiring that “all Ecotect Analysis, new Federal buildings, entering the design phase in 2020 or later, are Revit Architecture, designed to achieve zero net energy by 2030.” 3ds Max and Project Vasari To achieve “net zero” a building or installation must be able to generate the Implementation services necessary to supply energy, water, and dispose of waste internally, were used to without relying on outside resources or services. deconstruct, analyze, and model energy As Katherine Hammack, Assistant Secretary of the Army for Installations, usage and Energy & Environment, explained: savings. “Addressing energy security and sustainability is operationally necessary, This process will financially prudent, and essential to mission accomplishment…We are be applied to other facilities as work creating a culture that recognizes the value of sustainability measured not just continues to make in terms of financial benefits, but benefits to maintaining mission capability, all military quality of life, relationships with local communities, and the preservation of installations self- options for the Army's future.”* sustaining by 2030. . * Hammack, K. (2010). Office of the Assistant Secretary of the Army. Retrieved 12 15, 2010, from http://www.asaie.army.mil/public/IE Autodesk Internal – Do Not Distribute 1/4
  • 2. Case Study: United States Army Corps of Engineers AC AEC The Project In 2009, the USACE hired the National Renewable Energy Laboratory and the Construction Engineering Research Laboratory to analyze the energy footprints of five standard designs currently used for U.S. military buildings and determine what changes could be made to reduce the buildings’ energy usage. The study focused specifically on passive design strategies, and reported that, while it was possible to reduce the energy consumption of these facilities by approximately 20-30%, achieving the mandated reductions of 65% and higher at existing facilities was not possible. In the autumn of 2010, the USACE began work to create a process for renovating, retrofitting, and designing military installations that would use only internally available resources and be completely self-sustaining or “net zero.” The decision was made to select one existing installation, analyze its specific site and climactic conditions, and develop an integrated design that could be applied to infrastructure, water, and waste treatment/disposal at all U.S. military installations. In January of 2011, 16 Army installations were asked to apply to become the first “net zero” site for energy, water, and waste by 2030. The installation selected was Fort Leonard Wood in Missouri. Developing a plan to make Fort Leonard Wood self-sustaining was more than a challenge; it was an imperative. The cost of supplying Fort Leonard Wood with power had risen 55% in the previous year. Now, the supplier was about to disappear entirely. The Challenges The team was tasked with developing comprehensive, synergistic solutions for providing water to the base, handling its waste and reducing energy consumption. These solutions would also need to be transferable to other installations. Achieving this required creating a digital, simulated model baseline for a “net zero” installation. The first step involved deconstructing the installation’s master plan, design, and the orientation of its facilities. The base’s specific needs and problems were analyzed in light of the new self-sustaining imperative, which meant challenging deeply ingrained beliefs and conventions. The orientation of buildings, the placement of windows, building systems, and many other factors had to be studied simultaneously to assess the feasibility of the changes proposed. The 26-person project team was highly diverse, multidisciplinary, and located around the globe. The program sought to elicit conceptual thinking and 2/4
  • 3. Case Study: United States Army Corps of Engineers AC AEC innovative solutions, and only employees who had been employed by USACE for two years of les were selected for the team. The budget for the entire project had been pared to the point where crucial analyses could be conducted on only a small sample of the installation’s buildings. The Solution The program employed an iterative design process, and was completed in a short time in a predominantly virtual environment. The programs used in this project were Autodesk® Ecotect® Analysis, Autodesk® Revit® Architecture, Autodesk® 3ds Max®, Autodesk ® Project Vasari Implementation. Ecotect was used to determine the best orientation for buildings, the amount of direct solar radiation available to the site, and whether available wind power was a viable source of renewable energy. It generated and critical performance data regarding shading, solar path, insulation, radiation, and glazing that was used to weigh and prioritize proposed options. Vasari & Revit Architecture’s Conceptual Energy Analysis (CEA) functionality, used in conjunction with the Green Building Studio (GBS) web service, allowed building information to be restacked and rearranged to produce simulated design alternatives, which were then compared to find the most energy-efficient results. 3DS Max produced qualitative and quantitative data about natural lighting. Throughout the four-month project, Autodesk Customer Success Manager, Mike Juros, an architect and Senior Technical Specialist, provided online “train the trainer” coaching and phone support to USACE Architect and Technical Designer, Jennifer Ramirez, USACE for Vasari, Revit , and GBS. AC provided the team with whitepapers, videos and guides to help facilitate learning before formal training was mobilized. Key Architects and Engineers from the Construction Engineering Research Laboratory (CERL) received special training. ELA provided design and analysis software and ensured accessibility and consistent performance. The benefits of involving key stakeholders from the start became increasingly clear as the project progressed. Engineers, local contractors, and the construction manager were part of the team from the schematic design phase. During the process, many factors came to light. For example, it was discovered that when soldiers’ barracks are empty, the lack of body heat increases the disparity between the side of the building in the sun and the side in shadow which, in turn, creates a lop-sided cooling/heating demand that puts additional strain on the HVAC system. This knowledge led to a 3/4
  • 4. Case Study: United States Army Corps of Engineers AC AEC reorientation of the building on the site, and reduced the energy demand without moving any interior walls. The Results The project was presented to the installation and was well received. The USACE intends to develop the processes used in the Fort Leonard Wood study, and apply the same strategies to other installations that have similar utilities issues. Based on the findings and success of this study, funding for the planning of two more area developments has been secured, and these projects are currently in progress. Following the Ft. Leonard Wood pilot project period, AC conducted three Sustainable Design sessions to train 36 people at locations in Omaha, NE, Norfolk, VA, and Vicksburg, MS. Autodesk AC and software played a key role in developing solutions that demonstrate how U.S. military installations can dramatically reduce their energy consumption. The data generated by the project provides good reason to believe that, with continued research and study, the “net zero” goal set by President Obama for 2030 may be achievable. The Contacts Xxxxxxxxxx Customer Success Manager Global Services, Autodesk Consulting Direct: Xxx-xxx-xxxx Email: xxxxxxxxxxxxxxxxx White House press release for Executive Order 13514: http://www.whitehouse.gov/the_press_office/President- Obama-signs-an-Executive-Order-Focused-on-Federal- Leadership-in-Environmental-Energy-and-Economic- Performance/ FedCenter site providing informational links http://www.fedcenter.gov/programs/eo13514/ Autodesk, Building Information Modeling (BIM), Revit, 3ds max, are registered trademarks or trademarks of Autodesk, Inc., and/or its subsidiaries and/or affiliates in the USA and/or other countries. All other brand names, product names, or trademarks belong to their respective holders. Autodesk reserves the right to alter product and services offerings, and specifications and pricing at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document. © 2010 Autodesk, Inc. All rights reserved. 4/4