The document describes a topographic survey conducted for the construction of a new railway bridge. It discusses using a topographic map to identify potential alignment options for the railway track. A field survey was then carried out using a total station to determine the central line alignment and elevation levels at different points. Soil exploration work, including lab testing, was also performed. Following this, the land acquisition process began by contacting local authorities to purchase the necessary land from owners. Foundation excavation work then commenced based on the ground conditions. Piers were constructed using a total station to ensure proper alignment. Bed blocks were then marked for placing precast girders. Sleepers were later laid to allow for track alignment along the central line.