Regional Planning Commission’s
Brownfield Redevelopment Program
RPC’s Brownfield Program
 Regional Planning Commission Overview
‐ Government Entity
‐ Member Parishes: Jefferson, Orleans, Plaquemines,
St. Bernard, St. Tammany & Tangipahoa Parishes
‐ Commission is made up of elected officials,
community representatives, transportation
agencies
‐ Professional Staff carries out day-to-day work
 Program Director: Rebecca Otte
‐ Secures & Manages Grant Funding (EPA Grants)
‐ Oversees Environmental Assessments
‐ Helps Applicants through the Environmental Process
‐ Coordinates Brownfield-related Outreach
 U.S. Environmental Protection Agency (EPA)
‐ Provides funding through competitive grants
‐ Oversees compliance with EPA grant
requirements
 Louisiana Dept. of Environmental Quality (LDEQ)
‐ State Environmental Regulatory Agency
‐ Overseas technical aspects of environmental
assessments & cleanups
‐ Responsible for approving all environmental
cleanup activities
‐ Also has a Brownfields Program
 Louisiana Brownfield Association
RPC’s Brownfield Partners
What we look for in a Brownfield Project:
 Redevelopment of an Underutilized/Abandoned Property which is
hindered by real or perceived environmental contamination
 Site Champion that will be involved throughout the process
 Redevelop will be Income Producing or for Community Benefit
 Will help spur further economic development/ investment
 Redevelopment is a Good Possibility
 Site access
 Compliance with EPA’s Continuing
Obligations
RPC’s Brownfield Program
What IS NOT included under Brownfields Funding:
 Payment for environmental assessments already conducted
 Funding for Site Purchase
 Funding for Site Redevelopment, unless related to the Cleanup
 Payments to other consultants or to property owners for
environmental activities
Remediation/ Cleanup
 Reducing the risk of exposure
‐ Treating contamination on-site or in situ (in the ground)
‐ Removing the contamination
‐ Institutional Controls (e.g., conveyance notice to not allow
groundwater to be used for drinking water)
‐ Engineering Controls (e.g., capping contamination with a parking lot)
Goal: Reduce the risk of exposure to
unsafe levels of contamination to protect
Human Health & the Environment
Remediation/ Cleanup
 Proposed Redevelopment affects
the Cleanup Plan
 Coordinate Cleanup with
Redevelopment
 Can layer funding
‐ Public/ private Funding
‐ Grants/loans
 EPA Cleanup Funding = Additional
Requirements
Examples of Brownfield Sites
Former Schwegmann’s Superstore
Algiers (New Orleans)
 Environmental Issue: Needed to
address fuel tanks to secure bank
loan for site purchase
 Proposed Redevelopment: Event
Rentals expanded operations
 Environmental Work:
 Event Rentals – Phase I
 RPC – Phase II & UST Closure
Event Rentals also worked with New
Orleans City council to create
Economic Development District
around the site
Progressive Church Family Life Center
Site History
 Asbestos in soil from previous fill activities
 Updated Phase I ESA- former junkyard on
the site
 Phase II ESA delineated asbestos
contamination & limited area of heavy
metal & petroleum contamination
 Cleanup: 12,876 tons of soil removed
 LDEQ Certificate of Completion issued
Sept. 10, 2008
Location: 4th and Cohen Streets, Marrero, Jefferson Parish, LA
Size: 18 acres
 Total Investigation Cost: $111,500 - Paid for through RPC’s Brownfield Assessment Grants;
LDEQ waived their oversight fees
 Total Cleanup Cost: just shy of $500,000
 $200,000 USEPA Brownfield Cleanup Grant (Competitive Selection)
 $300,000 Loan from RPC’s Brownfield Cleanup Revolving Loan Fund
 Also received LA Brownfield Cleanup Tax Credit
Garden on Marais
4600 Marais St., New Orleans (near Industrial Canal)
 Environmental Issue: Former Pesticide Facility
 Proposed Redevelopment: Community Garden
 Environmental Work:
 RPC Phase I & II assessment
 Incorporated sampling for LSU Ag Center Evaluation
 Utilized Workforce Development Students
 Rec’d NFA from LDEQ
Former St. Rose de Lima Cathedral & School
 Proposed Redevelopment:
- Charter School Incubator
- Artist Space & Support Services
- Community Meeting Space
Bayou Treme Center
 Environmental Issues:
- Underground Tank – Heating Oil
- Lead, Asbestos & Bird Droppings
 Environmental Work:
 Phase I & Update
 Phase II under VRP
 Closed & Removed UST
 Prepared Cleanup Plan & Related
Documents
 Working with BTC on Lead &
Asbestos Abatement
 Other Considerations:
 Historic District
 Use of CDBG Funding
 Owned by Catholic Archdiocese
Bayou Treme Center
St. Margaret’s at Mercy
 Environmental Issues:
- Asbestos in Building
- Fuel tanks onsite
 Environmental Assessment Work:
- Phase I - St. Margaret’s
- Phase II Work Plan – City of New
Orleans
- Phase II implementation – RPC
- Cleanup Plan – RPC
 Cleanup Funding:
- UST Removal - LDEQ Grant
- Asbestos Abatement:
 EPA Competitive Cleanup Grant
 Brownfield Cleanup Loan from
City of New Orleans
St. Margaret’s at Mercy
 Redevelopment Planning Underway:
- Senior Living Facility already built
- Additional Senior Living Units in
Renovated Structure
- More information on the tour!
 Considerations:
- Historic Tax Credits
- Significant community interest
Falstaff Brewery
Location: 2600 Gravier Street, New Orleans, LA
Size: 8 acres
Site History:
 Brewery Closed in 1978; Site left vacant
 Phase I ESA conducted in Aug. 2005 in
preparation for site purchase; Paid for by
RPC Brownfield Assessment Grant
 Extensive Asbestos Containing Materials,
Lead-Based Paint, and Solid Waste
throughout 7-Story Structure
 Falstaff Properties I LLC purchased property
and cleaned up contamination
Success Status:
 Opened in 2008
 Currently at 95% Occupancy
 Mixed-Use Residential & Commercial Property
 Includes Affordable Housing Units
Before:
After:
New Orleans BioInnovations Center
Location: 1441 Canal St.
Site History:
 Former gas station
 UST Cleanup funded by the LA Dept. of
Economic Development and U.S. EDA
Success Status:
 LEED Gold
 200 direct jobs
 Clad with precast panels fitted with glass, which
reduces the amount of heat entering the
building.
 Sunscreens on the glazing provide lighting and
storm protection and reduce energy costs.
 The white reflective roof of the building also
reduces the energy costs. Other sustainable
features of the facility include a rainwater
retention system to collect water from the roof
and electric vehicle charging stations.
Considerations for Brownfield Funding
 EPA Funding Comes with Strings Attached
 EPA & LDEQ approvals
 EPA reporting
 Quality Assurance Project Plan
 RPC helps with “string management”
 RPC helps facilitate the LDEQ review process by:
‐ Flagging sites as redevelopment projects
‐ Reviewing documents prior to submission
‐ Working with the LDEQ Team Leaders on timing
 Brownfields does not move quickly
 Takes about 30 days to enroll a site
‐ Timing depends on how long it takes to receive paperwork & access
agreement from applicant
 Phase I: 60-90 days (normally 30 days with private funding)
 Phase II: 6- 12 months
 VRP Phase II: 12 – 18 months
 Cleanup: At least 12 months
Brownfields Timing
Contact Information
Rebecca Otte
Brownfield Redevelopment Program Director
Regional Planning Commission
brownfields@norpc.org
(504) 483-8513
Questions?
Brownfields Case Studies
Environmental Process
Site Cleanup/Reuse Plans & Remediation
Address contamination to mitigate risk of exposure that may impact human
health or the environment
Not always in this order
Phase I Environmental Site Assessment (ESA)
Research report to look at what was at the site previously and what’s there now
and identify any potential environmental concerns
Phase II Environmental Site Assessment (ESA)
Collect and analyze soil and groundwater samples to determine if
contamination is present and if so, to what extent
Environmental Process
Reasons to Conduct a Phase I Environmental Site
Assessment:
 Determine if contamination may be present
‐ Avoid surprises during the construction phase
‐ Reduce purchase price
‐ Address environmental issues prior to redeveloping the
site
 Document site conditions before you purchased it
‐ Liability Protection from EPA & LDEQ
‐ Eligibility for Brownfield Funding
Environmental Process
Liability Protection Conditions:
 Phase I Environmental Site Assessments must meet EPA’s All
Appropriate Inquiry / ASTM E1527-13 Standard
 Performed by a “Qualified Environmental Professional”
 Timing: Important to time the Phase I assessment to
ensure it’s valid at time of purchase
‐ Phase I Assessments expire after 1 year for
liability protection
‐ Portions of the Phase I report need to be
updated after 6 months
Environmental Process
Regulatory Oversight Options for
Phase II Assessments and Cleanups/ Remediation:
 Traditional Oversight - Commonly called RECAP: Risk
Evaluation/ Corrective Action Program
 Only address areas with recognized environmental concerns
 Assessment Phase is generally quicker and lower costs
 May need to sample offsite to determine horizontal extent of
contamination (increases costs & time)
 Less flexibility if cleanup is required
 LDEQ may reopened the investigation in the future (e.g., if LDEQ lowers
the maximum safe concentration levels of a contaminant found onsite)
Environmental Process
Regulatory Oversight Options for
Phase II Assessments and Cleanups/ Remediation:
 VRP: Voluntary Remediation Program
 Investigation/Cleanup covers the entire Site as defined by the Applicant
 Requires additional sampling & analysis which increases upfront costs
 Requires public notice & specific LDEQ approvals which increases time
 Not required to sample offsite to determine horizontal extent of
contamination (may save costs & time)
 More flexibility if cleanup is required
Can use Engineering/ Institutional Controls
 Once the LDEQ approves the cleanup, the site cannot be reopened
Liability protection flows down to future owners
Example: Traditional Program/ RECAP
Building
Heating Oil Tank
Fuel Tank
Example: Voluntary Remediation Program
Building
Heating Oil Tank
Fuel Tank
RECAP Investigation (Phase II ESA) VRP Investigation (Phase II ESA)
 Generally lower in costs
- Less samples collected
- Fewer pollutants to analyze for
 Generally a faster process
- No public notice required
 May miss contamination in another area of
the site
 May need to sample offsite to determine
horizontal extent of contamination
 Generally more expensive
- Requires more samples to be collected
- Requires a wider range of analyses
 More time consuming
- Specific process requires more approvals
- Public notice requirements
 May find other contamination that was not
previously known
 Investigation confined to site boundaries
RECAP Remediation/ Cleanup VRP Remediation/ Cleanup
 Remediation of all risks is required, e.g. any
contamination that is above RECAP standards
needs to be remediated
 Engineering/ Institutional controls generally
not acceptable
 Remediation can be tailored for the intended
future use of the site
 Engineering/Institutional controls may be
used to prevent exposure to contamination
- Cost savings
RECAP Final Result VRP Final Result
 No further action at this time (NFA) letter
from LDEQ
 Site may be reopened in the future (for
example, if LDEQ lowers the maximum safe
concentration levels)
 Certificate of Completion (COC) for the entire
site defined in the application
 Release of liability from EPA & LDEQ for all
past contamination at the site (transferable to
future site owners)
Environmental Process - Cleanup
 Remediation/ Cleanup is reducing the risk of exposure to
contamination at the site as detailed in the Site Cleanup
Plan, including:
‐ Treating contamination on-site or in situ (in the ground)
‐ Removing the contamination
‐ Institutional Controls (e.g., conveyance notice to not allow
groundwater to be used for drinking water)
‐ Engineering Controls (e.g., capping contamination with a parking
lot)
Goal: Reduce the risk of exposure to unsafe
levels of contamination to protect Human Health
& the Environment
Environmental Process - Cleanup
 Proposed Redevelopment affects
the Cleanup Plan
 Coordinate Cleanup with
Redevelopment
 Can layer funding
‐ Public/ private Funding
‐ Grants/loans
 EPA Cleanup Funding = Additional
Requirements
Web Resources
 US Environmental Protection Agency’s (EPA’s) Brownfields Website:
www.epa.gov/brownfields/
 US Department of Housing and Urban Development (HUD):
http://portal.hud.gov/hudportal/HUD?src=/program_offices/comm_plann
ing/economicdevelopment/programs
 EPA’s RE-Powering America’s Land Initiative: www2.epa.gov/re-powering
 The Brownfield and Land Revitalization Technology Support Center (EPA,
USACE, ANL): www.brownfieldstsc.org

More Related Content

PDF
Bhendi bazaar
PDF
Neighbourhood planning
PPTX
Jane Jacobs- urban activist
PPTX
Ebenezer howard
PPTX
Urban studies case study townships
PDF
Chandigarh City Planning
PPTX
Image of the city
PDF
New Urbanism- Jane Jacobs
Bhendi bazaar
Neighbourhood planning
Jane Jacobs- urban activist
Ebenezer howard
Urban studies case study townships
Chandigarh City Planning
Image of the city
New Urbanism- Jane Jacobs

What's hot (20)

PPTX
Garden Cities of Tommorow by Sir Ebenezer Howard
PDF
Neighborhood planning case study
PDF
Industrial revolution
PDF
Le corbusier
PPTX
Riverfront development
PDF
Determinants or Urban Form urban morphology
PDF
Neighbourhood-Planning--Design-Standards-combined-June-2015
PPTX
Planning concept of Chandigarh city.
PPTX
Udcpr Maharashtra
PPTX
PPT
Role of different institutions in housing
PPTX
Sir ebenezer howard
PDF
CAMPUS DESIGN - CONCEPT STUDY
PDF
Elements of city planning_Building and Town Planning
PPTX
GARDEN CITY MOVEMENT
PPTX
buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...
PDF
Integrated Township
PPT
Ud ppt
PDF
Urban Design project 1
PDF
Bhubaneshwar Planning
Garden Cities of Tommorow by Sir Ebenezer Howard
Neighborhood planning case study
Industrial revolution
Le corbusier
Riverfront development
Determinants or Urban Form urban morphology
Neighbourhood-Planning--Design-Standards-combined-June-2015
Planning concept of Chandigarh city.
Udcpr Maharashtra
Role of different institutions in housing
Sir ebenezer howard
CAMPUS DESIGN - CONCEPT STUDY
Elements of city planning_Building and Town Planning
GARDEN CITY MOVEMENT
buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...
Integrated Township
Ud ppt
Urban Design project 1
Bhubaneshwar Planning
Ad

Viewers also liked (10)

PPTX
Technical Assistance and Funds for Redeveloping Brownfields
PPTX
Overview of Brownfields
PDF
Fundraising – Case Study of a NGO
DOC
Issues Risklog
PPTX
Lesson 13 case study of a dam & reservoir
PPTX
Project Risk Register
PDF
Project Management Templates
DOCX
Project Risk register
PPTX
Varanasi Riverfront Development
PDF
Risk assessment principles and guidelines
Technical Assistance and Funds for Redeveloping Brownfields
Overview of Brownfields
Fundraising – Case Study of a NGO
Issues Risklog
Lesson 13 case study of a dam & reservoir
Project Risk Register
Project Management Templates
Project Risk register
Varanasi Riverfront Development
Risk assessment principles and guidelines
Ad

Similar to Brownfields Case Studies (20)

PPTX
Brownfields for Redeveloping Resilience
PDF
Adaptive Reuse - Brownfields Redevelopment
PPTX
Brownfields Redevelopment Journey: Nolan
PPTX
Superfund sites
PPTX
Brownfields Presentation
PPT
Tarc
PDF
Brownfields Program and Grant Overview
PPT
Hsca overview may 2007 jim werner
PPTX
Learning Lab: Brownfields Redevelopment to Support Growing and Diversified Ec...
PPTX
Brownfields Redevelopment Overview
PPT
tu-f1-corrective-action-101-ice-&-nailor-2016-02-19-final
PDF
EPA Superfund
PPTX
PP - Real Estate CLE June 2015 - final
PPTX
NJFuture Redevelopment Forum 2016 Mitchell
PPT
W-F1-Corrective Action 101-Ice and Wickham 2015-01-30
PDF
Brownfields: On the Road to Redevelopment
PPTX
Environmental considerations and land use
PDF
Brownfields under trump panel
 
PDF
Brownfields Under Trump panel
PDF
Brownfields Under Trump - Panel
 
Brownfields for Redeveloping Resilience
Adaptive Reuse - Brownfields Redevelopment
Brownfields Redevelopment Journey: Nolan
Superfund sites
Brownfields Presentation
Tarc
Brownfields Program and Grant Overview
Hsca overview may 2007 jim werner
Learning Lab: Brownfields Redevelopment to Support Growing and Diversified Ec...
Brownfields Redevelopment Overview
tu-f1-corrective-action-101-ice-&-nailor-2016-02-19-final
EPA Superfund
PP - Real Estate CLE June 2015 - final
NJFuture Redevelopment Forum 2016 Mitchell
W-F1-Corrective Action 101-Ice and Wickham 2015-01-30
Brownfields: On the Road to Redevelopment
Environmental considerations and land use
Brownfields under trump panel
 
Brownfields Under Trump panel
Brownfields Under Trump - Panel
 

More from nado-web (20)

PDF
Federal Legislative Update
PPTX
Plenary - Stars of the Southwest: Lifting Regional Economies
PDF
Outdoor Rec in Southwest New Mexico
PPTX
Affordable and Accessible Housing: Imperative for Strong Economies
PPTX
Creative Collaborations: Tribal Nations
PPTX
Regional Resilience Partnership
PDF
Louisiana's Digital Equity Plan
PPTX
Broadband- Ruffin
PDF
West Texas Aerospace and Defense Manufacturing Coalition
PPTX
H2theFuture
PPTX
Tulsa Regional Advanced Mobility (TRAM) Corridor
PPTX
Oklahoma Biotech Innovation Center
PDF
Northern New Mexico Workforce Integration Network (WIN)
PPTX
Kansas State University UC Showcase
PDF
KCSL UMKCIC University Center
PPTX
University of Montana Rural Innovation Initiative
PPTX
University of Kansas University Center
PDF
University of North Dakota Center for Innovation
PPTX
Iowa State University CIRAS
PPTX
University of Northern Iowa EDA University Center
Federal Legislative Update
Plenary - Stars of the Southwest: Lifting Regional Economies
Outdoor Rec in Southwest New Mexico
Affordable and Accessible Housing: Imperative for Strong Economies
Creative Collaborations: Tribal Nations
Regional Resilience Partnership
Louisiana's Digital Equity Plan
Broadband- Ruffin
West Texas Aerospace and Defense Manufacturing Coalition
H2theFuture
Tulsa Regional Advanced Mobility (TRAM) Corridor
Oklahoma Biotech Innovation Center
Northern New Mexico Workforce Integration Network (WIN)
Kansas State University UC Showcase
KCSL UMKCIC University Center
University of Montana Rural Innovation Initiative
University of Kansas University Center
University of North Dakota Center for Innovation
Iowa State University CIRAS
University of Northern Iowa EDA University Center

Recently uploaded (20)

PPTX
20231018_SRP Tanzania_IRC2023 FAO side event.pptx
PPTX
True Fruits_ reportcccccccccccccccc.pptx
PPTX
Portland FPDR Oregon Legislature 2025.pptx
PPTX
BHARATIYA NAGARIKA SURAKSHA SAHMITA^J2023 (1).pptx
PPTX
Neurons.pptx and the family in London are you chatgpt
PPT
The Central Civil Services (Leave Travel Concession) Rules, 1988, govern the ...
PPTX
DFARS Part 252 - Clauses - Defense Regulations
PPTX
Part I CSO Conference and AVP Overview.pptx
PPTX
Part II LGU Accreditation of CSOs and Selection of Reps to LSBs ver2.pptx
PDF
Item # 5 - 5307 Broadway St final review
PPTX
Core Humanitarian Standard Presentation by Abraham Lebeza
PPTX
SOMANJAN PRAMANIK_3500032 2042.pptx
PDF
eVerify Overview and Detailed Instructions to Set up an account
PDF
PPT Items # 6&7 - 900 Cambridge Oval Right-of-Way
PPTX
Workshop-Session-1-LGU-WFP-Formulation.pptx
PDF
CXPA Finland Webinar: Rated 5 Stars - Delivering Service That Customers Truly...
PDF
Concept_Note_-_GoAP_Primary_Sector_-_The_Great_Rural_Reset_-_Updated_18_June_...
PPTX
ANALYSIS OF THE PROCLAMATION OF THE PHILIPPHINE INDEPENDENCE.pptx
PDF
Building Bridges (of Hope) over Our Troubled Waters_PART 1
PPTX
cpgram enivaran cpgram enivaran cpgram enivaran
20231018_SRP Tanzania_IRC2023 FAO side event.pptx
True Fruits_ reportcccccccccccccccc.pptx
Portland FPDR Oregon Legislature 2025.pptx
BHARATIYA NAGARIKA SURAKSHA SAHMITA^J2023 (1).pptx
Neurons.pptx and the family in London are you chatgpt
The Central Civil Services (Leave Travel Concession) Rules, 1988, govern the ...
DFARS Part 252 - Clauses - Defense Regulations
Part I CSO Conference and AVP Overview.pptx
Part II LGU Accreditation of CSOs and Selection of Reps to LSBs ver2.pptx
Item # 5 - 5307 Broadway St final review
Core Humanitarian Standard Presentation by Abraham Lebeza
SOMANJAN PRAMANIK_3500032 2042.pptx
eVerify Overview and Detailed Instructions to Set up an account
PPT Items # 6&7 - 900 Cambridge Oval Right-of-Way
Workshop-Session-1-LGU-WFP-Formulation.pptx
CXPA Finland Webinar: Rated 5 Stars - Delivering Service That Customers Truly...
Concept_Note_-_GoAP_Primary_Sector_-_The_Great_Rural_Reset_-_Updated_18_June_...
ANALYSIS OF THE PROCLAMATION OF THE PHILIPPHINE INDEPENDENCE.pptx
Building Bridges (of Hope) over Our Troubled Waters_PART 1
cpgram enivaran cpgram enivaran cpgram enivaran

Brownfields Case Studies

  • 2. RPC’s Brownfield Program  Regional Planning Commission Overview ‐ Government Entity ‐ Member Parishes: Jefferson, Orleans, Plaquemines, St. Bernard, St. Tammany & Tangipahoa Parishes ‐ Commission is made up of elected officials, community representatives, transportation agencies ‐ Professional Staff carries out day-to-day work  Program Director: Rebecca Otte ‐ Secures & Manages Grant Funding (EPA Grants) ‐ Oversees Environmental Assessments ‐ Helps Applicants through the Environmental Process ‐ Coordinates Brownfield-related Outreach
  • 3.  U.S. Environmental Protection Agency (EPA) ‐ Provides funding through competitive grants ‐ Oversees compliance with EPA grant requirements  Louisiana Dept. of Environmental Quality (LDEQ) ‐ State Environmental Regulatory Agency ‐ Overseas technical aspects of environmental assessments & cleanups ‐ Responsible for approving all environmental cleanup activities ‐ Also has a Brownfields Program  Louisiana Brownfield Association RPC’s Brownfield Partners
  • 4. What we look for in a Brownfield Project:  Redevelopment of an Underutilized/Abandoned Property which is hindered by real or perceived environmental contamination  Site Champion that will be involved throughout the process  Redevelop will be Income Producing or for Community Benefit  Will help spur further economic development/ investment  Redevelopment is a Good Possibility  Site access  Compliance with EPA’s Continuing Obligations
  • 5. RPC’s Brownfield Program What IS NOT included under Brownfields Funding:  Payment for environmental assessments already conducted  Funding for Site Purchase  Funding for Site Redevelopment, unless related to the Cleanup  Payments to other consultants or to property owners for environmental activities
  • 6. Remediation/ Cleanup  Reducing the risk of exposure ‐ Treating contamination on-site or in situ (in the ground) ‐ Removing the contamination ‐ Institutional Controls (e.g., conveyance notice to not allow groundwater to be used for drinking water) ‐ Engineering Controls (e.g., capping contamination with a parking lot) Goal: Reduce the risk of exposure to unsafe levels of contamination to protect Human Health & the Environment
  • 7. Remediation/ Cleanup  Proposed Redevelopment affects the Cleanup Plan  Coordinate Cleanup with Redevelopment  Can layer funding ‐ Public/ private Funding ‐ Grants/loans  EPA Cleanup Funding = Additional Requirements
  • 9. Former Schwegmann’s Superstore Algiers (New Orleans)  Environmental Issue: Needed to address fuel tanks to secure bank loan for site purchase  Proposed Redevelopment: Event Rentals expanded operations  Environmental Work:  Event Rentals – Phase I  RPC – Phase II & UST Closure Event Rentals also worked with New Orleans City council to create Economic Development District around the site
  • 10. Progressive Church Family Life Center Site History  Asbestos in soil from previous fill activities  Updated Phase I ESA- former junkyard on the site  Phase II ESA delineated asbestos contamination & limited area of heavy metal & petroleum contamination  Cleanup: 12,876 tons of soil removed  LDEQ Certificate of Completion issued Sept. 10, 2008 Location: 4th and Cohen Streets, Marrero, Jefferson Parish, LA Size: 18 acres  Total Investigation Cost: $111,500 - Paid for through RPC’s Brownfield Assessment Grants; LDEQ waived their oversight fees  Total Cleanup Cost: just shy of $500,000  $200,000 USEPA Brownfield Cleanup Grant (Competitive Selection)  $300,000 Loan from RPC’s Brownfield Cleanup Revolving Loan Fund  Also received LA Brownfield Cleanup Tax Credit
  • 11. Garden on Marais 4600 Marais St., New Orleans (near Industrial Canal)  Environmental Issue: Former Pesticide Facility  Proposed Redevelopment: Community Garden  Environmental Work:  RPC Phase I & II assessment  Incorporated sampling for LSU Ag Center Evaluation  Utilized Workforce Development Students  Rec’d NFA from LDEQ
  • 12. Former St. Rose de Lima Cathedral & School  Proposed Redevelopment: - Charter School Incubator - Artist Space & Support Services - Community Meeting Space Bayou Treme Center
  • 13.  Environmental Issues: - Underground Tank – Heating Oil - Lead, Asbestos & Bird Droppings  Environmental Work:  Phase I & Update  Phase II under VRP  Closed & Removed UST  Prepared Cleanup Plan & Related Documents  Working with BTC on Lead & Asbestos Abatement  Other Considerations:  Historic District  Use of CDBG Funding  Owned by Catholic Archdiocese Bayou Treme Center
  • 14. St. Margaret’s at Mercy  Environmental Issues: - Asbestos in Building - Fuel tanks onsite  Environmental Assessment Work: - Phase I - St. Margaret’s - Phase II Work Plan – City of New Orleans - Phase II implementation – RPC - Cleanup Plan – RPC  Cleanup Funding: - UST Removal - LDEQ Grant - Asbestos Abatement:  EPA Competitive Cleanup Grant  Brownfield Cleanup Loan from City of New Orleans
  • 15. St. Margaret’s at Mercy  Redevelopment Planning Underway: - Senior Living Facility already built - Additional Senior Living Units in Renovated Structure - More information on the tour!  Considerations: - Historic Tax Credits - Significant community interest
  • 16. Falstaff Brewery Location: 2600 Gravier Street, New Orleans, LA Size: 8 acres Site History:  Brewery Closed in 1978; Site left vacant  Phase I ESA conducted in Aug. 2005 in preparation for site purchase; Paid for by RPC Brownfield Assessment Grant  Extensive Asbestos Containing Materials, Lead-Based Paint, and Solid Waste throughout 7-Story Structure  Falstaff Properties I LLC purchased property and cleaned up contamination Success Status:  Opened in 2008  Currently at 95% Occupancy  Mixed-Use Residential & Commercial Property  Includes Affordable Housing Units Before: After:
  • 17. New Orleans BioInnovations Center Location: 1441 Canal St. Site History:  Former gas station  UST Cleanup funded by the LA Dept. of Economic Development and U.S. EDA Success Status:  LEED Gold  200 direct jobs  Clad with precast panels fitted with glass, which reduces the amount of heat entering the building.  Sunscreens on the glazing provide lighting and storm protection and reduce energy costs.  The white reflective roof of the building also reduces the energy costs. Other sustainable features of the facility include a rainwater retention system to collect water from the roof and electric vehicle charging stations.
  • 18. Considerations for Brownfield Funding  EPA Funding Comes with Strings Attached  EPA & LDEQ approvals  EPA reporting  Quality Assurance Project Plan  RPC helps with “string management”  RPC helps facilitate the LDEQ review process by: ‐ Flagging sites as redevelopment projects ‐ Reviewing documents prior to submission ‐ Working with the LDEQ Team Leaders on timing
  • 19.  Brownfields does not move quickly  Takes about 30 days to enroll a site ‐ Timing depends on how long it takes to receive paperwork & access agreement from applicant  Phase I: 60-90 days (normally 30 days with private funding)  Phase II: 6- 12 months  VRP Phase II: 12 – 18 months  Cleanup: At least 12 months Brownfields Timing
  • 20. Contact Information Rebecca Otte Brownfield Redevelopment Program Director Regional Planning Commission brownfields@norpc.org (504) 483-8513 Questions?
  • 22. Environmental Process Site Cleanup/Reuse Plans & Remediation Address contamination to mitigate risk of exposure that may impact human health or the environment Not always in this order Phase I Environmental Site Assessment (ESA) Research report to look at what was at the site previously and what’s there now and identify any potential environmental concerns Phase II Environmental Site Assessment (ESA) Collect and analyze soil and groundwater samples to determine if contamination is present and if so, to what extent
  • 23. Environmental Process Reasons to Conduct a Phase I Environmental Site Assessment:  Determine if contamination may be present ‐ Avoid surprises during the construction phase ‐ Reduce purchase price ‐ Address environmental issues prior to redeveloping the site  Document site conditions before you purchased it ‐ Liability Protection from EPA & LDEQ ‐ Eligibility for Brownfield Funding
  • 24. Environmental Process Liability Protection Conditions:  Phase I Environmental Site Assessments must meet EPA’s All Appropriate Inquiry / ASTM E1527-13 Standard  Performed by a “Qualified Environmental Professional”  Timing: Important to time the Phase I assessment to ensure it’s valid at time of purchase ‐ Phase I Assessments expire after 1 year for liability protection ‐ Portions of the Phase I report need to be updated after 6 months
  • 25. Environmental Process Regulatory Oversight Options for Phase II Assessments and Cleanups/ Remediation:  Traditional Oversight - Commonly called RECAP: Risk Evaluation/ Corrective Action Program  Only address areas with recognized environmental concerns  Assessment Phase is generally quicker and lower costs  May need to sample offsite to determine horizontal extent of contamination (increases costs & time)  Less flexibility if cleanup is required  LDEQ may reopened the investigation in the future (e.g., if LDEQ lowers the maximum safe concentration levels of a contaminant found onsite)
  • 26. Environmental Process Regulatory Oversight Options for Phase II Assessments and Cleanups/ Remediation:  VRP: Voluntary Remediation Program  Investigation/Cleanup covers the entire Site as defined by the Applicant  Requires additional sampling & analysis which increases upfront costs  Requires public notice & specific LDEQ approvals which increases time  Not required to sample offsite to determine horizontal extent of contamination (may save costs & time)  More flexibility if cleanup is required Can use Engineering/ Institutional Controls  Once the LDEQ approves the cleanup, the site cannot be reopened Liability protection flows down to future owners
  • 27. Example: Traditional Program/ RECAP Building Heating Oil Tank Fuel Tank
  • 28. Example: Voluntary Remediation Program Building Heating Oil Tank Fuel Tank
  • 29. RECAP Investigation (Phase II ESA) VRP Investigation (Phase II ESA)  Generally lower in costs - Less samples collected - Fewer pollutants to analyze for  Generally a faster process - No public notice required  May miss contamination in another area of the site  May need to sample offsite to determine horizontal extent of contamination  Generally more expensive - Requires more samples to be collected - Requires a wider range of analyses  More time consuming - Specific process requires more approvals - Public notice requirements  May find other contamination that was not previously known  Investigation confined to site boundaries RECAP Remediation/ Cleanup VRP Remediation/ Cleanup  Remediation of all risks is required, e.g. any contamination that is above RECAP standards needs to be remediated  Engineering/ Institutional controls generally not acceptable  Remediation can be tailored for the intended future use of the site  Engineering/Institutional controls may be used to prevent exposure to contamination - Cost savings RECAP Final Result VRP Final Result  No further action at this time (NFA) letter from LDEQ  Site may be reopened in the future (for example, if LDEQ lowers the maximum safe concentration levels)  Certificate of Completion (COC) for the entire site defined in the application  Release of liability from EPA & LDEQ for all past contamination at the site (transferable to future site owners)
  • 30. Environmental Process - Cleanup  Remediation/ Cleanup is reducing the risk of exposure to contamination at the site as detailed in the Site Cleanup Plan, including: ‐ Treating contamination on-site or in situ (in the ground) ‐ Removing the contamination ‐ Institutional Controls (e.g., conveyance notice to not allow groundwater to be used for drinking water) ‐ Engineering Controls (e.g., capping contamination with a parking lot) Goal: Reduce the risk of exposure to unsafe levels of contamination to protect Human Health & the Environment
  • 31. Environmental Process - Cleanup  Proposed Redevelopment affects the Cleanup Plan  Coordinate Cleanup with Redevelopment  Can layer funding ‐ Public/ private Funding ‐ Grants/loans  EPA Cleanup Funding = Additional Requirements
  • 32. Web Resources  US Environmental Protection Agency’s (EPA’s) Brownfields Website: www.epa.gov/brownfields/  US Department of Housing and Urban Development (HUD): http://portal.hud.gov/hudportal/HUD?src=/program_offices/comm_plann ing/economicdevelopment/programs  EPA’s RE-Powering America’s Land Initiative: www2.epa.gov/re-powering  The Brownfield and Land Revitalization Technology Support Center (EPA, USACE, ANL): www.brownfieldstsc.org