BUILDING CONSTRUCTION 1
CONSTRUCTION ACTIVITY AND PROCESS
MR. BRUCE LEE XIA SHENG
EVELYN PAUL
0311619
Week 1
Construction Activity 1: SETTING OUT
DURATION: 8 Days
EQUIPMENTS:
1. Backhoe
2. Bulldozer
3. Excavator
SKILLED WORKERS:
1. 2 Construction Supervisors
2. 3 Equipment Operators
3. 1 Excavation Foreman
4. 1 Ground Leveling Staff
5. 3 Contractors
6. 1 Plumber
7. 1 Electrician
8. 1 Carpenter
TECHNICAL INFORMATION:
Before earthworks, the planned building is set out.
 Building profiles and the use of string lines to mark the outside perimeters of the
construction and any other critical measurements. One of the most important things
in setting out is position and accuracy in which the hurdles are placed .
 Excavations will proceed and plumbers will be able to install the underground
plumbing.
 Electricians will be able to install the meter box and any pre-wires necessary.
 Carpenters may also use these set out lines to begin framing on the construction.
 Levels have to be set out based on benchmarks in the surroundings. Geometric
surveying measures the difference in height of a horizontally set up level from a
benchmark with levelling staff held vertically.
Week 2
Construction Activity 1: Earthwork
DURATION: 2 Days
EQUIPMENTS:
1. Backhoe
2. Bulldozer
3. Excavator
SKILLED WORKERS:
1. 3 Heavy Equipment Operator
2. 2 Construction Supervisor
3. 1 Excavation Foreman
4. 3 General Workers
TECHNICAL INFORMATION:
 The earth may be moved to another location and formed into a desired shape for a
purpose.
 Much of earthworks involves machine excavation and fill or backfill.
 Preservation of topsoil, slope protection, soil formation, soil loosening and soil
improvement take part of the earthwork.
 Preparing holes for the piles.
Week 3
Construction Activity 1: Piling
DURATION: 4 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
EQUIPMENTS:
1. 1 Hydraulic hammer
2. 1 Concrete vibrator
3. 1 Bar bending machine
SKILLED WORKERS:
1. 1 Pile Driver Operator
2. 2 Carpenters
3. 2 Bar Benders
4. 3 Construction Workers
TECHNICAL INFORMATION:
 According to the location of the piles in the ground reinforced concrete piles are driven
to transfer the load-bearing from the building through the weak ground to the load
bearing ground below.
Week 3
Construction Activity 2: Pile Cap
DUARTION: 4 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber formwork
EQUIPMENT:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKER:
1. 2 Carpenters
2. 2 Bar Benders
3. 5 Construction workers
TECHNICAL INFORMATION:
 After driving piles, reinforced concrete pile caps joins the head of the cluster of the
piles in order to distribute the load from a column among the piles.
 The framework is installed and reinforced cage is also installed in the framework.
 The mold is filled with the concrete.
 The framework is removed after.
Week 7
Construction Activity 1: Stump
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcement
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 3 Construction Workers
TECHNICAL INFORMATION:
 The stumps are installed between the pile cap and column.
 The framework is installed and rebar is also installed in the framework.
 The mold is filled with the concrete.
 The framework is removed after.
Week 9
Construction Activity 1: Ground Beam
DURATION: 7 Days
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Bar Bending Machine
2. 1 Concrete Vibrator
SKILLED WORKERS:
1. 2 Bar Benders
2. 3 Carpenters
3. 4 Construction Workers
TECHNICAL INFORMATION:
 Ground beams are mostly formed and placed along with the slab they support and to
distribute the tension forces.
Week 9
Construction Activity 2: Ground Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Bar Bending Machines
2. 1 Concrete Vibrator
3. Hammers
4. Nails
SKILLED WORKERS:
1. 2 Bar Benders
2. 3 Carpenters
3. 4 Construction Workers
TECHNICAL INFORMATION:
 According to the location of the column plans, reinforced concrete fills the plywood
formwork placed.
Week 10
Construction Activity 1: Ground Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
3. Hammers
4. Nails
SKILLED WORKERS:
1. 2 Carpenters
2. 3 Construction Workers
3. 1 Bar Bender
TECHNICAL INFORMATION:
 According to the location of the column plans, reinforced concrete fills the plywood
formwork placed.
Week 11
Construction Activity 1:First Floor Beam
DURATION: 7 Days
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 3 Construction Workers
TECHNICAL INFORMATION:
 The beams are mostly formed and placed along with the slabs they support to
distribute the tension forces.
Week 11
Construction Activity 1:First Floor Slab
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
 Concrete slab is a plate structure reinforced to span either a structural bay.
Week 13
Construction Activity 1: First Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 4 Construction Workers
TECHNICAL INFORMATION:
 According to the location of the column plans, reinforced concrete fills the plywood
formwork placed.
Week 14
Construction Activity 1: First Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 3 Construction Workers
TECHNICAL INFORMATION:
 According to the location of the column plans,
reinforced concrete fills the plywood formwork
placed.
Week 15
Construction Activity 1: Second Floor Beam
DURATION: 7 Days
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
 The beams are mostly formed and placed along with the slab they support and to
distribute the tension forces throughout the building.
Week 15
Construction Activity 2: Second Floor Slab
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
 Concrete slab is a plate structure
reinforced to span either a structural bay.
Week 17
Construction Activity 1: Ground Floor Slab
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
 Concrete slab is a plate structure reinforced to span either a structural bay.
Week 19
Construction Activity 1: First Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenter
2. 1 Bar Bender
3. 3 Construction Workers
TECHNICAL INFORMATION:
 According to the location of the column plans,
reinforced concrete fills the plywood formwork placed.
Week 21
Construction Activity 1: Ground Floor Staircase
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 3 Construction Workers
TECHNICAL INFORMATION:
 After the formwork is installed, the reinforced bars
join the starter bars then the concrete is poured to fill
up the formwork which will be removed after the
concrete is cured.
Week 22
Construction Activity 1: First Floor Staircase
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 3 Construction Worker
TECHNICAL INFORMATION:
 After the formwork is installed, the reinforced bars join
the starter bars then the concrete is poured to fill up
the formwork which will be removed after the
concrete is cured.
Week 23
Construction Activity 1: Roof Beam
DURATION: 7 Days
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 3 Construction Workers
TECHNICAL INFORMATION:
 The beams are mostly formed and placed along with
the slab they support and to distribute the tension
forces.
Week 24
Construction Activity 1: Roof Slab
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
 Concrete slab is a plate structure reinforced
to span either a structural bay.
 The structure of a flat roof may consist of
reinforced concrete slabs, timber or steel
beams decking and wood or steel joints and
sheathing.
 The roof slabs may be supported by reinforced concrete columns, reinforced concrete
frames or bearing walls of reinforced concrete.
Week 26
Construction Activity 1: Ground Floor Exterior Brickwork
DURATION: 3 Weeks
MATERIALS:
1. Common Clay Bricks
2. Mortar
3. Brickwork Reinforcement Mesh (Ex-Mesh)
EQUIPMENTS:
1. Brick Trowels
2. Leveling Instruments
3. Bucket
SKILLED WORKERS:
1. 1 Carpenter
2. 4 Construction Workers
TECHNICAL INFORMATION:
 Except for the spaces for the curtain walls, windows and doors, exterior brick walls are
constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
Week 27
Construction Activity 1: First Floor Exterior Brickwork
DURATION: 3 Weeks
MATERIALS:
1. Common Clay Brick
2. Mortar
3. Brickwork Reinforcement Mesh (Ex-Mesh)
EQUIPMENTS:
1. Brick Trowels
2. Leveling Instrument
3. Bucket
SKILLED WORKERS:
1. 1 Carpenter
2. 4 General Workers
TECHNICAL INFORMATION:
 Except for the spaces for the curtain walls, windows and doors, exterior brick walls are
constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
Week 28
Construction Activity 1: Second Floor Exterior Brickwork
DURATION: 3 Weeks
MATERIALS:
1. Common Clay Brick
2. Mortar
3. Brickwork Reinforcements Mesh (Ex-Mesh)
EQUIPMENTS:
1. Brick Trowels
2. Leveling Instruments
3. Bucket
SKILLED WORKERS:
1. 1 Carpenter
2. 4 Construction Workers
TECHNICAL INFORMATION:
 Except for the spaces for the curtain walls, windows and doors, exterior brick walls are
constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
Week 29
Construction Activity 1: Interior Brickwork
DURATION: 3 Weeks
MATERIALS:
1. Common Clay Brick
2. Mortar
3. Brickwork Reinforcement Mesh (Ex-
Mesh)
EQUIPMENTS:
1. Brick Trowels
2. Leveling Instruments
3. Bucket
SKILLED WORKERS:
1. 1 Carpenter
2. 4 General Workers
TECHNICAL INFORMATION:
 Except for the spaces for the curtain walls, windows and doors, exterior brick walls are
constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
Week 32
Construction Activity 1: Roof Tiling
DURATION: 3 Days
MATERIALS:
1. 1 Concrete Grade 30
2. Roof Tiles
EQUIPMENTS:
1. Mortar
2. Trowel
3. Mesh Tape
4. Sealer
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
 Concrete slab is a plate structure reinforced to span either a structural bay.
 The structure of a flat roof may consist of reinforced concrete slabs, timber or steel
beams decking and wood or steel joints and sheathing.
 The roof slabs may be supported by reinforced concrete columns, reinforced concrete
frames or bearing walls of reinforced concrete.
Week 33
Construction Activity 1: Installation of the windows and doors frame
DURATION: 11 Days
MATERIALS:
1. Aluminum
2. Timber
EQUIPMENTS:
1. Hammers
2. Nails
3. Leveling Instruments
SKILLED WORKERS:
1. 3 Construction Workers
TECHNICAL INFORMATION:
 The frames of windows and doors are installed o the space prepared after the
brickwork.
Week 35
Construction Activity 1: Plumbing and electrical
DURATION: 4 Weeks
MATERIALS:
1. Pipes
2. Wires
EQUIPMENTS:
1. Pliers
2. Cutters
3. Sealers
SKILLED WORKERS:
1. 1 Plumber
2. 1 Electrical Engineer
3. 2 Carpenters
4. 3 Construction Workers
TECHNICAL INFORMATION:
 The pipes and wires are installed for the water and electricity supply system.
Week 49
Construction Activity 1: Exterior and Interior
walls finishing
DURATION: 6 Weeks
MATERIALS:
1. Primer
2. Paint
3. Wall Plaster
EQUIPMENTS:
1. Paint Brushes
2. Rollers
3. Ladders
4. Steel Wool
SKILLED WORKERS:
1. 2 Carpenters
2. 4 Construction Workers
TECHNICAL INFORMATION:
 Painting on the exterior and interior for
both the protection and aesthetic purpose.
Week 45
Construction Activity 1: Installation of Door panels
DURATION: 7 Days
MATERIALS:
1. Wooden Door Panels
2. Hinge
EQUIPMENTS:
1. Screw Drivers
2. Sealers
SKILLED WORKERS:
1. 4 Construction Workers
TECHNICAL INFORMATION:
 The wooden door panels are installed on the prepared
space with the frame.
Week 46
Construction Activity 1: Installation of Curtain walls and glass panel
DURATION: 2 Weeks
MATERIALS:
1. Steel Mullions
2. Sealant
3. Screws
EQUIPMENTS:
1. Screw Drivers
2. Sealers
SKILLED WORKERS:
1. 4 Construction Workers
TECHNICAL INFORMATION:
 Curtain wall panel and glass panel are installed
on the prepared space with the frame. The
mullions are installed on the curtain walls after.
Week 47
Construction Activity 1: Installation of glass
sliding doors
DURATION: 2 Weeks
MATERIALS:
1. Glass panels
2. Sealant
EQUIPMENTS:
1. Sealer
SKILLED WORKERS:
1. 3 Construction Workers
TECHNICAL INFORMATION:
 Glass panels are installed on the prepared
space with the frame.
Week 59
Construction Activity 1: Installation of
staircase railing
DURATION: 3 Days
MATERIALS:
1. Glass Panels
2. Sealant
3. Steel Rail
4. Screws
EQUIPMENTS:
1. Sealer
2. Screw Driver
SKILLED WORKERS:
1. 2 Construction Workers
TECHNICAL INFORMATION:
 The steel railing and glass panels are
installed on the staircase.
Week 50
Construction Activity 1: Floor tile and wooden finishing
DURATION: 2 Weeks
MATERIALS:
1. Ceramic Tiles
2. Solid Timber Flooring
3. Porcelain Tiles
EQUIPMENTS:
5. Mortar
6. Trowel
7. Mesh Tape
8. Sealer
SKILLED WORKERS:
1. 2 Construction Workers
TECHNICAL INFORMATION:
 The tile finishing for the living room, kitchen, balcony and bathroom and wooden
finishing for the rooms are installed.
Week 52
Construction Activity 1: Installation of Window Panels
DURATION: 7 Days
MATERIALS:
3. Wooden window
4. Hinge
EQUIPMENTS:
3. Screw Drivers
4. Sealers
SKILLED WORKERS:
2. 4 Construction Workers
TECHNICAL INFORMATION:
 The wooden window panels are installed on the prepared space with the frame.
Week 53
Construction Activity 1: Installation of fixed furniture and utilities
DURATION: 2 Weeks
MATERIALS:
1. Medium and Soft Woods
2. Varnish
3. Glue
4. Water Heater
5. Paint
6. Light Bulbs
7. Fixed Electrical Appliances
EQUIPMENTS:
1. Hammers
2. Nails
3. Cutters
4. Table Saw
SKILLED WORKERS:
1. 2 Construction Workers
2. 1 Electrician
TECHNICAL INFORMATION:
 The fixed furniture such as lighting , telephone, door bell, fan, bath tub, basin, toilet
bowl, cabinet and etc are installed at the end.
Building Construction 1 - Final Project

More Related Content

DOCX
Construction Activities and Process
PDF
U.S. Construction Perspective Q3 2015
 
PDF
Bungalow
PDF
Building Construction process
DOCX
Bcon final report
PDF
Construction Activities and Process
PDF
Project Report - CECL
PPTX
kuku.pptx
Construction Activities and Process
U.S. Construction Perspective Q3 2015
 
Bungalow
Building Construction process
Bcon final report
Construction Activities and Process
Project Report - CECL
kuku.pptx

Similar to Building Construction 1 - Final Project (20)

DOCX
Ayush
DOCX
Site report
DOCX
Report
PPTX
D&G 07 8tH 30-compressed silica fluid.pptx
PPTX
Educational opportunities Internship CIE-4-25-1.pptx
DOCX
Site report
PPT
rustomji urbania- technical presentation (r2) (1).ppt
PPT
Construction basic SIP
DOCX
D18cl124 internship_report
DOCX
Report
DOCX
Site report assignment
DOCX
Site visitation
PPTX
Document design for presentation in class
DOCX
CPCCBC5018A Apply Structural Principles To The Construction Of Medium Rise.docx
PPTX
Practical field Training and Report submission
PPTX
CHETHAN PPT cambridge college details.pptx
PPTX
internship report of a civil engineer student
PPTX
Industrial training report of construction of the residential building
DOCX
Site visit report
PPTX
1GC20CV01223vggfgcghcgftgftyfhgtydtydtt.pptx
Ayush
Site report
Report
D&G 07 8tH 30-compressed silica fluid.pptx
Educational opportunities Internship CIE-4-25-1.pptx
Site report
rustomji urbania- technical presentation (r2) (1).ppt
Construction basic SIP
D18cl124 internship_report
Report
Site report assignment
Site visitation
Document design for presentation in class
CPCCBC5018A Apply Structural Principles To The Construction Of Medium Rise.docx
Practical field Training and Report submission
CHETHAN PPT cambridge college details.pptx
internship report of a civil engineer student
Industrial training report of construction of the residential building
Site visit report
1GC20CV01223vggfgcghcgftgftyfhgtydtydtt.pptx
Ad

Recently uploaded (20)

PDF
Pongal 2026 Sponsorship Presentation - Bhopal Tamil Sangam
PPTX
Orthtotics presentation regarding physcial therapy
PDF
intro_to_rust.pptx_123456789012446789.pdf
PPTX
EDP Competencies-types, process, explanation
PPTX
CLASSIFICATION OF YARN- process, explanation
PDF
Skskkxiixijsjsnwkwkaksixindndndjdjdjsjjssk
PDF
ART & DESIGN HISTORY OF VEDIC CIVILISATION.pdf
PDF
2025_AIFG_Akane_Kikuchi_Empathy_Design.PDF
PPTX
Causes of Flooding by Slidesgo sdnl;asnjdl;asj.pptx
PDF
Test slideshare presentation for blog post
PDF
UNIT 1 Introduction fnfbbfhfhfbdhdbdto Java.pptx.pdf
PPTX
rapid fire quiz in your house is your india.pptx
PPTX
2. Competency Based Interviewing - September'16.pptx
PDF
GSH-Vicky1-Complete-Plans on Housing.pdf
PPT
EthicsNotesSTUDENTCOPYfghhnmncssssx sjsjsj
PDF
SOUND-NOTE-ARCHITECT-MOHIUDDIN AKHAND SMUCT
PPT
WHY_R12 Uaafafafpgradeaffafafafaffff.ppt
PPT
aksharma-dfs.pptgfgfgdfgdgdfgdfgdgdrgdgdgdgdgdgadgdgd
PPTX
Media And Information Literacy for Grade 12
PDF
Chalkpiece Annual Report from 2019 To 2025
Pongal 2026 Sponsorship Presentation - Bhopal Tamil Sangam
Orthtotics presentation regarding physcial therapy
intro_to_rust.pptx_123456789012446789.pdf
EDP Competencies-types, process, explanation
CLASSIFICATION OF YARN- process, explanation
Skskkxiixijsjsnwkwkaksixindndndjdjdjsjjssk
ART & DESIGN HISTORY OF VEDIC CIVILISATION.pdf
2025_AIFG_Akane_Kikuchi_Empathy_Design.PDF
Causes of Flooding by Slidesgo sdnl;asnjdl;asj.pptx
Test slideshare presentation for blog post
UNIT 1 Introduction fnfbbfhfhfbdhdbdto Java.pptx.pdf
rapid fire quiz in your house is your india.pptx
2. Competency Based Interviewing - September'16.pptx
GSH-Vicky1-Complete-Plans on Housing.pdf
EthicsNotesSTUDENTCOPYfghhnmncssssx sjsjsj
SOUND-NOTE-ARCHITECT-MOHIUDDIN AKHAND SMUCT
WHY_R12 Uaafafafpgradeaffafafafaffff.ppt
aksharma-dfs.pptgfgfgdfgdgdfgdfgdgdrgdgdgdgdgdgadgdgd
Media And Information Literacy for Grade 12
Chalkpiece Annual Report from 2019 To 2025
Ad

Building Construction 1 - Final Project

  • 1. BUILDING CONSTRUCTION 1 CONSTRUCTION ACTIVITY AND PROCESS MR. BRUCE LEE XIA SHENG EVELYN PAUL 0311619
  • 2. Week 1 Construction Activity 1: SETTING OUT DURATION: 8 Days EQUIPMENTS: 1. Backhoe 2. Bulldozer 3. Excavator SKILLED WORKERS: 1. 2 Construction Supervisors 2. 3 Equipment Operators 3. 1 Excavation Foreman 4. 1 Ground Leveling Staff 5. 3 Contractors 6. 1 Plumber 7. 1 Electrician 8. 1 Carpenter TECHNICAL INFORMATION: Before earthworks, the planned building is set out.  Building profiles and the use of string lines to mark the outside perimeters of the construction and any other critical measurements. One of the most important things in setting out is position and accuracy in which the hurdles are placed .  Excavations will proceed and plumbers will be able to install the underground plumbing.  Electricians will be able to install the meter box and any pre-wires necessary.  Carpenters may also use these set out lines to begin framing on the construction.  Levels have to be set out based on benchmarks in the surroundings. Geometric surveying measures the difference in height of a horizontally set up level from a benchmark with levelling staff held vertically.
  • 3. Week 2 Construction Activity 1: Earthwork DURATION: 2 Days EQUIPMENTS: 1. Backhoe 2. Bulldozer 3. Excavator SKILLED WORKERS: 1. 3 Heavy Equipment Operator 2. 2 Construction Supervisor 3. 1 Excavation Foreman 4. 3 General Workers TECHNICAL INFORMATION:  The earth may be moved to another location and formed into a desired shape for a purpose.  Much of earthworks involves machine excavation and fill or backfill.  Preservation of topsoil, slope protection, soil formation, soil loosening and soil improvement take part of the earthwork.  Preparing holes for the piles.
  • 4. Week 3 Construction Activity 1: Piling DURATION: 4 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements EQUIPMENTS: 1. 1 Hydraulic hammer 2. 1 Concrete vibrator 3. 1 Bar bending machine SKILLED WORKERS: 1. 1 Pile Driver Operator 2. 2 Carpenters 3. 2 Bar Benders 4. 3 Construction Workers TECHNICAL INFORMATION:  According to the location of the piles in the ground reinforced concrete piles are driven to transfer the load-bearing from the building through the weak ground to the load bearing ground below.
  • 5. Week 3 Construction Activity 2: Pile Cap DUARTION: 4 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber formwork EQUIPMENT: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKER: 1. 2 Carpenters 2. 2 Bar Benders 3. 5 Construction workers TECHNICAL INFORMATION:  After driving piles, reinforced concrete pile caps joins the head of the cluster of the piles in order to distribute the load from a column among the piles.  The framework is installed and reinforced cage is also installed in the framework.  The mold is filled with the concrete.  The framework is removed after.
  • 6. Week 7 Construction Activity 1: Stump DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcement 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 3 Construction Workers TECHNICAL INFORMATION:  The stumps are installed between the pile cap and column.  The framework is installed and rebar is also installed in the framework.  The mold is filled with the concrete.  The framework is removed after.
  • 7. Week 9 Construction Activity 1: Ground Beam DURATION: 7 Days MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Bar Bending Machine 2. 1 Concrete Vibrator SKILLED WORKERS: 1. 2 Bar Benders 2. 3 Carpenters 3. 4 Construction Workers TECHNICAL INFORMATION:  Ground beams are mostly formed and placed along with the slab they support and to distribute the tension forces.
  • 8. Week 9 Construction Activity 2: Ground Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Bar Bending Machines 2. 1 Concrete Vibrator 3. Hammers 4. Nails SKILLED WORKERS: 1. 2 Bar Benders 2. 3 Carpenters 3. 4 Construction Workers TECHNICAL INFORMATION:  According to the location of the column plans, reinforced concrete fills the plywood formwork placed.
  • 9. Week 10 Construction Activity 1: Ground Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine 3. Hammers 4. Nails SKILLED WORKERS: 1. 2 Carpenters 2. 3 Construction Workers 3. 1 Bar Bender TECHNICAL INFORMATION:  According to the location of the column plans, reinforced concrete fills the plywood formwork placed.
  • 10. Week 11 Construction Activity 1:First Floor Beam DURATION: 7 Days MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 3 Construction Workers TECHNICAL INFORMATION:  The beams are mostly formed and placed along with the slabs they support to distribute the tension forces.
  • 11. Week 11 Construction Activity 1:First Floor Slab DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION:  Concrete slab is a plate structure reinforced to span either a structural bay.
  • 12. Week 13 Construction Activity 1: First Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 4 Construction Workers TECHNICAL INFORMATION:  According to the location of the column plans, reinforced concrete fills the plywood formwork placed.
  • 13. Week 14 Construction Activity 1: First Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 3 Construction Workers TECHNICAL INFORMATION:  According to the location of the column plans, reinforced concrete fills the plywood formwork placed.
  • 14. Week 15 Construction Activity 1: Second Floor Beam DURATION: 7 Days MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION:  The beams are mostly formed and placed along with the slab they support and to distribute the tension forces throughout the building.
  • 15. Week 15 Construction Activity 2: Second Floor Slab DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar benders 3. 4 Construction Workers TECHNICAL INFORMATION:  Concrete slab is a plate structure reinforced to span either a structural bay.
  • 16. Week 17 Construction Activity 1: Ground Floor Slab DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION:  Concrete slab is a plate structure reinforced to span either a structural bay.
  • 17. Week 19 Construction Activity 1: First Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenter 2. 1 Bar Bender 3. 3 Construction Workers TECHNICAL INFORMATION:  According to the location of the column plans, reinforced concrete fills the plywood formwork placed.
  • 18. Week 21 Construction Activity 1: Ground Floor Staircase DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 3 Construction Workers TECHNICAL INFORMATION:  After the formwork is installed, the reinforced bars join the starter bars then the concrete is poured to fill up the formwork which will be removed after the concrete is cured.
  • 19. Week 22 Construction Activity 1: First Floor Staircase DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 3 Construction Worker TECHNICAL INFORMATION:  After the formwork is installed, the reinforced bars join the starter bars then the concrete is poured to fill up the formwork which will be removed after the concrete is cured.
  • 20. Week 23 Construction Activity 1: Roof Beam DURATION: 7 Days MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 3 Construction Workers TECHNICAL INFORMATION:  The beams are mostly formed and placed along with the slab they support and to distribute the tension forces.
  • 21. Week 24 Construction Activity 1: Roof Slab DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION:  Concrete slab is a plate structure reinforced to span either a structural bay.  The structure of a flat roof may consist of reinforced concrete slabs, timber or steel beams decking and wood or steel joints and sheathing.  The roof slabs may be supported by reinforced concrete columns, reinforced concrete frames or bearing walls of reinforced concrete.
  • 22. Week 26 Construction Activity 1: Ground Floor Exterior Brickwork DURATION: 3 Weeks MATERIALS: 1. Common Clay Bricks 2. Mortar 3. Brickwork Reinforcement Mesh (Ex-Mesh) EQUIPMENTS: 1. Brick Trowels 2. Leveling Instruments 3. Bucket SKILLED WORKERS: 1. 1 Carpenter 2. 4 Construction Workers TECHNICAL INFORMATION:  Except for the spaces for the curtain walls, windows and doors, exterior brick walls are constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
  • 23. Week 27 Construction Activity 1: First Floor Exterior Brickwork DURATION: 3 Weeks MATERIALS: 1. Common Clay Brick 2. Mortar 3. Brickwork Reinforcement Mesh (Ex-Mesh) EQUIPMENTS: 1. Brick Trowels 2. Leveling Instrument 3. Bucket SKILLED WORKERS: 1. 1 Carpenter 2. 4 General Workers TECHNICAL INFORMATION:  Except for the spaces for the curtain walls, windows and doors, exterior brick walls are constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
  • 24. Week 28 Construction Activity 1: Second Floor Exterior Brickwork DURATION: 3 Weeks MATERIALS: 1. Common Clay Brick 2. Mortar 3. Brickwork Reinforcements Mesh (Ex-Mesh) EQUIPMENTS: 1. Brick Trowels 2. Leveling Instruments 3. Bucket SKILLED WORKERS: 1. 1 Carpenter 2. 4 Construction Workers TECHNICAL INFORMATION:  Except for the spaces for the curtain walls, windows and doors, exterior brick walls are constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
  • 25. Week 29 Construction Activity 1: Interior Brickwork DURATION: 3 Weeks MATERIALS: 1. Common Clay Brick 2. Mortar 3. Brickwork Reinforcement Mesh (Ex- Mesh) EQUIPMENTS: 1. Brick Trowels 2. Leveling Instruments 3. Bucket SKILLED WORKERS: 1. 1 Carpenter 2. 4 General Workers TECHNICAL INFORMATION:  Except for the spaces for the curtain walls, windows and doors, exterior brick walls are constructed. Ex-meshes are placed on every fifth brick joint to strengthen. GROUND FLOOR
  • 27. Week 32 Construction Activity 1: Roof Tiling DURATION: 3 Days MATERIALS: 1. 1 Concrete Grade 30 2. Roof Tiles EQUIPMENTS: 1. Mortar 2. Trowel 3. Mesh Tape 4. Sealer SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION:  Concrete slab is a plate structure reinforced to span either a structural bay.  The structure of a flat roof may consist of reinforced concrete slabs, timber or steel beams decking and wood or steel joints and sheathing.  The roof slabs may be supported by reinforced concrete columns, reinforced concrete frames or bearing walls of reinforced concrete.
  • 28. Week 33 Construction Activity 1: Installation of the windows and doors frame DURATION: 11 Days MATERIALS: 1. Aluminum 2. Timber EQUIPMENTS: 1. Hammers 2. Nails 3. Leveling Instruments SKILLED WORKERS: 1. 3 Construction Workers TECHNICAL INFORMATION:  The frames of windows and doors are installed o the space prepared after the brickwork. Week 35 Construction Activity 1: Plumbing and electrical DURATION: 4 Weeks MATERIALS: 1. Pipes 2. Wires EQUIPMENTS: 1. Pliers 2. Cutters 3. Sealers SKILLED WORKERS: 1. 1 Plumber 2. 1 Electrical Engineer 3. 2 Carpenters 4. 3 Construction Workers TECHNICAL INFORMATION:  The pipes and wires are installed for the water and electricity supply system.
  • 29. Week 49 Construction Activity 1: Exterior and Interior walls finishing DURATION: 6 Weeks MATERIALS: 1. Primer 2. Paint 3. Wall Plaster EQUIPMENTS: 1. Paint Brushes 2. Rollers 3. Ladders 4. Steel Wool SKILLED WORKERS: 1. 2 Carpenters 2. 4 Construction Workers TECHNICAL INFORMATION:  Painting on the exterior and interior for both the protection and aesthetic purpose.
  • 30. Week 45 Construction Activity 1: Installation of Door panels DURATION: 7 Days MATERIALS: 1. Wooden Door Panels 2. Hinge EQUIPMENTS: 1. Screw Drivers 2. Sealers SKILLED WORKERS: 1. 4 Construction Workers TECHNICAL INFORMATION:  The wooden door panels are installed on the prepared space with the frame. Week 46 Construction Activity 1: Installation of Curtain walls and glass panel DURATION: 2 Weeks MATERIALS: 1. Steel Mullions 2. Sealant 3. Screws EQUIPMENTS: 1. Screw Drivers 2. Sealers SKILLED WORKERS: 1. 4 Construction Workers TECHNICAL INFORMATION:  Curtain wall panel and glass panel are installed on the prepared space with the frame. The mullions are installed on the curtain walls after.
  • 31. Week 47 Construction Activity 1: Installation of glass sliding doors DURATION: 2 Weeks MATERIALS: 1. Glass panels 2. Sealant EQUIPMENTS: 1. Sealer SKILLED WORKERS: 1. 3 Construction Workers TECHNICAL INFORMATION:  Glass panels are installed on the prepared space with the frame. Week 59 Construction Activity 1: Installation of staircase railing DURATION: 3 Days MATERIALS: 1. Glass Panels 2. Sealant 3. Steel Rail 4. Screws EQUIPMENTS: 1. Sealer 2. Screw Driver SKILLED WORKERS: 1. 2 Construction Workers TECHNICAL INFORMATION:  The steel railing and glass panels are installed on the staircase.
  • 32. Week 50 Construction Activity 1: Floor tile and wooden finishing DURATION: 2 Weeks MATERIALS: 1. Ceramic Tiles 2. Solid Timber Flooring 3. Porcelain Tiles EQUIPMENTS: 5. Mortar 6. Trowel 7. Mesh Tape 8. Sealer SKILLED WORKERS: 1. 2 Construction Workers TECHNICAL INFORMATION:  The tile finishing for the living room, kitchen, balcony and bathroom and wooden finishing for the rooms are installed.
  • 33. Week 52 Construction Activity 1: Installation of Window Panels DURATION: 7 Days MATERIALS: 3. Wooden window 4. Hinge EQUIPMENTS: 3. Screw Drivers 4. Sealers SKILLED WORKERS: 2. 4 Construction Workers TECHNICAL INFORMATION:  The wooden window panels are installed on the prepared space with the frame.
  • 34. Week 53 Construction Activity 1: Installation of fixed furniture and utilities DURATION: 2 Weeks MATERIALS: 1. Medium and Soft Woods 2. Varnish 3. Glue 4. Water Heater 5. Paint 6. Light Bulbs 7. Fixed Electrical Appliances EQUIPMENTS: 1. Hammers 2. Nails 3. Cutters 4. Table Saw SKILLED WORKERS: 1. 2 Construction Workers 2. 1 Electrician TECHNICAL INFORMATION:  The fixed furniture such as lighting , telephone, door bell, fan, bath tub, basin, toilet bowl, cabinet and etc are installed at the end.