Building Construction 1 [ARC 1523]
Project 2: Construction Activities and Process
Tan Wei How 0310707
Week 1
Week 2
Activity 1: Grading and Site Preparation
Duration: 5 days
Materials: Timber, Hoarding
Equipment: Theodolite, waste storage tank, backhoe, shovels, truck, construction
trolleys
Skilled worker: Land surveyor, Mobilization of manpower (carpenter), general
workers (2), Backhoe operator (1)
Technical information: Clearing up the site. Land demarcation for the site
boundary of site by using hoarding as safety guideline for whole construction site.
Activity 1: Earthwork
Duration: 6 days
Materials: -
Equipment: Vibrating plate compactor, backhoe, excavator, paver, dumper
Skilled worker: Backhoe operator, excavator operator, paver operator, dumper
operator
Technical information: Site is cut and filled to required lengths, depths, breadths.
Unflatten land surface need to fill up and cut down with sand or soil just to flatten
the land boundary that had been demarked.
Week 3 - 4
Activity 1: Foundation Construction (Piling process)
Duration: 10 days
Materials: piles, pile cushion, bituminous paint
Equipment: Hydraulic drop hammer (1)
Skilled worker: contractor (1), Hydraulic drop hammer operator (1), General
worker (2)
Technical information: Mobilize the hydraulic drop hammer to the intended pile
position after marking penetration of the piles, set out the position of drop hammer
above the pile point, pile driving, weld the joints between the piles, apply
bituminous paint around the joints of welded piles to prevent rusting.
Activity 2: Foundation Construction (Cut off process)
Duration: 2 days
Materials: -
Equipment: Multipurpose excavator, Pneumatic hammer, Oxy-cutter
Skilled worker: Excavator operator (1), General worker (2)
Technical information: Excavate 1m to 1.5m depth by using Multipurpose
excavator, Cut the piles to make sure all are in the same height using Pneumatic
hammer, the reinforcement in the pile is cut by oxy-cutter.
Week 5
Activity 1: Foundation Construction (Setting up formwork for pile cap)
Duration: 3 days
Materials: Plywood, nails, reinforcement mesh
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general worker (2), carpenter (1)
Technical information: Set up formwork for pile cap, insert reinforcement for
pile cap, and set up the reinforcement for column stump before pouring the
concrete.
Activity 2: Foundation Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: Concrete mixer truck, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (2)
Technical information: Pour the concrete into the formwork through skip from
concrete mixer truck, vibrate and mix the concrete evenly using concrete vibrator
to increase its strength by preventing air pockets.
Week 6
Week 7
Activity 1: Foundation Construction (Setting up formwork for column stump)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (1), carpenter (1)
Technical information: Set up formwork for column stump before pouring the
concrete.
Activity 1: Foundation Construction (Pile cap curing period)
Duration: 7days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete pile cap harden for 7 days to wait it
mature and sufficient strength, open formwork after completed.
Activity 2: Foundation Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: Concrete mixer truck, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (2)
Technical information: Pour the concrete into the formwork, vibrate the
concrete to increase its strength.
Week 8
Activity 1: Foundation Construction (Column Stump Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete column stump harden for 7 days
to wait it mature and sufficient strength, open formwork after completed
Activity 2: Slab Electrical Installation
Duration: 3 days
Materials: Metal conduit, Steel/Aluminum tubing or PVC tubing
Equipment: Plow Chute, Winch
Skilled worker: Contractor (1), General worker (2)
Technical information: Socket of connection to the utility wiring is covered
in the ground at a depth that protects conductors from physical damage and
physical contact. Burying cable preinstalled in cable-in-conduit (CIC) offers
greater physical protection against environment, abrasion, and rocks than
direct burial, which can prolong the life of the cable.
Activity 3: Slab Plumbing Installation
Duration: 3 days
Materials: PVC pipes, PVC pipefittings, soft copper tubing, septic tank
Equipment: pressure test pump, bobcat, trencher, measuring tape, shovel
Skilled worker: Plumber (1), Trencher operator (1)
Technical information: Dig trenches as needed to run the sewer pipes and water
pipes, and should smooth the dirt or sand back when finished.
Week 9
Activity 1: Ground Floor Construction (Tying Rebar for Beam)
Duration: 4 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel
cage that will reinforce the pour concrete. They are tied together with tie wire
at varying intervals.
Activity 3: Slab Plumbing Installation
Duration: 3 days
Materials: PVC pipes, PVC pipefittings, soft copper tubing, septic tank
Equipment: pressure test pump, bobcat, trencher, measuring tape, shovel
Skilled worker: Plumber (1), Trencher operator (1)
Technical information: Dig trenches as needed to run the sewer pipes and water
pipes, and should smooth the dirt or sand back when finished.
Activity 2: Slab Electrical Installation
Duration: 3 days
Materials: Metal conduit, Steel/Aluminum tubing or PVC tubing
Equipment: Plow Chute, Winch
Skilled worker: Contractor (1), General worker (2)
Technical information: Socket of connection to the utility wiring is covered
in the ground at a depth that protects conductors from physical damage and
physical contact. Burying cable preinstalled in cable-in-conduit (CIC) offers
greater physical protection against environment, abrasion, and rocks than
direct burial, which can prolong the life of the cable.
Week 10
Week 11
Activity 1: Ground Floor Construction (Setting up formwork for beam)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for beam before pouring the concrete.
Activity 2: Ground Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: Concrete mixer truck, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (2))
Technical information: Pour the concrete into the formwork through skip
from concrete mixer truck, vibrate the concrete to increase its strength.
Activity 1: Ground Floor Construction (Beam Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete beam harden for 7 days to wait it
mature and sufficient strength, open formwork after completed
Week 12
Week 13
Activity 1: Ground Floor Construction (Tying Rebar for Slab)
Duration: 5 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel
cage that will reinforce the pour concrete. They are tied together with tie wire
at varying intervals.
Activity 1: Ground Floor Construction (Setting up formwork for Slab)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for beam before pouring the concrete.
Activity 2: Ground Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: Concrete mixer truck, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (2))
Technical information: Pour the concrete into the formwork through skip
from concrete mixer truck, vibrate the concrete to increase its strength
Week 14
Week 15
Activity 1: Ground Floor Construction (Slab Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete slab harden for 7 days to wait it mature
and sufficient strength, open formwork after completed
Activity 1: Ground Floor Construction (Reinforce Column)
Duration: 6 days
Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
concrete mixer truck, concrete vibrator
Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1)
Technical information: Place rebar as instructed, position formwork for column, pour
the concrete into the formwork through skip from concrete mixer truck, vibrate the
concrete to increase its strength.
Week 16
Activity 2: Rough Electrical Installation (Ground Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members. Wiring requirements differ
depending on the construction type and building element.
Activity 3: Rough Plumbing Installation (Ground Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader,
steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping
Activity 4: Rough HVAC Installation (Ground Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed and
run to each location. The furnace is installed as well.
Activity 1: Ground Floor Construction (Column Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete column harden for 7 days to wait it mature
and sufficient strength, open formwork after completed
Week 17
Activity 1: First Floor Construction (Tying Rebar for Beam)
Duration: 4 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel cage that
will reinforce the pour concrete. They are tied together with tie wire at varying intervals.
Activity 2: Rough Electrical Installation (Ground Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members. Wiring requirements differ
depending on the construction type and building element.
Activity 3: Rough Plumbing Installation (Ground Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader,
steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping
Activity 4: Rough HVAC Installation (Ground Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed and
run to each location. The furnace is installed as well.
Week 18
Activity 1: First Floor Construction (Setting up formwork for beam)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for beam before pouring the concrete.
Activity 2: First Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: concrete mixer truck, concrete vibrator, pumps and boom-mounted
hoses
Skilled worker: Concrete mixer truck operator (1), pumps and boom-mounted
hoses operator (1), general worker (1)
Technical information: Concrete is pumped and poured into the formwork
through pipes and large hoses, vibrate the concrete to increase its strength.
Week 19
Week 20
Activity 1: First Floor Construction (Beam Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete beam harden for 7 days to wait it
mature and sufficient strength, open formwork after completed
Activity 1: First Floor Construction (Tying Rebar for Slab)
Duration: 5 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel cage
that will reinforce the pour concrete. They are tied together with tie wire at varying
intervals.
Week 21
Activity 1: First Floor Construction (Setting up formwork for Slab)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for slab before pouring the concrete.
Activity 2: First Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: concrete mixer truck, concrete vibrator, pumps and boom-
mounted hoses
Skilled worker: Concrete mixer truck operator (1), pumps and boom-
mounted hoses operator (1), general worker (1)
Technical information: Concrete is pumped and poured into the
formwork through pipes and large hoses, vibrate the concrete to
increase its strength.
Week 22
Activity 2: Staircase Construction (Ground Floor)
Duration: 6 days
Materials: Plywood, Timber Battens, rebar ribs, steel cage, concrete grade 30
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
Concrete mixer truck, Concrete vibrator
Skilled worker: Carpenter (1), Concrete mixer truck operator (1), general worker (2)
Technical information: Construct formwork by laying out riser heights and tread
widths followed by soffit, joist and stringer lines. Then lay out thickness of risers
from boards. Place rebar as instructed. Pour the concrete into the formwork. Keep
the concrete wet or damp to prevent cracks for up to one week while it cures.
Activity 1: First Floor Construction (Slab Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete slab harden for 7 days to wait it
mature and sufficient strength, open formwork after completed
Week 23
Activity 2: Wall Construction (Ground Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Activity 1: First Floor Construction (Reinforce Column)
Duration: 6 days
Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses
Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1)
Technical information: Place rebar as instructed, position formwork for column.
Concrete is pumped and poured into the formwork through pipes and large hoses,
vibrate the concrete to increase its strength.
Week 24
Activity 1: First Floor Construction (Column Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete column harden for 7 days to wait it mature
and sufficient strength, open formwork after completed
Activity 2: Wall Construction (Ground Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Activity 5: Rough HVAC Installation (First Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed
and run to each location. The furnace is installed as well.
Activity 3: Rough Electrical Installation (First Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members such as the interior walls,
ceilings and floors. Wiring requirements differ depending on the construction type
and building element.
Activity 4: Rough Plumbing Installation (First Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader,
steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping.
Week 25
Activity 1: Second Floor Construction (Tying Rebar for Beam)
Duration: 4 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel cage
that will reinforce the pour concrete. They are tied together with tie wire at varying
intervals.
Activity 2: Wall Construction (Ground Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Activity 5: Rough HVAC Installation (First Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed and
run to each location. The furnace is installed as well.
Activity 3: Rough Electrical Installation (First Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members such as the interior walls,
ceilings and floors. Wiring requirements differ depending on the construction type
and building element.
Activity 4: Rough Plumbing Installation (First Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader,
steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping
Week 26
Activity 1: Second Floor Construction (Setting up formwork for beam)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for beam before pouring the concrete.
Activity 2: Second Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: concrete mixer truck, concrete vibrator, pumps and boom-mounted
hoses
Skilled worker: Concrete mixer truck operator (1), pumps and boom-mounted
hoses operator (1), general worker (1)
Technical information: Concrete is pumped and poured into the formwork
through pipes and large hoses, vibrate the concrete to increase its strength.
Activity 3: Wall Construction (Ground Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Week 27
Week 28
Activity 1: Second Floor Construction (Beam Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete beam harden for 7 days to wait it
mature and sufficient strength, open formwork after completed
Activity 1: Second Floor Construction (Tying Rebar for Slab)
Duration: 5 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel cage
that will reinforce the pour concrete. They are tied together with tie wire at varying
intervals.
Week 29
Activity 1: Second Floor Construction (Setting up formwork for Slab)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for slab before pouring the concrete.
Activity 2: Second Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: concrete mixer truck, concrete vibrator, pumps and boom-
mounted hoses
Skilled worker: Concrete mixer truck operator (1), pumps and boom-
mounted hoses operator (1), general worker (1)
Technical information: Concrete is pumped and poured into the
formwork through pipes and large hoses, vibrate the concrete to
increase its strength.
Week 30
Activity 2: Staircase Construction (First Floor)
Duration: 6 days
Materials: Plywood, Timber Battens, rebar ribs, steel cage, concrete grade 30
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
Concrete mixer truck, Concrete vibrator
Skilled worker: Carpenter (1), Concrete mixer truck operator (1), general worker (2)
Technical information: Construct formwork by laying out riser heights and tread
widths followed by soffit, joist and stringer lines. Then lay out thickness of risers
from boards. Place rebar as instructed. Pour the concrete into the formwork. Keep
the concrete wet or damp to prevent cracks for up to one week while it cures
Activity 1: Second Floor Construction (Slab Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete slab harden for 7 days to wait it mature
and sufficient strength, open formwork after completed
Week 31
Activity 2: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Activity 1: Second Floor Construction (Reinforce Column)
Duration: 6 days
Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses
Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1)
Technical information: Place rebar as instructed, position formwork for column.
Concrete is pumped and poured into the formwork through pipes and large
hoses, vibrate the concrete to increase its strength.
Week 32
Activity 1: Second Floor Construction (Column Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete column harden for 7 days to wait it mature
and sufficient strength, open formwork after completed
Activity 2: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Week 33
Week 34
Activity 1: Roof Construction (Reinforce Beam)
Duration: 6 days
Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses
Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1)
Technical information: Place rebar as instructed, position formwork for beam.
Concrete is pumped and poured into the formwork through pipes and large
hoses, vibrate the concrete to increase its strength.
Activity 2: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Activity 1: Roof Construction
Duration: 6 days
Materials: steel joists, concrete slab, rebar, grout (sand and Portland cement)
Equipment: Concrete mixer truck, concrete vibrator, scaffold, rebar mesh making
machine, pumps and boom-mounted hoses
Skilled worker: concrete mixer truck operator (1), general workers (2)
Technical information: Place the steel joists. The bottom of the steel joists should
rest on either a beam or a wall. This will give it the required support. Place the
concrete slab on its face. Insert full-length rebar to the unit. The grout has to be
poured into the space between the rows of concrete slabs. The joists have to be
covered completely.
Activity 2: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Week 35
Activity 1: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Activity 2: Rough Electrical Installation (Second Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members. Wiring requirements differ
depending on the construction type and building element.
Activity 4: Rough HVAC Installation (Second Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed
and run to each location. The furnace is installed as well.
Activity 3: Rough Plumbing Installation (Second Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe
threader, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe
cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping
Week 36
Activity 2: Ceiling Installation (Ground Floor)
Duration: 3 days
Materials: Ceiling panels, main runners
Equipment: hacksaw, utility knife, measuring tape
Skilled worker: general workers (2)
Technical information: Set the main runners into place. Install the cross tee
sections of the ceiling grid. Install the panels. Tilt each panel to angle it through a
grid opening, then carefully lower it until it rests on the bracket edges of the grid
sections.
Activity 1: Wall Construction (Second Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel
fully embedded in Portland cement grout. The steel angles, can provide all the
support, or be attached to the primary structure such as a reinforced concrete
frame, to which the load is transferred.
Week 37
Activity 1: Wall Construction (Second Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.
Activity 2: Ceiling Installation (First Floor)
Duration: 3 days
Materials: Ceiling panels, main runners
Equipment: hacksaw, utility knife, measuring tape
Skilled worker: general workers (2)
Technical information: Set the main runners into place. Install the cross tee
sections of the ceiling grid. Install the panels. Tilt each panel to angle it through a
grid opening, then carefully lower it until it rests on the bracket edges of the grid
sections.
Week 38
Activity 1: Wall Construction (Second Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel
fully embedded in Portland cement grout. The steel angles, can provide all the
support, or be attached to the primary structure such as a reinforced concrete
frame, to which the load is transferred.
Activity 2: Ceiling Installation (Second Floor)
Duration: 3 days
Materials: Ceiling panels, main runners
Equipment: hacksaw, utility knife, measuring tape
Skilled worker: general workers (2)
Technical information: Set the main runners into place. Install the cross tee
sections of the ceiling grid. Install the panels. Tilt each panel to angle it through a
grid opening, then carefully lower it until it rests on the bracket edges of the grid
sections.
Week 39 - 40
Activity 1: Plastering and Painting of Exterior and Interior Walls
Duration: 8 days
Materials: plaster, mixed blended white cement, coving, paint
Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders,
scaffolds, tape and masking
Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1),
painter (1)
Technical information: Plastering on the surface of brick wall after cleaning
with masonry brush. Then, scratch first coat of render before it set to provide
key for second layer. Wall painting with color chosen.
Activity 2: Finish Electrical
Duration: 3 days
Materials: main electrical panel, receptacle
Equipment: Driller, locknut, screw, nickel/silver, beryllium copper, plastic
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: The panel distributes the electricity to all the electrical
circuits that are installed in the house. Electrician installs receptacles for outlets,
lights and switches and runs wires from the breaker panel to each receptacle.
Activity 3: Finish Plumbing
Duration: 2 days
Materials: Waters taps
Equipment: clamp tool, flaring pliers
Skilled worker: Plumber (1)
Technical information: Water taps are installed to every sink in kitchen and
bathroom, and against exterior wall.
Week 41
Activity 4: Finish HVAC
Duration: 2 days
Materials: Thermostats, Registers
Equipment: Hand Tool Set
Skilled worker: HVAC installer
Technical information: Nearly all of the HVAC work is done during the
rough in stage. The HVAC installer install the thermostats, placed the
registers and made a few final adjustments and tests to make sure that
everything was running properly.
Activity 2: Finish Electrical
Duration: 3 days
Materials: main electrical panel, receptacle
Equipment: Driller, locknut, screw, nickel/silver, beryllium copper, plastic
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: The panel distributes the electricity to all the electrical
circuits that are installed in the house. Electrician installs receptacles for outlets,
lights and switches and runs wires from the breaker panel to each receptacle
Activity 3: Finish Plumbing
Duration: 2 days
Materials: Waters taps
Equipment: clamp tool, flaring pliers
Skilled worker: Plumber (1)
Technical information: Water taps are installed to every sink in kitchen and
bathroom, and against exterior wall.
Activity 1: Plastering and Painting of Exterior and Interior Walls
Duration: 8 days
Materials: plaster, mixed blended white cement, coving, paint
Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders,
scaffolds, tape and masking
Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1),
painter (1)
Technical information: Plastering on the surface of brick wall after cleaning
with masonry brush. Then, scratch first coat of render before it set to provide
key for second layer. Wall painting with color chosen.
Week 42 - 43
Activity 2: Bathroom Equipment Installation
Duration: 2 days
Materials: Sockets, Heaters, Showers, Shower pumps, Water closet, Sink, PVC
pipes
Equipment: Clamp tool, measuring tape, steel pipe wrench, flaring pliers, pipe
vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: Materials are installed at first fix stage as they need to
be fitted prior to the commencement of tiling. This is essential to get professional
watertight seals, as water ingress resulting from doing things in the wrong order
can cause massive problems later on.
Activity 1: Plastering and Painting of Exterior and Interior Walls
Duration: 8 days
Materials: plaster, mixed blended white cement, coving, paint
Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders,
scaffolds, tape and masking
Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1),
painter (1)
Technical information: Plastering on the surface of brick wall after cleaning
with masonry brush. Then, scratch first coat of render before it set to provide
key for second layer. Wall painting with color chosen.
Week 44
Activity 4: Lighting Installation
Duration: 2 days
Materials: bulbs
Equipment: Screw, screwdriver, driller, locknut
Skilled worker: Electrician (1), general workers (1)
Technical information: Light bulbs are installed in every location.
Activity 3: Kitchen Counters and Cabinets Installation
Duration: 2 days
Materials: Kitchen counters and cabinets
Equipment: Hammer, screw drivers
Skilled worker: general workers (2)
Technical information: Materials are installed at first fix stage as they need to
be fitted prior to the commencement of tiling.
Activity 1: Plastering and Painting of Exterior and Interior Walls
Duration: 8 days
Materials: plaster, mixed blended white cement, coving, paint
Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders,
scaffolds, tape and masking
Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1),
painter (1)
Technical information: Plastering on the surface of brick wall after cleaning
with masonry brush. Then, scratch first coat of render before it set to provide
key for second layer. Wall painting with color chosen.
Week 45 - 46
Activity 1: Windows, Doors and Railings Installation
Duration: 10 days
Materials: Windows, backer rod, insulation, shims, roofing nails, screws, silicone
sealant, flashing, fastener, corner guard, doors, door lock, doorknob and screws,
railings.
Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding,
square ruler, measuring tape, stapler, and screwdriver
Skilled worker: carpenter (2), general worker (1)
Technical information: Verify window opening, apply weather resistant barrier,
create flashing, prepare window for installation, set the unit and secure, apply
flashing at jambs and head, seal and insulate interior cavity, insert backer rod.
Install required door types and measurement with door lock and doorknob.
Install railings.
Week 47 – 48
Week 49 – 50
Week 51
Activity 1: Cleaning Up
Duration: 8 days
Materials: -
Equipment: Vacuum, broom, skip
Skilled worker: general workers (2)
Technical information: -
Activity 1: Test and Commissioning
Duration: 6 days
Materials: -
Equipment: -
Skilled worker: Commissioning agent (CA),
Technical information: Review design intent and basis of design documentation
(prepared by others). Assist with incorporation of commissioning requirements into
the construction documents. Develop a commissioning plan and assist with its
utilization. Verify installation, functional performance, training and operation and
maintenance documentation. Prepare commissioning report and related systems
documentation.
Activity 2: Final Inspection
Duration: 2 days
Materials: -
Equipment: -
Skilled worker: Final Inspector (professional engineer)
Technical information: Turn on and off every light fixture, run water & look under
sinks for leaks, test all appliances, check garage door openers, open and close all
doors, flush toilets, inspect ceilings, wall and floors, run garbage disposal and
exhaust fans, test heating and air conditioning, open and close windows, make
sure all debris is removed from the home
Activity 1: Hand Over
Duration: 2 days
Materials: -
Equipment: -
Skilled worker: Builder’s representative, accountant
Technical information: Take client on a tour of the home showing how everything
works and what have to do to maintain the new home, with a copy of all relevant
warranties and certificates arising from the contract. Final payment will be made.
Week 52
Activity 1: Move in Furniture
Duration: 3 days
Materials: -
Equipment: -
Skilled worker: general workers (3)
Technical information: -

More Related Content

PDF
Construction activities and Process
PDF
Building Construction process
PDF
Bungalow
PDF
Construction Activities and Process
PDF
Construction Project Schedule Template- Residential Building
PDF
Construction work of a multi storied residential building
PPT
Boq piling works
PPTX
CTM - 02 - Construction Project Planning.pptx
Construction activities and Process
Building Construction process
Bungalow
Construction Activities and Process
Construction Project Schedule Template- Residential Building
Construction work of a multi storied residential building
Boq piling works
CTM - 02 - Construction Project Planning.pptx

What's hot (20)

PDF
Construction Methods & Sequence
PPTX
Construction of flexible pavement
PPTX
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
DOC
Building work method statement cm - ms- bw - 001
PPTX
Casting yard
PDF
Construction technology presentation
PDF
Project Execution Plan for Bridge Construction
PDF
Method statement of temporary office and fa
PPTX
Industrial training presentation
PPTX
Industrial training report of construction of the residential building
PDF
Method statement for civil works
PDF
Method of Statement - Pavement works
DOCX
Traditional procurement method
PPTX
Demolition of Structures.
PDF
Erection method statement
PDF
PPT
Prestressed composite beams
PPTX
CONSTRUCTION OF ROADS
PPTX
Finishing works (Building Construction)
PPTX
NEW AUSTRIAN TUNNELING METHOD
Construction Methods & Sequence
Construction of flexible pavement
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
Building work method statement cm - ms- bw - 001
Casting yard
Construction technology presentation
Project Execution Plan for Bridge Construction
Method statement of temporary office and fa
Industrial training presentation
Industrial training report of construction of the residential building
Method statement for civil works
Method of Statement - Pavement works
Traditional procurement method
Demolition of Structures.
Erection method statement
Prestressed composite beams
CONSTRUCTION OF ROADS
Finishing works (Building Construction)
NEW AUSTRIAN TUNNELING METHOD
Ad

Similar to Construction Activities and Process (20)

DOCX
Bcon final report
DOCX
Building Construction 1 - Final Project
PPTX
kuku.pptx
PPTX
2022-07-13.pptx
PPT
Construction basic SIP
PDF
Ae 372 Project 1 Final
PPTX
Building Construction powerpoint for diploma engineering students
DOC
Site visit report
PPT
11 lecture project scheduling 3
PDF
Re development works at east kidwai nagar, New Delhi
PDF
Construction Project Schedule Example- Residential Building
PPT
Construction maintenance
PPTX
internship report of a civil engineer student
PPTX
Presentation, Final internship presentetionPPT.pptx
DOCX
industrial training report
PPTX
BCON PJT 1
PPTX
Building construction
PDF
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
DOCX
Report
DOCX
Site report
Bcon final report
Building Construction 1 - Final Project
kuku.pptx
2022-07-13.pptx
Construction basic SIP
Ae 372 Project 1 Final
Building Construction powerpoint for diploma engineering students
Site visit report
11 lecture project scheduling 3
Re development works at east kidwai nagar, New Delhi
Construction Project Schedule Example- Residential Building
Construction maintenance
internship report of a civil engineer student
Presentation, Final internship presentetionPPT.pptx
industrial training report
BCON PJT 1
Building construction
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
Report
Site report
Ad

More from Wilden How (14)

DOC
Building Construction 2 Project 2 Report
DOCX
Building Construction 2 Report
DOCX
Esd project2 final
PDF
Esd final report
PPTX
Building Construction
PDF
Gropius House Analysis Essay
DOCX
The Colosseum
DOCX
Charity Drive Report
PPT
business presentation
DOC
Research report
DOCX
Debate
DOCX
Musical movie
DOCX
The vegetable
DOCX
EPC Individual Essay
Building Construction 2 Project 2 Report
Building Construction 2 Report
Esd project2 final
Esd final report
Building Construction
Gropius House Analysis Essay
The Colosseum
Charity Drive Report
business presentation
Research report
Debate
Musical movie
The vegetable
EPC Individual Essay

Recently uploaded (20)

PDF
Trump Administration's workforce development strategy
PDF
Complications of Minimal Access-Surgery.pdf
PDF
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PDF
HVAC Specification 2024 according to central public works department
PPTX
History, Philosophy and sociology of education (1).pptx
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PDF
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PDF
Environmental Education MCQ BD2EE - Share Source.pdf
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PDF
Empowerment Technology for Senior High School Guide
DOCX
Cambridge-Practice-Tests-for-IELTS-12.docx
PDF
What if we spent less time fighting change, and more time building what’s rig...
PDF
IGGE1 Understanding the Self1234567891011
PPTX
Unit 4 Computer Architecture Multicore Processor.pptx
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
Trump Administration's workforce development strategy
Complications of Minimal Access-Surgery.pdf
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
HVAC Specification 2024 according to central public works department
History, Philosophy and sociology of education (1).pptx
LDMMIA Reiki Yoga Finals Review Spring Summer
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
Share_Module_2_Power_conflict_and_negotiation.pptx
Environmental Education MCQ BD2EE - Share Source.pdf
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
Empowerment Technology for Senior High School Guide
Cambridge-Practice-Tests-for-IELTS-12.docx
What if we spent less time fighting change, and more time building what’s rig...
IGGE1 Understanding the Self1234567891011
Unit 4 Computer Architecture Multicore Processor.pptx
202450812 BayCHI UCSC-SV 20250812 v17.pptx
Paper A Mock Exam 9_ Attempt review.pdf.
Practical Manual AGRO-233 Principles and Practices of Natural Farming

Construction Activities and Process

  • 1. Building Construction 1 [ARC 1523] Project 2: Construction Activities and Process Tan Wei How 0310707
  • 2. Week 1 Week 2 Activity 1: Grading and Site Preparation Duration: 5 days Materials: Timber, Hoarding Equipment: Theodolite, waste storage tank, backhoe, shovels, truck, construction trolleys Skilled worker: Land surveyor, Mobilization of manpower (carpenter), general workers (2), Backhoe operator (1) Technical information: Clearing up the site. Land demarcation for the site boundary of site by using hoarding as safety guideline for whole construction site. Activity 1: Earthwork Duration: 6 days Materials: - Equipment: Vibrating plate compactor, backhoe, excavator, paver, dumper Skilled worker: Backhoe operator, excavator operator, paver operator, dumper operator Technical information: Site is cut and filled to required lengths, depths, breadths. Unflatten land surface need to fill up and cut down with sand or soil just to flatten the land boundary that had been demarked.
  • 3. Week 3 - 4 Activity 1: Foundation Construction (Piling process) Duration: 10 days Materials: piles, pile cushion, bituminous paint Equipment: Hydraulic drop hammer (1) Skilled worker: contractor (1), Hydraulic drop hammer operator (1), General worker (2) Technical information: Mobilize the hydraulic drop hammer to the intended pile position after marking penetration of the piles, set out the position of drop hammer above the pile point, pile driving, weld the joints between the piles, apply bituminous paint around the joints of welded piles to prevent rusting. Activity 2: Foundation Construction (Cut off process) Duration: 2 days Materials: - Equipment: Multipurpose excavator, Pneumatic hammer, Oxy-cutter Skilled worker: Excavator operator (1), General worker (2) Technical information: Excavate 1m to 1.5m depth by using Multipurpose excavator, Cut the piles to make sure all are in the same height using Pneumatic hammer, the reinforcement in the pile is cut by oxy-cutter.
  • 4. Week 5 Activity 1: Foundation Construction (Setting up formwork for pile cap) Duration: 3 days Materials: Plywood, nails, reinforcement mesh Equipment: hammer, measuring tape, drill, handsaw Skilled worker: general worker (2), carpenter (1) Technical information: Set up formwork for pile cap, insert reinforcement for pile cap, and set up the reinforcement for column stump before pouring the concrete. Activity 2: Foundation Construction (Pour concrete into the formwork) Duration: 2 days Materials: Concrete grade 30 Equipment: Concrete mixer truck, Concrete vibrator Skilled worker: Concrete mixer truck operator (1), general worker (2) Technical information: Pour the concrete into the formwork through skip from concrete mixer truck, vibrate and mix the concrete evenly using concrete vibrator to increase its strength by preventing air pockets.
  • 5. Week 6 Week 7 Activity 1: Foundation Construction (Setting up formwork for column stump) Duration: 2 days Materials: Plywood, nails Equipment: hammer, measuring tape, drill, handsaw Skilled worker: general workers (1), carpenter (1) Technical information: Set up formwork for column stump before pouring the concrete. Activity 1: Foundation Construction (Pile cap curing period) Duration: 7days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete pile cap harden for 7 days to wait it mature and sufficient strength, open formwork after completed. Activity 2: Foundation Construction (Pour concrete into the formwork) Duration: 2 days Materials: Concrete grade 30 Equipment: Concrete mixer truck, Concrete vibrator Skilled worker: Concrete mixer truck operator (1), general worker (2) Technical information: Pour the concrete into the formwork, vibrate the concrete to increase its strength.
  • 6. Week 8 Activity 1: Foundation Construction (Column Stump Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete column stump harden for 7 days to wait it mature and sufficient strength, open formwork after completed Activity 2: Slab Electrical Installation Duration: 3 days Materials: Metal conduit, Steel/Aluminum tubing or PVC tubing Equipment: Plow Chute, Winch Skilled worker: Contractor (1), General worker (2) Technical information: Socket of connection to the utility wiring is covered in the ground at a depth that protects conductors from physical damage and physical contact. Burying cable preinstalled in cable-in-conduit (CIC) offers greater physical protection against environment, abrasion, and rocks than direct burial, which can prolong the life of the cable. Activity 3: Slab Plumbing Installation Duration: 3 days Materials: PVC pipes, PVC pipefittings, soft copper tubing, septic tank Equipment: pressure test pump, bobcat, trencher, measuring tape, shovel Skilled worker: Plumber (1), Trencher operator (1) Technical information: Dig trenches as needed to run the sewer pipes and water pipes, and should smooth the dirt or sand back when finished.
  • 7. Week 9 Activity 1: Ground Floor Construction (Tying Rebar for Beam) Duration: 4 days Materials: rebar ribs, steel cage Equipment: rebar mesh making machine Skilled worker: general workers (2) Technical information: rebar is formed with rebar ribs to contract the steel cage that will reinforce the pour concrete. They are tied together with tie wire at varying intervals. Activity 3: Slab Plumbing Installation Duration: 3 days Materials: PVC pipes, PVC pipefittings, soft copper tubing, septic tank Equipment: pressure test pump, bobcat, trencher, measuring tape, shovel Skilled worker: Plumber (1), Trencher operator (1) Technical information: Dig trenches as needed to run the sewer pipes and water pipes, and should smooth the dirt or sand back when finished. Activity 2: Slab Electrical Installation Duration: 3 days Materials: Metal conduit, Steel/Aluminum tubing or PVC tubing Equipment: Plow Chute, Winch Skilled worker: Contractor (1), General worker (2) Technical information: Socket of connection to the utility wiring is covered in the ground at a depth that protects conductors from physical damage and physical contact. Burying cable preinstalled in cable-in-conduit (CIC) offers greater physical protection against environment, abrasion, and rocks than direct burial, which can prolong the life of the cable.
  • 8. Week 10 Week 11 Activity 1: Ground Floor Construction (Setting up formwork for beam) Duration: 2 days Materials: Plywood, nails Equipment: hammer, measuring tape, drill, handsaw Skilled worker: general workers (2), carpenter (1) Technical information: Set up formwork for beam before pouring the concrete. Activity 2: Ground Floor Construction (Pour concrete into the formwork) Duration: 2 days Materials: Concrete grade 30 Equipment: Concrete mixer truck, Concrete vibrator Skilled worker: Concrete mixer truck operator (1), general worker (2)) Technical information: Pour the concrete into the formwork through skip from concrete mixer truck, vibrate the concrete to increase its strength. Activity 1: Ground Floor Construction (Beam Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete beam harden for 7 days to wait it mature and sufficient strength, open formwork after completed
  • 9. Week 12 Week 13 Activity 1: Ground Floor Construction (Tying Rebar for Slab) Duration: 5 days Materials: rebar ribs, steel cage Equipment: rebar mesh making machine Skilled worker: general workers (2) Technical information: rebar is formed with rebar ribs to contract the steel cage that will reinforce the pour concrete. They are tied together with tie wire at varying intervals. Activity 1: Ground Floor Construction (Setting up formwork for Slab) Duration: 2 days Materials: Plywood, nails Equipment: hammer, measuring tape, drill, handsaw Skilled worker: general workers (2), carpenter (1) Technical information: Set up formwork for beam before pouring the concrete. Activity 2: Ground Floor Construction (Pour concrete into the formwork) Duration: 2 days Materials: Concrete grade 30 Equipment: Concrete mixer truck, Concrete vibrator Skilled worker: Concrete mixer truck operator (1), general worker (2)) Technical information: Pour the concrete into the formwork through skip from concrete mixer truck, vibrate the concrete to increase its strength
  • 10. Week 14 Week 15 Activity 1: Ground Floor Construction (Slab Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete slab harden for 7 days to wait it mature and sufficient strength, open formwork after completed Activity 1: Ground Floor Construction (Reinforce Column) Duration: 6 days Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw, concrete mixer truck, concrete vibrator Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1) Technical information: Place rebar as instructed, position formwork for column, pour the concrete into the formwork through skip from concrete mixer truck, vibrate the concrete to increase its strength.
  • 11. Week 16 Activity 2: Rough Electrical Installation (Ground Floor) Duration: 4 days Materials: PVC insulated cable, copper/aluminum conductors Equipment: Power strip/ surge protectors, fish tape, flex bits Skilled worker: Electrical Contractor (1), Electrician (1) Technical information: After rough frame is completed, wiring methods have to be installing on or through building framing members. Wiring requirements differ depending on the construction type and building element. Activity 3: Rough Plumbing Installation (Ground Floor) Duration: 4 days Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings, hangers, insulating materials, oakum Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter Skilled worker: Plumber (1), General worker (1) Technical information: The major categories of plumbing systems or subsystems are potable cold and hot tap water supply, plumbing drainage venting, septic systems, rainwater, surface, and subsurface water drainage, fuel gas piping Activity 4: Rough HVAC Installation (Ground Floor) Duration: 2 days Materials: Duct HVAC, furnace, service valve adapters, Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels, plumb bobs and chalk lines, ladder Skilled worker: HVAC installer (1), general worker (1) Technical information: The ductwork of HVAC system is planned and installed and run to each location. The furnace is installed as well. Activity 1: Ground Floor Construction (Column Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete column harden for 7 days to wait it mature and sufficient strength, open formwork after completed
  • 12. Week 17 Activity 1: First Floor Construction (Tying Rebar for Beam) Duration: 4 days Materials: rebar ribs, steel cage Equipment: rebar mesh making machine Skilled worker: general workers (2) Technical information: rebar is formed with rebar ribs to contract the steel cage that will reinforce the pour concrete. They are tied together with tie wire at varying intervals. Activity 2: Rough Electrical Installation (Ground Floor) Duration: 4 days Materials: PVC insulated cable, copper/aluminum conductors Equipment: Power strip/ surge protectors, fish tape, flex bits Skilled worker: Electrical Contractor (1), Electrician (1) Technical information: After rough frame is completed, wiring methods have to be installing on or through building framing members. Wiring requirements differ depending on the construction type and building element. Activity 3: Rough Plumbing Installation (Ground Floor) Duration: 4 days Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings, hangers, insulating materials, oakum Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter Skilled worker: Plumber (1), General worker (1) Technical information: The major categories of plumbing systems or subsystems are potable cold and hot tap water supply, plumbing drainage venting, septic systems, rainwater, surface, and subsurface water drainage, fuel gas piping Activity 4: Rough HVAC Installation (Ground Floor) Duration: 2 days Materials: Duct HVAC, furnace, service valve adapters, Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels, plumb bobs and chalk lines, ladder Skilled worker: HVAC installer (1), general worker (1) Technical information: The ductwork of HVAC system is planned and installed and run to each location. The furnace is installed as well.
  • 13. Week 18 Activity 1: First Floor Construction (Setting up formwork for beam) Duration: 2 days Materials: Plywood, nails Equipment: hammer, measuring tape, drill, handsaw Skilled worker: general workers (2), carpenter (1) Technical information: Set up formwork for beam before pouring the concrete. Activity 2: First Floor Construction (Pour concrete into the formwork) Duration: 2 days Materials: Concrete grade 30 Equipment: concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses Skilled worker: Concrete mixer truck operator (1), pumps and boom-mounted hoses operator (1), general worker (1) Technical information: Concrete is pumped and poured into the formwork through pipes and large hoses, vibrate the concrete to increase its strength.
  • 14. Week 19 Week 20 Activity 1: First Floor Construction (Beam Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete beam harden for 7 days to wait it mature and sufficient strength, open formwork after completed Activity 1: First Floor Construction (Tying Rebar for Slab) Duration: 5 days Materials: rebar ribs, steel cage Equipment: rebar mesh making machine Skilled worker: general workers (2) Technical information: rebar is formed with rebar ribs to contract the steel cage that will reinforce the pour concrete. They are tied together with tie wire at varying intervals.
  • 15. Week 21 Activity 1: First Floor Construction (Setting up formwork for Slab) Duration: 2 days Materials: Plywood, nails Equipment: hammer, measuring tape, drill, handsaw Skilled worker: general workers (2), carpenter (1) Technical information: Set up formwork for slab before pouring the concrete. Activity 2: First Floor Construction (Pour concrete into the formwork) Duration: 2 days Materials: Concrete grade 30 Equipment: concrete mixer truck, concrete vibrator, pumps and boom- mounted hoses Skilled worker: Concrete mixer truck operator (1), pumps and boom- mounted hoses operator (1), general worker (1) Technical information: Concrete is pumped and poured into the formwork through pipes and large hoses, vibrate the concrete to increase its strength.
  • 16. Week 22 Activity 2: Staircase Construction (Ground Floor) Duration: 6 days Materials: Plywood, Timber Battens, rebar ribs, steel cage, concrete grade 30 Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw, Concrete mixer truck, Concrete vibrator Skilled worker: Carpenter (1), Concrete mixer truck operator (1), general worker (2) Technical information: Construct formwork by laying out riser heights and tread widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Place rebar as instructed. Pour the concrete into the formwork. Keep the concrete wet or damp to prevent cracks for up to one week while it cures. Activity 1: First Floor Construction (Slab Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete slab harden for 7 days to wait it mature and sufficient strength, open formwork after completed
  • 17. Week 23 Activity 2: Wall Construction (Ground Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred. Activity 1: First Floor Construction (Reinforce Column) Duration: 6 days Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw, concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1) Technical information: Place rebar as instructed, position formwork for column. Concrete is pumped and poured into the formwork through pipes and large hoses, vibrate the concrete to increase its strength.
  • 18. Week 24 Activity 1: First Floor Construction (Column Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete column harden for 7 days to wait it mature and sufficient strength, open formwork after completed Activity 2: Wall Construction (Ground Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred.
  • 19. Activity 5: Rough HVAC Installation (First Floor) Duration: 2 days Materials: Duct HVAC, furnace, service valve adapters, Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels, plumb bobs and chalk lines, ladder Skilled worker: HVAC installer (1), general worker (1) Technical information: The ductwork of HVAC system is planned and installed and run to each location. The furnace is installed as well. Activity 3: Rough Electrical Installation (First Floor) Duration: 4 days Materials: PVC insulated cable, copper/aluminum conductors Equipment: Power strip/ surge protectors, fish tape, flex bits Skilled worker: Electrical Contractor (1), Electrician (1) Technical information: After rough frame is completed, wiring methods have to be installing on or through building framing members such as the interior walls, ceilings and floors. Wiring requirements differ depending on the construction type and building element. Activity 4: Rough Plumbing Installation (First Floor) Duration: 4 days Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings, hangers, insulating materials, oakum Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter Skilled worker: Plumber (1), General worker (1) Technical information: The major categories of plumbing systems or subsystems are potable cold and hot tap water supply, plumbing drainage venting, septic systems, rainwater, surface, and subsurface water drainage, fuel gas piping.
  • 20. Week 25 Activity 1: Second Floor Construction (Tying Rebar for Beam) Duration: 4 days Materials: rebar ribs, steel cage Equipment: rebar mesh making machine Skilled worker: general workers (2) Technical information: rebar is formed with rebar ribs to contract the steel cage that will reinforce the pour concrete. They are tied together with tie wire at varying intervals. Activity 2: Wall Construction (Ground Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred.
  • 21. Activity 5: Rough HVAC Installation (First Floor) Duration: 2 days Materials: Duct HVAC, furnace, service valve adapters, Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels, plumb bobs and chalk lines, ladder Skilled worker: HVAC installer (1), general worker (1) Technical information: The ductwork of HVAC system is planned and installed and run to each location. The furnace is installed as well. Activity 3: Rough Electrical Installation (First Floor) Duration: 4 days Materials: PVC insulated cable, copper/aluminum conductors Equipment: Power strip/ surge protectors, fish tape, flex bits Skilled worker: Electrical Contractor (1), Electrician (1) Technical information: After rough frame is completed, wiring methods have to be installing on or through building framing members such as the interior walls, ceilings and floors. Wiring requirements differ depending on the construction type and building element. Activity 4: Rough Plumbing Installation (First Floor) Duration: 4 days Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings, hangers, insulating materials, oakum Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter Skilled worker: Plumber (1), General worker (1) Technical information: The major categories of plumbing systems or subsystems are potable cold and hot tap water supply, plumbing drainage venting, septic systems, rainwater, surface, and subsurface water drainage, fuel gas piping
  • 22. Week 26 Activity 1: Second Floor Construction (Setting up formwork for beam) Duration: 2 days Materials: Plywood, nails Equipment: hammer, measuring tape, drill, handsaw Skilled worker: general workers (2), carpenter (1) Technical information: Set up formwork for beam before pouring the concrete. Activity 2: Second Floor Construction (Pour concrete into the formwork) Duration: 2 days Materials: Concrete grade 30 Equipment: concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses Skilled worker: Concrete mixer truck operator (1), pumps and boom-mounted hoses operator (1), general worker (1) Technical information: Concrete is pumped and poured into the formwork through pipes and large hoses, vibrate the concrete to increase its strength. Activity 3: Wall Construction (Ground Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred.
  • 23. Week 27 Week 28 Activity 1: Second Floor Construction (Beam Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete beam harden for 7 days to wait it mature and sufficient strength, open formwork after completed Activity 1: Second Floor Construction (Tying Rebar for Slab) Duration: 5 days Materials: rebar ribs, steel cage Equipment: rebar mesh making machine Skilled worker: general workers (2) Technical information: rebar is formed with rebar ribs to contract the steel cage that will reinforce the pour concrete. They are tied together with tie wire at varying intervals.
  • 24. Week 29 Activity 1: Second Floor Construction (Setting up formwork for Slab) Duration: 2 days Materials: Plywood, nails Equipment: hammer, measuring tape, drill, handsaw Skilled worker: general workers (2), carpenter (1) Technical information: Set up formwork for slab before pouring the concrete. Activity 2: Second Construction (Pour concrete into the formwork) Duration: 2 days Materials: Concrete grade 30 Equipment: concrete mixer truck, concrete vibrator, pumps and boom- mounted hoses Skilled worker: Concrete mixer truck operator (1), pumps and boom- mounted hoses operator (1), general worker (1) Technical information: Concrete is pumped and poured into the formwork through pipes and large hoses, vibrate the concrete to increase its strength.
  • 25. Week 30 Activity 2: Staircase Construction (First Floor) Duration: 6 days Materials: Plywood, Timber Battens, rebar ribs, steel cage, concrete grade 30 Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw, Concrete mixer truck, Concrete vibrator Skilled worker: Carpenter (1), Concrete mixer truck operator (1), general worker (2) Technical information: Construct formwork by laying out riser heights and tread widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Place rebar as instructed. Pour the concrete into the formwork. Keep the concrete wet or damp to prevent cracks for up to one week while it cures Activity 1: Second Floor Construction (Slab Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete slab harden for 7 days to wait it mature and sufficient strength, open formwork after completed
  • 26. Week 31 Activity 2: Wall Construction (First Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred. Activity 1: Second Floor Construction (Reinforce Column) Duration: 6 days Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw, concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1) Technical information: Place rebar as instructed, position formwork for column. Concrete is pumped and poured into the formwork through pipes and large hoses, vibrate the concrete to increase its strength.
  • 27. Week 32 Activity 1: Second Floor Construction (Column Curing Period) Duration: 7 days Materials: - Equipment: - Skilled worker: - Technical information: Let the concrete column harden for 7 days to wait it mature and sufficient strength, open formwork after completed Activity 2: Wall Construction (First Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred.
  • 28. Week 33 Week 34 Activity 1: Roof Construction (Reinforce Beam) Duration: 6 days Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw, concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1) Technical information: Place rebar as instructed, position formwork for beam. Concrete is pumped and poured into the formwork through pipes and large hoses, vibrate the concrete to increase its strength. Activity 2: Wall Construction (First Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred.
  • 29. Activity 1: Roof Construction Duration: 6 days Materials: steel joists, concrete slab, rebar, grout (sand and Portland cement) Equipment: Concrete mixer truck, concrete vibrator, scaffold, rebar mesh making machine, pumps and boom-mounted hoses Skilled worker: concrete mixer truck operator (1), general workers (2) Technical information: Place the steel joists. The bottom of the steel joists should rest on either a beam or a wall. This will give it the required support. Place the concrete slab on its face. Insert full-length rebar to the unit. The grout has to be poured into the space between the rows of concrete slabs. The joists have to be covered completely. Activity 2: Wall Construction (First Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred.
  • 30. Week 35 Activity 1: Wall Construction (First Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred. Activity 2: Rough Electrical Installation (Second Floor) Duration: 4 days Materials: PVC insulated cable, copper/aluminum conductors Equipment: Power strip/ surge protectors, fish tape, flex bits Skilled worker: Electrical Contractor (1), Electrician (1) Technical information: After rough frame is completed, wiring methods have to be installing on or through building framing members. Wiring requirements differ depending on the construction type and building element.
  • 31. Activity 4: Rough HVAC Installation (Second Floor) Duration: 2 days Materials: Duct HVAC, furnace, service valve adapters, Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels, plumb bobs and chalk lines, ladder Skilled worker: HVAC installer (1), general worker (1) Technical information: The ductwork of HVAC system is planned and installed and run to each location. The furnace is installed as well. Activity 3: Rough Plumbing Installation (Second Floor) Duration: 4 days Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings, hangers, insulating materials, oakum Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter Skilled worker: Plumber (1), General worker (1) Technical information: The major categories of plumbing systems or subsystems are potable cold and hot tap water supply, plumbing drainage venting, septic systems, rainwater, surface, and subsurface water drainage, fuel gas piping
  • 32. Week 36 Activity 2: Ceiling Installation (Ground Floor) Duration: 3 days Materials: Ceiling panels, main runners Equipment: hacksaw, utility knife, measuring tape Skilled worker: general workers (2) Technical information: Set the main runners into place. Install the cross tee sections of the ceiling grid. Install the panels. Tilt each panel to angle it through a grid opening, then carefully lower it until it rests on the bracket edges of the grid sections. Activity 1: Wall Construction (Second Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred.
  • 33. Week 37 Activity 1: Wall Construction (Second Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred. Activity 2: Ceiling Installation (First Floor) Duration: 3 days Materials: Ceiling panels, main runners Equipment: hacksaw, utility knife, measuring tape Skilled worker: general workers (2) Technical information: Set the main runners into place. Install the cross tee sections of the ceiling grid. Install the panels. Tilt each panel to angle it through a grid opening, then carefully lower it until it rests on the bracket edges of the grid sections.
  • 34. Week 38 Activity 1: Wall Construction (Second Floor) Duration: 4 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Bricklayers (2) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. It needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred. Activity 2: Ceiling Installation (Second Floor) Duration: 3 days Materials: Ceiling panels, main runners Equipment: hacksaw, utility knife, measuring tape Skilled worker: general workers (2) Technical information: Set the main runners into place. Install the cross tee sections of the ceiling grid. Install the panels. Tilt each panel to angle it through a grid opening, then carefully lower it until it rests on the bracket edges of the grid sections.
  • 35. Week 39 - 40 Activity 1: Plastering and Painting of Exterior and Interior Walls Duration: 8 days Materials: plaster, mixed blended white cement, coving, paint Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders, scaffolds, tape and masking Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1), painter (1) Technical information: Plastering on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Wall painting with color chosen. Activity 2: Finish Electrical Duration: 3 days Materials: main electrical panel, receptacle Equipment: Driller, locknut, screw, nickel/silver, beryllium copper, plastic Skilled worker: Electrical Contractor (1), Electrician (1) Technical information: The panel distributes the electricity to all the electrical circuits that are installed in the house. Electrician installs receptacles for outlets, lights and switches and runs wires from the breaker panel to each receptacle. Activity 3: Finish Plumbing Duration: 2 days Materials: Waters taps Equipment: clamp tool, flaring pliers Skilled worker: Plumber (1) Technical information: Water taps are installed to every sink in kitchen and bathroom, and against exterior wall.
  • 36. Week 41 Activity 4: Finish HVAC Duration: 2 days Materials: Thermostats, Registers Equipment: Hand Tool Set Skilled worker: HVAC installer Technical information: Nearly all of the HVAC work is done during the rough in stage. The HVAC installer install the thermostats, placed the registers and made a few final adjustments and tests to make sure that everything was running properly. Activity 2: Finish Electrical Duration: 3 days Materials: main electrical panel, receptacle Equipment: Driller, locknut, screw, nickel/silver, beryllium copper, plastic Skilled worker: Electrical Contractor (1), Electrician (1) Technical information: The panel distributes the electricity to all the electrical circuits that are installed in the house. Electrician installs receptacles for outlets, lights and switches and runs wires from the breaker panel to each receptacle Activity 3: Finish Plumbing Duration: 2 days Materials: Waters taps Equipment: clamp tool, flaring pliers Skilled worker: Plumber (1) Technical information: Water taps are installed to every sink in kitchen and bathroom, and against exterior wall. Activity 1: Plastering and Painting of Exterior and Interior Walls Duration: 8 days Materials: plaster, mixed blended white cement, coving, paint Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders, scaffolds, tape and masking Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1), painter (1) Technical information: Plastering on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Wall painting with color chosen.
  • 37. Week 42 - 43 Activity 2: Bathroom Equipment Installation Duration: 2 days Materials: Sockets, Heaters, Showers, Shower pumps, Water closet, Sink, PVC pipes Equipment: Clamp tool, measuring tape, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter Skilled worker: Plumber (1), General worker (1) Technical information: Materials are installed at first fix stage as they need to be fitted prior to the commencement of tiling. This is essential to get professional watertight seals, as water ingress resulting from doing things in the wrong order can cause massive problems later on. Activity 1: Plastering and Painting of Exterior and Interior Walls Duration: 8 days Materials: plaster, mixed blended white cement, coving, paint Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders, scaffolds, tape and masking Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1), painter (1) Technical information: Plastering on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Wall painting with color chosen.
  • 38. Week 44 Activity 4: Lighting Installation Duration: 2 days Materials: bulbs Equipment: Screw, screwdriver, driller, locknut Skilled worker: Electrician (1), general workers (1) Technical information: Light bulbs are installed in every location. Activity 3: Kitchen Counters and Cabinets Installation Duration: 2 days Materials: Kitchen counters and cabinets Equipment: Hammer, screw drivers Skilled worker: general workers (2) Technical information: Materials are installed at first fix stage as they need to be fitted prior to the commencement of tiling. Activity 1: Plastering and Painting of Exterior and Interior Walls Duration: 8 days Materials: plaster, mixed blended white cement, coving, paint Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders, scaffolds, tape and masking Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1), painter (1) Technical information: Plastering on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Wall painting with color chosen.
  • 39. Week 45 - 46 Activity 1: Windows, Doors and Railings Installation Duration: 10 days Materials: Windows, backer rod, insulation, shims, roofing nails, screws, silicone sealant, flashing, fastener, corner guard, doors, door lock, doorknob and screws, railings. Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler, measuring tape, stapler, and screwdriver Skilled worker: carpenter (2), general worker (1) Technical information: Verify window opening, apply weather resistant barrier, create flashing, prepare window for installation, set the unit and secure, apply flashing at jambs and head, seal and insulate interior cavity, insert backer rod. Install required door types and measurement with door lock and doorknob. Install railings.
  • 40. Week 47 – 48 Week 49 – 50 Week 51 Activity 1: Cleaning Up Duration: 8 days Materials: - Equipment: Vacuum, broom, skip Skilled worker: general workers (2) Technical information: - Activity 1: Test and Commissioning Duration: 6 days Materials: - Equipment: - Skilled worker: Commissioning agent (CA), Technical information: Review design intent and basis of design documentation (prepared by others). Assist with incorporation of commissioning requirements into the construction documents. Develop a commissioning plan and assist with its utilization. Verify installation, functional performance, training and operation and maintenance documentation. Prepare commissioning report and related systems documentation. Activity 2: Final Inspection Duration: 2 days Materials: - Equipment: - Skilled worker: Final Inspector (professional engineer) Technical information: Turn on and off every light fixture, run water & look under sinks for leaks, test all appliances, check garage door openers, open and close all doors, flush toilets, inspect ceilings, wall and floors, run garbage disposal and exhaust fans, test heating and air conditioning, open and close windows, make sure all debris is removed from the home Activity 1: Hand Over Duration: 2 days Materials: - Equipment: - Skilled worker: Builder’s representative, accountant Technical information: Take client on a tour of the home showing how everything works and what have to do to maintain the new home, with a copy of all relevant warranties and certificates arising from the contract. Final payment will be made.
  • 41. Week 52 Activity 1: Move in Furniture Duration: 3 days Materials: - Equipment: - Skilled worker: general workers (3) Technical information: -