Introduction
Introduction
 Service tunnel
 Basement car park
 A lower ground, ground and 1st floor
Introduction
HVAC
Ventilation:
No natural ventilation - sealed building.
Mechanical ventilation : 1. extraction fan (car park)
2. air-conditioning (every shops, lift, toilets)
3. extraction grilles (toilets, roof level)
Air-conditioning system: - centralized system (water chiller system)
- cooled air supplied via ducting system (outlet)
- use “open-ceiling” (inlet)
- Plant room –3 chillers, compressor, distributor
pumps,condenser pumps, chiller pumps.
- T.G.I.FRiDAY’S restaurant –package system
“Open ceiling”
Condenser pumps
Linear diffuser Cone diffuser
Multi-direction diffuser
Air Handling Unit (AHU):
- 68 units
- manually operated
- controls the air-conditioning system of 5 shops.
- Air supplied = 2˚C, returns = 23˚C.
- Thermostat - control the temperature of air supplied.
- Maintenance works for cooling coil – every 2 months.
Control panel
Thermostat
Air filters
Cooled air supply
Chiller:
- 3 chillers
- 1 chiller filled with 750 tons of water (10:30a.m to 7:00 p.m.)
- 2 chillers filled with 1500 tons of water(9:30 a.m. to 9:30 p.m.).
- have been used for over 26 years and do not encounter any
overheat problems.
Chiller Chiller control penal
Cooling tower:
- 6 at roof top.
- balancing pipes - ensure the water is supplied at the same volume.
- ball valve - indicate and control the supply of water.
- hot water is pumped from the condenser to the cooling tower by using
condenser water pump.
Cooling tower
Ball valve
Cooling towers
Zoning:
- single zone variable air volume. (air is supplied in same
temperature but different volume).
- MBO cinema - single zone constant air volume.
Fire Protection
Fire Protection
Active Passive
1. portable fire extinguishers 1. Escape route: Pressurized staircase
2. Automatic extinguisher
- Carbon dioxide gas extinguishing
system
- Sprinkler system
2. Fire rated door
3. Fire hydrant 3. Fire man lift
4. Hose reel
5. Risers
6. Detectors
7. Alarm system and voice
communication system
1. Portable fire extinguishers
 Powder type
- used inside the mall
- provided one in every shop
- placed in white metal box
 Carbon dioxide type
-Used in electrical room, transformer room and water plant room
 Maintenance: once a year
 9kg
2. Automatic extinguishing system
a. Automatic Carbon dioxide system
 TNB rooms
 both smoke and heat detectors
 non-conductive properties
b. Sprinkler system
- wet sprinkler
- distance: 3m
- red bulb liquid color = 68 degree Celsius
- pressed steel storage tank = 48,000 gallons capacity
-1 duty pump, 2 standby pumps and 2 jockey pumps
-ball valves
Building services presentation subang parade
3. Fire hydrant
 8
 3- way hydrant
 Hydrant – hydrant = 68m
 hydrant - building = 8.90m
 hydrant - road = 6m
4. Hose reel
 11 sets
 wet riser tank & close range pumps
 30m long
 diameter of 8.47mm
 Canvas reel – landing valve
Building services presentation subang parade
5. Risers
 11 Wet risers
 basement level -first floor (16.458m)
 8.534m×3.658m×2.438m tank
 16,800 gallons capacity
6. Detectors
a. Smoke
-lift lobby and inside the mall
-35m2
b. Heat
-TNB rooms
 connected to fire alarm panel and linked to fire control
room
Building services presentation subang parade
7. Alarm detection
 Manual call points = 1.46m
 connected to fire alarm panel and fire control room
 Automatic alarm bells
 Fire switch
8. Voice communication system
 installed at every services room and lift lobbies
 Communicate to the people in the fire control room.
Passive: 1. Escape route- Pressurized staircase
 purpose made ventilation grille of independent pressurization
system
 Fire switch
 Emergency light
 riser =160mm
 tread =270mm
Building services presentation subang parade
2. Fire rated door
 1 hour
 escape route and service rooms
3. Fire Elevator
 When there is fire, all elevators will return in sequence
directly to the designated floor, which is the LG Floor.
 Only fire elevator can be manually operated by the
firemen via the fire lift switch.
fire elevator fire lift switch
Vertical Transportation
System
1. Elevator
2. Escalator
Elevator
9 groups serving the whole shopping mall.
• 7 are connected directly to the car park.
( electric elevators )
• 2 groups within the shopping mall excluding car
park level
( hydraulic elevators )
• In one group, there are 2 elevators, with one of the
elevator designated for Bomba in terms of
emergency.
Electric elevators accessible directly to the car park
hydarulic
elevators for
interfloor traffic
only, excluding
car park
Specifications
Electric Elevator Hydraulic Elevator
Elevator Capacity 1800kg 1360kg, 26 persons
Internal Car Size 180cm*183cm 90cm*270cm
Door arrangement two - speed centre
opening
single - speed centre
opening
Round-Trip Time(RTT) 1 minute 2 minutes 15 seconds
Operation of System
Electric Elevators moves
the elevator car up and down
using traction steel ropes and
sheaves with a counterweight
to balance the load.
Operation of System
Hydraulic Elevator use
hydraulic power to
pressurise the piston at the
base of the elevator to
raise and lower the car.
Motor Room
 Located on top of the elevator shaft.
 Housed traction machines of all elevators, including the
control panel.
Traction Machine Traction Sheave
Escalators
 moving stairs used to convey people between floor
levels.
 It can be constructed in few arrangements, which are
one-way traffic and two-way traffic.
 7 criss-cross and 2 parallel
Two-way traffic (parallel)
Two-way traffic (criss-cross)
Electricity
High Voltage Room
Feeder
 3 Feeder with 11kVA
switchboard section
 Circuit conductor for
power supply source
 Final branch circuit
overcurrent device.
Vacuum Circuit Breaker
 25 VCB
 interrupt the current using
vacuum
Transformer Room
Transformers
17 transformers
5 12
HVAC system Electric supply
Step down 11kV 415V
Silica gel breather
Prevent damage as incoming
air consists of moisture & dirt.
Blue when installed & turn
purple when they absorb
moisture.
Low Voltage Room
Main Switch Board (MSB)
 3 main switch board
Bar coupler
Electric Riser
Feeder pillar panel
2 feeder pillar panel
Only 1 feeder pillar
panel is used
Another 1 is use when
the existing feeder
failure
Electric riser
Distributes electric
supply
Bar coupler
Transfers electric
when the feeder is
failure.
Generator Set
 Electrical generator + engine
mounted together
 Convert mechanicalelectrical
energy
 3 generator set
 With battery
 11250kVa
 21000kVa
 Use for backup
Air Circuit Breaker (ACB)
 Main circuit breakers
 Compressed air is used to
interrupt circuit.
Electric Panel Room
Distribution Panel
 Distributes power to the
consuming loads
Miniature Circuit Breaker
(MCB)
 A small trip switch
Busbar
 A copper conductor
A copper conductor
Enclosed busbar for safety
purposes
Electric distribution Main switch board
Busbar
.
Miniature
Circuit
Breaker
(MCB)
Distribution
Panel.
Load.
Cold Water Supply
Cold Water Supply
 Pneumatic water pressure boosting system
 Suitable for tall buildings
 Water enter from rising main> store in tank
 System consists electrical control panel, hydro-
pneumatic pump, water storage tank.
 Pneumatic water pressure boosting system
 System pressure maintained by small air compressor and
pneumatic cylinder
 Small air compressor: contain water with pressurized air
space
 Indirect boosting from break tank
- using pneumatic cylinder
- a continuous running pump
 Break tank
- supply the system if main supply becomes
insufficient
- create pressure zones
 GI piping- rust easily
 Why choose?
- first mall in KL in the 80’s
- PVC not popular
 Make up tank- compensate water shortage period
Let’s watch a video
 http://www.youtube.com/watch?v=LJiT3VHJwZI
1. Single Zone Variable Air Volume  Multi
Zone Variable Air Volume
More energy efficiency
Recommendations- HVAC
2. Manual Controller  Automatic Controller
 The operation will be more accurate
 Energy efficiency
 Usage of manpower and related cost can be cut down
How it works
 The electronic control unit evaluates the signals from sensors to
determine the operating conditions, and controls the actuators to
move dampers and valves that control the volume, temperature and
direction of the air delivered
3. Industrial fan & UV glass
• Distribute air evenly
• Block 99% of UV radiation while transmitting the desired light
4.Return duct
• Can be used to extract warm air & recycle it through
the system for either cooling or heating purpose
• Energy efficient compared to open ceiling system
1. Fire blanket and fire extinguishing ball 
Portable Fire extinguisher
Recommendations- Fire Protection
 i. Fire blanket
 flame-resistant blanket
 extinguish small fire or protect a person from fire by wrapping the
blanket around
 made from 2 layers of woven glass fibre fabric and an inner layer
of fire retardant film
 ii. Fire extinguishing ball
 spherical shape of fire extinguisher
 1.3kg only
 is activated when it is contact with flame and it will burst to
spread dry chemical to extinguish fire when temperature is
reach 70 Degree Celsius
 Make noise when activated to alert occupants
2. Fire rated door for landing door & fire control room door
i. UBBL clause 152.2
ii. landing door shall have a FRP (fire
resistance period) of not less than half
the FRP of hoist way structure with
minimum FRP of one hour.
iii. prevent the spread of fire from landing
side into the lift shaft for a period time
 Infra-red photo of landing doors of
lift during fire test.
3.Visible Fire alarm system + Alarm bell  Alarm bell system
i. UBBL clause 242
ii. special requirements for fire alarm system
should be provided where occupants are
undesirable for audible alarm system
iii. visible alarm signal such as fire alarm strobe
lighting device
 Fire alarm strobe lighting device
4. Replace Diameter of hose reel
i. 8.47mm diameter (old)
ii. BS EN 671-1,
requirement is 19mm or 25mm
Conclusion
THE END~

More Related Content

DOCX
Building services report subang parade
PDF
Building Services : Subang Parade
PPTX
bs slides
PDF
Subang parade b.service
DOCX
Bs final report
PPTX
HVAC Sysems & AHU
PDF
A Compact Remote Switching With Efficient Monitoring For AC Plants
PDF
Ultimatefinalservicereport
Building services report subang parade
Building Services : Subang Parade
bs slides
Subang parade b.service
Bs final report
HVAC Sysems & AHU
A Compact Remote Switching With Efficient Monitoring For AC Plants
Ultimatefinalservicereport

What's hot (17)

PPTX
Screw Air Compressors
PDF
Eta lyra series reflow oven
PDF
chillers
PPT
Basic Pneumatics
PDF
HVAC Service Class
PDF
How Does A Chiller Work? - What Is A Chiller & How To Choose the Best One
PPTX
Air conditioning system presentation
PPTX
B&d air compressor promotion(2019)
PDF
Bs2 presentation
PDF
2012 ASHRAE HANDBOOK: HVAC SYSTEMS AND EQUIPMENT
PPTX
Heat ventilation and air conditioning (hvac)
PPTX
Air conditioning of small buildings
PDF
Integrated building systems measures & evaluation
PPTX
PDF
Technical description vd 2014 (en) light
PDF
Multipurpose Device Using Single Vapor Compression Refrigeration Cycle
PDF
Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)
Screw Air Compressors
Eta lyra series reflow oven
chillers
Basic Pneumatics
HVAC Service Class
How Does A Chiller Work? - What Is A Chiller & How To Choose the Best One
Air conditioning system presentation
B&d air compressor promotion(2019)
Bs2 presentation
2012 ASHRAE HANDBOOK: HVAC SYSTEMS AND EQUIPMENT
Heat ventilation and air conditioning (hvac)
Air conditioning of small buildings
Integrated building systems measures & evaluation
Technical description vd 2014 (en) light
Multipurpose Device Using Single Vapor Compression Refrigeration Cycle
Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)
Ad

Viewers also liked (20)

PDF
Gíardia lamblia
PPT
Mitosiscellcycle2012
PDF
الناس اللي شادين الطريق.. ردو البال فالويكاند!!
PDF
2nd Annual Congress Discovery Partnerships 2011
PPT
Cell factory2012
PDF
Graduate-recruiting-Extended-2-12-2012
PPT
Nucleic acids and proteins academy
PPTX
Comex umh 20 20
DOCX
BS Stormwater management assignment
PPTX
Chapter 2 - Basic Chemistry
PDF
CL Project02_Briefing.pdf
PDF
6949 comparative analysis b321
DOCX
Essay structure new
DOCX
L11 l14 - footnote resource
PPTX
Hidrostática flotabilidad
DOCX
blitzkrieg
PPTX
End of Summer Project (2)
DOC
Proposal
PPTX
Kerb's cycle.
PDF
LA Ember.js Meetup, Jan 2017
Gíardia lamblia
Mitosiscellcycle2012
الناس اللي شادين الطريق.. ردو البال فالويكاند!!
2nd Annual Congress Discovery Partnerships 2011
Cell factory2012
Graduate-recruiting-Extended-2-12-2012
Nucleic acids and proteins academy
Comex umh 20 20
BS Stormwater management assignment
Chapter 2 - Basic Chemistry
CL Project02_Briefing.pdf
6949 comparative analysis b321
Essay structure new
L11 l14 - footnote resource
Hidrostática flotabilidad
blitzkrieg
End of Summer Project (2)
Proposal
Kerb's cycle.
LA Ember.js Meetup, Jan 2017
Ad

Similar to Building services presentation subang parade (20)

PDF
Xenon lamp aging test chamber
PPTX
Bs ii-presentation
PPTX
Bs ii presentation finale
PDF
Xenon lamp-aging-test-chamber
PDF
Xenon lamp-aging-test-chamber
PPTX
Summer Training in DMRC
PDF
CPD Presentation: Smoke Ventilation using Shafts
PDF
Environmental test chamber
PPT
Bs present yeahh!
PPTX
DEBORA PPT.pptx
PDF
Bs ii
PDF
Hecu – high energy efficiency solution for condensing units fitted with DC co...
PPTX
Building
PPT
Fire protection system ax 272 f
PPTX
L3 Unit 11 LO 3 Fire Systems Master .pptx
PPTX
BUILDING SERVICE GROUP ASSIGNMENT
PPTX
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
PDF
Control Valves for the Power Generation Industry" A Product and Applications ...
PDF
Eurocar_en
DOCX
Muffle furnace
Xenon lamp aging test chamber
Bs ii-presentation
Bs ii presentation finale
Xenon lamp-aging-test-chamber
Xenon lamp-aging-test-chamber
Summer Training in DMRC
CPD Presentation: Smoke Ventilation using Shafts
Environmental test chamber
Bs present yeahh!
DEBORA PPT.pptx
Bs ii
Hecu – high energy efficiency solution for condensing units fitted with DC co...
Building
Fire protection system ax 272 f
L3 Unit 11 LO 3 Fire Systems Master .pptx
BUILDING SERVICE GROUP ASSIGNMENT
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Control Valves for the Power Generation Industry" A Product and Applications ...
Eurocar_en
Muffle furnace

More from Yap Xin (11)

PDF
Compile version communication in consruction
DOCX
Site Surveying Fieldwork 2
DOCX
SMART tunnel report
DOCX
Site Surveying Fieldwork 1
DOCX
CT site visit report
DOCX
CT Part 2
PPTX
Rubber presentation slide
PDF
CT Presentation (KLCC)
DOCX
CT Assignment Written Report
DOCX
Site report for Measurement 1
DOCX
Site research report bm (steel) corrected
Compile version communication in consruction
Site Surveying Fieldwork 2
SMART tunnel report
Site Surveying Fieldwork 1
CT site visit report
CT Part 2
Rubber presentation slide
CT Presentation (KLCC)
CT Assignment Written Report
Site report for Measurement 1
Site research report bm (steel) corrected

Recently uploaded (20)

PPTX
Tour Presentation Educational Activity.pptx
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PPTX
PHIL.-ASTRONOMY-AND-NAVIGATION of ..pptx
PPTX
Intro to ISO 9001 2015.pptx wareness raising
PDF
IKS PPT.....................................
PPTX
NORMAN_RESEARCH_PRESENTATION.in education
PPTX
FINAL TEST 3C_OCTAVIA RAMADHANI SANTOSO-1.pptx
PDF
_Nature and dynamics of communities and community development .pdf
PPTX
chapter8-180915055454bycuufucdghrwtrt.pptx
DOCX
ENGLISH PROJECT FOR BINOD BIHARI MAHTO KOYLANCHAL UNIVERSITY
PPTX
Human Mind & its character Characteristics
PPTX
Tablets And Capsule Preformulation Of Paracetamol
PPTX
An Unlikely Response 08 10 2025.pptx
DOCX
"Project Management: Ultimate Guide to Tools, Techniques, and Strategies (2025)"
PPTX
nose tajweed for the arabic alphabets for the responsive
PPTX
2025-08-17 Joseph 03 (shared slides).pptx
DOCX
Action plan to easily understanding okey
PPTX
BIOLOGY TISSUE PPT CLASS 9 PROJECT PUBLIC
PPTX
Lesson-7-Gas. -Exchange_074636.pptx
PDF
Yusen Logistics Group Sustainability Report 2024.pdf
Tour Presentation Educational Activity.pptx
_ISO_Presentation_ISO 9001 and 45001.pptx
PHIL.-ASTRONOMY-AND-NAVIGATION of ..pptx
Intro to ISO 9001 2015.pptx wareness raising
IKS PPT.....................................
NORMAN_RESEARCH_PRESENTATION.in education
FINAL TEST 3C_OCTAVIA RAMADHANI SANTOSO-1.pptx
_Nature and dynamics of communities and community development .pdf
chapter8-180915055454bycuufucdghrwtrt.pptx
ENGLISH PROJECT FOR BINOD BIHARI MAHTO KOYLANCHAL UNIVERSITY
Human Mind & its character Characteristics
Tablets And Capsule Preformulation Of Paracetamol
An Unlikely Response 08 10 2025.pptx
"Project Management: Ultimate Guide to Tools, Techniques, and Strategies (2025)"
nose tajweed for the arabic alphabets for the responsive
2025-08-17 Joseph 03 (shared slides).pptx
Action plan to easily understanding okey
BIOLOGY TISSUE PPT CLASS 9 PROJECT PUBLIC
Lesson-7-Gas. -Exchange_074636.pptx
Yusen Logistics Group Sustainability Report 2024.pdf

Building services presentation subang parade

  • 1. Group member 1. Chia Khai Yuean 2. Chin Wei Sun 3. Jenny Wong Yen Li 4. Teo Jun Tang 5. Yap Hue Eng 6. Yap Zhi Xin
  • 4.  Service tunnel  Basement car park  A lower ground, ground and 1st floor Introduction
  • 6. Ventilation: No natural ventilation - sealed building. Mechanical ventilation : 1. extraction fan (car park) 2. air-conditioning (every shops, lift, toilets) 3. extraction grilles (toilets, roof level) Air-conditioning system: - centralized system (water chiller system) - cooled air supplied via ducting system (outlet) - use “open-ceiling” (inlet) - Plant room –3 chillers, compressor, distributor pumps,condenser pumps, chiller pumps. - T.G.I.FRiDAY’S restaurant –package system “Open ceiling”
  • 7. Condenser pumps Linear diffuser Cone diffuser Multi-direction diffuser
  • 8. Air Handling Unit (AHU): - 68 units - manually operated - controls the air-conditioning system of 5 shops. - Air supplied = 2˚C, returns = 23˚C. - Thermostat - control the temperature of air supplied. - Maintenance works for cooling coil – every 2 months. Control panel Thermostat
  • 10. Chiller: - 3 chillers - 1 chiller filled with 750 tons of water (10:30a.m to 7:00 p.m.) - 2 chillers filled with 1500 tons of water(9:30 a.m. to 9:30 p.m.). - have been used for over 26 years and do not encounter any overheat problems. Chiller Chiller control penal
  • 11. Cooling tower: - 6 at roof top. - balancing pipes - ensure the water is supplied at the same volume. - ball valve - indicate and control the supply of water. - hot water is pumped from the condenser to the cooling tower by using condenser water pump. Cooling tower
  • 13. Zoning: - single zone variable air volume. (air is supplied in same temperature but different volume). - MBO cinema - single zone constant air volume.
  • 15. Fire Protection Active Passive 1. portable fire extinguishers 1. Escape route: Pressurized staircase 2. Automatic extinguisher - Carbon dioxide gas extinguishing system - Sprinkler system 2. Fire rated door 3. Fire hydrant 3. Fire man lift 4. Hose reel 5. Risers 6. Detectors 7. Alarm system and voice communication system
  • 16. 1. Portable fire extinguishers  Powder type - used inside the mall - provided one in every shop - placed in white metal box  Carbon dioxide type -Used in electrical room, transformer room and water plant room  Maintenance: once a year  9kg
  • 17. 2. Automatic extinguishing system a. Automatic Carbon dioxide system  TNB rooms  both smoke and heat detectors  non-conductive properties
  • 18. b. Sprinkler system - wet sprinkler - distance: 3m - red bulb liquid color = 68 degree Celsius - pressed steel storage tank = 48,000 gallons capacity -1 duty pump, 2 standby pumps and 2 jockey pumps -ball valves
  • 20. 3. Fire hydrant  8  3- way hydrant  Hydrant – hydrant = 68m  hydrant - building = 8.90m  hydrant - road = 6m
  • 21. 4. Hose reel  11 sets  wet riser tank & close range pumps  30m long  diameter of 8.47mm  Canvas reel – landing valve
  • 23. 5. Risers  11 Wet risers  basement level -first floor (16.458m)  8.534m×3.658m×2.438m tank  16,800 gallons capacity
  • 24. 6. Detectors a. Smoke -lift lobby and inside the mall -35m2 b. Heat -TNB rooms  connected to fire alarm panel and linked to fire control room
  • 26. 7. Alarm detection  Manual call points = 1.46m  connected to fire alarm panel and fire control room  Automatic alarm bells  Fire switch
  • 27. 8. Voice communication system  installed at every services room and lift lobbies  Communicate to the people in the fire control room.
  • 28. Passive: 1. Escape route- Pressurized staircase  purpose made ventilation grille of independent pressurization system  Fire switch  Emergency light  riser =160mm  tread =270mm
  • 30. 2. Fire rated door  1 hour  escape route and service rooms
  • 31. 3. Fire Elevator  When there is fire, all elevators will return in sequence directly to the designated floor, which is the LG Floor.  Only fire elevator can be manually operated by the firemen via the fire lift switch.
  • 32. fire elevator fire lift switch
  • 34. Elevator 9 groups serving the whole shopping mall. • 7 are connected directly to the car park. ( electric elevators ) • 2 groups within the shopping mall excluding car park level ( hydraulic elevators ) • In one group, there are 2 elevators, with one of the elevator designated for Bomba in terms of emergency.
  • 35. Electric elevators accessible directly to the car park
  • 37. Specifications Electric Elevator Hydraulic Elevator Elevator Capacity 1800kg 1360kg, 26 persons Internal Car Size 180cm*183cm 90cm*270cm Door arrangement two - speed centre opening single - speed centre opening Round-Trip Time(RTT) 1 minute 2 minutes 15 seconds
  • 38. Operation of System Electric Elevators moves the elevator car up and down using traction steel ropes and sheaves with a counterweight to balance the load.
  • 39. Operation of System Hydraulic Elevator use hydraulic power to pressurise the piston at the base of the elevator to raise and lower the car.
  • 40. Motor Room  Located on top of the elevator shaft.  Housed traction machines of all elevators, including the control panel. Traction Machine Traction Sheave
  • 41. Escalators  moving stairs used to convey people between floor levels.  It can be constructed in few arrangements, which are one-way traffic and two-way traffic.  7 criss-cross and 2 parallel
  • 46. Feeder  3 Feeder with 11kVA switchboard section  Circuit conductor for power supply source  Final branch circuit overcurrent device.
  • 47. Vacuum Circuit Breaker  25 VCB  interrupt the current using vacuum
  • 49. Transformers 17 transformers 5 12 HVAC system Electric supply Step down 11kV 415V Silica gel breather Prevent damage as incoming air consists of moisture & dirt. Blue when installed & turn purple when they absorb moisture.
  • 51. Main Switch Board (MSB)  3 main switch board
  • 52. Bar coupler Electric Riser Feeder pillar panel 2 feeder pillar panel Only 1 feeder pillar panel is used Another 1 is use when the existing feeder failure Electric riser Distributes electric supply Bar coupler Transfers electric when the feeder is failure.
  • 53. Generator Set  Electrical generator + engine mounted together  Convert mechanicalelectrical energy  3 generator set  With battery  11250kVa  21000kVa  Use for backup
  • 54. Air Circuit Breaker (ACB)  Main circuit breakers  Compressed air is used to interrupt circuit.
  • 56. Distribution Panel  Distributes power to the consuming loads
  • 57. Miniature Circuit Breaker (MCB)  A small trip switch
  • 58. Busbar  A copper conductor A copper conductor Enclosed busbar for safety purposes
  • 59. Electric distribution Main switch board Busbar . Miniature Circuit Breaker (MCB) Distribution Panel. Load.
  • 61. Cold Water Supply  Pneumatic water pressure boosting system  Suitable for tall buildings  Water enter from rising main> store in tank
  • 62.  System consists electrical control panel, hydro- pneumatic pump, water storage tank.
  • 63.  Pneumatic water pressure boosting system  System pressure maintained by small air compressor and pneumatic cylinder  Small air compressor: contain water with pressurized air space
  • 64.  Indirect boosting from break tank - using pneumatic cylinder - a continuous running pump
  • 65.  Break tank - supply the system if main supply becomes insufficient - create pressure zones
  • 66.  GI piping- rust easily  Why choose? - first mall in KL in the 80’s - PVC not popular  Make up tank- compensate water shortage period
  • 67. Let’s watch a video  http://www.youtube.com/watch?v=LJiT3VHJwZI
  • 68. 1. Single Zone Variable Air Volume  Multi Zone Variable Air Volume More energy efficiency Recommendations- HVAC
  • 69. 2. Manual Controller  Automatic Controller  The operation will be more accurate  Energy efficiency  Usage of manpower and related cost can be cut down How it works  The electronic control unit evaluates the signals from sensors to determine the operating conditions, and controls the actuators to move dampers and valves that control the volume, temperature and direction of the air delivered
  • 70. 3. Industrial fan & UV glass • Distribute air evenly • Block 99% of UV radiation while transmitting the desired light
  • 71. 4.Return duct • Can be used to extract warm air & recycle it through the system for either cooling or heating purpose • Energy efficient compared to open ceiling system
  • 72. 1. Fire blanket and fire extinguishing ball  Portable Fire extinguisher Recommendations- Fire Protection
  • 73.  i. Fire blanket  flame-resistant blanket  extinguish small fire or protect a person from fire by wrapping the blanket around  made from 2 layers of woven glass fibre fabric and an inner layer of fire retardant film
  • 74.  ii. Fire extinguishing ball  spherical shape of fire extinguisher  1.3kg only  is activated when it is contact with flame and it will burst to spread dry chemical to extinguish fire when temperature is reach 70 Degree Celsius  Make noise when activated to alert occupants
  • 75. 2. Fire rated door for landing door & fire control room door i. UBBL clause 152.2 ii. landing door shall have a FRP (fire resistance period) of not less than half the FRP of hoist way structure with minimum FRP of one hour. iii. prevent the spread of fire from landing side into the lift shaft for a period time
  • 76.  Infra-red photo of landing doors of lift during fire test.
  • 77. 3.Visible Fire alarm system + Alarm bell  Alarm bell system i. UBBL clause 242 ii. special requirements for fire alarm system should be provided where occupants are undesirable for audible alarm system iii. visible alarm signal such as fire alarm strobe lighting device
  • 78.  Fire alarm strobe lighting device
  • 79. 4. Replace Diameter of hose reel i. 8.47mm diameter (old) ii. BS EN 671-1, requirement is 19mm or 25mm