SUBMITTED BY:-
GAURI RAJ
SWATI GOEL
BUILDING SPECIFICATION
WHITE WASH AND COLOUR WASH
WHITE WASHING
Scaffolding
 It shall be erected on double
supports tied together by
horizontal pieces over which
scaffolding shall be fixed.
Scaffolding shall rest on the
surface which is been white
washed.
 Scaffolding should be sound
and strong.
 For ceiling proper stage
scaffolding shall Be erected.
Preparation of surface
Then surface shall be thoroughly brushed
free from mortar droppings and foreign
material.
In case of old surface the surface should be
thoroughly scraped of and holes in plaster
shall be filled up with mortar.
The surface shall then be allowed to dry for
at least 48hrs before white washing is done.
PREPARATION OF LIME WASH
The lime wash shall be prepared from fresh white lime
stone the lime shall be thoroughly slaked ,mixed, stirred
with sufficient water to make a thin cream.
Now shall be allowed to stand for 24hrs then shall be
screened through a clean course cloth.
40 gram of gum dissolved in hot water, shall be added
to each 10 cubic decimeters of the cream.
Approx quantity: 5:1 where 5 is water 1 is for 1kg of
lime.
Indigo up to 3gm per kg of lime is dissolved in water
and stirred well. Water shall then be added at a rate of
about 5 liters/kg of lime.
Building specification
APPLICATION
 White wash shall be applied with moonj brushes.
 The operation for each coat shall consist of stroke
given from top downwards and other from bottom
upwards over the first stroke and similarly one
stroke horizontally from right and another from the
left before it dries.
 for new work 3 or more coats shall be applied till
the surface presents a smooth and uniform finish.
 For old work single coat or 2 or more coats shall
be applied.
COLOUR WASH
 The mineral colors shall be added to white wash.
 No color wash shall be done un till a sample of color
wash of the required tint or shade has been got
approved from the interior in charge.
 Color shall be even over the whole surface.
 For new work 2 or more coats: smooth surface
 For old work: repairing of surface: two or more coat
surface shall present a uniform finish.
 For new work the priming coat shall be of white wash
 The rate shall be for a unit of 1 sq.m

More Related Content

PPTX
Building specification
PDF
Lino pfgh high performance, high gloss solution, bee chems,india
PDF
Rottenstone&pumice use info
PPTX
Resin casting
PDF
Brochure Wall
PDF
Polymer Tech Mastercast 121A
PPTX
Laying Terracotta Floor Tiles
PDF
educational sheet clay plaster
Building specification
Lino pfgh high performance, high gloss solution, bee chems,india
Rottenstone&pumice use info
Resin casting
Brochure Wall
Polymer Tech Mastercast 121A
Laying Terracotta Floor Tiles
educational sheet clay plaster

What's hot (7)

PDF
Sealing & Cleaning Marble Limestone Tile or Travertine Stone Flooring
PPT
Foundation and plain paper power point
PPTX
Soil And Mixing preparation
PDF
DIY Epoxy Floor Coating
PPTX
impression materials and recent advances
PPTX
Est sales
PPTX
Housekeeping Workshop DAY - 3 (Chemical R - Series )
Sealing & Cleaning Marble Limestone Tile or Travertine Stone Flooring
Foundation and plain paper power point
Soil And Mixing preparation
DIY Epoxy Floor Coating
impression materials and recent advances
Est sales
Housekeeping Workshop DAY - 3 (Chemical R - Series )
Ad

Recently uploaded (20)

PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PPTX
TNA_Presentation-1-Final(SAVE)) (1).pptx
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PDF
Environmental Education MCQ BD2EE - Share Source.pdf
PDF
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
advance database management system book.pdf
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
Complications of Minimal Access-Surgery.pdf
PPTX
Introduction to pro and eukaryotes and differences.pptx
PPTX
Unit 4 Computer Architecture Multicore Processor.pptx
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
PDF
Trump Administration's workforce development strategy
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
FORM 1 BIOLOGY MIND MAPS and their schemes
B.Sc. DS Unit 2 Software Engineering.pptx
202450812 BayCHI UCSC-SV 20250812 v17.pptx
TNA_Presentation-1-Final(SAVE)) (1).pptx
A powerpoint presentation on the Revised K-10 Science Shaping Paper
Environmental Education MCQ BD2EE - Share Source.pdf
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
Weekly quiz Compilation Jan -July 25.pdf
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
advance database management system book.pdf
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
Complications of Minimal Access-Surgery.pdf
Introduction to pro and eukaryotes and differences.pptx
Unit 4 Computer Architecture Multicore Processor.pptx
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
Trump Administration's workforce development strategy
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
Ad

Building specification

  • 1. SUBMITTED BY:- GAURI RAJ SWATI GOEL BUILDING SPECIFICATION WHITE WASH AND COLOUR WASH
  • 2. WHITE WASHING Scaffolding  It shall be erected on double supports tied together by horizontal pieces over which scaffolding shall be fixed. Scaffolding shall rest on the surface which is been white washed.  Scaffolding should be sound and strong.  For ceiling proper stage scaffolding shall Be erected.
  • 3. Preparation of surface Then surface shall be thoroughly brushed free from mortar droppings and foreign material. In case of old surface the surface should be thoroughly scraped of and holes in plaster shall be filled up with mortar. The surface shall then be allowed to dry for at least 48hrs before white washing is done.
  • 4. PREPARATION OF LIME WASH The lime wash shall be prepared from fresh white lime stone the lime shall be thoroughly slaked ,mixed, stirred with sufficient water to make a thin cream. Now shall be allowed to stand for 24hrs then shall be screened through a clean course cloth. 40 gram of gum dissolved in hot water, shall be added to each 10 cubic decimeters of the cream. Approx quantity: 5:1 where 5 is water 1 is for 1kg of lime. Indigo up to 3gm per kg of lime is dissolved in water and stirred well. Water shall then be added at a rate of about 5 liters/kg of lime.
  • 6. APPLICATION  White wash shall be applied with moonj brushes.  The operation for each coat shall consist of stroke given from top downwards and other from bottom upwards over the first stroke and similarly one stroke horizontally from right and another from the left before it dries.  for new work 3 or more coats shall be applied till the surface presents a smooth and uniform finish.  For old work single coat or 2 or more coats shall be applied.
  • 7. COLOUR WASH  The mineral colors shall be added to white wash.  No color wash shall be done un till a sample of color wash of the required tint or shade has been got approved from the interior in charge.  Color shall be even over the whole surface.  For new work 2 or more coats: smooth surface  For old work: repairing of surface: two or more coat surface shall present a uniform finish.  For new work the priming coat shall be of white wash  The rate shall be for a unit of 1 sq.m