SlideShare a Scribd company logo
Can a Subcontractor Have a Critical Path Delay
          When the GC Does Not?



Christopher Carson, PSP
Shannon Campbell, PSP
Shannon Campbell, PSP

• Degree:
   – B.S. Civil Engineering
   – M.S. Engineering Management
• University:
   – B.S – United States Military Academy
   – M.S. – University of Missouri-Rolla
• Years of Experience:
   – 10 years
• Professional Field:
   – Engineering Claims Consultant
• Something you do not know about me:
   – Served 6.5 years in the military as an army engineer travelling to 14 different countries across 5
     continents – many of these visits were to view construction projects throughout the world.




                                                                                                      2
Chris Carson, PSP, CCM, PMP

 •   Corporate Director of Project Controls, Alpha Corporation
      –   Responsible for standards, processes, and procedures for a team of schedulers, analysts, and project
          managers in multiple office locations, as well as analysis, work product, and testimony
      –   Developed and manages the in-house project controls training program at Alpha
 •   Certifications:
      –   PSP (Planning & Scheduling Professional – AACEi)
      –   CCM (Certified Construction Manager - CMAA)
      –   PMP (Project Management Professional – PMI)
 •   University: University of Virginia, Mechanical Engineering, 1972
 •   Professional Field: 38 years of experience in Construction Management Services specializing in
     Scheduling, Schedule Analysis, Estimating, Claims
 •   Active in AACEi (Association for the Advancement of Cost Estimating International)
      –   Author of Recommended Practices in Scheduling & Forensic Schedule Analysis RP
 •   Active in PMI (Project Management Institute) College of Scheduling
      –   Vice President of Scheduling Excellence
      –   Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and Guidelines for
          Scheduling and Schedule Impact Analysis
      –   Serving on team writing Best Practices for Scheduling for GAO
 •   Active in CMAA (Construction Management Association of America)
      –   Served on committee revising Time Management Chapter of CMAA’s CM Standards of Practice
 •   Active in Planning Planet (global planning association)
      –   Chief Editor for US, writing Planner Users’ Guide, developing accreditation Guild for planners
 •   Something you don’t know about me: I’m a glider co-pilot, see picture
                                                                                                                   3
                                                                                                                   3
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                               Introduction
• Entitlement to Delay Damages only when there is Critical Path
  Delay to Project Completion
• What happens when an owner impact extends the time a
  subcontractor is on the job but the impact does NOT extend the
  Project Completion?
• What, if any, entitlement does the Subcontractor have to recover
  delay-related costs?




                                                                       4
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                        Topics to be Covered
•   Example
•   Pass-Through Claims
•   The Miller Act
•   Combating the No Damage For Delay Clause
•   Strategies for Proving a Subcontractor’s Delay Claim
•   From the Owner’s Standpoint




                                                                       5
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                        Topics to be Covered
•   Example
•   Pass-Through Claims
•   The Miller Act
•   Combating the No Damage For Delay Clause
•   Strategies for Proving a Subcontractor’s Delay Claim
•   From the Owner’s Standpoint




                                                                       6
As–Planned Schedule - Office Building
 Months
 1    2   3     4    5    6    7    8       9      10 11 12 13 14 15 16 17 18



 Foundations
                4    Structural Steel
                                            Roof
                                        4
                                             1
NTP                           Curtainwall
                                                   4   Interior Finishes     Punch
 Coord. Dwgs.                                                              4
                                                                              List

           3    Fab/Deliver   MEP Rough In                 MEP Finishes         1
                         3                         4                3




                                                                                     7
As–Planned v. As–Built Schedule
 Months
 1    2   3     4    5    6    7       8     9     10 11 12 13 14 15 16 17 18
  Foundations
                4    Structural Steel
                                            Roof
                                        4
                                             1
NTP                           Curtainwall
                                                   4   Interior Finishes     Punch
 Coord. Dwgs.                                                              4
                                                                              List

           3    Fab/Deliver   MEP Rough In                 MEP Finishes         1
                         3                         4                3
 Foundations
                4   Structural Steel
                                            Roof
                                        4
                                             1
NTP                           Curtainwall
                                                   4 Interior Finishes       Punch
 Coord. Dwgs.                                                              4
                                                                              List

           3    Fab/Deliver   MEP Rough In                 MEP Finishes         1
                         3                   4     3 Wks           3
                                                                                     8
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                        Topics to be Covered
•   Example
•   Pass-Through Claims
•   The Miller Act
•   Combating the No Damage For Delay Clause
•   Strategies for Proving a Subcontractor’s Delay Claim
•   From the Owner’s Standpoint




                                                                       9
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                        Pass-Through Claims
• Privity of Contract
• Recovery of Damages through a Pass Through Claim
• Definition:

      A pass-through claim is a claim:
    1) by a Subcontractor who has incurred damages due to the
       actions of the Owner/Government with whom it has no
       contract; and
    2) submitted by the GC who has a contractual relationship with
       both the Subcontractor and the Owner/Government.



                                                                       10
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                            Severin Doctrine

       “a prime contractor may sue the Government on behalf of its
       Subcontractor, in the nature of a pass-through suit, for costs
       incurred by the Subcontractor [due to the Government’s
       conduct] . . . [i]f the prime contractor proves its liability to the
       Subcontractor for the damages sustained by the latter . . . a
       showing [which] overcomes the objection to the lack of privity
       between the Government and the Subcontractor.”




                                                                              11
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                           Liquidating Agreements
• Acknowledgement of liability to the Subcontractor
    – Satisfies the Severin doctrine requirement that the GC is technically and legally liable to the
      subcontractor for the claim before submitting to Government
• Limits liability to the amount that a prime is able to recover from the
  owner
    – Protects the prime




                                                                                                        12
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


               E.R. Mitchell Constr. Co. v. Danzig
   • Basics of the case
   • Players
   • Facts
      • No dispute of Federal Government liability
      • Government approved schedule
      • Government put on notice of damages to both GC and
         subcontractor
      • Owner responsible delays not of project schedule critical path
   • Results
      • Subcontractor satisfied all requirements for entitlement to
         Eichleay damages

                                                                         13
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                        Pass Through Claims -
                         General Information
  • J.L. Simmons v. United States – provides the definition of the
  requirements of a liquidating agreement
  • Case law varies among State courts
  • Benefits of the Pass Through Claim




                                                                       14
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                        Topics to be Covered
•   Example
•   Pass-Through Claims
•   The Miller Act
•   Combating the No Damage For Delay Clause
•   Strategies for Proving a Subcontractor’s Delay Claim
•   From the Owner’s Standpoint




                                                                       15
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                              The Miller Act
• Basic Purpose – means for a subcontractor to receive payment for labor
  and materials furnished Players
• Successful recovery of delay damages through the Miller Act




                                                                           16
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                             The Miller Act -
                      Recovering Delay Damages
• Generally recoverable if characterized as increased cost of labor and
  materials – other costs have been successfully recovered
• Not relevant whether fault lies with the Owner of the Prime
• Seen as the only alternative in many cases for a subcontractor to recover
  increased costs




                                                                              17
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                             The Miller Act -
                 Considerations & Recommendations
•   Is a payment bond required?
•   Was the payment bond actually attained?
•   Timely initiation of a payment bond
•   Limited liability by surety – multiple claimants may require each to take a
    pro rata share of the penal sum




                                                                              18
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                        Topics to be Covered
•   Example
•   Pass-Through Claims
•   The Miller Act
•   Combating the No Damage For Delay Clause
•   Strategies for Proving a Subcontractor’s Delay Claim
•   From the Owner’s Standpoint




                                                                       19
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                  No Damage for Delay (NDFD)
• Basic Purpose – protects an owner or GC from paying monetary damages
  when a project is delayed
• Sample Clause

 “No payment or compensation of any kind shall be made to the contractor
      for damages because of hindrance or delay from any cause in the
   progress of the work, whether such hindrances or delays be avoidable or
                               unavoidable.”




                                                                             20
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


            No Damage for Delay - Enforceability
• Unenforceable in many states
• Established exceptions otherwise –
   • (1) not contemplated by the parties;
   • (2) so unreasonable in length as to amount to an abandonment of
      the project by the Owner;
   • (3) caused by acts of bad faith or fraud by the Owner; or
   • (4) caused by active interference by the Owner.
   • A fifth exception is also sometimes cited - delays caused by gross
      negligence.




                                                                          21
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


           No Damage for Delay – Considerations
• Sometimes incorporated by reference or in a “Flow-Down” Provision
• May be defense for an owner when presented with a pass through claim
   • Has been circumvented by use of a liquidating agreement as already
     discussed




                                                                          22
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                        Topics to be Covered
•   Example
•   Pass-Through Claims
•   The Miller Act
•   Combating the No Damage For Delay Clause
•   Strategies for Proving a Subcontractor’s Delay Claim
•   From the Owner’s Standpoint




                                                                       23
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


    Strategies for Proving a Subcontractor’s Delay Claim
•   Review and Negotiation of the Contract
•   Timely Notice
•   Waiver of Rights
•   Good Documentation
•   Involvement in the Baseline Schedule and Subsequent Updates




                                                                       24
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


 Strategies for Proving a Subcontractor’s Delay Claim
• Review and Negotiation of the Contract
   • Subcontractor should
       • Carefully review contract, especially from a legal perspective
       • Assume any NDFD will be enforced
       • Attempt to remove or reduce general assumption of delay risk
          • Reduce to specific risks that are under sub’s control
       • Watch for verbiage that limits recovery to “active interference”
         only by Owner
       • Attempt to include language that provides a “Grace Period” that
         delays must exceed to allow an adjustment for delays
          • Allows a contingency for that period to be carried
       • Seek language related to specific events, proof required or price

                                                                             25
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


 Strategies for Proving a Subcontractor’s Delay Claim
• Timely Notice
   • Assume that notice requirements will be enforced and meet them
   • Keep the GC informed so he can inform the Owner
      • Owner then has opportunity to participate in mitigation
      • Owner must be made aware of delays contemporaneously




                                                                       26
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


 Strategies for Proving a Subcontractor’s Delay Claim
• Waiver of Rights
  • Watch for waiver language
      • Could be part of a payment application or certification
      • Could be part of a change order indicating all past claims are
         waived as of change order date
  • Provide reservation of rights language to any document if
     contemplating submitting a delay claim




                                                                         27
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


 Strategies for Proving a Subcontractor’s Delay Claim
• Good Documentation
   • Key to proving damages
   • Accurate and contemporaneous
   • All documents including bid documentation, daily reports, pay
     requisitions, invoices, correspondence, all input into baseline and
     update scheduling process, minutes, resources both planned and
     actual




                                                                           28
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


 Strategies for Proving a Subcontractor’s Delay Claim
• Involvement in the Baseline Schedule and Subsequent Updates
   • Ensure input into all schedules
   • Review any updates provided by GC to ensure no acceleration or
      stacking of crews are planned
       • Ensure adequate time and sequencing
       • Note subcontractor’s expectations for period of performance
           • Includes planned resources in crews and composition
           • Stockpiling and materials distribution needs
       • Watch for reduction in durations or overlapping of work
       • Watch for shifts in start dates, access dates, or completion dates
       • Document any problems with schedules

                                                                              29
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


 Strategies for Proving a Subcontractor’s Delay Claim
• Involvement in the Baseline Schedule and Subsequent Updates
   • Review total float for subcontractors’ work to identify criticality at
      project schedule
   • Attempt to have the impacts to the subcontractor shown on the
      schedule
       • If failed, document the delay or disruption
   • Recognize that the Measured Mile is the most effective analysis for
      loss of efficiency
       • Requires good resource information
       • Related to the schedule to prove impacted & unimpacted times
   • Includes participation in any REAs submitted by GC – subcontractors
      can lose their rights against the Owner if not involved with REAs
                                                                              30
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                        Topics to be Covered
•   Example
•   Pass-Through Claims
•   The Miller Act
•   Combating the No Damage For Delay Clause
•   Strategies for Proving a Subcontractor’s Delay Claim
•   From the Owner’s Standpoint




                                                                       31
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                  From the Owner’s Standpoint
• Provide fair allocation of risk
   • Assign risk to the party most able to control it
   • This will reduce claims efforts
• Provide timely and fair review and approval of legitimate time extension
  requests
• Follow the same general rules as outlined in the strategies for the
  Subcontractor
• Should an Owner be able recover equivalent damages from a
  Subcontractor due to Subcontractor impacts?




                                                                             32
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?


                                Conclusion
•   Negotiate the Contract
•   Know the Contract
•   Be involved in the schedule from start to finish
•   Maintain accurate documentation
•   Seek legal advice




                                                                       33
Can a Subcontractor Have a Critical Path Delay
          When the GC Does Not?

Questions?
Shannon Campbell, PSP
   Chris Carson, PSP

More Related Content

PDF
2010 AACEi Great Debate - Approval of Schedule Revisions
PDF
Schedule-Centric View Of Contract Admin
PDF
How To Structure A Successful Mediation
PDF
Pmicos 2011 Review And Analysis Of Mitigation Schedules
PDF
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
PDF
Planning For Adverse Weather
PDF
Mitigation of Risk in Dual Schedules
PPT
Subcontractor Scheduling
2010 AACEi Great Debate - Approval of Schedule Revisions
Schedule-Centric View Of Contract Admin
How To Structure A Successful Mediation
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Planning For Adverse Weather
Mitigation of Risk in Dual Schedules
Subcontractor Scheduling

What's hot (20)

PDF
Use Of Schedule Logs 2012 Pmi Scop Conference
PDF
Innovative Program Delivery - Airport
PDF
Claims
PDF
Recovery Scheduling
PDF
Schedule Recovery Using Earned Value
PDF
Use Of A Claims Triage Workshop To Choose An Analysis Method
PDF
Roadmap To World Class Project Controls Pp
PDF
Schedule Updates
PPTX
Claim Presentation Rev 03 FINAL
PDF
Fleming.jon
PDF
Update Delay Analysis
PDF
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
PDF
Baseline Schedules 1
PPT
Business of anaerobic digestion project delivery basics
PDF
Schedule Design AACE
PDF
The Commissioning Process
PDF
Balancing Flexibility and Cost Control in Construction Projects
PDF
Miros Design Build Approach 3.20.02
PDF
Airport Quaraterly update feb.14 2012
PPT
ACH 216 Lecture 06 (Pre Construction Planning)
Use Of Schedule Logs 2012 Pmi Scop Conference
Innovative Program Delivery - Airport
Claims
Recovery Scheduling
Schedule Recovery Using Earned Value
Use Of A Claims Triage Workshop To Choose An Analysis Method
Roadmap To World Class Project Controls Pp
Schedule Updates
Claim Presentation Rev 03 FINAL
Fleming.jon
Update Delay Analysis
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Baseline Schedules 1
Business of anaerobic digestion project delivery basics
Schedule Design AACE
The Commissioning Process
Balancing Flexibility and Cost Control in Construction Projects
Miros Design Build Approach 3.20.02
Airport Quaraterly update feb.14 2012
ACH 216 Lecture 06 (Pre Construction Planning)
Ad

Viewers also liked (14)

PPT
Break Even
PDF
Estimate Summary Example
PPSX
Aba february 2013_presentation
PPT
Overhead analysis cost final ppt (1)
PPS
Create a Profit Plan for a Successful 2011
PDF
PPT on Construction Costing
PPTX
Overhead
PPT
ACH 216 Lecture 04a (Estimating)
PPTX
Pricing by Philiph Kotler
PPT
Pricing strategies(philip kotler)
PPTX
Estimation and quantity surveying
PPT
Pricing strategies
PPT
Pricing Ppt
PPT
Pricing Strategies
Break Even
Estimate Summary Example
Aba february 2013_presentation
Overhead analysis cost final ppt (1)
Create a Profit Plan for a Successful 2011
PPT on Construction Costing
Overhead
ACH 216 Lecture 04a (Estimating)
Pricing by Philiph Kotler
Pricing strategies(philip kotler)
Estimation and quantity surveying
Pricing strategies
Pricing Ppt
Pricing Strategies
Ad

Similar to Can A Subcontractor Have CP Delay When The Gc Does Not (20)

PDF
Pmi Pifg Presentation Nov2011
PDF
Pmi Pifg Presentation Nov2011
PPTX
LPMC Presentation - Engineering for Non Engineers 2 (1).pptx
PDF
Concurrent_Delay_Analysis_Best_Practice_1631211329.pdf
PPTX
A8 construction management bill downs - usda
PPTX
claims management framework
PDF
Energy Star In Modular Resnet 2009 Revised
PDF
FPSO & FLNG Asia 2016 - Final
PDF
Muthukumar Civil engineer resume UPDATED (1).pdf
PPTX
Coordinated project information (cpi)
PDF
GCCC contracts experience to date 08'03'11
PDF
Infrastructure project and responsibility break down
PDF
Contracting strategies for_terminal_construction
PDF
Contracting strategies for_terminal_construction
PPTX
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...
PDF
Cut & bend rebars
DOCX
CEM455 CONSTRUCTION Final Project
PDF
Project Management Report for Tank Farm
PPTX
PECDisputeResolution25102018.pptx
Pmi Pifg Presentation Nov2011
Pmi Pifg Presentation Nov2011
LPMC Presentation - Engineering for Non Engineers 2 (1).pptx
Concurrent_Delay_Analysis_Best_Practice_1631211329.pdf
A8 construction management bill downs - usda
claims management framework
Energy Star In Modular Resnet 2009 Revised
FPSO & FLNG Asia 2016 - Final
Muthukumar Civil engineer resume UPDATED (1).pdf
Coordinated project information (cpi)
GCCC contracts experience to date 08'03'11
Infrastructure project and responsibility break down
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...
Cut & bend rebars
CEM455 CONSTRUCTION Final Project
Project Management Report for Tank Farm
PECDisputeResolution25102018.pptx

More from Chris Carson (16)

PDF
Favorite Delay Analysis Methodologies Town Hall SEI
PDF
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
PDF
Mitigation And Performance Recovery Using Earned Value
PDF
Types Of Industry Scheduling
PDF
Early Completion Schedules
PDF
Design & Development Of A Schedule Management Plan Presentation
PDF
Presentation Classification Of Schedule Types
PPTX
Claims Triage
PDF
Mitigation Of Risks In Using Parallel Schedules
PDF
Planning A Complex Project
PDF
Schedule Review PMI
PDF
Testimony Mistakes
PDF
Schedule Development
PDF
Schedule Design PMI
PDF
DB Medical Pgm Mgmnt.
PDF
Baseline Schedules 2
Favorite Delay Analysis Methodologies Town Hall SEI
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Mitigation And Performance Recovery Using Earned Value
Types Of Industry Scheduling
Early Completion Schedules
Design & Development Of A Schedule Management Plan Presentation
Presentation Classification Of Schedule Types
Claims Triage
Mitigation Of Risks In Using Parallel Schedules
Planning A Complex Project
Schedule Review PMI
Testimony Mistakes
Schedule Development
Schedule Design PMI
DB Medical Pgm Mgmnt.
Baseline Schedules 2

Recently uploaded (20)

PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
Deliverable file - Regulatory guideline analysis.pdf
PPTX
Lecture (1)-Introduction.pptx business communication
PPT
Chapter four Project-Preparation material
PDF
Training And Development of Employee .pdf
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
Unit 1 Cost Accounting - Cost sheet
PPT
Data mining for business intelligence ch04 sharda
PPTX
Amazon (Business Studies) management studies
PDF
Types of control:Qualitative vs Quantitative
PPTX
5 Stages of group development guide.pptx
PDF
IFRS Notes in your pocket for study all the time
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PDF
How to Get Funding for Your Trucking Business
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PDF
Nidhal Samdaie CV - International Business Consultant
New Microsoft PowerPoint Presentation - Copy.pptx
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
unit 1 COST ACCOUNTING AND COST SHEET
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
Deliverable file - Regulatory guideline analysis.pdf
Lecture (1)-Introduction.pptx business communication
Chapter four Project-Preparation material
Training And Development of Employee .pdf
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
Unit 1 Cost Accounting - Cost sheet
Data mining for business intelligence ch04 sharda
Amazon (Business Studies) management studies
Types of control:Qualitative vs Quantitative
5 Stages of group development guide.pptx
IFRS Notes in your pocket for study all the time
DOC-20250806-WA0002._20250806_112011_0000.pdf
How to Get Funding for Your Trucking Business
Reconciliation AND MEMORANDUM RECONCILATION
Nidhal Samdaie CV - International Business Consultant

Can A Subcontractor Have CP Delay When The Gc Does Not

  • 1. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Christopher Carson, PSP Shannon Campbell, PSP
  • 2. Shannon Campbell, PSP • Degree: – B.S. Civil Engineering – M.S. Engineering Management • University: – B.S – United States Military Academy – M.S. – University of Missouri-Rolla • Years of Experience: – 10 years • Professional Field: – Engineering Claims Consultant • Something you do not know about me: – Served 6.5 years in the military as an army engineer travelling to 14 different countries across 5 continents – many of these visits were to view construction projects throughout the world. 2
  • 3. Chris Carson, PSP, CCM, PMP • Corporate Director of Project Controls, Alpha Corporation – Responsible for standards, processes, and procedures for a team of schedulers, analysts, and project managers in multiple office locations, as well as analysis, work product, and testimony – Developed and manages the in-house project controls training program at Alpha • Certifications: – PSP (Planning & Scheduling Professional – AACEi) – CCM (Certified Construction Manager - CMAA) – PMP (Project Management Professional – PMI) • University: University of Virginia, Mechanical Engineering, 1972 • Professional Field: 38 years of experience in Construction Management Services specializing in Scheduling, Schedule Analysis, Estimating, Claims • Active in AACEi (Association for the Advancement of Cost Estimating International) – Author of Recommended Practices in Scheduling & Forensic Schedule Analysis RP • Active in PMI (Project Management Institute) College of Scheduling – Vice President of Scheduling Excellence – Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and Guidelines for Scheduling and Schedule Impact Analysis – Serving on team writing Best Practices for Scheduling for GAO • Active in CMAA (Construction Management Association of America) – Served on committee revising Time Management Chapter of CMAA’s CM Standards of Practice • Active in Planning Planet (global planning association) – Chief Editor for US, writing Planner Users’ Guide, developing accreditation Guild for planners • Something you don’t know about me: I’m a glider co-pilot, see picture 3 3
  • 4. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Introduction • Entitlement to Delay Damages only when there is Critical Path Delay to Project Completion • What happens when an owner impact extends the time a subcontractor is on the job but the impact does NOT extend the Project Completion? • What, if any, entitlement does the Subcontractor have to recover delay-related costs? 4
  • 5. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Topics to be Covered • Example • Pass-Through Claims • The Miller Act • Combating the No Damage For Delay Clause • Strategies for Proving a Subcontractor’s Delay Claim • From the Owner’s Standpoint 5
  • 6. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Topics to be Covered • Example • Pass-Through Claims • The Miller Act • Combating the No Damage For Delay Clause • Strategies for Proving a Subcontractor’s Delay Claim • From the Owner’s Standpoint 6
  • 7. As–Planned Schedule - Office Building Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Foundations 4 Structural Steel Roof 4 1 NTP Curtainwall 4 Interior Finishes Punch Coord. Dwgs. 4 List 3 Fab/Deliver MEP Rough In MEP Finishes 1 3 4 3 7
  • 8. As–Planned v. As–Built Schedule Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Foundations 4 Structural Steel Roof 4 1 NTP Curtainwall 4 Interior Finishes Punch Coord. Dwgs. 4 List 3 Fab/Deliver MEP Rough In MEP Finishes 1 3 4 3 Foundations 4 Structural Steel Roof 4 1 NTP Curtainwall 4 Interior Finishes Punch Coord. Dwgs. 4 List 3 Fab/Deliver MEP Rough In MEP Finishes 1 3 4 3 Wks 3 8
  • 9. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Topics to be Covered • Example • Pass-Through Claims • The Miller Act • Combating the No Damage For Delay Clause • Strategies for Proving a Subcontractor’s Delay Claim • From the Owner’s Standpoint 9
  • 10. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Pass-Through Claims • Privity of Contract • Recovery of Damages through a Pass Through Claim • Definition: A pass-through claim is a claim: 1) by a Subcontractor who has incurred damages due to the actions of the Owner/Government with whom it has no contract; and 2) submitted by the GC who has a contractual relationship with both the Subcontractor and the Owner/Government. 10
  • 11. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Severin Doctrine “a prime contractor may sue the Government on behalf of its Subcontractor, in the nature of a pass-through suit, for costs incurred by the Subcontractor [due to the Government’s conduct] . . . [i]f the prime contractor proves its liability to the Subcontractor for the damages sustained by the latter . . . a showing [which] overcomes the objection to the lack of privity between the Government and the Subcontractor.” 11
  • 12. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Liquidating Agreements • Acknowledgement of liability to the Subcontractor – Satisfies the Severin doctrine requirement that the GC is technically and legally liable to the subcontractor for the claim before submitting to Government • Limits liability to the amount that a prime is able to recover from the owner – Protects the prime 12
  • 13. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? E.R. Mitchell Constr. Co. v. Danzig • Basics of the case • Players • Facts • No dispute of Federal Government liability • Government approved schedule • Government put on notice of damages to both GC and subcontractor • Owner responsible delays not of project schedule critical path • Results • Subcontractor satisfied all requirements for entitlement to Eichleay damages 13
  • 14. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Pass Through Claims - General Information • J.L. Simmons v. United States – provides the definition of the requirements of a liquidating agreement • Case law varies among State courts • Benefits of the Pass Through Claim 14
  • 15. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Topics to be Covered • Example • Pass-Through Claims • The Miller Act • Combating the No Damage For Delay Clause • Strategies for Proving a Subcontractor’s Delay Claim • From the Owner’s Standpoint 15
  • 16. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? The Miller Act • Basic Purpose – means for a subcontractor to receive payment for labor and materials furnished Players • Successful recovery of delay damages through the Miller Act 16
  • 17. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? The Miller Act - Recovering Delay Damages • Generally recoverable if characterized as increased cost of labor and materials – other costs have been successfully recovered • Not relevant whether fault lies with the Owner of the Prime • Seen as the only alternative in many cases for a subcontractor to recover increased costs 17
  • 18. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? The Miller Act - Considerations & Recommendations • Is a payment bond required? • Was the payment bond actually attained? • Timely initiation of a payment bond • Limited liability by surety – multiple claimants may require each to take a pro rata share of the penal sum 18
  • 19. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Topics to be Covered • Example • Pass-Through Claims • The Miller Act • Combating the No Damage For Delay Clause • Strategies for Proving a Subcontractor’s Delay Claim • From the Owner’s Standpoint 19
  • 20. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? No Damage for Delay (NDFD) • Basic Purpose – protects an owner or GC from paying monetary damages when a project is delayed • Sample Clause “No payment or compensation of any kind shall be made to the contractor for damages because of hindrance or delay from any cause in the progress of the work, whether such hindrances or delays be avoidable or unavoidable.” 20
  • 21. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? No Damage for Delay - Enforceability • Unenforceable in many states • Established exceptions otherwise – • (1) not contemplated by the parties; • (2) so unreasonable in length as to amount to an abandonment of the project by the Owner; • (3) caused by acts of bad faith or fraud by the Owner; or • (4) caused by active interference by the Owner. • A fifth exception is also sometimes cited - delays caused by gross negligence. 21
  • 22. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? No Damage for Delay – Considerations • Sometimes incorporated by reference or in a “Flow-Down” Provision • May be defense for an owner when presented with a pass through claim • Has been circumvented by use of a liquidating agreement as already discussed 22
  • 23. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Topics to be Covered • Example • Pass-Through Claims • The Miller Act • Combating the No Damage For Delay Clause • Strategies for Proving a Subcontractor’s Delay Claim • From the Owner’s Standpoint 23
  • 24. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Strategies for Proving a Subcontractor’s Delay Claim • Review and Negotiation of the Contract • Timely Notice • Waiver of Rights • Good Documentation • Involvement in the Baseline Schedule and Subsequent Updates 24
  • 25. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Strategies for Proving a Subcontractor’s Delay Claim • Review and Negotiation of the Contract • Subcontractor should • Carefully review contract, especially from a legal perspective • Assume any NDFD will be enforced • Attempt to remove or reduce general assumption of delay risk • Reduce to specific risks that are under sub’s control • Watch for verbiage that limits recovery to “active interference” only by Owner • Attempt to include language that provides a “Grace Period” that delays must exceed to allow an adjustment for delays • Allows a contingency for that period to be carried • Seek language related to specific events, proof required or price 25
  • 26. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Strategies for Proving a Subcontractor’s Delay Claim • Timely Notice • Assume that notice requirements will be enforced and meet them • Keep the GC informed so he can inform the Owner • Owner then has opportunity to participate in mitigation • Owner must be made aware of delays contemporaneously 26
  • 27. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Strategies for Proving a Subcontractor’s Delay Claim • Waiver of Rights • Watch for waiver language • Could be part of a payment application or certification • Could be part of a change order indicating all past claims are waived as of change order date • Provide reservation of rights language to any document if contemplating submitting a delay claim 27
  • 28. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Strategies for Proving a Subcontractor’s Delay Claim • Good Documentation • Key to proving damages • Accurate and contemporaneous • All documents including bid documentation, daily reports, pay requisitions, invoices, correspondence, all input into baseline and update scheduling process, minutes, resources both planned and actual 28
  • 29. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Strategies for Proving a Subcontractor’s Delay Claim • Involvement in the Baseline Schedule and Subsequent Updates • Ensure input into all schedules • Review any updates provided by GC to ensure no acceleration or stacking of crews are planned • Ensure adequate time and sequencing • Note subcontractor’s expectations for period of performance • Includes planned resources in crews and composition • Stockpiling and materials distribution needs • Watch for reduction in durations or overlapping of work • Watch for shifts in start dates, access dates, or completion dates • Document any problems with schedules 29
  • 30. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Strategies for Proving a Subcontractor’s Delay Claim • Involvement in the Baseline Schedule and Subsequent Updates • Review total float for subcontractors’ work to identify criticality at project schedule • Attempt to have the impacts to the subcontractor shown on the schedule • If failed, document the delay or disruption • Recognize that the Measured Mile is the most effective analysis for loss of efficiency • Requires good resource information • Related to the schedule to prove impacted & unimpacted times • Includes participation in any REAs submitted by GC – subcontractors can lose their rights against the Owner if not involved with REAs 30
  • 31. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Topics to be Covered • Example • Pass-Through Claims • The Miller Act • Combating the No Damage For Delay Clause • Strategies for Proving a Subcontractor’s Delay Claim • From the Owner’s Standpoint 31
  • 32. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? From the Owner’s Standpoint • Provide fair allocation of risk • Assign risk to the party most able to control it • This will reduce claims efforts • Provide timely and fair review and approval of legitimate time extension requests • Follow the same general rules as outlined in the strategies for the Subcontractor • Should an Owner be able recover equivalent damages from a Subcontractor due to Subcontractor impacts? 32
  • 33. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Conclusion • Negotiate the Contract • Know the Contract • Be involved in the schedule from start to finish • Maintain accurate documentation • Seek legal advice 33
  • 34. Can a Subcontractor Have a Critical Path Delay When the GC Does Not? Questions? Shannon Campbell, PSP Chris Carson, PSP