In the ideal Scrum world, end of the sprint planning team will have the details to start the sprint
execution but in the real world because of some issues even though the sprint planning is
completed and the backlog may not have all the details but business point of view those
Userstories may be very important and needs to be delivered early. Typical issues faced by the
scrum teams where Userstories are prioritized in the current sprint but still clarity is not there
because of various reasons like:
 Customer not provided all the details
 Dependency Userstory is not ready
 Architecture is not ready
So team may not start the Userstories from the first day of the sprint and they may need to have
some wait time to solve the above issues which will result in low velocity or team needs to spend
more time to meet the commitment.
What better can be done in Sprint Planning?
Each sprint begins with a sprint planning meeting. For a one month or four-week sprint this
meeting should last eight hours. For a two-week sprint, plan for about four hours. As a general
rule of thumb, multiply the number of weeks in your sprint by two hours to get your total sprint
planning meeting length. Sprint planning is a collaborative effort involving a Scrum Master, who
facilitates the meeting, a Product Owner, who clarifies the details of the product backlog items
and their respective acceptance criteria, and the Entire Agile Team, who define the work and
effort necessary to meet their sprint commitment
Instead of having the 4 hours Sprint planning at a stretch on the first day of the 2 weeks Sprint,
it can be split into two, 2 hours meeting.
First part of the Sprint planning can be done in the 2nd week of the last sprint where Product
owner and Scrum Master can perform below things:
 The Product Owner defines the Sprint Goal.
 Based on this goal the relevant entries in the Scrum Product Backlog are chosen by the
Product Owner.
 These entries are updated and broken into smaller stories so that they can be
completed within one Sprint.
 If any of the Userstory is not clear during the backlog grooming Scrum Master can reach
them to get the clarity before the 2nd part of the Scrum Planning.
Second part of Sprint planning can be done on the Sprint planning day. The expectation is Scrum
Master and Product owner should have gathered the information which was not clear in the 1st
phase planning. In the 2nd part of the planning meeting below thing can be performed to have
solid backlog for the scrum team.
 Team will estimate the userstories.
 Product owner can prioritize the backlog
 Based on the capacity available in the team the no. of userstories will be finalized by the
team for the Sprint.
 Team can have two stretch goal Userstories in the backlog. In case of any issues in the
prioritized backlog or team is able to finish the userstories early compared to the planned
estimation, then team cantake the stretch goal userstory which will help in increasing the
velocity of the team

More Related Content

PPTX
Agile scrum
PPTX
How scrum works
PDF
10 Key Words of Agile Scrum
PPTX
Agile scrum
PPTX
:: Agile Scrum Methodology ::
PDF
What is scrum & Agile
PDF
3 Common Scrum team Failure Modes
PDF
Scaling Agile without frameworks
Agile scrum
How scrum works
10 Key Words of Agile Scrum
Agile scrum
:: Agile Scrum Methodology ::
What is scrum & Agile
3 Common Scrum team Failure Modes
Scaling Agile without frameworks

Similar to Can I make the sprint planning better? (20)

PPT
What Is A Sprint Planning Meeting
PPTX
Unit III Scrum Events.pptx for Agile software
PPTX
Scrum framework
PPT
Introduction To Scrum
PPTX
Lecture #4 introduction to scrum in project management
PPT
Agile processes scrum
PPTX
Scrum methodology 
PDF
PSPO(Scrum Product Owner) Preparation Quick Guide.pdf
PPTX
AGILE METHODOLOGY
PDF
Scrum Reference Card
PPTX
Sprint Planning in Scrum and How to do it without Tearing Your Eyes Out
PPTX
Managing Agile Projects using Scrum Framework
PPTX
Scrum Project Health Standards
PPTX
Benefit of scrum ceremonies presentation
PPTX
Daily Scrum, Sprint Review & Retrospective.pptx
PPTX
ODP
Scrum Process
PDF
Scrum- Anit Patterns
PPTX
Agile development
What Is A Sprint Planning Meeting
Unit III Scrum Events.pptx for Agile software
Scrum framework
Introduction To Scrum
Lecture #4 introduction to scrum in project management
Agile processes scrum
Scrum methodology 
PSPO(Scrum Product Owner) Preparation Quick Guide.pdf
AGILE METHODOLOGY
Scrum Reference Card
Sprint Planning in Scrum and How to do it without Tearing Your Eyes Out
Managing Agile Projects using Scrum Framework
Scrum Project Health Standards
Benefit of scrum ceremonies presentation
Daily Scrum, Sprint Review & Retrospective.pptx
Scrum Process
Scrum- Anit Patterns
Agile development
Ad

Recently uploaded (20)

PDF
Leading with Empathy: Building Inclusive Growth in Bangladesh
PPTX
International trading agreements in world.pptx
PPTX
Principles & Theories of Mgt-Master in PM.pptx
PDF
JOB APPLICATION AND RESUME WRITING IN MANAGEMENT
PPTX
Management and Leadership across diverse culture
PDF
TED Talk on how to make TED Talk slides.pdf
PPTX
Basics of Project Management for development of leadership skills in practice
PPTX
Organizing and Staffing, Staffing process.pptx
PPTX
Time Management 2 power point presentation
PDF
Certified Information Systems Security Professional (CISSP) Specialization Ce...
PDF
Boost the power of design | Design Impulse
PPTX
EMOTIONAL INTELLIGENCE IN LEADERSHIP.pptx
PPT
Operations Management Supply-Chain Management
PPT
Introduction to Operations And Supply Management
PDF
Organizational Effectiveness in companies
PDF
Joshua Moll on Leadership & Mindset..pdf
PDF
250816-Risk Evaluation & Mitigation Strategy-CQS.pdf
PPTX
Spotlight on road Injury in the Philippines
PPTX
Self-Awareness and Values Development presentation
PPTX
Management and Leadership across culture at McDonald's
Leading with Empathy: Building Inclusive Growth in Bangladesh
International trading agreements in world.pptx
Principles & Theories of Mgt-Master in PM.pptx
JOB APPLICATION AND RESUME WRITING IN MANAGEMENT
Management and Leadership across diverse culture
TED Talk on how to make TED Talk slides.pdf
Basics of Project Management for development of leadership skills in practice
Organizing and Staffing, Staffing process.pptx
Time Management 2 power point presentation
Certified Information Systems Security Professional (CISSP) Specialization Ce...
Boost the power of design | Design Impulse
EMOTIONAL INTELLIGENCE IN LEADERSHIP.pptx
Operations Management Supply-Chain Management
Introduction to Operations And Supply Management
Organizational Effectiveness in companies
Joshua Moll on Leadership & Mindset..pdf
250816-Risk Evaluation & Mitigation Strategy-CQS.pdf
Spotlight on road Injury in the Philippines
Self-Awareness and Values Development presentation
Management and Leadership across culture at McDonald's
Ad

Can I make the sprint planning better?

  • 1. In the ideal Scrum world, end of the sprint planning team will have the details to start the sprint execution but in the real world because of some issues even though the sprint planning is completed and the backlog may not have all the details but business point of view those Userstories may be very important and needs to be delivered early. Typical issues faced by the scrum teams where Userstories are prioritized in the current sprint but still clarity is not there because of various reasons like:  Customer not provided all the details  Dependency Userstory is not ready  Architecture is not ready So team may not start the Userstories from the first day of the sprint and they may need to have some wait time to solve the above issues which will result in low velocity or team needs to spend more time to meet the commitment. What better can be done in Sprint Planning? Each sprint begins with a sprint planning meeting. For a one month or four-week sprint this meeting should last eight hours. For a two-week sprint, plan for about four hours. As a general rule of thumb, multiply the number of weeks in your sprint by two hours to get your total sprint planning meeting length. Sprint planning is a collaborative effort involving a Scrum Master, who facilitates the meeting, a Product Owner, who clarifies the details of the product backlog items and their respective acceptance criteria, and the Entire Agile Team, who define the work and effort necessary to meet their sprint commitment
  • 2. Instead of having the 4 hours Sprint planning at a stretch on the first day of the 2 weeks Sprint, it can be split into two, 2 hours meeting. First part of the Sprint planning can be done in the 2nd week of the last sprint where Product owner and Scrum Master can perform below things:  The Product Owner defines the Sprint Goal.  Based on this goal the relevant entries in the Scrum Product Backlog are chosen by the Product Owner.  These entries are updated and broken into smaller stories so that they can be completed within one Sprint.  If any of the Userstory is not clear during the backlog grooming Scrum Master can reach them to get the clarity before the 2nd part of the Scrum Planning. Second part of Sprint planning can be done on the Sprint planning day. The expectation is Scrum Master and Product owner should have gathered the information which was not clear in the 1st phase planning. In the 2nd part of the planning meeting below thing can be performed to have solid backlog for the scrum team.  Team will estimate the userstories.  Product owner can prioritize the backlog  Based on the capacity available in the team the no. of userstories will be finalized by the team for the Sprint.  Team can have two stretch goal Userstories in the backlog. In case of any issues in the prioritized backlog or team is able to finish the userstories early compared to the planned estimation, then team cantake the stretch goal userstory which will help in increasing the velocity of the team