CAPTIVE POWER POLICY
Presented BY:-
NAVAJYOTI MARTHA
HISTORY
• Captive generation “concept”& “activity” was
recognized under the repealed law prior to
Electricity Act-2003.
• In section 44 of Electricity (Supply) Act,1948
there was the provision for captive generation.
• The provision enabled that any licensee/person
(other than central govt. body) can set up captive
generation by taking the permission of SEB.
• Also the SEB need to consult with CEA before
giving any consent if the capacity of generation
exceeds 25 MW.
• The restrictions & controls on captive generation
have been scrapped under the EA-2003.
• The new act allows any person to set up captive
generating plant.
PROVISION FOR CAPTIVE GENERATION
UNDER ELECTRICITY ACT-2003
• Under section 2(8), the expression “captive
generating plant” has been defined as a
generating plant set up by any
person/society/association to generate
electricity primarily for his/their own use .
• Section 9(1) stipulates that the person need to
construct, maintain “DEDICATED” transmission
lines primarily for his own use & that can sell the
“surplus power” available to the grid.
• They can avail “open access” to the existing
transmission lines subjected to availability of
adequate transmission capacity determined by
STU/CTU.
• Also the person shall not required to obtain license
for setup,operating,maintaining a “dedicated T/L”
if the person complies with the followings
(1)Grid code,
(2)Technical standards,
(3)system of operation as per the norms of the
concerned SLDC/RLDC
• Also “CESS” & “EXCISE DUTY” levied at
different stages of Production or at the stage of
Retail Sale.
• Also both the taxes are leviable for different
purposes. “CESS” charged on consumption of
electricity & “EXCISE DUTY” charged on the
consumption of electricity on the installed
capacity within the premises.
• To the extent of sale the captive plants treated at
par with the regulations applicable to the
generating companies.
• Under section 9,the person owning captive
generating plant has also been allowed “OPEN
ACCESS” for conveyance of energy to a destination
for his own use without paying any “SURCHARGE”.
• The objective of the act to create “Competitive
Pressure” on the utilities to prevent charging
industrial consumers with high Cross subsidy.
REALITY ISSUES
• Most of the available capacity may not available to
Grid because of 2 reasons
(1) Open Access
(2)Transmission Tariff
Because the open access linked to the attitude of the
state & RLDC/SLDC.
In case of postage transmission tariff captive capacity
has to pay the “entire transmission cost”
THE ELECTRICITY RULE-2005
• According to the rule in case of a power plant-
(1) Captive users shall not hold less than 26% of
the ownership of the plant.
(2) Such Captive users shall not consume less than
51% of the electricity generated.
• NEP spells the use of the “SPARE CAPACITY”
of the Captive Generators for contributing to
the GRID.
• So that the “Quality of power supply” &
“Competitive” environment will be enhanced.
ACCORDING TO NTP
• A two-part tariff structure should be adopted for all
long term contracts to facilitate “Merit Order
dispatch”.
• “Availability Based Tariff (ABT)” framework would be
extended to generating stations (including grid
connected captive plants of capacities as determined
by the SERC).
• Appropriate Commission may also introduce
differential rates of fixed charges for peak and off
peak hours for better management of load.
• The basic focus is to Harnessing captive generation .
CAPTIVE POLICY OF ORISSA
• The Commission through a consultative process
followed by Public Hearing on 03.01.2008 had
issued a “Policy on harnessing of Surplus Power”
from Captive Generating Plants.
(1)Firm Power:
Those captive generators who give a commitment
for supply of power for a period of more than 3
months & up to 1 year shall be considered as
supplier of firm power of electricity form their
Captive Generating Plants.
• The procurement of power through the
Competitive Bidding route as per provision under
Section-63 of Electricity Act, 2003.
• To avoid cartelization of a few large CGPs artificially
boosting the pricing of surplus power from CGPs
Commission has capped .
• The “Acceptable Cost” determined through the
competitive bidding route should be within 10% of
the Maximum of cost of generation which can be
certified by reputed firm of CAs.
• State Utilities are free to purchase Power at a
higher rate than 110 % of the cost of
generation through the competitive route for
purpose of “TRADING”.
• CGPs selling power to GRIDCO will have the
indirect advantage of saving in “Transmission
charge and Transmission loss” which at 2007-
08 level will be around 34 to 35 paisa/ unit.
(2) Non-firm Power:
• Those of the captive generators who are
capable of giving day ahead schedule but are
not in a position to give supply continuously for a
period up to three months.
• If a CGP is in a position to give its day ahead
schedule for 21 days, 35 days, 40 days etc. during
a period of three months shall be considered as
non-firm supplier of electricity in a block period
of 3 months.
• It has to declare at the beginning of the
period of three months about the volume of
energy that they would be supplying to the
state grid.
• In case of failure to supply the declared
volume, they may have to pay penalty at
double the rate.
(3) Inadvertent Power:
• Power injected by the Captive Generators
without giving day ahead schedule.
• It would be priced equal to the pooled cost of
hydro power of the State.
• However, there shall be no payment for any kind
of injection firm, non-firm or inadvertent at
frequency of 50.4 HZ or more as a matter of grid
discipline.
• CGPs are given the facilities like land at
concessional rate, water supply and other benefits
by the state for setting up the industries If they
enter into an agreement for sale of their surplus
power to the state.
• The Captive Generating Plants are free to sell their
power through Open Access if they do not want to
participate in a bidding process for determination
of tariff for sale of power inside Orissa to GRIDCO.
THANK U

More Related Content

DOCX
Group captive mechanism
PPT
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
PPTX
Captive power Policy
PDF
Presentation on captive power plants
PDF
Captive Power Plants
DOCX
Regulations, Supply Rules and Standards of Electricity
PDF
Solar net metering policy
PPT
Presentation On Salient Features Of The Electricity Act , 2003
Group captive mechanism
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
Captive power Policy
Presentation on captive power plants
Captive Power Plants
Regulations, Supply Rules and Standards of Electricity
Solar net metering policy
Presentation On Salient Features Of The Electricity Act , 2003

What's hot (20)

PDF
Mo p electricity rules, 2005
PPTX
Electricity policies
PPTX
Electricity act 2003
PDF
Elecact2003
PPTX
Electricity Act 2003, Amendments and way forward
PDF
Electricity act2003
PDF
Indian Regulatory Framework Of Power Sector
PPTX
Electricity laws and regulations
PPT
Elec act
PPTX
Electricity act 2003 INDIA
PPTX
Electricity Act 2003 and its proposed amendments
PDF
Proposed Amendments to Electricity Act, 2003
PPTX
Open access ppt
PDF
Abt meter
PPTX
Restructuring of power grid
PDF
Feasibility of Solar Project with Open Access in Maharashtra
PPTX
Environmental show of the south 2014 new entrants in electricity generation
DOCX
Tariff policy of India: Salient Points
PPTX
Restructuring and Privatization
PDF
14.10.2019 proposed framework for real time market for electricity
Mo p electricity rules, 2005
Electricity policies
Electricity act 2003
Elecact2003
Electricity Act 2003, Amendments and way forward
Electricity act2003
Indian Regulatory Framework Of Power Sector
Electricity laws and regulations
Elec act
Electricity act 2003 INDIA
Electricity Act 2003 and its proposed amendments
Proposed Amendments to Electricity Act, 2003
Open access ppt
Abt meter
Restructuring of power grid
Feasibility of Solar Project with Open Access in Maharashtra
Environmental show of the south 2014 new entrants in electricity generation
Tariff policy of India: Salient Points
Restructuring and Privatization
14.10.2019 proposed framework for real time market for electricity
Ad

Viewers also liked (20)

DOCX
Wind project cost & financing
DOCX
National solar mission
PDF
Energizing roofs using Solar Energy for Captive Consumption
PPTX
NTPC Dadri Gas plant
PPTX
Ramgarh Gas Power Plant, Jaisalmer
PDF
Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...
PPT
Training power exchanges_18-may-2014
PPT
POWER SYSTEM INTRODUCTION priyank pulkit rads praveer
PPS
Gas power plant
PPTX
Hydal power plant
PPTX
Combined operation of power plants
PPT
Siemens - Power Generation Power Plants
PPT
Steam Power Plants
PPTX
MET 401 Chapter 7 -_combined_cycle_power_plant
PPTX
Hydro electric power plant
PPTX
Combined Cycle Power Plant
PPTX
Hydroelectric power
PPTX
Ppt combined cycle power plant
PDF
Steam power plant complete
Wind project cost & financing
National solar mission
Energizing roofs using Solar Energy for Captive Consumption
NTPC Dadri Gas plant
Ramgarh Gas Power Plant, Jaisalmer
Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...
Training power exchanges_18-may-2014
POWER SYSTEM INTRODUCTION priyank pulkit rads praveer
Gas power plant
Hydal power plant
Combined operation of power plants
Siemens - Power Generation Power Plants
Steam Power Plants
MET 401 Chapter 7 -_combined_cycle_power_plant
Hydro electric power plant
Combined Cycle Power Plant
Hydroelectric power
Ppt combined cycle power plant
Steam power plant complete
Ad

Similar to Captive gen (20)

PPTX
Electricity Act (Amendment) Bill 2022.pptx
PDF
New Entrants in Electric Generation in Tennessee Valley
PPTX
Ee09 801 eed ppt
PPTX
roof top solar for net metering and gross metering.pptx
PPT
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
PDF
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
PDF
DIRECT POWER PURCHASE AGREEMENTS - THE NEW DECREE IS IN EFFECT - WHAT YOU MUS...
PPTX
brief policies.pptx
PPTX
Glen Wright - Legal and Regulatory Aspects of RE
PDF
CBP16_PPT on GNA and Transmission Pricing
PPTX
Tapping potential of waste heat to power and energy conservation
PDF
Gujarat Wind Power Policy 2013
PPSX
Electricity Act 2003 pdfffffffffffff 1.ppsx
PDF
Wind Force Newsletter Feb, Edition, 2012
PPT
Duties of electrical engineer in plant.ppt
PPTX
Energy policy northeast
PDF
PM_kusum_yojna.pdf
PDF
1 final com.sum
PPTX
DSM.pptx
PPTX
Electricity_Act_2003_Detailed_Presentation (1).pptx
Electricity Act (Amendment) Bill 2022.pptx
New Entrants in Electric Generation in Tennessee Valley
Ee09 801 eed ppt
roof top solar for net metering and gross metering.pptx
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
DIRECT POWER PURCHASE AGREEMENTS - THE NEW DECREE IS IN EFFECT - WHAT YOU MUS...
brief policies.pptx
Glen Wright - Legal and Regulatory Aspects of RE
CBP16_PPT on GNA and Transmission Pricing
Tapping potential of waste heat to power and energy conservation
Gujarat Wind Power Policy 2013
Electricity Act 2003 pdfffffffffffff 1.ppsx
Wind Force Newsletter Feb, Edition, 2012
Duties of electrical engineer in plant.ppt
Energy policy northeast
PM_kusum_yojna.pdf
1 final com.sum
DSM.pptx
Electricity_Act_2003_Detailed_Presentation (1).pptx

Captive gen

  • 1. CAPTIVE POWER POLICY Presented BY:- NAVAJYOTI MARTHA
  • 2. HISTORY • Captive generation “concept”& “activity” was recognized under the repealed law prior to Electricity Act-2003. • In section 44 of Electricity (Supply) Act,1948 there was the provision for captive generation. • The provision enabled that any licensee/person (other than central govt. body) can set up captive generation by taking the permission of SEB.
  • 3. • Also the SEB need to consult with CEA before giving any consent if the capacity of generation exceeds 25 MW. • The restrictions & controls on captive generation have been scrapped under the EA-2003. • The new act allows any person to set up captive generating plant.
  • 4. PROVISION FOR CAPTIVE GENERATION UNDER ELECTRICITY ACT-2003 • Under section 2(8), the expression “captive generating plant” has been defined as a generating plant set up by any person/society/association to generate electricity primarily for his/their own use . • Section 9(1) stipulates that the person need to construct, maintain “DEDICATED” transmission lines primarily for his own use & that can sell the “surplus power” available to the grid.
  • 5. • They can avail “open access” to the existing transmission lines subjected to availability of adequate transmission capacity determined by STU/CTU. • Also the person shall not required to obtain license for setup,operating,maintaining a “dedicated T/L” if the person complies with the followings (1)Grid code, (2)Technical standards, (3)system of operation as per the norms of the concerned SLDC/RLDC
  • 6. • Also “CESS” & “EXCISE DUTY” levied at different stages of Production or at the stage of Retail Sale. • Also both the taxes are leviable for different purposes. “CESS” charged on consumption of electricity & “EXCISE DUTY” charged on the consumption of electricity on the installed capacity within the premises.
  • 7. • To the extent of sale the captive plants treated at par with the regulations applicable to the generating companies. • Under section 9,the person owning captive generating plant has also been allowed “OPEN ACCESS” for conveyance of energy to a destination for his own use without paying any “SURCHARGE”. • The objective of the act to create “Competitive Pressure” on the utilities to prevent charging industrial consumers with high Cross subsidy.
  • 8. REALITY ISSUES • Most of the available capacity may not available to Grid because of 2 reasons (1) Open Access (2)Transmission Tariff Because the open access linked to the attitude of the state & RLDC/SLDC. In case of postage transmission tariff captive capacity has to pay the “entire transmission cost”
  • 9. THE ELECTRICITY RULE-2005 • According to the rule in case of a power plant- (1) Captive users shall not hold less than 26% of the ownership of the plant. (2) Such Captive users shall not consume less than 51% of the electricity generated.
  • 10. • NEP spells the use of the “SPARE CAPACITY” of the Captive Generators for contributing to the GRID. • So that the “Quality of power supply” & “Competitive” environment will be enhanced.
  • 11. ACCORDING TO NTP • A two-part tariff structure should be adopted for all long term contracts to facilitate “Merit Order dispatch”. • “Availability Based Tariff (ABT)” framework would be extended to generating stations (including grid connected captive plants of capacities as determined by the SERC). • Appropriate Commission may also introduce differential rates of fixed charges for peak and off peak hours for better management of load. • The basic focus is to Harnessing captive generation .
  • 12. CAPTIVE POLICY OF ORISSA • The Commission through a consultative process followed by Public Hearing on 03.01.2008 had issued a “Policy on harnessing of Surplus Power” from Captive Generating Plants. (1)Firm Power: Those captive generators who give a commitment for supply of power for a period of more than 3 months & up to 1 year shall be considered as supplier of firm power of electricity form their Captive Generating Plants.
  • 13. • The procurement of power through the Competitive Bidding route as per provision under Section-63 of Electricity Act, 2003. • To avoid cartelization of a few large CGPs artificially boosting the pricing of surplus power from CGPs Commission has capped . • The “Acceptable Cost” determined through the competitive bidding route should be within 10% of the Maximum of cost of generation which can be certified by reputed firm of CAs.
  • 14. • State Utilities are free to purchase Power at a higher rate than 110 % of the cost of generation through the competitive route for purpose of “TRADING”. • CGPs selling power to GRIDCO will have the indirect advantage of saving in “Transmission charge and Transmission loss” which at 2007- 08 level will be around 34 to 35 paisa/ unit.
  • 15. (2) Non-firm Power: • Those of the captive generators who are capable of giving day ahead schedule but are not in a position to give supply continuously for a period up to three months. • If a CGP is in a position to give its day ahead schedule for 21 days, 35 days, 40 days etc. during a period of three months shall be considered as non-firm supplier of electricity in a block period of 3 months.
  • 16. • It has to declare at the beginning of the period of three months about the volume of energy that they would be supplying to the state grid. • In case of failure to supply the declared volume, they may have to pay penalty at double the rate.
  • 17. (3) Inadvertent Power: • Power injected by the Captive Generators without giving day ahead schedule. • It would be priced equal to the pooled cost of hydro power of the State. • However, there shall be no payment for any kind of injection firm, non-firm or inadvertent at frequency of 50.4 HZ or more as a matter of grid discipline.
  • 18. • CGPs are given the facilities like land at concessional rate, water supply and other benefits by the state for setting up the industries If they enter into an agreement for sale of their surplus power to the state. • The Captive Generating Plants are free to sell their power through Open Access if they do not want to participate in a bidding process for determination of tariff for sale of power inside Orissa to GRIDCO.