Case Study : THE INVISIBLE SPONSOR1
Background
Some executives prefer to micromanage projects whereas other
executives
are fearful of making a decision because, if they were to make
the wrong
decision, it could impact their career. In this case study, the
president of the company assigned one of the vice presidents to
act as the project sponsor on a project designed to build tooling
for a client. The sponsor, however, was reluctant to make any
decisions.
Assigning the VP
Moreland Company was well-respected as a tooling design-and-
build
company. Moreland was project-driven because all of its income
came
from projects. Moreland was also reasonably mature in project
management.
When the previous VP for engineering retired, Moreland hired
an executive from a manufacturing company to replace him. The
new VP for engineering, Al Zink, had excellent engineering
knowledge about tooling but had worked for companies that
were not project-driven. Al had very little knowledge about
project management and had never functioned as a project
sponsor. Because of Al’s lack of experience as a sponsor, the
president decided that Al should “get his feet wet” as quickly as
possible and assigned him as the project sponsor on a
mediumsized project. The project manager on this project was
Fred Cutler. Fred was an engineer with more than twenty years
of experience in tooling design and manufacturing. Fred
reported directly to Al Zink administratively.
Fred's Dilemma
Fred understood the situation; he would have to train Al Zink on
how to
function as a project sponsor. This was a new experience for
Fred because subordinates usually do not train senior personnel
on how to do their job. Would Al Zink be receptive?
Fred explained the role of the sponsor and how there are certain
project documents that require the signatures of both the project
manager and the project sponsor. Everything seemed to be
going well until Fred informed Al that the project sponsor is the
person that the president eventually holds accountable for the
success or failure of the project. Fred could tell that Al was
quite upset over this statement.
Al realized that the failure of a project where he was the
sponsor could damage his reputation and career. Al was now
uncomfortable about having to act as a sponsor but knew that he
might eventually be assigned as a sponsor on other projects. Al
also knew that this project was somewhat of a high risk. If Al
could function as an invisible sponsor, he could avoid making
any critical decisions.
In the first meeting between Fred and Al where Al was the
sponsor, Al asked Fred for a copy of the schedule for the
project. Fred responded: I’m working on the schedule right now.
I cannot finish the schedule until you tell me whether you want
me to lay out the schedule based upon best time, least cost, or
least risk.
Al stated that he would think about it and get back to Fred as
soon as possible.
During the middle of the next week, Fred and Al met in the
company’s cafeteria. Al asked Fred again, “How is the schedule
coming along?” and Fred responded as before: I cannot finish
the schedule until you tell me whether you want me to lay out
the schedule based upon best time, least cost, or least risk. Al
was furious, turned around, and walked away from Fred. Fred
was now getting nervous about how upset Al was and began
worrying if Al might remove him as the project manager.
But Fred decided to hold his ground and get Al to make a
decision. At the weekly sponsor meeting between Fred and Al,
once again Al asked the same question, and once again Fred
gave the same response as before. Al now became quite angry
and yelled out: Just give me a least time schedule.
Fred had gotten Al to make his first decision. Fred finalized his
schedule and had it on Al’s desk two days later awaiting Al’s
signature. Once again, Al procrastinated and refused to sign off
on the schedule. Al believed that, if he delayed making the
decision, Fred would take the initiative and begin working on
the schedule without Al’s signature. Fred kept sending e-mails
to Al asking when he intended to sign off on the schedule or, if
something was not correct, what changes needed to be made. As
expected, Al did not respond. Fred then decided that he had to
pressure Al one way or another into making timely decisions as
the project sponsor. Fred then sent an e-mail to Al that stated:
I sent you the project schedule last week. If the schedule is not
signed by this Friday, there could be an impact on the end date
of the project. If I do not hear from you, one way or another, by
this Friday, I will assume you approve the schedule and I can
begin implementation.
The president’s e-mail address was also included in the CC
location on the e-mail. The next morning, Fred found the
schedule on his desk, signed by Al Zink.
Answer Questions based on Case Study above- (Total words
adding all 3 answers should be 300+) Reference and citations
needed
1. Why do some executives refuse to function as project
sponsors?
2. Can an executive be “forced” to function as a sponsor?
3. Is it right for the sponsor to be the ultimate person
responsible for the success
or failure of the project?

More Related Content

DOCX
Read the case study The Invisible Sponsor on page 658 and then.docx
DOCX
THE INVISIBLE SPONSORBackgroundSome executives prefer to mi.docx
DOCX
LinkedIn_ProRef_MZirklebach_CIO_LLUMC_02Jul16
DOCX
Herb had been with the company for more than eight years and had wor
DOCX
Project Human Resources and Communications Management Assignment.docx
DOCX
Herb had been with the company for more than eight years and had
DOCX
Case Study 1 Applying Theory to PracticeSocial scientists hav.docx
DOCX
Case Study - Option 3 BarbaraBarbara is a 22 year old woman who h.docx
Read the case study The Invisible Sponsor on page 658 and then.docx
THE INVISIBLE SPONSORBackgroundSome executives prefer to mi.docx
LinkedIn_ProRef_MZirklebach_CIO_LLUMC_02Jul16
Herb had been with the company for more than eight years and had wor
Project Human Resources and Communications Management Assignment.docx
Herb had been with the company for more than eight years and had
Case Study 1 Applying Theory to PracticeSocial scientists hav.docx
Case Study - Option 3 BarbaraBarbara is a 22 year old woman who h.docx

More from cowinhelen (20)

DOCX
Case Study - Cyberterrorism—A New RealityWhen hackers claiming .docx
DOCX
Case Study - APA paper with min 4 page content Review the Blai.docx
DOCX
Case Study - Global Mobile Corporation Damn it, .docx
DOCX
Case Study #3Apple Suppliers & Labor PracticesWith its h.docx
DOCX
CASE STUDY (Individual) Scotland  In terms of its physical l.docx
DOCX
Case Study #2 T.D. enjoys caring for the children and young peop.docx
DOCX
CASE STUDY #2 Chief Complaint I have pain in my belly”.docx
DOCX
Case Study #1Jennifer is a 29-year-old administrative assistan.docx
DOCX
Case Study # 2 –Danny’s Unhappy DutyEmployee ProfilesCaro.docx
DOCX
Case Study – Multicultural ParadeRead the Case below, and answe.docx
DOCX
CASE STUDY Experiential training encourages changes in work beha.docx
DOCX
Case Study Hereditary AngioedemaAll responses must be in your .docx
DOCX
case studieson Gentrification and Displacement in the Sa.docx
DOCX
Case Studt on KFC Introduction1) Identify the type of .docx
DOCX
Case Study Crocs Revolutionizing an Industry’s Supply Chain .docx
DOCX
Case Studies Student must complete 5 case studies as instructed.docx
DOCX
Case Studies in Telehealth AdoptionThe mission of The Comm.docx
DOCX
Case Studies in Abnormal PsychologyYou Decide The Case of J.docx
DOCX
Case Studies Focusing on Fluency StrategiesCase Scenario .docx
DOCX
Case Studies 329to turn or what to say. He had no control .docx
Case Study - Cyberterrorism—A New RealityWhen hackers claiming .docx
Case Study - APA paper with min 4 page content Review the Blai.docx
Case Study - Global Mobile Corporation Damn it, .docx
Case Study #3Apple Suppliers & Labor PracticesWith its h.docx
CASE STUDY (Individual) Scotland  In terms of its physical l.docx
Case Study #2 T.D. enjoys caring for the children and young peop.docx
CASE STUDY #2 Chief Complaint I have pain in my belly”.docx
Case Study #1Jennifer is a 29-year-old administrative assistan.docx
Case Study # 2 –Danny’s Unhappy DutyEmployee ProfilesCaro.docx
Case Study – Multicultural ParadeRead the Case below, and answe.docx
CASE STUDY Experiential training encourages changes in work beha.docx
Case Study Hereditary AngioedemaAll responses must be in your .docx
case studieson Gentrification and Displacement in the Sa.docx
Case Studt on KFC Introduction1) Identify the type of .docx
Case Study Crocs Revolutionizing an Industry’s Supply Chain .docx
Case Studies Student must complete 5 case studies as instructed.docx
Case Studies in Telehealth AdoptionThe mission of The Comm.docx
Case Studies in Abnormal PsychologyYou Decide The Case of J.docx
Case Studies Focusing on Fluency StrategiesCase Scenario .docx
Case Studies 329to turn or what to say. He had no control .docx

Recently uploaded (20)

PDF
Complications of Minimal Access-Surgery.pdf
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PDF
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
PPTX
Introduction to pro and eukaryotes and differences.pptx
PDF
HVAC Specification 2024 according to central public works department
PPTX
Virtual and Augmented Reality in Current Scenario
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
Environmental Education MCQ BD2EE - Share Source.pdf
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PPTX
Unit 4 Computer Architecture Multicore Processor.pptx
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
Trump Administration's workforce development strategy
PDF
AI-driven educational solutions for real-life interventions in the Philippine...
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PPTX
TNA_Presentation-1-Final(SAVE)) (1).pptx
PDF
Weekly quiz Compilation Jan -July 25.pdf
Complications of Minimal Access-Surgery.pdf
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
Introduction to pro and eukaryotes and differences.pptx
HVAC Specification 2024 according to central public works department
Virtual and Augmented Reality in Current Scenario
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
Chinmaya Tiranga quiz Grand Finale.pdf
Environmental Education MCQ BD2EE - Share Source.pdf
Share_Module_2_Power_conflict_and_negotiation.pptx
Unit 4 Computer Architecture Multicore Processor.pptx
FORM 1 BIOLOGY MIND MAPS and their schemes
202450812 BayCHI UCSC-SV 20250812 v17.pptx
Trump Administration's workforce development strategy
AI-driven educational solutions for real-life interventions in the Philippine...
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
Paper A Mock Exam 9_ Attempt review.pdf.
TNA_Presentation-1-Final(SAVE)) (1).pptx
Weekly quiz Compilation Jan -July 25.pdf

Case Study   THE INVISIBLE SPONSOR1BackgroundSome execut.docx

  • 1. Case Study : THE INVISIBLE SPONSOR1 Background Some executives prefer to micromanage projects whereas other executives are fearful of making a decision because, if they were to make the wrong decision, it could impact their career. In this case study, the president of the company assigned one of the vice presidents to act as the project sponsor on a project designed to build tooling for a client. The sponsor, however, was reluctant to make any decisions. Assigning the VP Moreland Company was well-respected as a tooling design-and- build company. Moreland was project-driven because all of its income came from projects. Moreland was also reasonably mature in project management. When the previous VP for engineering retired, Moreland hired an executive from a manufacturing company to replace him. The new VP for engineering, Al Zink, had excellent engineering knowledge about tooling but had worked for companies that were not project-driven. Al had very little knowledge about project management and had never functioned as a project
  • 2. sponsor. Because of Al’s lack of experience as a sponsor, the president decided that Al should “get his feet wet” as quickly as possible and assigned him as the project sponsor on a mediumsized project. The project manager on this project was Fred Cutler. Fred was an engineer with more than twenty years of experience in tooling design and manufacturing. Fred reported directly to Al Zink administratively. Fred's Dilemma Fred understood the situation; he would have to train Al Zink on how to function as a project sponsor. This was a new experience for Fred because subordinates usually do not train senior personnel on how to do their job. Would Al Zink be receptive? Fred explained the role of the sponsor and how there are certain project documents that require the signatures of both the project manager and the project sponsor. Everything seemed to be going well until Fred informed Al that the project sponsor is the person that the president eventually holds accountable for the success or failure of the project. Fred could tell that Al was quite upset over this statement. Al realized that the failure of a project where he was the sponsor could damage his reputation and career. Al was now uncomfortable about having to act as a sponsor but knew that he might eventually be assigned as a sponsor on other projects. Al also knew that this project was somewhat of a high risk. If Al could function as an invisible sponsor, he could avoid making any critical decisions. In the first meeting between Fred and Al where Al was the
  • 3. sponsor, Al asked Fred for a copy of the schedule for the project. Fred responded: I’m working on the schedule right now. I cannot finish the schedule until you tell me whether you want me to lay out the schedule based upon best time, least cost, or least risk. Al stated that he would think about it and get back to Fred as soon as possible. During the middle of the next week, Fred and Al met in the company’s cafeteria. Al asked Fred again, “How is the schedule coming along?” and Fred responded as before: I cannot finish the schedule until you tell me whether you want me to lay out the schedule based upon best time, least cost, or least risk. Al was furious, turned around, and walked away from Fred. Fred was now getting nervous about how upset Al was and began worrying if Al might remove him as the project manager. But Fred decided to hold his ground and get Al to make a decision. At the weekly sponsor meeting between Fred and Al, once again Al asked the same question, and once again Fred gave the same response as before. Al now became quite angry and yelled out: Just give me a least time schedule. Fred had gotten Al to make his first decision. Fred finalized his schedule and had it on Al’s desk two days later awaiting Al’s signature. Once again, Al procrastinated and refused to sign off on the schedule. Al believed that, if he delayed making the decision, Fred would take the initiative and begin working on the schedule without Al’s signature. Fred kept sending e-mails to Al asking when he intended to sign off on the schedule or, if something was not correct, what changes needed to be made. As expected, Al did not respond. Fred then decided that he had to pressure Al one way or another into making timely decisions as the project sponsor. Fred then sent an e-mail to Al that stated:
  • 4. I sent you the project schedule last week. If the schedule is not signed by this Friday, there could be an impact on the end date of the project. If I do not hear from you, one way or another, by this Friday, I will assume you approve the schedule and I can begin implementation. The president’s e-mail address was also included in the CC location on the e-mail. The next morning, Fred found the schedule on his desk, signed by Al Zink. Answer Questions based on Case Study above- (Total words adding all 3 answers should be 300+) Reference and citations needed 1. Why do some executives refuse to function as project sponsors? 2. Can an executive be “forced” to function as a sponsor? 3. Is it right for the sponsor to be the ultimate person responsible for the success or failure of the project?