CERC (Deviation settlement Mechanism
and related matters) 4th Amendment
Regulations,2018:
Highlights with necessary changes required in ABT
software
for monitoring of DSM.
Notification
date:20.11.2018
Effective from: 01.01.2019
Comparison of DSM 4th amendment Regulation with existing DSM Regulation
AG
Sr. No. Description New Regulation Old Regulation
1 Effective from 01/01/2019 17/02/2014
2
Operational
Frequency Band
49.85 to 50.05 49.70 to 50.10
DSM Rate
3 Max. DSM rate 8.00 INR/KWH below 49.85 Hz
8.2404 INR/KWH below 49.70
Hz
4 Min. DSM Rate 0 at 50.05 Hz & above 0 at 50.05 Hz & above
5 DSM price vector
DSM rate vector will have a dynamic slope determined by
joining the identified price points at 50 Hz (daily simple
average ACP), frequency of 49.85 Hz (Rs. 8 per unit) and
50.05 Hz (zero) on a daily basis. Max ACP capped at Rs 8.
After review within one year , CERC may substituted daily
average ACP, by the time-block-wise ACP in the DAM or
hourly ACP when the real time market is introduced.
• In case of no-trade on a given day, daily simple average
ACP of the last available day shall be considered for
determining the DSM charge.
Fixed slope with joining the
identified points at 50Hz
(178p),
49.7Hz(824.04p) and
50.05Hz(zero p).
Sr. No. Description New Regulation Old Regulation
6
Cap Rate for
Generating
station using
coal/lignite/APM
gas as the fuel
Linked to variable charge (ECR) of previous month billed of
the station.
No Capping for GAS /Hydro stations/Buyers
303.04 paisa per unit (Linked
to UI rate at freq 49.95 Hz.)
No Capping for GAS /Hydro
stations/Buyers
DSM Volume Limit
7
For under/over drawal
/injection by
buyer/seller in
a time block
Not to exceed 12% of its drawl
schedule or 150 MW whichever is lower
in a time block
Not to exceed 12% of its drawl
schedule or 150 MW
whichever is lower in a time
block
8
Limits on day Deviation
*To be implemented
after
one (01) year.
Total deviation from schedule in either
direction, in energy terms during a day
shall not be in excess of 3% of the total
schedule for the drawee entities and
1% for the generators* NO Such Provision earlier
9
*Additional charge for
Violating Day Deviation
Limits:
*To be implemented
after
one (01) year.
20% of the daily base DSM payable /
receivable NO Such Provision earlier
Additional DSM Charge
10
Additional DSM
charge Applicable for over drawl or under injection for each time
block when freq. >49.85 Hz & < 50.05 Hz
Applicable for over drawl or
under injection for each time
block when fr. >49.7 Hz & <
50.05 HzAG
Sr. No. Description New Regulation Old Regulation
11
Additional DSM
beyond operating
range
100% of DSM cap rate i.e station variable charge(ECR)
for under injection below 49.85 Hz
100% of DSM cap
rate(303.04p/kWh) for
under injection below 49.7Hz
12
Over injection beyond 50.05 Hz will attract Add Dev
charge for each unit @ DSM rate of 50Hz(ACP) or Cap
rate of station whichever is lower.
Over injection beyond 50.10Hz will
attract Add Dev Charge for each unit
@ DSM rate of 50Hz(178p/kWh)
Sign Change
13
Sign Change
Counter
In the event of sustained deviation from SG in one
direction (positive or negative) by any regional entity
(buyer or seller), such regional entity shall have to
change sign of their deviation from schedule, at least
once, after every 6 time blocks.
In the event of sustained deviation
from SG in one direction (positive or
negative) by any regional entity
(buyer or seller), such regional
entity shall have to change sign of
their deviation from schedule, at
least once, after every 12 time
blocks.
14
Add Charge
for violating
the regulation:
Violation of the requirement under this clause shall
attract an additional charge of 20% on the daily base
DSM payable / receivable.
The additional charge for violation of sign change
stipulation shall be levied for each such violation during
a day.
No Additional Charge for such
Violations
AG
AG
AG
AG
Operational Challenges from the Amendment Regulation:
 Strictly adhere to the given Schedule as over injection will result in no gain due to capping
with variable charge of the station.
 Under injection above break even frequency is the only scenario of gain upto 12% in a block
but with compliance of “Sign Change of deviation”.
 Strictly follow the sign change of deviations after every 6 blocks ,there should be an early alert
from 5th time block in case of sustained deviation in one direction.
 There should be a asking rate to run the station for rest of the blocks for a day to avoid add
deviation charge due to violation of +/-1% volume limit of deviation.
(clause.—applicable after one year.)
 Block wise deviation Volume Limits and add deviation for violating them will remain same.
 DSM price vector will change daily based on ACP of DAM in IEX so ABT software at each
station has to be modified accordingly. Preferably software should crawl ACP data from NLDC
website and automatically create DSM price vector for the next day.
AG

More Related Content

PPSX
ABT-UI & Deviation Settlement Mechanism (DSM)
PPTX
Deviation Settlement Mechanism (DSM)
PDF
Deviation settelment mechanism
PPT
ABT a complete report and a case study
PPSX
ABT (Availability Based Tariff) - UI (Unscheduled Interchange)
PPTX
DSM.pptx
PPTX
Tariff structure & Cerc tariff regulation
PPT
Availability Based Tariff and UI charges
ABT-UI & Deviation Settlement Mechanism (DSM)
Deviation Settlement Mechanism (DSM)
Deviation settelment mechanism
ABT a complete report and a case study
ABT (Availability Based Tariff) - UI (Unscheduled Interchange)
DSM.pptx
Tariff structure & Cerc tariff regulation
Availability Based Tariff and UI charges

What's hot (20)

PPTX
Availability based tariff
PPTX
Indian electricity market and power exchanges
DOCX
Power Grid's Inter-State transmission charges in India
PPTX
NPTI 15th batch Indian electricity grid code (IEGC)
PPT
Multi year tariffs and regulations
DOC
Electricity Trading in India
PPT
Grid code
PPTX
PPTX
Unit - V DC Motor.pptx
PPT
Generator capability curve
PPT
Unit 3
DOCX
500 MW synchronous generator rotor construction report
PPSX
Power System Planning
PPTX
Electric traction
PPTX
Load dispatch center
PPTX
Symmetrical Fault Analysis
PPTX
Power electronic converter in wind turbine
PDF
Indian Regulatory Framework Of Power Sector
PDF
Tariff-based Competitive Bidding in the Power Sector
Availability based tariff
Indian electricity market and power exchanges
Power Grid's Inter-State transmission charges in India
NPTI 15th batch Indian electricity grid code (IEGC)
Multi year tariffs and regulations
Electricity Trading in India
Grid code
Unit - V DC Motor.pptx
Generator capability curve
Unit 3
500 MW synchronous generator rotor construction report
Power System Planning
Electric traction
Load dispatch center
Symmetrical Fault Analysis
Power electronic converter in wind turbine
Indian Regulatory Framework Of Power Sector
Tariff-based Competitive Bidding in the Power Sector
Ad

Recently uploaded (20)

PDF
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PDF
737-MAX_SRG.pdf student reference guides
PPT
Total quality management ppt for engineering students
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PDF
Design Guidelines and solutions for Plastics parts
PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
PPTX
Software Engineering and software moduleing
PDF
22EC502-MICROCONTROLLER AND INTERFACING-8051 MICROCONTROLLER.pdf
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
PPTX
Management Information system : MIS-e-Business Systems.pptx
PPTX
introduction to high performance computing
PPTX
Amdahl’s law is explained in the above power point presentations
PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
737-MAX_SRG.pdf student reference guides
Total quality management ppt for engineering students
Categorization of Factors Affecting Classification Algorithms Selection
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
Design Guidelines and solutions for Plastics parts
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
Software Engineering and software moduleing
22EC502-MICROCONTROLLER AND INTERFACING-8051 MICROCONTROLLER.pdf
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
Management Information system : MIS-e-Business Systems.pptx
introduction to high performance computing
Amdahl’s law is explained in the above power point presentations
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
"Array and Linked List in Data Structures with Types, Operations, Implementat...
Exploratory_Data_Analysis_Fundamentals.pdf
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Ad

Cerc Deviation Settlement Mechanism ( DSM ) 4th ammendment Summary wef 01/01/2019

  • 1. AG CERC (Deviation settlement Mechanism and related matters) 4th Amendment Regulations,2018: Highlights with necessary changes required in ABT software for monitoring of DSM. Notification date:20.11.2018 Effective from: 01.01.2019
  • 2. Comparison of DSM 4th amendment Regulation with existing DSM Regulation AG Sr. No. Description New Regulation Old Regulation 1 Effective from 01/01/2019 17/02/2014 2 Operational Frequency Band 49.85 to 50.05 49.70 to 50.10 DSM Rate 3 Max. DSM rate 8.00 INR/KWH below 49.85 Hz 8.2404 INR/KWH below 49.70 Hz 4 Min. DSM Rate 0 at 50.05 Hz & above 0 at 50.05 Hz & above 5 DSM price vector DSM rate vector will have a dynamic slope determined by joining the identified price points at 50 Hz (daily simple average ACP), frequency of 49.85 Hz (Rs. 8 per unit) and 50.05 Hz (zero) on a daily basis. Max ACP capped at Rs 8. After review within one year , CERC may substituted daily average ACP, by the time-block-wise ACP in the DAM or hourly ACP when the real time market is introduced. • In case of no-trade on a given day, daily simple average ACP of the last available day shall be considered for determining the DSM charge. Fixed slope with joining the identified points at 50Hz (178p), 49.7Hz(824.04p) and 50.05Hz(zero p).
  • 3. Sr. No. Description New Regulation Old Regulation 6 Cap Rate for Generating station using coal/lignite/APM gas as the fuel Linked to variable charge (ECR) of previous month billed of the station. No Capping for GAS /Hydro stations/Buyers 303.04 paisa per unit (Linked to UI rate at freq 49.95 Hz.) No Capping for GAS /Hydro stations/Buyers DSM Volume Limit 7 For under/over drawal /injection by buyer/seller in a time block Not to exceed 12% of its drawl schedule or 150 MW whichever is lower in a time block Not to exceed 12% of its drawl schedule or 150 MW whichever is lower in a time block 8 Limits on day Deviation *To be implemented after one (01) year. Total deviation from schedule in either direction, in energy terms during a day shall not be in excess of 3% of the total schedule for the drawee entities and 1% for the generators* NO Such Provision earlier 9 *Additional charge for Violating Day Deviation Limits: *To be implemented after one (01) year. 20% of the daily base DSM payable / receivable NO Such Provision earlier Additional DSM Charge 10 Additional DSM charge Applicable for over drawl or under injection for each time block when freq. >49.85 Hz & < 50.05 Hz Applicable for over drawl or under injection for each time block when fr. >49.7 Hz & < 50.05 HzAG
  • 4. Sr. No. Description New Regulation Old Regulation 11 Additional DSM beyond operating range 100% of DSM cap rate i.e station variable charge(ECR) for under injection below 49.85 Hz 100% of DSM cap rate(303.04p/kWh) for under injection below 49.7Hz 12 Over injection beyond 50.05 Hz will attract Add Dev charge for each unit @ DSM rate of 50Hz(ACP) or Cap rate of station whichever is lower. Over injection beyond 50.10Hz will attract Add Dev Charge for each unit @ DSM rate of 50Hz(178p/kWh) Sign Change 13 Sign Change Counter In the event of sustained deviation from SG in one direction (positive or negative) by any regional entity (buyer or seller), such regional entity shall have to change sign of their deviation from schedule, at least once, after every 6 time blocks. In the event of sustained deviation from SG in one direction (positive or negative) by any regional entity (buyer or seller), such regional entity shall have to change sign of their deviation from schedule, at least once, after every 12 time blocks. 14 Add Charge for violating the regulation: Violation of the requirement under this clause shall attract an additional charge of 20% on the daily base DSM payable / receivable. The additional charge for violation of sign change stipulation shall be levied for each such violation during a day. No Additional Charge for such Violations AG
  • 5. AG
  • 6. AG
  • 7. AG
  • 8. Operational Challenges from the Amendment Regulation:  Strictly adhere to the given Schedule as over injection will result in no gain due to capping with variable charge of the station.  Under injection above break even frequency is the only scenario of gain upto 12% in a block but with compliance of “Sign Change of deviation”.  Strictly follow the sign change of deviations after every 6 blocks ,there should be an early alert from 5th time block in case of sustained deviation in one direction.  There should be a asking rate to run the station for rest of the blocks for a day to avoid add deviation charge due to violation of +/-1% volume limit of deviation. (clause.—applicable after one year.)  Block wise deviation Volume Limits and add deviation for violating them will remain same.  DSM price vector will change daily based on ACP of DAM in IEX so ABT software at each station has to be modified accordingly. Preferably software should crawl ACP data from NLDC website and automatically create DSM price vector for the next day. AG