© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-1
Lecture slides to accompany
Engineering Economy
7th
edition
Leland Blank
Anthony Tarquin
Chapter 2Chapter 2
Factors: How TimeFactors: How Time
and Interest Affectand Interest Affect
MoneyMoney
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-2
LEARNING OUTCOMESLEARNING OUTCOMES
1. F/P and P/F Factors
2. P/A and A/P Factors
3. F/A and A/F Factors
4. Factor Values
5. Arithmetic Gradient
6. Geometric Gradient
7. Find i or n
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-3
Single Payment Factors (F/P and P/F)Single Payment Factors (F/P and P/F)
Single payment factors involve only P and F. Cash flow diagrams are as follows:
F = P(1 + i ) n P = F[1 / (1 + i ) n
]
Formulas are as follows:
Terms in parentheses or brackets are called factors. Values are in tables for i and n values
Factors are represented in standard factor notation such as (F/P,i,n),
where letter to left of slash is what is sought; letter to right represents what is given
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-4
F/P and P/F for SpreadsheetsF/P and P/F for Spreadsheets
Future value F is calculated using FV function:
= FV(i%,n,,P)
Present value P is calculated using PV function:
= PV(i%,n,,F)
Note the use of double commas in each function
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-5
Example: Finding Future ValueExample: Finding Future Value
A person deposits $5000 into an account which pays interest at a rate of 8%
per year. The amount in the account after 10 years is closest to:
(A) $2,792 (B) $9,000 (C) $10,795 (D) $12,165
The cash flow diagram is:
Solution:
F = P(F/P,i,n )
= 5000(F/P,8%,10 )
= $10,794.50
Answer is (C)
= 5000(2.1589)
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-6
Example: Finding Present ValueExample: Finding Present Value
A small company wants to make a single deposit now so it will have enough money to
purchase a backhoe costing $50,000 five years from now. If the account will earn
interest of 10% per year, the amount that must be deposited now is nearest to:
(A) $10,000 (B) $ 31,050 (C) $ 33,250 (D) $319,160
The cash flow diagram is: Solution:
P = F(P/F,i,n )
= 50,000(P/F,10%,5 )
= 50,000(0.6209)
= $31,045
Answer is (B)
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-7
Uniform Series Involving P/A and A/PUniform Series Involving P/A and A/P
The cash flow diagrams are:
Standard Factor NotationP = A(P/A,i,n) A = P(A/P,i,n)
Note: P is one period Ahead of first A value
(1) Cash flow occurs in consecutive interest periods
The uniform series factors that involve P and A are derived as follows:
(2) Cash flow amount is same in each interest period
Example: Uniform Series Involving P/AExample: Uniform Series Involving P/A
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-8
A chemical engineer believes that by modifying the structure of a certain water
treatment polymer, his company would earn an extra $5000 per year. At an interest
rate of 10% per year, how much could the company afford to spend now to just
break even over a 5 year project period?
(A) $11,170 (B) 13,640 (C) $15,300 (D) $18,950
The cash flow diagram is as follows:
P = 5000(P/A,10%,5)
= 5000(3.7908)
= $18,954
Answer is (D)
Solution:
Uniform Series Involving F/A and A/FUniform Series Involving F/A and A/F
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-9
(1) Cash flow occurs in consecutive interest periods
The uniform series factors that involve F and A are derived as follows:
(2) Last cash flow occurs in same period as F
Note: F takes place in the same period as last A
Cash flow diagrams are:
Standard Factor NotationF = A(F/A,i,n) A = F(A/F,i,n)
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-10
Example: Uniform Series Involving F/AExample: Uniform Series Involving F/A
An industrial engineer made a modification to a chip manufacturing
process that will save her company $10,000 per year. At an interest
rate of 8% per year, how much will the savings amount to in 7 years?
(A) $45,300 (B) $68,500 (C) $89,228 (D) $151,500
The cash flow diagram is:
A = $10,000
F = ?
i = 8%
0 1 2 3 4 5 6 7
Solution:
F = 10,000(F/A,8%,7)
= 10,000(8.9228)
= $89,228
Answer is (C)
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-11
Factor Values for Untabulated i or nFactor Values for Untabulated i or n
3 ways to find factor values for untabulated i or n values
Use formula
Use spreadsheet function with corresponding P, F, or A value set to 1
Linearly interpolate in interest tables
Formula or spreadsheet function is fast and accurate
Interpolation is only approximate
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-12
Example: Untabulated iExample: Untabulated i
Determine the value for (F/P, 8.3%,10)
Formula: F = (1 + 0.083)10
= 2.2197
Spreadsheet: = FV(8.3%,10,,1) = 2.2197
Interpolation: 8% ------ 2.1589
8.3% ------ x
9% ------ 2.3674
x = 2.1589 + [(8.3 - 8.0)/(9.0 - 8.0)][2.3674 – 2.1589]
= 2.2215
Absolute Error = 2.2215 – 2.2197 = 0.0018
OK
OK
(Too high)
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-13
Arithmetic GradientsArithmetic Gradients
Arithmetic gradients change by the same amount each period
The cash flow diagram for the PG
of an arithmetic gradient is: G starts betweenG starts between periods 1 and 2periods 1 and 2
(not between 0 and 1)(not between 0 and 1)
This is because cash flow in year 1 is
usually not equal to G and is handled
separately as a base amount
(shown on next slide)
Note that PNote that PGG isis locatedlocated TwoTwo PeriodsPeriods
AheadAhead of the first change that is equalof the first change that is equal
to Gto G
Standard factor notation is
PG = G(P/G,i,n)
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-14
Typical Arithmetic Gradient Cash FlowTypical Arithmetic Gradient Cash Flow
PT = ?
i = 10%
0 1 2 3 4 5
400
450
500
550
600
PA = ?
i = 10%
0 1 2 3 4 5
400 400 400 400 400
PG = ?
i = 10%
0 1 2 3 4 5
50
100
150
200
+
This diagram = this base amount plus this gradient
PA = 400(P/A,10%,5) PG = 50(P/G,10%,5)
PT = PA + PG = 400(P/A,10%,5) + 50(P/G,10%,5)
Amount
in year 1
is base
amount
Amount in year 1
is base amount
Converting Arithmetic Gradient to AConverting Arithmetic Gradient to A
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-15
i = 10%
0 1 2 3 4 5
G
2G
3G
4G
i = 10%
0 1 2 3 4 5
A = ?
Arithmetic gradient can be converted into equivalent A value using G(A/G,i,n)
General equation when base amount is involved is
A = base amount + G(A/G,i,n)
0 1 2 3 4 5
G
2G
3G
4G
For decreasing gradients,
change plus sign to minus
A = base amount - G(A/G,i,n)
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-16
Example: Arithmetic GradientExample: Arithmetic Gradient
= 400(3.6048) + 30(6.3970)
= $1,633.83
Answer is (B)
PT = 400(P/A,12%,5) + 30(P/G,12%,5)
The cash flow could also be converted
into an A value as follows:
A = 400 + 30(A/G,12%,5)
= 400 + 30(1.7746)
= $453.24
Solution:
Geometric GradientsGeometric Gradients
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-17
Geometric gradients change by the same percentage each period
0
1 2 3 n
A1
A 1(1+g)1
4
A 1(1+g)2
A 1(1+g)n-1
Pg = ?
There are no tables for geometric factors
Use following equation for g ≠ i:
Pg = A1{1- [(1+g)/(1+i)]n
}/(i-g)
where: A1 = cash flow in period 1
g = rate of increase
If g = i, Pg = A1n/(1+i)
Note: If g is negative, change signs in front of both g values
Cash flow diagram for present worth
of geometric gradient
Note: g starts between
periods 1 and 2
Example: Geometric GradientExample: Geometric Gradient
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-18
0
1 2 3 10
1000
1070
4
1145
1838
Pg = ? Solution:
Pg = 1000[1-(1+0.07/1+0.12)10
]/(0.12-0.07)
= $7,333
Answer is (b)
g = 7%
i = 12%
To find A, multiply Pg by (A/P,12%,10)
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-19
Unknown Interest Rate i
(Usually requires a trial and error solution or interpolation in interest tables)
Can use either the P/A or A/P factor. Using A/P:Solution:
60,000(A/P,i%,10) = 16,000
(A/P,i%,10) = 0.26667
From A/P column at n = 10 in the interest tables, i is between 22% and 24% Answer is (d)
Procedure: Set up equation with all symbols involved and solve for i
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-20
Unknown Recovery Period nUnknown Recovery Period n
Unknown recovery period problems involve solving for n,
given i and 2 other values (P, F, or A)
(Like interest rate problems, they usually require a trial & error solution or interpolation in interest tables)
Procedure: Set up equation with all symbols involved and solve for n
A contractor purchased equipment for $60,000 that provided income of $8,000
per year. At an interest rate of 10% per year, the length of time required to recover
the investment was closest to:
(a) 10 years (b) 12 years (c) 15 years (d) 18 years
Can use either the P/A or A/P factor. Using A/P:Solution:
60,000(A/P,10%,n) = 8,000
(A/P,10%,n) = 0.13333
From A/P column in i = 10% interest tables, n is between 14 and 15 years Answer is (c)
Summary of Important PointsSummary of Important Points
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
2-21
In P/A and A/P factors, P is one period ahead of first A
In F/A and A/F factors, F is in same period as last A
To find untabulated factor values, best way is to use formula or spreadsheet
For arithmetic gradients, gradient G starts between periods 1 and 2
Arithmetic gradients have 2 parts, base amount (year 1) and gradient amount
For geometric gradients, gradient g starts been periods 1 and 2
In geometric gradient formula, A1 is amount in period 1
To find unknown i or n, set up equation involving all terms and solve for i or n

More Related Content

PPT
Chapter 7 ror analysis for a single alternative
PPT
Chapter 8 ror analysis for multiple alternatives
PPT
Chapter 9 benefit & cost analysis
PPT
Chapter 3 combining factors
PPT
Chapter 12 independent projects & budget limitation
PPT
Chapter 5 present worth analysis
PPT
Chapter 1 foundations of engineering economy
PPT
Chapter 4 nominal & effective interest rates
Chapter 7 ror analysis for a single alternative
Chapter 8 ror analysis for multiple alternatives
Chapter 9 benefit & cost analysis
Chapter 3 combining factors
Chapter 12 independent projects & budget limitation
Chapter 5 present worth analysis
Chapter 1 foundations of engineering economy
Chapter 4 nominal & effective interest rates

What's hot (20)

PPT
Chapter 11 replacement & retention decisions
PPT
Chapter 6 annual worth analysis
PPT
Chapter 10 making choices & marr
PPT
Chapter 11 replacement & retention decisions
PPT
Chapter 5 present worth analysis
PPT
Chapter 14 effects of inflation
PPT
Chapter 4 nominal & effective interest rates
PPT
Chapter 6 annual worth analysis
PPT
Chapter 8 ror analysis for multiple alternatives
PPT
Chapter 15 cost estimation
PPT
Chapter 5 present worth analysis -with examples
PPT
Chapter 3 combining factors
PPT
Chapter 13 breakeven analysis
PPT
Chapter 2 factors, effect of time & interest on money
PPT
Chapter 13 breakeven analysis
PPT
Evaluating a Single Project
PDF
Lecture # 9 taxes and eva
PPT
Chapter 18 sensitivity analysis
PPT
Replacement analysis
PPT
Chapter-4 Time value of money
Chapter 11 replacement & retention decisions
Chapter 6 annual worth analysis
Chapter 10 making choices & marr
Chapter 11 replacement & retention decisions
Chapter 5 present worth analysis
Chapter 14 effects of inflation
Chapter 4 nominal & effective interest rates
Chapter 6 annual worth analysis
Chapter 8 ror analysis for multiple alternatives
Chapter 15 cost estimation
Chapter 5 present worth analysis -with examples
Chapter 3 combining factors
Chapter 13 breakeven analysis
Chapter 2 factors, effect of time & interest on money
Chapter 13 breakeven analysis
Evaluating a Single Project
Lecture # 9 taxes and eva
Chapter 18 sensitivity analysis
Replacement analysis
Chapter-4 Time value of money
Ad

Similar to Chapter 2 factors, effect of time & interest on money (20)

PDF
chapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdf
PPT
Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...
PPT
002- Factors_Effect_Time_Interest_Money.ppt
PDF
exam6.pdf
PPTX
Lo 2 b factors
PDF
Chapter 2 full slides to students
PPTX
Lecture 4 Engineering Economics a detail lecutrer.pptx
PPT
Arithmetic gradient.ppt
PPT
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
PDF
Lecture # 4 gradients factors and nominal and effective interest rates
PDF
Lecture # 4 gradients factors and nominal and effective interest rates
PPTX
Lecture 04 (1).pptxjbhvjhvjvhvvjhvjgcgcg
DOC
solucionario capitulo 1
PPT
Ch2 (part1)econ factors_rev2
PDF
Blank L, Tarquin A (2006) Solucionario Engineering Economy (6th ed).pdf
PDF
Chapter_3_Time_Value_of_Money.pdf
PDF
Solutions manual for engineering economy 8th edition by blank ibsn 0073523437
PDF
Engineering economy 8th edition blank solutions manual
PDF
Engineering Economy, 9th Edition (Leland T. Blank, Anthony Tarquin) (Z-Librar...
PDF
economy Ch4 part.1 _by louy Alhami
chapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdf
Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...
002- Factors_Effect_Time_Interest_Money.ppt
exam6.pdf
Lo 2 b factors
Chapter 2 full slides to students
Lecture 4 Engineering Economics a detail lecutrer.pptx
Arithmetic gradient.ppt
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture 04 (1).pptxjbhvjhvjvhvvjhvjgcgcg
solucionario capitulo 1
Ch2 (part1)econ factors_rev2
Blank L, Tarquin A (2006) Solucionario Engineering Economy (6th ed).pdf
Chapter_3_Time_Value_of_Money.pdf
Solutions manual for engineering economy 8th edition by blank ibsn 0073523437
Engineering economy 8th edition blank solutions manual
Engineering Economy, 9th Edition (Leland T. Blank, Anthony Tarquin) (Z-Librar...
economy Ch4 part.1 _by louy Alhami
Ad

More from Bich Lien Pham (20)

PDF
Lecture # 13 investment alternatives i
PDF
Lecture # 12 measures of profitability ii
PDF
Lecture # 11 measures of profitability i
PDF
Lecture # 10 eva and disposal of assets
PDF
Lecture # 8 depreciation ii
PDF
Lecture # 7 depreciation i
PDF
Lecture # 6 cost estimation ii
PDF
Lecture # 5 cost estimation i
PDF
Lecture # 3 compounding factors effects of inflation
PDF
Lecture # 2 time value of money
PDF
Lecture # 1 foundation
PPT
Chapter 19 decision-making under risk
PPT
Chapter 17 after-tax economic analysis
PPT
Chapter 16 depreciation methods
PPT
Chapter 15 cost estimation
PPT
Chapter 14 effects of inflation
PPT
Chapter 12 independent projects & budget limitation
PPT
Chapter 10 making choices & marr
PPT
Chapter 9 benefit & cost analysis
PPT
Chapter 7 ror analysis for a single alternative
Lecture # 13 investment alternatives i
Lecture # 12 measures of profitability ii
Lecture # 11 measures of profitability i
Lecture # 10 eva and disposal of assets
Lecture # 8 depreciation ii
Lecture # 7 depreciation i
Lecture # 6 cost estimation ii
Lecture # 5 cost estimation i
Lecture # 3 compounding factors effects of inflation
Lecture # 2 time value of money
Lecture # 1 foundation
Chapter 19 decision-making under risk
Chapter 17 after-tax economic analysis
Chapter 16 depreciation methods
Chapter 15 cost estimation
Chapter 14 effects of inflation
Chapter 12 independent projects & budget limitation
Chapter 10 making choices & marr
Chapter 9 benefit & cost analysis
Chapter 7 ror analysis for a single alternative

Chapter 2 factors, effect of time & interest on money

  • 1. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-1 Lecture slides to accompany Engineering Economy 7th edition Leland Blank Anthony Tarquin Chapter 2Chapter 2 Factors: How TimeFactors: How Time and Interest Affectand Interest Affect MoneyMoney
  • 2. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-2 LEARNING OUTCOMESLEARNING OUTCOMES 1. F/P and P/F Factors 2. P/A and A/P Factors 3. F/A and A/F Factors 4. Factor Values 5. Arithmetic Gradient 6. Geometric Gradient 7. Find i or n
  • 3. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-3 Single Payment Factors (F/P and P/F)Single Payment Factors (F/P and P/F) Single payment factors involve only P and F. Cash flow diagrams are as follows: F = P(1 + i ) n P = F[1 / (1 + i ) n ] Formulas are as follows: Terms in parentheses or brackets are called factors. Values are in tables for i and n values Factors are represented in standard factor notation such as (F/P,i,n), where letter to left of slash is what is sought; letter to right represents what is given
  • 4. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-4 F/P and P/F for SpreadsheetsF/P and P/F for Spreadsheets Future value F is calculated using FV function: = FV(i%,n,,P) Present value P is calculated using PV function: = PV(i%,n,,F) Note the use of double commas in each function
  • 5. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-5 Example: Finding Future ValueExample: Finding Future Value A person deposits $5000 into an account which pays interest at a rate of 8% per year. The amount in the account after 10 years is closest to: (A) $2,792 (B) $9,000 (C) $10,795 (D) $12,165 The cash flow diagram is: Solution: F = P(F/P,i,n ) = 5000(F/P,8%,10 ) = $10,794.50 Answer is (C) = 5000(2.1589)
  • 6. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-6 Example: Finding Present ValueExample: Finding Present Value A small company wants to make a single deposit now so it will have enough money to purchase a backhoe costing $50,000 five years from now. If the account will earn interest of 10% per year, the amount that must be deposited now is nearest to: (A) $10,000 (B) $ 31,050 (C) $ 33,250 (D) $319,160 The cash flow diagram is: Solution: P = F(P/F,i,n ) = 50,000(P/F,10%,5 ) = 50,000(0.6209) = $31,045 Answer is (B)
  • 7. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-7 Uniform Series Involving P/A and A/PUniform Series Involving P/A and A/P The cash flow diagrams are: Standard Factor NotationP = A(P/A,i,n) A = P(A/P,i,n) Note: P is one period Ahead of first A value (1) Cash flow occurs in consecutive interest periods The uniform series factors that involve P and A are derived as follows: (2) Cash flow amount is same in each interest period
  • 8. Example: Uniform Series Involving P/AExample: Uniform Series Involving P/A © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-8 A chemical engineer believes that by modifying the structure of a certain water treatment polymer, his company would earn an extra $5000 per year. At an interest rate of 10% per year, how much could the company afford to spend now to just break even over a 5 year project period? (A) $11,170 (B) 13,640 (C) $15,300 (D) $18,950 The cash flow diagram is as follows: P = 5000(P/A,10%,5) = 5000(3.7908) = $18,954 Answer is (D) Solution:
  • 9. Uniform Series Involving F/A and A/FUniform Series Involving F/A and A/F © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-9 (1) Cash flow occurs in consecutive interest periods The uniform series factors that involve F and A are derived as follows: (2) Last cash flow occurs in same period as F Note: F takes place in the same period as last A Cash flow diagrams are: Standard Factor NotationF = A(F/A,i,n) A = F(A/F,i,n)
  • 10. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-10 Example: Uniform Series Involving F/AExample: Uniform Series Involving F/A An industrial engineer made a modification to a chip manufacturing process that will save her company $10,000 per year. At an interest rate of 8% per year, how much will the savings amount to in 7 years? (A) $45,300 (B) $68,500 (C) $89,228 (D) $151,500 The cash flow diagram is: A = $10,000 F = ? i = 8% 0 1 2 3 4 5 6 7 Solution: F = 10,000(F/A,8%,7) = 10,000(8.9228) = $89,228 Answer is (C)
  • 11. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-11 Factor Values for Untabulated i or nFactor Values for Untabulated i or n 3 ways to find factor values for untabulated i or n values Use formula Use spreadsheet function with corresponding P, F, or A value set to 1 Linearly interpolate in interest tables Formula or spreadsheet function is fast and accurate Interpolation is only approximate
  • 12. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-12 Example: Untabulated iExample: Untabulated i Determine the value for (F/P, 8.3%,10) Formula: F = (1 + 0.083)10 = 2.2197 Spreadsheet: = FV(8.3%,10,,1) = 2.2197 Interpolation: 8% ------ 2.1589 8.3% ------ x 9% ------ 2.3674 x = 2.1589 + [(8.3 - 8.0)/(9.0 - 8.0)][2.3674 – 2.1589] = 2.2215 Absolute Error = 2.2215 – 2.2197 = 0.0018 OK OK (Too high)
  • 13. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-13 Arithmetic GradientsArithmetic Gradients Arithmetic gradients change by the same amount each period The cash flow diagram for the PG of an arithmetic gradient is: G starts betweenG starts between periods 1 and 2periods 1 and 2 (not between 0 and 1)(not between 0 and 1) This is because cash flow in year 1 is usually not equal to G and is handled separately as a base amount (shown on next slide) Note that PNote that PGG isis locatedlocated TwoTwo PeriodsPeriods AheadAhead of the first change that is equalof the first change that is equal to Gto G Standard factor notation is PG = G(P/G,i,n)
  • 14. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-14 Typical Arithmetic Gradient Cash FlowTypical Arithmetic Gradient Cash Flow PT = ? i = 10% 0 1 2 3 4 5 400 450 500 550 600 PA = ? i = 10% 0 1 2 3 4 5 400 400 400 400 400 PG = ? i = 10% 0 1 2 3 4 5 50 100 150 200 + This diagram = this base amount plus this gradient PA = 400(P/A,10%,5) PG = 50(P/G,10%,5) PT = PA + PG = 400(P/A,10%,5) + 50(P/G,10%,5) Amount in year 1 is base amount Amount in year 1 is base amount
  • 15. Converting Arithmetic Gradient to AConverting Arithmetic Gradient to A © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-15 i = 10% 0 1 2 3 4 5 G 2G 3G 4G i = 10% 0 1 2 3 4 5 A = ? Arithmetic gradient can be converted into equivalent A value using G(A/G,i,n) General equation when base amount is involved is A = base amount + G(A/G,i,n) 0 1 2 3 4 5 G 2G 3G 4G For decreasing gradients, change plus sign to minus A = base amount - G(A/G,i,n)
  • 16. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-16 Example: Arithmetic GradientExample: Arithmetic Gradient = 400(3.6048) + 30(6.3970) = $1,633.83 Answer is (B) PT = 400(P/A,12%,5) + 30(P/G,12%,5) The cash flow could also be converted into an A value as follows: A = 400 + 30(A/G,12%,5) = 400 + 30(1.7746) = $453.24 Solution:
  • 17. Geometric GradientsGeometric Gradients © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-17 Geometric gradients change by the same percentage each period 0 1 2 3 n A1 A 1(1+g)1 4 A 1(1+g)2 A 1(1+g)n-1 Pg = ? There are no tables for geometric factors Use following equation for g ≠ i: Pg = A1{1- [(1+g)/(1+i)]n }/(i-g) where: A1 = cash flow in period 1 g = rate of increase If g = i, Pg = A1n/(1+i) Note: If g is negative, change signs in front of both g values Cash flow diagram for present worth of geometric gradient Note: g starts between periods 1 and 2
  • 18. Example: Geometric GradientExample: Geometric Gradient © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-18 0 1 2 3 10 1000 1070 4 1145 1838 Pg = ? Solution: Pg = 1000[1-(1+0.07/1+0.12)10 ]/(0.12-0.07) = $7,333 Answer is (b) g = 7% i = 12% To find A, multiply Pg by (A/P,12%,10)
  • 19. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-19 Unknown Interest Rate i (Usually requires a trial and error solution or interpolation in interest tables) Can use either the P/A or A/P factor. Using A/P:Solution: 60,000(A/P,i%,10) = 16,000 (A/P,i%,10) = 0.26667 From A/P column at n = 10 in the interest tables, i is between 22% and 24% Answer is (d) Procedure: Set up equation with all symbols involved and solve for i
  • 20. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-20 Unknown Recovery Period nUnknown Recovery Period n Unknown recovery period problems involve solving for n, given i and 2 other values (P, F, or A) (Like interest rate problems, they usually require a trial & error solution or interpolation in interest tables) Procedure: Set up equation with all symbols involved and solve for n A contractor purchased equipment for $60,000 that provided income of $8,000 per year. At an interest rate of 10% per year, the length of time required to recover the investment was closest to: (a) 10 years (b) 12 years (c) 15 years (d) 18 years Can use either the P/A or A/P factor. Using A/P:Solution: 60,000(A/P,10%,n) = 8,000 (A/P,10%,n) = 0.13333 From A/P column in i = 10% interest tables, n is between 14 and 15 years Answer is (c)
  • 21. Summary of Important PointsSummary of Important Points © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 2-21 In P/A and A/P factors, P is one period ahead of first A In F/A and A/F factors, F is in same period as last A To find untabulated factor values, best way is to use formula or spreadsheet For arithmetic gradients, gradient G starts between periods 1 and 2 Arithmetic gradients have 2 parts, base amount (year 1) and gradient amount For geometric gradients, gradient g starts been periods 1 and 2 In geometric gradient formula, A1 is amount in period 1 To find unknown i or n, set up equation involving all terms and solve for i or n