        Continuous Alignment in Engineering & Construction
        Programs Utilizing a Program Management Approach

                                                     By Bob Prieto

Alignment of project participants, especially during the pre-project planning phase is a
recognized key to project success.1 Alignment activities within a project context are
focused on defining, understanding and meeting project objectives by the various
project participants.




                                                                    Source: Fluor

Within a program context the same raison d’etre exists but with even greater influence
on overall program success and with a broader scope of participants and alignment
vectors. This expanded context for alignment in programs utilizing a program
management approach is described.



© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 1
PM World Today – April 2011 (Vol. XIII, Issue IV)


At each stage, the basic alignment process is the same:

        Pre-alignment preparation
        Alignment meeting
        Document alignment
        Monitor alignment

This process is reflected in the following figure and one or more alignment processes
may be undertaken at each stage in order to address specific items in more depth.
Examples of alignment activities requiring separate sessions from the main alignment
activity include alignment processes focused on automation alignment; invoice process,
procedure and associated documentation; and industrial relations.



        Pre-alignment                    Alignment                       Document                     Monitor
         Preparation                      Meeting                        Alignment                   Alignment




                                                    Alignment Activities


Major programs face challenges of scale and complexity but fundamentally are about
the achievement of a set of well defined strategic business objectives. These strategic
business objectives or SBOs represent the most fundamental outcomes to be achieved
through the implementation of a major program. This outcomes focus versus outputs
focus represents a principle difference between programs and projects and by
extension the nature, timing and parties involved in alignment activities changes to
reflect this difference.

As we move through this paper we will see the more typical project level alignment
processes with their focus on project objectives (outputs). Programs, however, require
much earlier alignment activities to be undertaken around an organization’s Strategic
Business Objectives or SBOs to be achieved by undertaking a major program.

Strategic Business Objectives represent the fundamental business drivers in a well
executed program. But not all programs are well executed and as such understanding
how the selection and translation of strategic business objectives into program strategy
and execution affects program performance and outcomes is essential.

Equally essential is to assure top level alignment on a program’s strategic business
objectives. Lack of consensus often acts as a passive drag on many programs. A
review of large engineering and construction program experiencing scope, schedule

© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net               Page 2
PM World Today – April 2011 (Vol. XIII, Issue IV)


and cost growth suggests that both articulation of the businesses strategic business
objectives and broad stakeholder consensus were lacking. Simply put, strategy was
flawed and organizational alignment inadequate since there was not agreement on the
fundamental strategic business objectives to be achieved.

This needed alignment around Strategic Business Objectives must begin with not only
executive alignment but equally important peer alignment since this later group’s roles,
responsibilities or authorities may be modified under a program management approach.

Strategic Business Objectives for a private, for profit company can include:

•        Return on Capital Employed (ROCE)
•        Market share
•        Satisfy a market need by providing a service
•        Targeted growth rates

or a number of other quantifiable and measurable objectives. These strategic business
objectives may also include other top level objectives that define the business rationale
or approach such as:

•        Patents granted
•        New products launched
•        Net zero carbon or other triple bottom line (TBL) objectives

For public sector owners, strategic business objectives will include more social and
environmental objectives including:

•        Improved access to transportation
•        Reduced congestion
•        Improved access to clean water
•        New jobs created
•        New industries created

While the nature and form of the investment decision process will differ, each type of
owner will undertake a process that will define one or more programs to achieve these
overarching strategic business objectives while cascading elements of the SBOs down
as top level key result areas (KRAs) of individual projects.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 3
PM World Today – April 2011 (Vol. XIII, Issue IV)




Alignment in major programs around Strategic Business Objectives is not confined to
internal stakeholders even though these objectives represent organizational goals. Key
external stakeholders will need to be engaged to ensure that these top level SBOs are
achievable. Examples of key external stakeholders can include:

        Major investors including founding shareholders, large institutional investors,
         pension funds
        Bond holders
        Institutional lenders or others who will provide capital to achieve the program’s
         objectives
        Executive Branch leadership for governmental programs
        Legislature, in general, and appropriating committees, in particular, for
         government funded or subsidized projects
        Regulatory authorities for objectives requiring significant regulatory support.

Alignment with key external stakeholders is reflected in the next chart.


© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 4
PM World Today – April 2011 (Vol. XIII, Issue IV)




Programs utilizing a dedicated program manager must achieve alignment on more than
just Strategic Business Objectives. This is essential since major programs may drive the
adoption of new engineering, procurement, construction and risk management
approaches versus an organization’s traditional approaches. The timing and nature of
involvement of many or the owner’s team’s organizational elements is likely to be
modified and without proactive alignment, friction, differing expectations and delays may
result.

The nature of strategy alignment in a major program must include not only the Program
Manager but also all those elements of the owner’s organization that collectively
encompass the owner’s team. Alignment cannot be limited to the owner’s element with
direct responsibility for Program Manager oversight.

© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 5
PM World Today – April 2011 (Vol. XIII, Issue IV)


A key benefit of alignment activities undertaken around program strategy is the
continued fostering of alignment within the owner’s own team.




With alignment now in place for both the program’s Strategic Business Objectives as
well as its top level execution strategy, the Program Manager now turns his attention to
developing a detailed Program Execution Plan (PrEP) to implement the detailed
strategy. The PrEP will lay out detailed approaches for all program activities including
planning, studies, engineering, procurement, construction management, construction,
HSE, risk management, materials management, logistics, commissioning, startup,
testing, acceptance of work, quality, sustainability, treasury and accounting, invoicing,
payment, sustainability, stakeholder management, change control and reporting.


© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 6
PM World Today – April 2011 (Vol. XIII, Issue IV)


The PrEP will define interactions, roles, responsibilities and authorities between the
Program Manager and Owner’s Team at a much more granular level of detail. Workflow
and work processes will be described and these may differ from those previously used
by the Owner’s Team or even components of the Program Manager. Alignment
activities at this stage are focused on getting the program execution team on the same
sheet of paper.

An effective alignment session at this stage will result in:

        Reinforcement of Strategic Business Objectives, ensuring that they cascade
         down into the Program Execution Plan

        Clear linkage between the agreed to program strategy and the defined program
         execution approach

        Clear, unambiguous definition of roles and responsibilities of the owner and
         program management organizations. These will include the development of
         detailed RACI (Responsible, Accountable, Consulted, Informed) charts.

        Key result areas (KRAs) for project success, linked to top level KPI’s associated
         with the SBOs, that have been clearly defined, including associated metrics, and
         agreed to by alignment participants.

        Communication channels, protocols and authorities well defined and commonly
         understood by alignment participants

It is at this stage that alignment activities requiring separate sessions from the main
alignment activity including alignment focused on automation; invoicing; and industrial
relations will likely occur for the first time. These added alignment sessions will likely
cascade down to individual projects as the program gets underway.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 7
PM World Today – April 2011 (Vol. XIII, Issue IV)




With an agreed to Program Execution Plan in hand the Program Manager now begins
the process of initiating the various projects that will comprise the program. Project
selection and definition are key to overall program success and alignment around these
projects would have happened between the owner and program manager at both the
strategy alignment and PrEP alignment stages.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 8
PM World Today – April 2011 (Vol. XIII, Issue IV)


Project initiation activities are very much consistent with a project traditional alignment
approach with the Program Manager undertaking many of the activities the owner would
have performed in a discrete project setting.

Alignment between the Program Manager and Contractor will be explicitly around the
project outputs as distinguished from the program outcomes. Project scope, purpose,
KRAs, open issues, program or externally imposed constraints, work processes,
required approvals and value improving opportunities will all be discussed.

Separate alignment sessions may be held around automation technology and industrial
relations with the later important because of its potential program affecting nature.

Pre-alignment efforts will include extensive interviews, development of an explicit
description of outcomes desired, definition of a manageable attendee list comprised of
personnel responsible for project execution and a formal agenda.

The alignment of the Program Manager and a specific project contractor is reflected in
the next figure.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 9
PM World Today – April 2011 (Vol. XIII, Issue IV)




The Program Manager’s project level alignment efforts cannot stop at this project by
project alignment process more typical of a project delivery effort. Rather the Program
Manager must recognize that the multiplicity of projects that may be competing for the
same labor, sourcing to the same suppliers, or competing for the same construction
equipment must be aligned as well.


© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 10
PM World Today – April 2011 (Vol. XIII, Issue IV)


These multi-project alignment activities provide the program manager the ability to
identify potential issues and conflicts early. They will also provide a basis for identifying
critical controls essential for overall achievement of the program’s desired outcomes.

This alignment across projects can be seen below.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 11
PM World Today – April 2011 (Vol. XIII, Issue IV)




Returning now to a specific project context, the selected project level Contractor now
prepares a Project Execution Plan (PEP) that build off the initial project alignment
session and reflects the Contractor’s approach to work, consistent with project
requirements laid out in the various contract documents including any referenced
sections of the PrEP or other program management procedures incorporated.

In many instances the Contractor’s project activities will interface with a set of external
stakeholders which may include permitting or regulatory agencies; key suppliers and
vendors; community based groups; other Contractors under management by the
Program Manager; or the general public.

Alignment with these external stakeholders is key to project success and one or more
alignment activities may be undertaken around various aspects of the project.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 12
PM World Today – April 2011 (Vol. XIII, Issue IV)




Program and project level alignments are not singular activities. They are subject to
change as projects and the program evolve; as the various projects comprising the
program interact with each other; and as stakeholder involvement changes and new
program and project level issues emerge. Continuous alignment is a key task of the
Program Manager and is one of the differentiators between successful and
unsuccessful programs. While change may be inevitable, surprises that are otherwise
manageable need not be.



© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 13
PM World Today – April 2011 (Vol. XIII, Issue IV)


This ongoing alignment across projects comprising the program is illustrated below.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 14
PM World Today – April 2011 (Vol. XIII, Issue IV)


Major programs move through a series of phases. Many of these phases may be linked
to the owner’s tollgate process for program and project approval. As the program moves
from one phase to another it is important for the program manager to reconfirm the
Strategic Business Objectives and continuing validity of the overall program strategy.

As each phase will likely change the nature of interaction between owner, program
manager and project level contractors it is important to undertake alignment activities to
reconfirm or re-baseline, as needed, the roles, responsibilities and authorities of
individual participants. New RACI charts may be appropriate in subsequent phases,
KRAs or associated metrics may evolve, and stakeholders may change.

This continuous alignment effort falls squarely on the shoulders of the Program
Manager. At each stage he is assuring that the necessary pre-alignment activities have
been comprehensively undertaken; effective alignment meetings conducted; alignment
documented (project purpose; roles & responsibilities; KRAs including critical success
factors; and an action plan); and achievement of the KRAs and other action plan items
carefully monitored.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 15
PM World Today – April 2011 (Vol. XIII, Issue IV)




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 16
PM World Today – April 2011 (Vol. XIII, Issue IV)




Continuous alignment in engineering and construction programs utilizing a program
management approach is essential to meeting an organization’s and program’s
Strategic Business Objectives. While the alignment process will share many
characteristics of those traditionally employed on well executed engineering projects,
the nature and timing of the various alignment activities will be much more extensive.
This is driven not only by the added scale and complexity of such programs but the
importance of understanding the issues and interfaces that exist in the “white space”
between the various projects comprising the program.

References:

  1)     Alignment During Pre-Project Planning; Implementation Resource 113-3, Version
         2.1; Construction Industry Institute; December, 2009

  2)     Getting Off on the Right Foot; PM World Today; December 2010

  3)     Strategic Program Management; published by the Construction Management
         Association of America (CMAA); ISBN 978-0-9815612-1-9; July 24, 2008




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 17
PM World Today – April 2011 (Vol. XIII, Issue IV)




       About the Author:



                                    Bob Prieto

                                    Author




                             Bob Prieto is a Senior Vice President of Fluor Corporation,
                             one of America’s largest engineering, construction and
     project management firms, where he is responsible for strategy in support of the
     firm’s Industrial & Infrastructure Group and its key clients. He focuses on the
     development, delivery and oversight of large, complex projects worldwide. Prior
     to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. He served
     as a member of the executive committee of the National Center for Asia-Pacific
     Economic Cooperation, a member of the Industry Leaders’ Council of the
     American Society of Civil Engineers (ASCE), and co-founder of the Disaster
     Resource Network. He currently serves on a number of committees looking at
     issues related to infrastructure delivery and resiliency and disaster response and
     rebuilding. Until 2006 he served as one of three U.S. presidential appointees to
     the Asia Pacific Economic Cooperation (APEC) Business Advisory Council
     (ABAC) and previously served as chairman of the Engineering and Construction
     Governors of The World Economic Forum and co-chair of the infrastructure task
     force formed after September 11th by the New York City Chamber of
     Commerce. He recently completed a ten year tenure as a member of the board
     of trustees of Polytechnic University of New York culminating in its merger with
     New York University. Bob is the author of “Strategic Program Management”
     published by the Construction Management Association of America (CMAA) and
     more recently a companion work entitled “Topics in Strategic Program
     management”.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 18

More Related Content

PPTX
Niloofer darbary orchestrating change final-111710
PDF
Project Management 02
PDF
Role of Functional Organization in Large Engineering and Construction Programs
PDF
Chapter 9
PPT
PROJECT PLANNING AND MANAGEMENT
PPT
Plan Implementation
PDF
Project Management Office (Anna Maria Felici)
PPTX
Introduction to pmp
Niloofer darbary orchestrating change final-111710
Project Management 02
Role of Functional Organization in Large Engineering and Construction Programs
Chapter 9
PROJECT PLANNING AND MANAGEMENT
Plan Implementation
Project Management Office (Anna Maria Felici)
Introduction to pmp

What's hot (20)

PDF
New Media Management - Project plan
PDF
Value Proposition
PPT
MSP 2011 part 1
DOCX
Moskalyk, C (Resume) Branch Manager
DOC
Project Management
PDF
Kanamanapalli 2010 (2)
PPT
Prince2017 part 1
PDF
Project Management Summary 2012
PPT
Infrastructure Project Manager
PPTX
Program Management Deployment Concept Consulting
PDF
KHass Resume 2015 with CV
PPT
Planning And Project Management
PPTX
Show me the value: Enabling BCM Program Success through Lean thinking
DOCX
project management in it context
PPT
Logical Framework And Project Proposal
PDF
Project management fundamentals
PPTX
Report doc-soriano-project-and-planning-manangement.pptx- references
PDF
Project Management Plan
PDF
PMP preparation course
PDF
Introduction DM 211 Project Development and Management
New Media Management - Project plan
Value Proposition
MSP 2011 part 1
Moskalyk, C (Resume) Branch Manager
Project Management
Kanamanapalli 2010 (2)
Prince2017 part 1
Project Management Summary 2012
Infrastructure Project Manager
Program Management Deployment Concept Consulting
KHass Resume 2015 with CV
Planning And Project Management
Show me the value: Enabling BCM Program Success through Lean thinking
project management in it context
Logical Framework And Project Proposal
Project management fundamentals
Report doc-soriano-project-and-planning-manangement.pptx- references
Project Management Plan
PMP preparation course
Introduction DM 211 Project Development and Management
Ad

Similar to Continuous Alignment (20)

PDF
Pm600 1103 a-02-schwappach-loren-p4-t4
PDF
Strategic alignment of horizontal and vertical pmo goals final
PDF
DPPM7
PDF
Principles of program governance
PDF
Attitude Adjustment (contribution to PM Network Magazine, May 2015 Issue
PDF
Contribution to PMI article "Attitude Adjustment"
PDF
Pmn0515 program
PDF
Principles of program governance
PPSX
What's the colour of your project?
PPT
Exec ed pm3
DOCX
CHAPTER 2 Strategic Management and Project SelectionMore and m.docx
PDF
(eBook PDF) Program Management 2nd Edition
PDF
Portfolio Management Fit For Executives Project World 2011
PDF
Strategy implementation challenges in albanian organizations
PPSX
Portfolio Management
PDF
Business PMO & IT Pmo What Is The Difference
PPTX
Measuring Strategic Performance
PDF
White Paper ITBA Part I Palomino
PDF
(eBook PDF) Program Management 2nd Edition
PPTX
Integrated Reporting: On-the-Ground Perspectives
Pm600 1103 a-02-schwappach-loren-p4-t4
Strategic alignment of horizontal and vertical pmo goals final
DPPM7
Principles of program governance
Attitude Adjustment (contribution to PM Network Magazine, May 2015 Issue
Contribution to PMI article "Attitude Adjustment"
Pmn0515 program
Principles of program governance
What's the colour of your project?
Exec ed pm3
CHAPTER 2 Strategic Management and Project SelectionMore and m.docx
(eBook PDF) Program Management 2nd Edition
Portfolio Management Fit For Executives Project World 2011
Strategy implementation challenges in albanian organizations
Portfolio Management
Business PMO & IT Pmo What Is The Difference
Measuring Strategic Performance
White Paper ITBA Part I Palomino
(eBook PDF) Program Management 2nd Edition
Integrated Reporting: On-the-Ground Perspectives
Ad

More from Bob Prieto (20)

PDF
Application of system life cycle processes to large complex engineering and c...
PDF
Engineering and construction project startup
PDF
Deeper look at the physics of projects
PDF
Systems nature of large complex projects
PDF
Governance of mega and giga programs
PDF
Strengthen outcome based capital project delivery
PDF
Rethinking Interface Management
PDF
Rework in Engineering & Construction Projects
PDF
Reversing Global Warming
PDF
Improving infrastructure project success
PDF
Large complex project success
PDF
Impact of correlation on risks in programs and projects
PDF
Decision Making Under Uncertainty
DOCX
Post Dorian Engineering & Construction in the Bahamas
PDF
Debating project decisions in an ai enabled environment
PDF
Chapters 11 12 13
PDF
Chapter 10
PDF
Chapter 8
PDF
Theory of Management of Large Complex Projects - Chapter 7
PDF
Theory of Management of Large Complex Projects - Chapter 6
Application of system life cycle processes to large complex engineering and c...
Engineering and construction project startup
Deeper look at the physics of projects
Systems nature of large complex projects
Governance of mega and giga programs
Strengthen outcome based capital project delivery
Rethinking Interface Management
Rework in Engineering & Construction Projects
Reversing Global Warming
Improving infrastructure project success
Large complex project success
Impact of correlation on risks in programs and projects
Decision Making Under Uncertainty
Post Dorian Engineering & Construction in the Bahamas
Debating project decisions in an ai enabled environment
Chapters 11 12 13
Chapter 10
Chapter 8
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 6

Continuous Alignment

  • 1. PM World Today – April 2011 (Vol. XIII, Issue IV) PM WORLD TODAY – FEATURED PAPER – APRIL 2011 Continuous Alignment in Engineering & Construction Programs Utilizing a Program Management Approach By Bob Prieto Alignment of project participants, especially during the pre-project planning phase is a recognized key to project success.1 Alignment activities within a project context are focused on defining, understanding and meeting project objectives by the various project participants. Source: Fluor Within a program context the same raison d’etre exists but with even greater influence on overall program success and with a broader scope of participants and alignment vectors. This expanded context for alignment in programs utilizing a program management approach is described. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 1
  • 2. PM World Today – April 2011 (Vol. XIII, Issue IV) At each stage, the basic alignment process is the same:  Pre-alignment preparation  Alignment meeting  Document alignment  Monitor alignment This process is reflected in the following figure and one or more alignment processes may be undertaken at each stage in order to address specific items in more depth. Examples of alignment activities requiring separate sessions from the main alignment activity include alignment processes focused on automation alignment; invoice process, procedure and associated documentation; and industrial relations. Pre-alignment Alignment Document Monitor Preparation Meeting Alignment Alignment Alignment Activities Major programs face challenges of scale and complexity but fundamentally are about the achievement of a set of well defined strategic business objectives. These strategic business objectives or SBOs represent the most fundamental outcomes to be achieved through the implementation of a major program. This outcomes focus versus outputs focus represents a principle difference between programs and projects and by extension the nature, timing and parties involved in alignment activities changes to reflect this difference. As we move through this paper we will see the more typical project level alignment processes with their focus on project objectives (outputs). Programs, however, require much earlier alignment activities to be undertaken around an organization’s Strategic Business Objectives or SBOs to be achieved by undertaking a major program. Strategic Business Objectives represent the fundamental business drivers in a well executed program. But not all programs are well executed and as such understanding how the selection and translation of strategic business objectives into program strategy and execution affects program performance and outcomes is essential. Equally essential is to assure top level alignment on a program’s strategic business objectives. Lack of consensus often acts as a passive drag on many programs. A review of large engineering and construction program experiencing scope, schedule © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 2
  • 3. PM World Today – April 2011 (Vol. XIII, Issue IV) and cost growth suggests that both articulation of the businesses strategic business objectives and broad stakeholder consensus were lacking. Simply put, strategy was flawed and organizational alignment inadequate since there was not agreement on the fundamental strategic business objectives to be achieved. This needed alignment around Strategic Business Objectives must begin with not only executive alignment but equally important peer alignment since this later group’s roles, responsibilities or authorities may be modified under a program management approach. Strategic Business Objectives for a private, for profit company can include: • Return on Capital Employed (ROCE) • Market share • Satisfy a market need by providing a service • Targeted growth rates or a number of other quantifiable and measurable objectives. These strategic business objectives may also include other top level objectives that define the business rationale or approach such as: • Patents granted • New products launched • Net zero carbon or other triple bottom line (TBL) objectives For public sector owners, strategic business objectives will include more social and environmental objectives including: • Improved access to transportation • Reduced congestion • Improved access to clean water • New jobs created • New industries created While the nature and form of the investment decision process will differ, each type of owner will undertake a process that will define one or more programs to achieve these overarching strategic business objectives while cascading elements of the SBOs down as top level key result areas (KRAs) of individual projects. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 3
  • 4. PM World Today – April 2011 (Vol. XIII, Issue IV) Alignment in major programs around Strategic Business Objectives is not confined to internal stakeholders even though these objectives represent organizational goals. Key external stakeholders will need to be engaged to ensure that these top level SBOs are achievable. Examples of key external stakeholders can include:  Major investors including founding shareholders, large institutional investors, pension funds  Bond holders  Institutional lenders or others who will provide capital to achieve the program’s objectives  Executive Branch leadership for governmental programs  Legislature, in general, and appropriating committees, in particular, for government funded or subsidized projects  Regulatory authorities for objectives requiring significant regulatory support. Alignment with key external stakeholders is reflected in the next chart. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 4
  • 5. PM World Today – April 2011 (Vol. XIII, Issue IV) Programs utilizing a dedicated program manager must achieve alignment on more than just Strategic Business Objectives. This is essential since major programs may drive the adoption of new engineering, procurement, construction and risk management approaches versus an organization’s traditional approaches. The timing and nature of involvement of many or the owner’s team’s organizational elements is likely to be modified and without proactive alignment, friction, differing expectations and delays may result. The nature of strategy alignment in a major program must include not only the Program Manager but also all those elements of the owner’s organization that collectively encompass the owner’s team. Alignment cannot be limited to the owner’s element with direct responsibility for Program Manager oversight. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 5
  • 6. PM World Today – April 2011 (Vol. XIII, Issue IV) A key benefit of alignment activities undertaken around program strategy is the continued fostering of alignment within the owner’s own team. With alignment now in place for both the program’s Strategic Business Objectives as well as its top level execution strategy, the Program Manager now turns his attention to developing a detailed Program Execution Plan (PrEP) to implement the detailed strategy. The PrEP will lay out detailed approaches for all program activities including planning, studies, engineering, procurement, construction management, construction, HSE, risk management, materials management, logistics, commissioning, startup, testing, acceptance of work, quality, sustainability, treasury and accounting, invoicing, payment, sustainability, stakeholder management, change control and reporting. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 6
  • 7. PM World Today – April 2011 (Vol. XIII, Issue IV) The PrEP will define interactions, roles, responsibilities and authorities between the Program Manager and Owner’s Team at a much more granular level of detail. Workflow and work processes will be described and these may differ from those previously used by the Owner’s Team or even components of the Program Manager. Alignment activities at this stage are focused on getting the program execution team on the same sheet of paper. An effective alignment session at this stage will result in:  Reinforcement of Strategic Business Objectives, ensuring that they cascade down into the Program Execution Plan  Clear linkage between the agreed to program strategy and the defined program execution approach  Clear, unambiguous definition of roles and responsibilities of the owner and program management organizations. These will include the development of detailed RACI (Responsible, Accountable, Consulted, Informed) charts.  Key result areas (KRAs) for project success, linked to top level KPI’s associated with the SBOs, that have been clearly defined, including associated metrics, and agreed to by alignment participants.  Communication channels, protocols and authorities well defined and commonly understood by alignment participants It is at this stage that alignment activities requiring separate sessions from the main alignment activity including alignment focused on automation; invoicing; and industrial relations will likely occur for the first time. These added alignment sessions will likely cascade down to individual projects as the program gets underway. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 7
  • 8. PM World Today – April 2011 (Vol. XIII, Issue IV) With an agreed to Program Execution Plan in hand the Program Manager now begins the process of initiating the various projects that will comprise the program. Project selection and definition are key to overall program success and alignment around these projects would have happened between the owner and program manager at both the strategy alignment and PrEP alignment stages. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 8
  • 9. PM World Today – April 2011 (Vol. XIII, Issue IV) Project initiation activities are very much consistent with a project traditional alignment approach with the Program Manager undertaking many of the activities the owner would have performed in a discrete project setting. Alignment between the Program Manager and Contractor will be explicitly around the project outputs as distinguished from the program outcomes. Project scope, purpose, KRAs, open issues, program or externally imposed constraints, work processes, required approvals and value improving opportunities will all be discussed. Separate alignment sessions may be held around automation technology and industrial relations with the later important because of its potential program affecting nature. Pre-alignment efforts will include extensive interviews, development of an explicit description of outcomes desired, definition of a manageable attendee list comprised of personnel responsible for project execution and a formal agenda. The alignment of the Program Manager and a specific project contractor is reflected in the next figure. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 9
  • 10. PM World Today – April 2011 (Vol. XIII, Issue IV) The Program Manager’s project level alignment efforts cannot stop at this project by project alignment process more typical of a project delivery effort. Rather the Program Manager must recognize that the multiplicity of projects that may be competing for the same labor, sourcing to the same suppliers, or competing for the same construction equipment must be aligned as well. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 10
  • 11. PM World Today – April 2011 (Vol. XIII, Issue IV) These multi-project alignment activities provide the program manager the ability to identify potential issues and conflicts early. They will also provide a basis for identifying critical controls essential for overall achievement of the program’s desired outcomes. This alignment across projects can be seen below. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 11
  • 12. PM World Today – April 2011 (Vol. XIII, Issue IV) Returning now to a specific project context, the selected project level Contractor now prepares a Project Execution Plan (PEP) that build off the initial project alignment session and reflects the Contractor’s approach to work, consistent with project requirements laid out in the various contract documents including any referenced sections of the PrEP or other program management procedures incorporated. In many instances the Contractor’s project activities will interface with a set of external stakeholders which may include permitting or regulatory agencies; key suppliers and vendors; community based groups; other Contractors under management by the Program Manager; or the general public. Alignment with these external stakeholders is key to project success and one or more alignment activities may be undertaken around various aspects of the project. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 12
  • 13. PM World Today – April 2011 (Vol. XIII, Issue IV) Program and project level alignments are not singular activities. They are subject to change as projects and the program evolve; as the various projects comprising the program interact with each other; and as stakeholder involvement changes and new program and project level issues emerge. Continuous alignment is a key task of the Program Manager and is one of the differentiators between successful and unsuccessful programs. While change may be inevitable, surprises that are otherwise manageable need not be. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 13
  • 14. PM World Today – April 2011 (Vol. XIII, Issue IV) This ongoing alignment across projects comprising the program is illustrated below. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 14
  • 15. PM World Today – April 2011 (Vol. XIII, Issue IV) Major programs move through a series of phases. Many of these phases may be linked to the owner’s tollgate process for program and project approval. As the program moves from one phase to another it is important for the program manager to reconfirm the Strategic Business Objectives and continuing validity of the overall program strategy. As each phase will likely change the nature of interaction between owner, program manager and project level contractors it is important to undertake alignment activities to reconfirm or re-baseline, as needed, the roles, responsibilities and authorities of individual participants. New RACI charts may be appropriate in subsequent phases, KRAs or associated metrics may evolve, and stakeholders may change. This continuous alignment effort falls squarely on the shoulders of the Program Manager. At each stage he is assuring that the necessary pre-alignment activities have been comprehensively undertaken; effective alignment meetings conducted; alignment documented (project purpose; roles & responsibilities; KRAs including critical success factors; and an action plan); and achievement of the KRAs and other action plan items carefully monitored. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 15
  • 16. PM World Today – April 2011 (Vol. XIII, Issue IV) © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 16
  • 17. PM World Today – April 2011 (Vol. XIII, Issue IV) Continuous alignment in engineering and construction programs utilizing a program management approach is essential to meeting an organization’s and program’s Strategic Business Objectives. While the alignment process will share many characteristics of those traditionally employed on well executed engineering projects, the nature and timing of the various alignment activities will be much more extensive. This is driven not only by the added scale and complexity of such programs but the importance of understanding the issues and interfaces that exist in the “white space” between the various projects comprising the program. References: 1) Alignment During Pre-Project Planning; Implementation Resource 113-3, Version 2.1; Construction Industry Institute; December, 2009 2) Getting Off on the Right Foot; PM World Today; December 2010 3) Strategic Program Management; published by the Construction Management Association of America (CMAA); ISBN 978-0-9815612-1-9; July 24, 2008 © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 17
  • 18. PM World Today – April 2011 (Vol. XIII, Issue IV) About the Author: Bob Prieto Author Bob Prieto is a Senior Vice President of Fluor Corporation, one of America’s largest engineering, construction and project management firms, where he is responsible for strategy in support of the firm’s Industrial & Infrastructure Group and its key clients. He focuses on the development, delivery and oversight of large, complex projects worldwide. Prior to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. He served as a member of the executive committee of the National Center for Asia-Pacific Economic Cooperation, a member of the Industry Leaders’ Council of the American Society of Civil Engineers (ASCE), and co-founder of the Disaster Resource Network. He currently serves on a number of committees looking at issues related to infrastructure delivery and resiliency and disaster response and rebuilding. Until 2006 he served as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC) and previously served as chairman of the Engineering and Construction Governors of The World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. He recently completed a ten year tenure as a member of the board of trustees of Polytechnic University of New York culminating in its merger with New York University. Bob is the author of “Strategic Program Management” published by the Construction Management Association of America (CMAA) and more recently a companion work entitled “Topics in Strategic Program management”. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 18