SlideShare a Scribd company logo
7
Most read
11
Most read
13
Most read
Contract Costing
PRESENTATION TOPIC:
“CONTRACT COSTING”
Contract Costing
Definition:
ICMA defines, "Contract costing is that form of specific order
costing which applies where work is undertaken to customer's
special requirements and each order is of long-term duration.“
Contract costing is applicable in:
 Building construction
 Road construction
 Bridge construction
 Ship building, etc.
 Features of Contract Costing:
1. Contracts are generally of large size and, therefore, a contractor usually
carries out a small number of contracts at a particular point of time.
2. A contract generally takes more than one year to complete,
3. Work on contracts is carried out at the site of contracts and not in
factory premises.
4. Each contract undertaken is treated as a cost unit.
5. A separate contract account is prepared for each contract.
6. Nearly all labor cost will be direct.
7. Most expenses (e.g. electricity, telephone, insurance, etc.) are also direct.
Basis of differences Job Order Costing Contract Costing
1. Size The work performed under job order costing
is comparatively small in size.
The work performed under contract costing is
larger in size than that the jobs order.
2. Place of work In job order costing, the manufacturing of
product is carried out inside the factory
premises.
But, the production or construction work is
carried out at site in contract costing.
3. Time It takes comparatively lesser time to
complete the work.
It takes a longer time to complete a contract,
even more than an accounting period.
4. Payment of price The price under job order is paid after the
completion of job.
The price under a contract, is gradually paid in
different installment before the completion of
the work.
5. Investment Preliminary investment in assets is low. Preliminary investment in assets is
comparatively high.
6. Nature of expenses The expenses are both direct and indirect in
nature.
Generally, the expenses are direct in nature.
 Differences between job order and contract costing
 Contract Costing Procedure:
1. Contract Account: Each contract is allotted a distinct number and a
separate account is opened for each contract.
2. Direct costs: Most of the costs of a contract are direct cost and are
debited to the contract account. Such direct costs are- 1. Materials, 2.
Labour and supervision, 3. Direct expenses, 4. Depreciation of plant and
machinery, 5. Subcontract costs, etc.
3. Indirect costs: Contract account is also debited with overheads which
tend to be small in relation to direct costs.
4. Transfers of materials or plant: When materials, plant or other
items are transferred from the contract, the contract account is
credited by the amount.
5. Contract price: The contract account is also credited with the
contract price.
6. Profit or loss on contract: The balance of contract account
represents profit or loss which is transferred to Profit and Loss
Account. However, when contract is not completed within the
financial year, only a part of the profit is taken into account and the
remaining profit is kept as reserve to meet any contingent loss on the
incomplete portion of the contract.
Types of contracts:
There are three types of contract which are mentioned below:
1. Fixed price contract: The contract that is executed with the fixed price
which is agreed by the contractor and the contractee is called the fixed price
contract.
2. Fixed price contract with escalation and de-escalation clauses: Escalation
clause is often provided in contracts to cover any likely changes in the price or
utilization of materials and labour.
An escalation clause safeguards the interest of the contractor by upward
revision of the contract price, a de-escalation clause may be interested to look
after the interest of the contractee by providing downward revision of the
contract price.
3. Cost-Plus Contracts: The contract in which the contract price is
determined by adding a certain percentage of profit on cost is known
as cost plus contract.
The cost plus contract is adopted to overcome with problem of
fixing the contract price caused due to nature of contract, duration of
completion of contract, uncertainty of material, change in the price
level, new technology etc. This type of contract is mostly followed by
the government for production of special articles not usually
manufactured, urgent repairs of vehicles, roads, bridges etc.
PROFIT ON INCOMPLETE CONTRACTS
There are two aspects of profit computation. They are-
1. Computation of notional profit or estimated profit.
2. Computation of the portion of such profit to be transferred to Profit & Loss
Account.
 Notional Profit:
Difference between the value of WIP certified and the value of WIP not
certified. It is computed as follows-
Value of work certified 10,00,000
Add: Cost of work not yet certified 2,00,000
12,00,000
Less: Cost of work to date 9,00,000
Notional Profit 3,00,000
 Estimated Profit:
Excess of the contract price over the estimated total cost of the
contract. It is computed as follows-
Contract Price 15,00,000
Less: Total cost already incurred 11,00,000
4,00,000
Less: Estimated additional cost required to 1,00,000
complete the contract
Estimated Profit 3,00,000
Portion of Notional Profit or Estimated Profit to be transferred to
Profit & Loss Account
There are some generally followed rules. They are -
(a) When work certified is less than 25% complete
No profit or Loss be accounted for
(b) When work certified is 25 % or more but less than 50%
Notional Profit Cash received
Work Certified
1
3
(c) When work certified is the 50% or more but less than 90%
Notional Profit 2
3
Cash received
Work Certified
(d) When the contractor estimates the profit:
Work Certified
Contract Price
Estimated Profit
THANK YOU

More Related Content

PPTX
Contract costing
PPTX
Contract costing
PPTX
Contract Costing.pptx
PPTX
Cost Accounting - Labour costing
PPTX
Labour cost accounting
PPTX
Chapter 04 Labour Costs
PPTX
Methods and techniques of Costing
PPTX
labour cost control
Contract costing
Contract costing
Contract Costing.pptx
Cost Accounting - Labour costing
Labour cost accounting
Chapter 04 Labour Costs
Methods and techniques of Costing
labour cost control

What's hot (20)

PPTX
Process costing
PPTX
Reconciliation of cost and financial accounts
PPT
Price level Accounting
PPTX
Activity-Based Costing System
PPTX
Inflation accounting
PPT
Standard costing presentation
PPTX
Method of costing
PPTX
Overheads
PPTX
Chapter 05 Overhead Costs
PPTX
Accounts : Marginal Costing
PPTX
Job costing
PPTX
APPLICATION OF MARGINAL COSTING
PPTX
Marginal costing and break even analysis
PPTX
Chapter 03 Material Costing
PPT
Cost sheet
PDF
5.capital and revenue
PPTX
Capitalisation
PPTX
Company Final accounts
PPTX
Cost accounting
Process costing
Reconciliation of cost and financial accounts
Price level Accounting
Activity-Based Costing System
Inflation accounting
Standard costing presentation
Method of costing
Overheads
Chapter 05 Overhead Costs
Accounts : Marginal Costing
Job costing
APPLICATION OF MARGINAL COSTING
Marginal costing and break even analysis
Chapter 03 Material Costing
Cost sheet
5.capital and revenue
Capitalisation
Company Final accounts
Cost accounting
Ad

Similar to Contract Costing (20)

PPTX
Contract costing, BCOM (HONS)
PPTX
Bba ii cost and management accounting u 3.3 contract costing
PPTX
Job,batch and contract costing
PPTX
Contract account
DOCX
Contract Costing NOtes.docx
PPTX
Contract and Job costing
PPTX
UNIT - II.pptx CONTRACT COSTING UNIT-1 PPT
PPTX
Construction contract
PPTX
6.1.1.-REVENUE-RECOGNITION-CONSTRUCTION-CONTRACTS.pptx
PPTX
Chapter 06 Costing Methods
PPTX
PPTX
IAS 11 Construction Contracts
PPTX
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
DOCX
IAS 11
PPTX
Contract costing
PDF
AS-7 Construction Contracts and AS-18 Related Party Transactions
PDF
Construction contracts
PPTX
CA Unit 4.pptx for getting knowledge and information
PPTX
ICDS - IIIConstruction contract
PPT
Contract costing
Contract costing, BCOM (HONS)
Bba ii cost and management accounting u 3.3 contract costing
Job,batch and contract costing
Contract account
Contract Costing NOtes.docx
Contract and Job costing
UNIT - II.pptx CONTRACT COSTING UNIT-1 PPT
Construction contract
6.1.1.-REVENUE-RECOGNITION-CONSTRUCTION-CONTRACTS.pptx
Chapter 06 Costing Methods
IAS 11 Construction Contracts
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
IAS 11
Contract costing
AS-7 Construction Contracts and AS-18 Related Party Transactions
Construction contracts
CA Unit 4.pptx for getting knowledge and information
ICDS - IIIConstruction contract
Contract costing
Ad

Recently uploaded (20)

PPTX
Cell Structure & Organelles in detailed.
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PDF
Origin of periodic table-Mendeleev’s Periodic-Modern Periodic table
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Classroom Observation Tools for Teachers
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PDF
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
PDF
Basic Mud Logging Guide for educational purpose
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PDF
Complications of Minimal Access Surgery at WLH
PPTX
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
PDF
TR - Agricultural Crops Production NC III.pdf
PDF
Microbial disease of the cardiovascular and lymphatic systems
PPTX
Cell Types and Its function , kingdom of life
PDF
Pre independence Education in Inndia.pdf
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Cell Structure & Organelles in detailed.
2.FourierTransform-ShortQuestionswithAnswers.pdf
Origin of periodic table-Mendeleev’s Periodic-Modern Periodic table
Microbial diseases, their pathogenesis and prophylaxis
Final Presentation General Medicine 03-08-2024.pptx
Classroom Observation Tools for Teachers
Abdominal Access Techniques with Prof. Dr. R K Mishra
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
Basic Mud Logging Guide for educational purpose
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Complications of Minimal Access Surgery at WLH
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
TR - Agricultural Crops Production NC III.pdf
Microbial disease of the cardiovascular and lymphatic systems
Cell Types and Its function , kingdom of life
Pre independence Education in Inndia.pdf
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student

Contract Costing

  • 4. Definition: ICMA defines, "Contract costing is that form of specific order costing which applies where work is undertaken to customer's special requirements and each order is of long-term duration.“ Contract costing is applicable in:  Building construction  Road construction  Bridge construction  Ship building, etc.
  • 5.  Features of Contract Costing: 1. Contracts are generally of large size and, therefore, a contractor usually carries out a small number of contracts at a particular point of time. 2. A contract generally takes more than one year to complete, 3. Work on contracts is carried out at the site of contracts and not in factory premises. 4. Each contract undertaken is treated as a cost unit. 5. A separate contract account is prepared for each contract. 6. Nearly all labor cost will be direct. 7. Most expenses (e.g. electricity, telephone, insurance, etc.) are also direct.
  • 6. Basis of differences Job Order Costing Contract Costing 1. Size The work performed under job order costing is comparatively small in size. The work performed under contract costing is larger in size than that the jobs order. 2. Place of work In job order costing, the manufacturing of product is carried out inside the factory premises. But, the production or construction work is carried out at site in contract costing. 3. Time It takes comparatively lesser time to complete the work. It takes a longer time to complete a contract, even more than an accounting period. 4. Payment of price The price under job order is paid after the completion of job. The price under a contract, is gradually paid in different installment before the completion of the work. 5. Investment Preliminary investment in assets is low. Preliminary investment in assets is comparatively high. 6. Nature of expenses The expenses are both direct and indirect in nature. Generally, the expenses are direct in nature.  Differences between job order and contract costing
  • 7.  Contract Costing Procedure: 1. Contract Account: Each contract is allotted a distinct number and a separate account is opened for each contract. 2. Direct costs: Most of the costs of a contract are direct cost and are debited to the contract account. Such direct costs are- 1. Materials, 2. Labour and supervision, 3. Direct expenses, 4. Depreciation of plant and machinery, 5. Subcontract costs, etc. 3. Indirect costs: Contract account is also debited with overheads which tend to be small in relation to direct costs.
  • 8. 4. Transfers of materials or plant: When materials, plant or other items are transferred from the contract, the contract account is credited by the amount. 5. Contract price: The contract account is also credited with the contract price. 6. Profit or loss on contract: The balance of contract account represents profit or loss which is transferred to Profit and Loss Account. However, when contract is not completed within the financial year, only a part of the profit is taken into account and the remaining profit is kept as reserve to meet any contingent loss on the incomplete portion of the contract.
  • 9. Types of contracts: There are three types of contract which are mentioned below: 1. Fixed price contract: The contract that is executed with the fixed price which is agreed by the contractor and the contractee is called the fixed price contract. 2. Fixed price contract with escalation and de-escalation clauses: Escalation clause is often provided in contracts to cover any likely changes in the price or utilization of materials and labour. An escalation clause safeguards the interest of the contractor by upward revision of the contract price, a de-escalation clause may be interested to look after the interest of the contractee by providing downward revision of the contract price.
  • 10. 3. Cost-Plus Contracts: The contract in which the contract price is determined by adding a certain percentage of profit on cost is known as cost plus contract. The cost plus contract is adopted to overcome with problem of fixing the contract price caused due to nature of contract, duration of completion of contract, uncertainty of material, change in the price level, new technology etc. This type of contract is mostly followed by the government for production of special articles not usually manufactured, urgent repairs of vehicles, roads, bridges etc.
  • 11. PROFIT ON INCOMPLETE CONTRACTS There are two aspects of profit computation. They are- 1. Computation of notional profit or estimated profit. 2. Computation of the portion of such profit to be transferred to Profit & Loss Account.  Notional Profit: Difference between the value of WIP certified and the value of WIP not certified. It is computed as follows- Value of work certified 10,00,000 Add: Cost of work not yet certified 2,00,000 12,00,000 Less: Cost of work to date 9,00,000 Notional Profit 3,00,000
  • 12.  Estimated Profit: Excess of the contract price over the estimated total cost of the contract. It is computed as follows- Contract Price 15,00,000 Less: Total cost already incurred 11,00,000 4,00,000 Less: Estimated additional cost required to 1,00,000 complete the contract Estimated Profit 3,00,000
  • 13. Portion of Notional Profit or Estimated Profit to be transferred to Profit & Loss Account There are some generally followed rules. They are - (a) When work certified is less than 25% complete No profit or Loss be accounted for (b) When work certified is 25 % or more but less than 50% Notional Profit Cash received Work Certified 1 3
  • 14. (c) When work certified is the 50% or more but less than 90% Notional Profit 2 3 Cash received Work Certified (d) When the contractor estimates the profit: Work Certified Contract Price Estimated Profit