Critical Path Analysis and PERT
             Charts




                               An overview of the article by
                                         Simu Mihai Stelian
                                                  An IV, CTI
       Full version http://www.mindtools.com/critpath.html
Critical Path Analysis and PERT are powerful tools that
help you to schedule and manage complex projects.
They were developed in the 1950s to control large
defense projects, and have been used routinely since
then.




These tools help monitor and improve scheduling for
complex interdependent activities such as commonly
involved in developing software. During management of
a project, they allow you to monitor achievement of
project goals. They help you to see where remedial
action needs to be taken to get a project back on course.
The benefit of using CPA within the planning process is
to help you develop and test your plan to ensure that it is
robust. Critical Path Analysis formally identifies tasks
which must be completed on time for the whole project to
be completed on time. It also identifies which tasks can be
delayed if resource needs to be reallocated to catch up on
missed or overrunning tasks.

       The disadvantage of CPA, if you use it as the
technique by which your project plans are
communicated and managed against, is that the
relation of tasks to time is not as immediately obvious
as with Gantt Charts. This can make them more difficult
to understand.
How to use the tool :
       As with Gantt Charts, the essential concept behind
Critical Path Analysis is that you cannot start some
activities until others are finished. These activities need
to be completed in a sequence, with each stage being
more-or-less completed before the next stage can begin.
These are 'sequential' activities.
       Other activities are not dependent on completion
of any other tasks. You can do these at any time before
or after a particular stage is reached. These are non-
dependent or 'parallel' tasks.
Step 1 : List all activities in the plan
Step 2 :Plot the activities as a circle and arrow
diagram
   In these, circles show events within the project, such as
the start and finish of tasks. The number shown in the left
hand half of the circle allows you to identify each one
easily. Circles are sometimes known as nodes.

   An arrow running between two event circles shows the
activity needed to complete that task. A description of the
task is written underneath the arrow. The length of the
task is shown above it. By convention, all arrows run left
to right. Arrows are also sometimes called arcs.
Here the activities of 'Select Hardware' and 'Core
Module Analysis' cannot be started until 'High Level
Analysis' has been completed.
Full Critical Path Diagram :
Each event circle also has a figure in the bottom,
right hand quadrant. This shows the latest finish time
that's permissible for the preceding activity if the
project is to be completed in the minimum time
possible. You can calculate this by starting at the last
event and working backwards. The latest finish time of
the preceding event and the earliest start time of the
following even will be the same for circles on the
critical path.
        The activities on the Critical Path must be very
closely managed to ensure that activities are
completed on time. If jobs on the critical path slip,
immediate action should be taken to get the project
back on schedule. Otherwise completion of the whole
project will slip.
Crash Action :
       You may find that you need to complete a project
earlier than your Critical Path Analysis says is possible. In
this case you need to re-plan your project.

        You have a number of options and would need to
assess the impact of each on the project’s cost, quality
and time required to complete it. For example, you could
increase resource available for each project activity to
bring down time spent on each but the impact of some
of this would be insignificant and a more efficient way of
doing this would be to look only at activities on the
critical path.
PERT (Program Evaluation and Review Technique)
       PERT is a variation on Critical Path Analysis that takes a
slightly more skeptical view of time estimates made for each
project stage. To use it, estimate the shortest possible time
each activity will take, the most likely length of time, and the
longest time that might be taken if the activity takes longer
than expected.
       Use the formula below to calculate the time to use for
each project stage:

shortest time + 4 x likely time + longest time
-----------------------------------------------------------
                         6
Key Points : CPA is a powerful tool for assessing
tasks, their parallelization, upper bound of shortest
time, resources and priority of activities within a
project.

       An effective Critical Path Analysis can make the
difference between success and failure on complex
projects. It can be very useful for assessing the
importance of problems faced during the
implementation of the plan.
       PERT is a variant of Critical Path Analysis that
takes a more skeptical view of the time needed to
complete each project stage.

More Related Content

PPTX
Critical Path Method (CPM) & Network Analysis
PPT
Critical Path Analysis Notes
PPTX
Lesson in fs cpm,cpa
PDF
Critical Path Analysis
PDF
Gantt PERT and CPM
PPTX
Program Evaluation and Review Technique (PERT)
PPTX
Critical path method
Critical Path Method (CPM) & Network Analysis
Critical Path Analysis Notes
Lesson in fs cpm,cpa
Critical Path Analysis
Gantt PERT and CPM
Program Evaluation and Review Technique (PERT)
Critical path method

What's hot (20)

PPT
06 pert cpm
PPTX
Project management technique PERT & CPM
PPTX
PPTX
Critical Path Method (CPM) Training
PPTX
Project planning and scheduling techniques
PPTX
PERT & Gantt Chart
ODP
Critical path method
PPTX
Critical Path Method presentation.
PPTX
CPM NETWORK
PPTX
Project management techniques
PPT
Critical path method (cpm)
PPTX
Network Techniques
PPTX
CPM/PERT and Gantt charts
PPTX
Programme evaluation and review technique &Gantt Chart
PPTX
Seminar on pert
PPTX
PM scheduling techniques
PPT
06 pert cpm
PPTX
Pert, cpm & gert
PPT
Pert
06 pert cpm
Project management technique PERT & CPM
Critical Path Method (CPM) Training
Project planning and scheduling techniques
PERT & Gantt Chart
Critical path method
Critical Path Method presentation.
CPM NETWORK
Project management techniques
Critical path method (cpm)
Network Techniques
CPM/PERT and Gantt charts
Programme evaluation and review technique &Gantt Chart
Seminar on pert
PM scheduling techniques
06 pert cpm
Pert, cpm & gert
Pert
Ad

Viewers also liked (20)

PPTX
Critical path analysis for pmp exam
PPT
Critical Path Analysis
PPTX
Critical path method
PDF
Cpa & pert charts
PPT
Critical path analysis
PPT
Critical path and pert
PPT
Lesson02_new
PDF
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
PPTX
Syam critical path cpa
PDF
Critical Path Analysis for a New Product Release
PDF
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
DOCX
Integrated Marketing Communications
PDF
Network Anaysis_ critical path methods
PPTX
Bpp 3213 lecture 2
PPTX
Session 4 critical path method upload
PPTX
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
PDF
Year 12 Maths A Textbook - Chapter 8
PPTX
Pictographs
PPTX
5. entr lesson 13
PPTX
Cpm critical path method
Critical path analysis for pmp exam
Critical Path Analysis
Critical path method
Cpa & pert charts
Critical path analysis
Critical path and pert
Lesson02_new
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Syam critical path cpa
Critical Path Analysis for a New Product Release
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Integrated Marketing Communications
Network Anaysis_ critical path methods
Bpp 3213 lecture 2
Session 4 critical path method upload
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Year 12 Maths A Textbook - Chapter 8
Pictographs
5. entr lesson 13
Cpm critical path method
Ad

Similar to Critical Path Analysis (20)

PPT
Critical path
PPT
Critical path
DOC
Critical Path Analysis
PPTX
PertGanttchart
PPTX
PERT/CPM
PPTX
TOOLS OF EDUCATIONAL MANAGEMENT-8615
PPTX
Week-4 GDPPD-project planning ad design pattern.pptx
PPTX
Critical path analysis
PPT
-Project-Management.ppt
PPTX
CPM & PERT analysishkuahjfahah,mfhmkjf,.pptx
PPTX
PERT and CPM revisedbusiness strategies.pptx
PPTX
CPM and pert(IT)-SOWFTWARE PROJECT MANAGEMENT
PPTX
or-pert
PDF
Critical path method(cpm)
PPTX
PROGRAM EVALUATION REVIEW TECHNIQUE.pptx
PPTX
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
PPTX
Pert and gantt chart.pptx
PPTX
Programme Evaluation and Review Technique
DOCX
Control techniques
Critical path
Critical path
Critical Path Analysis
PertGanttchart
PERT/CPM
TOOLS OF EDUCATIONAL MANAGEMENT-8615
Week-4 GDPPD-project planning ad design pattern.pptx
Critical path analysis
-Project-Management.ppt
CPM & PERT analysishkuahjfahah,mfhmkjf,.pptx
PERT and CPM revisedbusiness strategies.pptx
CPM and pert(IT)-SOWFTWARE PROJECT MANAGEMENT
or-pert
Critical path method(cpm)
PROGRAM EVALUATION REVIEW TECHNIQUE.pptx
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Pert and gantt chart.pptx
Programme Evaluation and Review Technique
Control techniques

Recently uploaded (20)

PPTX
Programs and apps: productivity, graphics, security and other tools
PDF
project resource management chapter-09.pdf
PDF
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
PPTX
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PPTX
Group 1 Presentation -Planning and Decision Making .pptx
PDF
Getting Started with Data Integration: FME Form 101
PPTX
SOPHOS-XG Firewall Administrator PPT.pptx
PDF
Accuracy of neural networks in brain wave diagnosis of schizophrenia
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PDF
A comparative study of natural language inference in Swahili using monolingua...
PPTX
Chapter 5: Probability Theory and Statistics
PDF
Web App vs Mobile App What Should You Build First.pdf
PDF
WOOl fibre morphology and structure.pdf for textiles
PDF
Zenith AI: Advanced Artificial Intelligence
PDF
Assigned Numbers - 2025 - Bluetooth® Document
PDF
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
PDF
Univ-Connecticut-ChatGPT-Presentaion.pdf
Programs and apps: productivity, graphics, security and other tools
project resource management chapter-09.pdf
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
Building Integrated photovoltaic BIPV_UPV.pdf
Digital-Transformation-Roadmap-for-Companies.pptx
Group 1 Presentation -Planning and Decision Making .pptx
Getting Started with Data Integration: FME Form 101
SOPHOS-XG Firewall Administrator PPT.pptx
Accuracy of neural networks in brain wave diagnosis of schizophrenia
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
A comparative study of natural language inference in Swahili using monolingua...
Chapter 5: Probability Theory and Statistics
Web App vs Mobile App What Should You Build First.pdf
WOOl fibre morphology and structure.pdf for textiles
Zenith AI: Advanced Artificial Intelligence
Assigned Numbers - 2025 - Bluetooth® Document
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
Univ-Connecticut-ChatGPT-Presentaion.pdf

Critical Path Analysis

  • 1. Critical Path Analysis and PERT Charts An overview of the article by Simu Mihai Stelian An IV, CTI Full version http://www.mindtools.com/critpath.html
  • 2. Critical Path Analysis and PERT are powerful tools that help you to schedule and manage complex projects. They were developed in the 1950s to control large defense projects, and have been used routinely since then. These tools help monitor and improve scheduling for complex interdependent activities such as commonly involved in developing software. During management of a project, they allow you to monitor achievement of project goals. They help you to see where remedial action needs to be taken to get a project back on course.
  • 3. The benefit of using CPA within the planning process is to help you develop and test your plan to ensure that it is robust. Critical Path Analysis formally identifies tasks which must be completed on time for the whole project to be completed on time. It also identifies which tasks can be delayed if resource needs to be reallocated to catch up on missed or overrunning tasks. The disadvantage of CPA, if you use it as the technique by which your project plans are communicated and managed against, is that the relation of tasks to time is not as immediately obvious as with Gantt Charts. This can make them more difficult to understand.
  • 4. How to use the tool : As with Gantt Charts, the essential concept behind Critical Path Analysis is that you cannot start some activities until others are finished. These activities need to be completed in a sequence, with each stage being more-or-less completed before the next stage can begin. These are 'sequential' activities. Other activities are not dependent on completion of any other tasks. You can do these at any time before or after a particular stage is reached. These are non- dependent or 'parallel' tasks.
  • 5. Step 1 : List all activities in the plan
  • 6. Step 2 :Plot the activities as a circle and arrow diagram In these, circles show events within the project, such as the start and finish of tasks. The number shown in the left hand half of the circle allows you to identify each one easily. Circles are sometimes known as nodes. An arrow running between two event circles shows the activity needed to complete that task. A description of the task is written underneath the arrow. The length of the task is shown above it. By convention, all arrows run left to right. Arrows are also sometimes called arcs.
  • 7. Here the activities of 'Select Hardware' and 'Core Module Analysis' cannot be started until 'High Level Analysis' has been completed.
  • 8. Full Critical Path Diagram :
  • 9. Each event circle also has a figure in the bottom, right hand quadrant. This shows the latest finish time that's permissible for the preceding activity if the project is to be completed in the minimum time possible. You can calculate this by starting at the last event and working backwards. The latest finish time of the preceding event and the earliest start time of the following even will be the same for circles on the critical path. The activities on the Critical Path must be very closely managed to ensure that activities are completed on time. If jobs on the critical path slip, immediate action should be taken to get the project back on schedule. Otherwise completion of the whole project will slip.
  • 10. Crash Action : You may find that you need to complete a project earlier than your Critical Path Analysis says is possible. In this case you need to re-plan your project. You have a number of options and would need to assess the impact of each on the project’s cost, quality and time required to complete it. For example, you could increase resource available for each project activity to bring down time spent on each but the impact of some of this would be insignificant and a more efficient way of doing this would be to look only at activities on the critical path.
  • 11. PERT (Program Evaluation and Review Technique) PERT is a variation on Critical Path Analysis that takes a slightly more skeptical view of time estimates made for each project stage. To use it, estimate the shortest possible time each activity will take, the most likely length of time, and the longest time that might be taken if the activity takes longer than expected. Use the formula below to calculate the time to use for each project stage: shortest time + 4 x likely time + longest time ----------------------------------------------------------- 6
  • 12. Key Points : CPA is a powerful tool for assessing tasks, their parallelization, upper bound of shortest time, resources and priority of activities within a project. An effective Critical Path Analysis can make the difference between success and failure on complex projects. It can be very useful for assessing the importance of problems faced during the implementation of the plan. PERT is a variant of Critical Path Analysis that takes a more skeptical view of the time needed to complete each project stage.