Technical Level Training
Instrument Transformers
Current Transformers
Theory & Testing
Prepared by
Hashem Talukder
High Voltage (HV) Service Team
Reverie Power & Automation Engineering Limited
Copyright ©2020 by Reverie Power & Automation Engineering Limited. All rights reserved
Current
Transformer
Why Instrument Transformers
▪ Supervision during normal conditions
▪ Energy Metering for buying and selling
▪ Registration of abnormal conditions- Faults
June , 2020 | Slide 02
Current
Transformer
Main Tasks of Current Transformers
▪ Transform currents from high levels to measureable levels
▪ Insulate the secondary circuits from the high voltage network
▪ Standardize meters and relays
June , 2020 | Slide 03
Current
Transformer
Convert Primary Power Signals to Manageable Values for
▪ Indicating Meters
▪ Revenue Metering
▪ Protective Relay Systems
▪ Power Generation
▪ Plant Monitoring Systems
▪ Fault Recorders
▪ SCADA
▪ Overall Electric Grid Monitoring (Local Dispatch & ISO Level)
▪ Building (Energy) Management Systems
▪ Load Control
June , 2020 | Slide 04
Current
Transformer
Basic Transformer
June , 2020 | Slide 05
Current
Transformer
In a Real CT
June , 2020 | Slide 06
Current
Transformer
CT Construction Types
▪ Window or Bus Type
▪ Split Core
▪ Outdoor ( Live & Dead Tank)
June , 2020 | Slide 07
Current
Transformer
June , 2020 | Slide 08
Current
Transformer
June , 2020 | Slide 09
Current
Transformer
Live Tank vs Dead Tank CT
June , 2020 | Slide 10
Current
Transformer
Live Tank vs Dead Tank CT
▪ The core with secondary winding is housed in the
top tank which is live ( At high voltage)
▪ The core with secondary winding is housed in the
bottom tank which is earthed (Dead)
▪ Core and Secondary winding - isolated ▪ Only primary winding is isolated
▪ Insulation is robust and reliable ▪ Insulation is not robust
▪ Primary winding is of shortest length possible
which offers high strength against the short time
dynamic force
▪ Primary winding has to pass through the porcelain
insulator and the larger length of primary
conductor produces maxm mechanical force
during short time dynamic force
▪ Minimum heat generation, maximum dissipation ▪ Maximum heat generation, minimum dissipation
▪ Compact and economical ▪ Bulky and costly
June , 2020 | Slide 11
Current
Transformer
CT Core
June , 2020 | Slide 12
Current
Transformer
IEC Standards
June , 2020 | Slide 13
Current
Transformer
Definition as per IEC 60044-1
▪ Accuracy Class : a designation assigned to a current transformer the error of which remain within
specified limits under prescribed conditions of use
▪ Burden : the impedance of secondary circuit in ohms and power-factor. Usually expressed in VA
▪ Instrument Security factor (FS): the ratio of rated instrument limit primary current to the rated
primary current
▪ Accuracy Limit Factor (ALF) : the ratio of the rated accuracy limit primary current to the rated
primary current
▪ Rated Knee-Point e.m.f : the minimum sinusoidal e.m.f at rated power frequency when applied to
the secondary terminals of the transformer, all others terminals being open circuited , which when
increased by 10% causes the r.m.s exciting current to increase by no more than 50%. The actual
knee point emf will be equal or greater rated knee point emf.
June , 2020 | Slide 14
Current
Transformer
Major Technical Specification of a Current Transformer
June , 2020 | Slide 15
Current
Transformer
CT Terminal Markings
▪ Expressed in 5A or 1A Ratio
▪ 1200/5 or 1200/1
June , 2020 | Slide 16
Current
Transformer
CTs for Protection and Metering Applications
▪ A distinction has to be made between a Metering and Protection Class CT
▪ The designs of the magnetic cores are different
▪ This ensures that they perform according to the needs of the particular device
connected
June , 2020 | Slide 17
Current
Transformer
Properties of Metering Core
▪ High Accuracy in a smaller range ( 5-120% of rated current / 1-120% for class S)
▪ Low Burden
▪ Low Over Current Factor (FS) (At FS, Core saturated and Accuracy isn’t guaranteed)
▪ Leads to lower Saturation Voltage ( Protects Metering Devices from overloading)
June , 2020 | Slide 18
Current
Transformer
Standard Accuracy Classes for Metering
▪ 0.1 – 0.2 – 0.5 – 1
▪ 0.2S – 0.5S
▪ 3 – 5
June , 2020 | Slide 19
Current
Transformer
IEC 60044 – 1 Metering Accuracy Requirements
June , 2020 | Slide 20
Current
Transformer
IEC 60044 – 1 Metering Accuracy Requirements
June , 2020 | Slide 21
Current
Transformer
Properties of Protection Core
▪ Designed to transform a distortion-free signal even well into the overcurrent
range
▪ Current range 100% of rated current to ALF x rated current
▪ Relays are required to perform in fault current type situations
▪ Low accuracy requirements
▪ High saturation voltage
▪ More core material is needed
June , 2020 | Slide 22
Current
Transformer
Standard Accuracy Classes for Protection
▪ 5P and 10P
▪ PX (User defined CT performance)
• Turn Ratio error should not exceed ± 0.25%
• Rated Knee point emf (𝐸𝑘)
• Maximum exciting current (𝐼𝑒) at rated (𝐸𝑘)
• Maximum Resistance (𝑅𝑐𝑡) at 75°C
June , 2020 | Slide 23
Current
Transformer
IEC 60044 – 1 Protection Accuracy Requirements
June , 2020 | Slide 24
Current
Transformer
June , 2020 | Slide 25
Current
Transformer
Testing CTs
When ?
▪ Initial Commissioning
▪ Investigation
▪ Scheduled
Why ?
▪ Verify Factory Tests
▪ Ordered/Delivered Correctly
▪ Ensure no Damages
June , 2020 | Slide 26
Current
Transformer
Test Methods
▪ Primary Injection
▪ Secondary Injection – Fixed Frequency
▪ Secondary Injection – Variable Frequency
Test Requirements
▪ Determination of Knee/Saturation Point
▪ Insulation
▪ Polarity
▪ Winding Resistance
▪ Primary/Secondary Ratio ( %Ratio Error )
▪ Burden Check
▪ Tan-Delta
▪ Documentation / Visual Check
June , 2020 | Slide 27
Current
Transformer
Why so many Tests
▪ Ensure proper Relay Operations
▪ Certify Billing Accuracy
▪ Reduce Possibility of Failure when Energized
▪ Manufacturing Defects Do Happen
▪ Installation Error Do Happens
June , 2020 | Slide 28
Current
Transformer
Before Testing Starts
▪ Ask Concerned Personnel to isolate CTs ( Electrically & Mechanically )
▪ DON’T Operate Yourself
▪ Ensure Isolation Yourself - Physically
▪ Use Caution Tape to avoid enthusiastic people from entering premises
▪ Ground One-End (P1 / P2 ) to avoid Induced Voltage
▪ Take notes if removal of secondary connection requires
▪ Ensure Proper Grounding of Testing Kits
▪ Collect FAT / Previous Test Reports
▪ Revert to Original Connection after Tests end ( Ensure Yourself )
June , 2020 | Slide 29
Current
Transformer
Testing Excitation / Knee Point
▪ Secondary kept Opened
▪ Voltage increased until knee-
point reached
June , 2020 | Slide 30
Current
Transformer
Testing Excitation / Knee Point
June , 2020 | Slide 31
Current
Transformer
Testing Turn Ratio Error%
▪ Current Injected at Primary
▪ Transformed Current is
measured from Secondary
June , 2020 | Slide 32
Current
Transformer
Testing Turn Ratio Error%
Current Error% =
𝐾𝑛𝐼𝑠−𝐼𝑝 ×100
𝐼𝑝
Kn = Rated Transformation Ratio
Is = Actual / Measured Secondary Current
Ip = Actual / Measured Primary Current
June , 2020 | Slide 33
Current
Transformer
Measuring Secondary Winding Resistance
▪ Usually done with AVO Meter but recommended way is to do with Test Kit / CT Analyzer
▪ Convert Resistance Value at 75°C and compare with Reference / Rated Value
▪ It’s the simplest test for diagnosing CT Secondary . It should be the 1st test to perform on CT if Core
Demagnetization option is available, otherwise, perform it at last.
▪ As DC current leads to Residual Magnetism, it may jeopardize other tests Accuracy
June , 2020 | Slide 34
Current
Transformer
How CTs Secondary are Connected
▪ Always Connected in SERIES
▪ Don’t Connect Burden Beyond its Rating
▪ Connect Cores as per Designation of
Devices
▪ Don’t Interchange CT Cores
June , 2020 | Slide 35
Current
Transformer
CTs Performance at Through-Fault
▪ CTs are designed to sustain a through-fault condition without being saturated
▪ To avoid saturation CT should develop adequate voltage at secondary
▪ Extra burden should not be imposed beyond its rating
▪ For Differential Protection, PX class CTs are recommended to be used as they are
calculated to provide sufficient voltage during a through-fault
For Protection Purposes, CTs are NEVER Expected to be Saturated
June , 2020 | Slide 36
Current
Transformer
Dos and Don’ts at Commissioning
▪ Do Primary Injection and check Continuity throughout the secondary circuit
▪ Measure Secondary Current as per transformation ratio at each junction point with Clamp Meter
▪ Ensure proper Core Allocation & Polarity
▪ Avoid Double-Grounding as it leads to Wrong Measurement
▪ Tighten CT secondary with Utmost care. Double Check !
▪ NEVER Leave CTs Secondary OPENED
▪ Once Primary Injection is done successfully, DON’T Touch CT secondary or Change Connections
▪ If Changes are made, Perform Primary Injection AGAIN
June , 2020 | Slide 37
Current
Transformer
June , 2020 | Slide 38
References
Most of the information is gathered from multiple online sources that are accessible to the public

More Related Content

PPTX
Factors to be considered while selecting CT
PPTX
Current Transformer.pptx
PPTX
Instrument transformer and his application.pptx
PPTX
Current_Transformer .......................
PPTX
CT & PT.pptx
PPTX
Instrument Transformer (ALIV - BANGLADESH)
PPTX
ct pt testing...........................................
PDF
475393259-Training-On-Current-Transformer.pdf
Factors to be considered while selecting CT
Current Transformer.pptx
Instrument transformer and his application.pptx
Current_Transformer .......................
CT & PT.pptx
Instrument Transformer (ALIV - BANGLADESH)
ct pt testing...........................................
475393259-Training-On-Current-Transformer.pdf

Similar to Current Transformers.pdf (20)

PPT
21955420-Power-System-Protective-Relaying-Part-Three.ppt
PDF
Instrument transformers in the Power System
PDF
Current transformer (ct)
PPTX
Ppt of current transformer
PPTX
Currentandpotentialtransformernotee.pptx
PPTX
Instrument Transformer Presentation
PPT
4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.ppt
PPTX
Electrical measurement & measuring instruments [emmi (nee-302) -unit-2]
PPTX
Introduction to CTs and PTs
PPTX
current transformers.pptx
PDF
Introduction to Current Transformer (Substation)
PPTX
6. emi instrument transformers (with marking)
PDF
TESCO Tuesday: CT Testing: Theory and Practice
PPTX
Current Transformer.pptx
PPTX
Introduction to Instrument Transformers
PPTX
CT and VT.pptx
PPTX
Introduction to CTs and PTs
PPTX
CT Testing: Theory and Practice
PPTX
Chapter_4_Instrument_transformers_ff9a45ab_0efd_4f66_9085_8925fec18377.pptx
PPTX
Ratio, Burden, and Admittance Testing
21955420-Power-System-Protective-Relaying-Part-Three.ppt
Instrument transformers in the Power System
Current transformer (ct)
Ppt of current transformer
Currentandpotentialtransformernotee.pptx
Instrument Transformer Presentation
4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.ppt
Electrical measurement & measuring instruments [emmi (nee-302) -unit-2]
Introduction to CTs and PTs
current transformers.pptx
Introduction to Current Transformer (Substation)
6. emi instrument transformers (with marking)
TESCO Tuesday: CT Testing: Theory and Practice
Current Transformer.pptx
Introduction to Instrument Transformers
CT and VT.pptx
Introduction to CTs and PTs
CT Testing: Theory and Practice
Chapter_4_Instrument_transformers_ff9a45ab_0efd_4f66_9085_8925fec18377.pptx
Ratio, Burden, and Admittance Testing
Ad

Recently uploaded (20)

PPTX
Feature types and data preprocessing steps
PDF
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PPTX
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
PPTX
Module 8- Technological and Communication Skills.pptx
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PPTX
communication and presentation skills 01
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
PPTX
Management Information system : MIS-e-Business Systems.pptx
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PPTX
Software Engineering and software moduleing
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PDF
August -2025_Top10 Read_Articles_ijait.pdf
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Feature types and data preprocessing steps
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
Module 8- Technological and Communication Skills.pptx
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
communication and presentation skills 01
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
Management Information system : MIS-e-Business Systems.pptx
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Software Engineering and software moduleing
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
August -2025_Top10 Read_Articles_ijait.pdf
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Ad

Current Transformers.pdf

  • 1. Technical Level Training Instrument Transformers Current Transformers Theory & Testing Prepared by Hashem Talukder High Voltage (HV) Service Team Reverie Power & Automation Engineering Limited Copyright ©2020 by Reverie Power & Automation Engineering Limited. All rights reserved
  • 2. Current Transformer Why Instrument Transformers ▪ Supervision during normal conditions ▪ Energy Metering for buying and selling ▪ Registration of abnormal conditions- Faults June , 2020 | Slide 02
  • 3. Current Transformer Main Tasks of Current Transformers ▪ Transform currents from high levels to measureable levels ▪ Insulate the secondary circuits from the high voltage network ▪ Standardize meters and relays June , 2020 | Slide 03
  • 4. Current Transformer Convert Primary Power Signals to Manageable Values for ▪ Indicating Meters ▪ Revenue Metering ▪ Protective Relay Systems ▪ Power Generation ▪ Plant Monitoring Systems ▪ Fault Recorders ▪ SCADA ▪ Overall Electric Grid Monitoring (Local Dispatch & ISO Level) ▪ Building (Energy) Management Systems ▪ Load Control June , 2020 | Slide 04
  • 6. Current Transformer In a Real CT June , 2020 | Slide 06
  • 7. Current Transformer CT Construction Types ▪ Window or Bus Type ▪ Split Core ▪ Outdoor ( Live & Dead Tank) June , 2020 | Slide 07
  • 10. Current Transformer Live Tank vs Dead Tank CT June , 2020 | Slide 10
  • 11. Current Transformer Live Tank vs Dead Tank CT ▪ The core with secondary winding is housed in the top tank which is live ( At high voltage) ▪ The core with secondary winding is housed in the bottom tank which is earthed (Dead) ▪ Core and Secondary winding - isolated ▪ Only primary winding is isolated ▪ Insulation is robust and reliable ▪ Insulation is not robust ▪ Primary winding is of shortest length possible which offers high strength against the short time dynamic force ▪ Primary winding has to pass through the porcelain insulator and the larger length of primary conductor produces maxm mechanical force during short time dynamic force ▪ Minimum heat generation, maximum dissipation ▪ Maximum heat generation, minimum dissipation ▪ Compact and economical ▪ Bulky and costly June , 2020 | Slide 11
  • 14. Current Transformer Definition as per IEC 60044-1 ▪ Accuracy Class : a designation assigned to a current transformer the error of which remain within specified limits under prescribed conditions of use ▪ Burden : the impedance of secondary circuit in ohms and power-factor. Usually expressed in VA ▪ Instrument Security factor (FS): the ratio of rated instrument limit primary current to the rated primary current ▪ Accuracy Limit Factor (ALF) : the ratio of the rated accuracy limit primary current to the rated primary current ▪ Rated Knee-Point e.m.f : the minimum sinusoidal e.m.f at rated power frequency when applied to the secondary terminals of the transformer, all others terminals being open circuited , which when increased by 10% causes the r.m.s exciting current to increase by no more than 50%. The actual knee point emf will be equal or greater rated knee point emf. June , 2020 | Slide 14
  • 15. Current Transformer Major Technical Specification of a Current Transformer June , 2020 | Slide 15
  • 16. Current Transformer CT Terminal Markings ▪ Expressed in 5A or 1A Ratio ▪ 1200/5 or 1200/1 June , 2020 | Slide 16
  • 17. Current Transformer CTs for Protection and Metering Applications ▪ A distinction has to be made between a Metering and Protection Class CT ▪ The designs of the magnetic cores are different ▪ This ensures that they perform according to the needs of the particular device connected June , 2020 | Slide 17
  • 18. Current Transformer Properties of Metering Core ▪ High Accuracy in a smaller range ( 5-120% of rated current / 1-120% for class S) ▪ Low Burden ▪ Low Over Current Factor (FS) (At FS, Core saturated and Accuracy isn’t guaranteed) ▪ Leads to lower Saturation Voltage ( Protects Metering Devices from overloading) June , 2020 | Slide 18
  • 19. Current Transformer Standard Accuracy Classes for Metering ▪ 0.1 – 0.2 – 0.5 – 1 ▪ 0.2S – 0.5S ▪ 3 – 5 June , 2020 | Slide 19
  • 20. Current Transformer IEC 60044 – 1 Metering Accuracy Requirements June , 2020 | Slide 20
  • 21. Current Transformer IEC 60044 – 1 Metering Accuracy Requirements June , 2020 | Slide 21
  • 22. Current Transformer Properties of Protection Core ▪ Designed to transform a distortion-free signal even well into the overcurrent range ▪ Current range 100% of rated current to ALF x rated current ▪ Relays are required to perform in fault current type situations ▪ Low accuracy requirements ▪ High saturation voltage ▪ More core material is needed June , 2020 | Slide 22
  • 23. Current Transformer Standard Accuracy Classes for Protection ▪ 5P and 10P ▪ PX (User defined CT performance) • Turn Ratio error should not exceed ± 0.25% • Rated Knee point emf (𝐸𝑘) • Maximum exciting current (𝐼𝑒) at rated (𝐸𝑘) • Maximum Resistance (𝑅𝑐𝑡) at 75°C June , 2020 | Slide 23
  • 24. Current Transformer IEC 60044 – 1 Protection Accuracy Requirements June , 2020 | Slide 24
  • 26. Current Transformer Testing CTs When ? ▪ Initial Commissioning ▪ Investigation ▪ Scheduled Why ? ▪ Verify Factory Tests ▪ Ordered/Delivered Correctly ▪ Ensure no Damages June , 2020 | Slide 26
  • 27. Current Transformer Test Methods ▪ Primary Injection ▪ Secondary Injection – Fixed Frequency ▪ Secondary Injection – Variable Frequency Test Requirements ▪ Determination of Knee/Saturation Point ▪ Insulation ▪ Polarity ▪ Winding Resistance ▪ Primary/Secondary Ratio ( %Ratio Error ) ▪ Burden Check ▪ Tan-Delta ▪ Documentation / Visual Check June , 2020 | Slide 27
  • 28. Current Transformer Why so many Tests ▪ Ensure proper Relay Operations ▪ Certify Billing Accuracy ▪ Reduce Possibility of Failure when Energized ▪ Manufacturing Defects Do Happen ▪ Installation Error Do Happens June , 2020 | Slide 28
  • 29. Current Transformer Before Testing Starts ▪ Ask Concerned Personnel to isolate CTs ( Electrically & Mechanically ) ▪ DON’T Operate Yourself ▪ Ensure Isolation Yourself - Physically ▪ Use Caution Tape to avoid enthusiastic people from entering premises ▪ Ground One-End (P1 / P2 ) to avoid Induced Voltage ▪ Take notes if removal of secondary connection requires ▪ Ensure Proper Grounding of Testing Kits ▪ Collect FAT / Previous Test Reports ▪ Revert to Original Connection after Tests end ( Ensure Yourself ) June , 2020 | Slide 29
  • 30. Current Transformer Testing Excitation / Knee Point ▪ Secondary kept Opened ▪ Voltage increased until knee- point reached June , 2020 | Slide 30
  • 31. Current Transformer Testing Excitation / Knee Point June , 2020 | Slide 31
  • 32. Current Transformer Testing Turn Ratio Error% ▪ Current Injected at Primary ▪ Transformed Current is measured from Secondary June , 2020 | Slide 32
  • 33. Current Transformer Testing Turn Ratio Error% Current Error% = 𝐾𝑛𝐼𝑠−𝐼𝑝 ×100 𝐼𝑝 Kn = Rated Transformation Ratio Is = Actual / Measured Secondary Current Ip = Actual / Measured Primary Current June , 2020 | Slide 33
  • 34. Current Transformer Measuring Secondary Winding Resistance ▪ Usually done with AVO Meter but recommended way is to do with Test Kit / CT Analyzer ▪ Convert Resistance Value at 75°C and compare with Reference / Rated Value ▪ It’s the simplest test for diagnosing CT Secondary . It should be the 1st test to perform on CT if Core Demagnetization option is available, otherwise, perform it at last. ▪ As DC current leads to Residual Magnetism, it may jeopardize other tests Accuracy June , 2020 | Slide 34
  • 35. Current Transformer How CTs Secondary are Connected ▪ Always Connected in SERIES ▪ Don’t Connect Burden Beyond its Rating ▪ Connect Cores as per Designation of Devices ▪ Don’t Interchange CT Cores June , 2020 | Slide 35
  • 36. Current Transformer CTs Performance at Through-Fault ▪ CTs are designed to sustain a through-fault condition without being saturated ▪ To avoid saturation CT should develop adequate voltage at secondary ▪ Extra burden should not be imposed beyond its rating ▪ For Differential Protection, PX class CTs are recommended to be used as they are calculated to provide sufficient voltage during a through-fault For Protection Purposes, CTs are NEVER Expected to be Saturated June , 2020 | Slide 36
  • 37. Current Transformer Dos and Don’ts at Commissioning ▪ Do Primary Injection and check Continuity throughout the secondary circuit ▪ Measure Secondary Current as per transformation ratio at each junction point with Clamp Meter ▪ Ensure proper Core Allocation & Polarity ▪ Avoid Double-Grounding as it leads to Wrong Measurement ▪ Tighten CT secondary with Utmost care. Double Check ! ▪ NEVER Leave CTs Secondary OPENED ▪ Once Primary Injection is done successfully, DON’T Touch CT secondary or Change Connections ▪ If Changes are made, Perform Primary Injection AGAIN June , 2020 | Slide 37
  • 39. References Most of the information is gathered from multiple online sources that are accessible to the public