CT Testing:
Theory and Practice
Presented Tom Lawton, TESCO
The Eastern Specialty Company
For North Carolina Electric Meter School
Polyphase
Tuesday, June 15, 2021 at 3:45 p.m.
2
What we will cover
• Why do we test CT’s?
• Shop testing
• How to read and interpret a transformer face plate
• Types of field tests
• Magnetization effects and demagnetization
3
Shop Testing
• New Transformers
• Manufacturer’s tests
• Utility tests
4
Self-Contained vs. Transformer-Rated
1S, 2S, 3S, 4S, 9S, 12S, 16S, 45S, etc., etc.
What’s the Difference?
Different Forms for Different Services and
Applications
5
Self-Contained vs. Transformer-Rated
Self-Contained
(direct)
Transformer-Rated
(indirect)
6
Self-Contained
Primarily Residential
(1S, 2S, 12S)
Relatively Low Current
Example: 100A
7
Transformer-Rated
Primarily Commercial/Industrial
(9S, 16S)
Relatively High Current
Example: 400A
8
What is a CT?
“A current transformer (CT) is used for measurement of
alternating electric currents. Current transformers, together
with voltage (or potential) transformers (VT or PT), are
known as instrument transformers. When current in a
circuit is too high to apply directly to measuring
instruments, a current transformer produces a reduced
current accurately proportional to the current in the circuit,
which can be conveniently connected to measuring and
recording instruments. A current transformer isolates the
measuring instruments from what may be very high voltage
in the monitored circuit. Current transformers are
commonly used in metering and protective relays in the
electrical power industry.” - Wikipedia
9
Transformer-Rated
Primarily Commercial/Industrial
(9S, 16S)
Relatively High Current
Example: 400A
400:5
5A
10
Current Transformers Conceptual
Representation
Real, with core losses
Ideal. No losses
11
CT’s – Functions and Terminology
Ratio
For instance, a CT with a 400:5 ratio will produce
5A on the secondary, when 400A are applied
to the primary.
12
CT’s – Functions and Terminology
Thermal Rating Factor
A value representing the amount by which the
primary current can be increased without
exceeding the allowable temperature rise.
For instance, a RF of 4.0 at 30° ambient on a
400:5 ratio CT would allow for a primary current
up to 1600A.
13
CT’s – Functions and Terminology
Accuracy Classifications and Burden
All CT’s fall within an accuracy class.
IEEE Standards have defined accuracy classes.
14
CT’s – Functions and Terminology
Accuracy Classifications and Burden
Example: 0.3% @ B0.1, B0.2, B0.5
15
CT’s – Functions and Terminology
Faceplate
16
Transformer-Rated
9S Meter Installation
5A
PHASE A
SOURCE
PHASE C
PHASE B
LOAD
400A
400A
400A
5A
5A
17
Transformer-Rated
9S Meter Installation
5A
PHASE A
SOURCE
PHASE C
PHASE B
LOAD
400A
400A
400A
5A
5A
18
Meter Testing
9S Meter Installation
5A
PHASE A
SOURCE
PHASE C
PHASE B
LOAD
400A
400A
400A
5A
5A
Isolate the Meter
from the Service
P
19
Meter Testing
9S Meter Installation
5A
PHASE A
SOURCE
PHASE C
PHASE B
LOAD
400A
400A
400A
5A
5A
? ? ?
20
Meter Testing
9S Meter Installation
5A
PHASE A
SOURCE
PHASE C
PHASE B
LOAD
400A
400A
400A
5A
5A
What if?
355:5
405:5
200:5
Shorted
etc.
21
CT Testing
CT Testing is Important!
1) Test for correct ratio
2) Test for functionality at
rated burdens
22
Ratio Testing
Ratio of Primary Current to Secondary Current
5A
PHASE A
SOURCE LOAD
400A
400A
400A
5A
5A
Calculate
Ratio
23
Burden Testing
Functionality with Burden Present on the
Secondary Loop
PHASE A
Some burden will always be
present – junctions, meter coils,
test switches, cables, etc.
CT’s must be able to maintain
an accurate ratio with burden on
the secondary.
24
Burden Testing
Functionality with Burden Present on the
Secondary Loop
25
Burden Testing
Functionality with Burden Present on the
Secondary Loop
Example Burden Spec:
0.3% @ B0.1, B0.2, B0.5
or
There should be less than the 0.3%
change in secondary current from initial
(“0” burden) reading, when up to
0.5Ohms of burden is applied
26
Burden Testing
Functionality with Burden Present on the
Secondary Loop
ANSI Burden Values
0.1 Ohms
0.2 Ohms
0.5 Ohms
1 Ohms
2 Ohms
4 Ohms
8 Ohms
27
Burden Testing
0.0000
1.0000
2.0000
3.0000
4.0000
5.0000
6.0000
0 2 4 6 8
0.3% @ B0.1, B0.2, B0.5
Initial Reading = 5Amps
0.3% x 5A = 0.015A
5A – 0.015 = 4.985A
Burden Reading
0 5.0000
0.1 4.9999
0.2 4.9950
0.5 4.9900
1 4.9800
2 4.9500
4 4.0000
8 0.8000
28
Burden Testing
4.9500
4.9600
4.9700
4.9800
4.9900
5.0000
5.0100
5.0200
5.0300
5.0400
5.0500
0 0.2 0.4 0.6 0.8 1
0.3% @ B0.1, B0.2, B0.5
Initial Reading = 5Amps
0.3% x 5A = 0.015A
5A – 0.015 = 4.985A
At 0.5Ohms of Burden
the secondary current is
still at 4.990A – Less
than 0.3% change –
Good CT!
Burden Reading
0 5.0000
0.1 4.9999
0.2 4.9950
0.5 4.9900
1 4.9800
2 4.9500
4 4.0000
8 0.8000
29
Analog Testing
Application of Burden and Calculation
Manual reading of initial and post-
burden secondary currents
30
Admittance Testing
Admittance test results are not immediately intuitive.
Some analysis and interpretation is need.
What do all these mS values mean?
31
Admittance Testing
What is Admittance?
Measured in units of MiliSiemens (mS)
Admittance is the inverse of impedance.
Impedance is the opposition to current.
Therefore, admittance testing measures the overall
“health” of the secondary loop of the CT.
32
Admittance Testing
Admittance testing devices inject an audio sine wave
signal into the secondary loop of the CT.
The resulting current is measured.
The voltage of the initial signal is known.
From these two parameters, the impedance, and thus
the admittance can be calculated.
33
Admittance Testing
Three phase process is
recommended.
1.Test each CT individually
2.Test the matched sets
3.Test over time
34
De-magnetization
CT’s can become magnetized, due to a number of reasons,
including leaving the shorting clip open, near lightning strikes,
and harmonic content.
CT’s can be demagnetized by slowly and smoothly increasing the
secondary resistance until saturation occurs, and then slowly
and smoothly decreasing the secondary resistance.
A resistance that will cause a secondary current reduction of 65%
to 75% will typically put the CT into saturation.
35
What we covered
• Why do we test CT’s?
• Shop testing
• How to read and interpret a transformer face plate
• Types of field tests
• Magnetization effects and demagnetization
36
Questions and Discussion
Tom Lawton
President
tom.lawton@tescometering.com
TESCO – The Eastern Specialty Company
Bristol, PA
215-228-0500
This presentation can also be found under Meter Conferences and
Schools on the TESCO website: www.tescometering.com
ISO 9001:2015 Certified Quality Company
ISO 17025:2017 Accredited Laboratory

More Related Content

PPTX
Ratio, Burden, and Admittance Testing
PPTX
PPTX
Communicating to Your Meters
PPTX
Single Phase Meter Testing Overview
PPTX
21st Century Power Measurements
PPTX
Ratio, Burden, Admittance Testing
PDF
TESCO Tuesday: Ratio, Burden and Admittance
PPTX
Ratio, Burden, and Admittance Testing
Communicating to Your Meters
Single Phase Meter Testing Overview
21st Century Power Measurements
Ratio, Burden, Admittance Testing
TESCO Tuesday: Ratio, Burden and Admittance

What's hot (20)

PPTX
TESCO Tuesday: Transformer-Rated & Self-Contained Metering Fundamentals
PPTX
Meter Forms: Wiring and Uses
PPTX
TESCO Tuesday: Communication Equipment
PPTX
Introduction to CTs and PTs
PPT
PPTX
Introduction to CTs and PTs
PPTX
CT Testing: Theory and Practice
PPTX
Introduction to Transformer Rated Metering
PDF
TESCO Tuesday: Meter Testing in the Field
PPT
Site Verification for Self-Contained Hot Socket Detection
PDF
TESCO Tuesday: Metering Testing by Form
PPT
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
PDF
TESCO Tuesday: Harmonics
PPT
Current Transformers: Ratio & Burden Testing
PDF
The art of meter testing on site 2019
PDF
How to conduct the test on the linearity of impulse voltage divider? (www.him...
PPTX
Calmet C300B power calibrator
PPTX
Calmet testing energy-measurement-equipment
PPTX
Advanced Polyphase Metering
TESCO Tuesday: Transformer-Rated & Self-Contained Metering Fundamentals
Meter Forms: Wiring and Uses
TESCO Tuesday: Communication Equipment
Introduction to CTs and PTs
Introduction to CTs and PTs
CT Testing: Theory and Practice
Introduction to Transformer Rated Metering
TESCO Tuesday: Meter Testing in the Field
Site Verification for Self-Contained Hot Socket Detection
TESCO Tuesday: Metering Testing by Form
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
TESCO Tuesday: Harmonics
Current Transformers: Ratio & Burden Testing
The art of meter testing on site 2019
How to conduct the test on the linearity of impulse voltage divider? (www.him...
Calmet C300B power calibrator
Calmet testing energy-measurement-equipment
Advanced Polyphase Metering
Ad

Similar to CT Testing: Theory and Practice (20)

PPTX
CT Testing - Theory and Practice.pptx
PPTX
Ratio Burden Admittance Testing
PPT
ECNE - Spring 2017 CT Theory and Practice
PPTX
CT Testing - Theory and Practice
PPT
Current Transformers: Ratio & Burden Testing
PDF
TESCO Tuesday: CT Testing: Theory and Practice
PPTX
Introduction to Transformer Rated Metering
PPT
Transformer Rated Metering
PPTX
Introduction to Instrument Transformers
PPT
Introduction to Transformer Rated Metering
PPT
21955420-Power-System-Protective-Relaying-Part-Three.ppt
PPT
Transformer Rated Metering Site Verification
PPT
Transformer Rated Metering Site Verification
PPTX
Current transformer AS ISTRUMINTATION EQUIPMENTS
PPT
Burden Testing, Theory, and Practice
PPT
Transformer Rated Metering 09.27.17
PPT
Instrument Transformer Testing in the Shop and Field
PPT
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
PDF
Power-Transformer-Testing-Brochure-ENU.pdf
PPT
Introduction to Transformer Rated Metering
CT Testing - Theory and Practice.pptx
Ratio Burden Admittance Testing
ECNE - Spring 2017 CT Theory and Practice
CT Testing - Theory and Practice
Current Transformers: Ratio & Burden Testing
TESCO Tuesday: CT Testing: Theory and Practice
Introduction to Transformer Rated Metering
Transformer Rated Metering
Introduction to Instrument Transformers
Introduction to Transformer Rated Metering
21955420-Power-System-Protective-Relaying-Part-Three.ppt
Transformer Rated Metering Site Verification
Transformer Rated Metering Site Verification
Current transformer AS ISTRUMINTATION EQUIPMENTS
Burden Testing, Theory, and Practice
Transformer Rated Metering 09.27.17
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Power-Transformer-Testing-Brochure-ENU.pdf
Introduction to Transformer Rated Metering
Ad

Recently uploaded (20)

PDF
WOOl fibre morphology and structure.pdf for textiles
PPTX
MicrosoftCybserSecurityReferenceArchitecture-April-2025.pptx
PDF
Zenith AI: Advanced Artificial Intelligence
PDF
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
PDF
August Patch Tuesday
PDF
TrustArc Webinar - Click, Consent, Trust: Winning the Privacy Game
PPTX
Chapter 5: Probability Theory and Statistics
PDF
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
PDF
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf
PDF
Enhancing emotion recognition model for a student engagement use case through...
PPTX
Tartificialntelligence_presentation.pptx
PDF
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
PDF
NewMind AI Weekly Chronicles – August ’25 Week III
PDF
Hindi spoken digit analysis for native and non-native speakers
PDF
Developing a website for English-speaking practice to English as a foreign la...
PDF
A novel scalable deep ensemble learning framework for big data classification...
PPTX
Modernising the Digital Integration Hub
PPTX
Programs and apps: productivity, graphics, security and other tools
PDF
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
PDF
A comparative study of natural language inference in Swahili using monolingua...
WOOl fibre morphology and structure.pdf for textiles
MicrosoftCybserSecurityReferenceArchitecture-April-2025.pptx
Zenith AI: Advanced Artificial Intelligence
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
August Patch Tuesday
TrustArc Webinar - Click, Consent, Trust: Winning the Privacy Game
Chapter 5: Probability Theory and Statistics
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf
Enhancing emotion recognition model for a student engagement use case through...
Tartificialntelligence_presentation.pptx
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
NewMind AI Weekly Chronicles – August ’25 Week III
Hindi spoken digit analysis for native and non-native speakers
Developing a website for English-speaking practice to English as a foreign la...
A novel scalable deep ensemble learning framework for big data classification...
Modernising the Digital Integration Hub
Programs and apps: productivity, graphics, security and other tools
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
A comparative study of natural language inference in Swahili using monolingua...

CT Testing: Theory and Practice