SlideShare a Scribd company logo
Slide 1
10/02/2012 Slide 1
Introduction to
Transformer Rated
Metering
Prepared by Tom Lawton,TESCO
For Southeastern Electricity Metering Association (SEMA)
Tuesday, November 7, 2017
10:15 a.m.
Slide 2
Topics we will be covering
• The Basics- Differences Between Self
Contained and Transformer or Instrument
Rated Meter Sites
• Transformer Rated Meter Forms
• Test Switches and CT’s
• Blondel’s Theorem and why this matters to
us in metering
• Meter Accuracy Testing in the Field
• Checking the Health of your CT’s and PT’s
• Site Verification and not just meter testing
Slide 3
Self Contained Metering
•Typically found in residential
metering
•Meters are capable of handling
the direct incoming amperage
•Meter is connected directly to
the load being measured
•Meter is part of the circuit
•When the meter is removed
from the socket, power to the
customer is interrupted
Slide 4
Transformer Rated Metering
• Meter measures scaled down
representation of the load.
• Scaling is accomplished by the use
of external current transformers
(CTs) and sometimes voltage
transformers or PTs).
• The meter is NOT part of the circuit
• When the meter is removed from
the socket, power to the customer
is not effected.
Slide 5
9S Meter Installation with 400:5 CT’s
400A
400A
400A
LOAD
5A 5A 5A
SOURCE
PHASE A
PHASE B
PHASE C
The Basic Components
Slide 6
Typical Connections
Typical Connections for Common
Transformer (Instrument)
Rated Meter Forms
Slide 7
TESCO/Georgia Power 2017 Caribbean Meter School
Fundamentals of Polyphase Field Meter Testing and Site Verification
 Full Load
 Light Load
 Power Factor
Meter Accuracy Testing
Meter Accuracy
Testing in a Nutshell
Slide 8
The Importance of CT Testing in the Field
• One transformer in three wired
backwards will give the customer a
bill of 1/3rd
the actual bill.
• One broken wire to a single
transformer will give the customer a
bill of 2/3rd
the actual bill
• One dual ratio transformer
inappropriately marked in the billing
system as 400:5 instead of 800:5
provides a bill that is ½ of the actual
bill. And the inverse will give a bill
double of what should have been
sent. Both are lose-lose situations
for the utility.
Slide 9
The Importance of CT Testing in the Field
(cont)
•Cross Phasing (wiring errors)
•Loose or Corroded Connections
•CT Mounted Backwards
•CT’s with Shorted Turns
•Wrong Selection of Dual Ratio CT
•Detect Magnetized CT’s
•Burden Failure in Secondary Circuit
•Open or Shorted Secondary
•Mislabeled CT’s
•Ensures all Shorting Blocks have been Removed
Slide 10
Testing at Transformer Rated Sites
Meter Accuracy
Full Load
Light Load
Power Factor
CT Health
Burden Testing
Ratio Testing
Admittance Testing
Site Verification
Slide 11
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Functionality with Burden Present on the Secondary Loop
PHASE A
• Some burden will always be
present – junctions, meter
coils, test switches, cables,
etc.
• CT’s must be able to
maintain an accurate ratio
with burden on the
secondary.
Slide 12
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Functionality with Burden Present on the Secondary Loop
Example Burden Spec:
0.3% @ B0.1, B0.2, B0.5
or
There should be less than the 0.3%
change in secondary current from initial
(“0” burden) reading, when up to 0.5Ohms
of burden is applied
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Slide 13
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Current Transformers Conceptual
Rtepresentation
Real, with core losses
Ideal. No losses
Slide 14
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Functionality with Burden Present on the Secondary Loop
0.3% @ B0.1, B0.2, B0.5
0.0000
1.0000
2.0000
3.0000
4.0000
5.0000
6.0000
0 2 4 6 8
Initial Reading = 5Amps
0.3% x 5A = 0.015A
5A – 0.015 = 4.985A
Burden Reading
0 5.0000
0.1 4.9999
0.2 4.9950
0.5 4.9900
1 4.9800
2 4.9500
4 4.0000
8 0.8000
Slide 15
Ratio of Primary Current to Secondary Current
PHASE A
SOURCE LOAD
400A
400A
400A
5A5A
Calculate Ratio
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Slide 16
Three Phase Power
Blondel’s Theorem
The theory of polyphase watthour metering was first set forth on a scientific
basis in 1893 by Andre E. Blondel, engineer and mathematician. His theorem
applies to the measurement of real power in a polyphase system of any number
of wires. The theorem is as follows:
- If energy is supplied to any system of conductors
through N wires, the total power in the system is given
by the algebraic sum of the readings of N wattmeters, so
arranged that each of the N wires contains one current
coil, the corresponding voltage coil being connected
between that wire and some common point. If this
common point is on one of the N wires, the
measurement may be made by the use of N-1
wattmeters.
Slide 17
Three Phase Power
Blondel’s Theorem
• Simply – We can measure the power in a
N wire system by measuring the power in
N-1 conductors.
• For example, in a 4-wire, 3-phase system
we need to measure the power in 3
circuits.
Slide 18
Three Phase Power
Blondel’s Theorem
• If a meter installation meets Blondel’s
Theorem then we will get accurate power
measurements under all circumstances.
• If a metering system does not meet
Blondel’s Theorem then we will only get
accurate measurements if certain
assumptions are met.
Slide 19
Blondel’s Theorem
• Three wires
• Two voltage measurements with
one side common to Line 2
• Current measurements on lines
1 & 3.
This satisfies Blondel’s
Theorem.
Slide 20
Blondel’s Theorem
• Four wires
• Two voltage measurements to
neutral
• Current measurements on lines 1 &
3. How about line 2?
This DOES NOT satisfy Blondel’s
Theorem.
Slide 21
Blondel’s Theorem
• In the previous example:
– What are the “ASSUMPTIONS”?
– When do we get errors?
• What would the “Right Answer” be?
• What did we measure?
)cos()cos()cos( cccbbbaaasys IVIVIVP θθθ ++=
)]cos()cos([)]cos()cos([ bbcccbbaaasys IIVIIVP θθθθ −+−=
Slide 22
Blondel’s Theorem
• Phase B power would be:
– P = Vb Ib cosθ
• But we aren’t measuring Vb
• What we are measuring is:
– IbVacos(60- θ) + IbVccos(60+ θ)
• cos(α + β) = cos(α)cos(β) - sin(α)sin(β)
• cos(α - β) = cos(α)cos(β) + sin(α)sin(β)
• So
Slide 23
Blondel’s Theorem
• Pb = Ib Va cos(60- θ) + Ib Vc cos(60+ θ)
• Applying the trig identity
– IbVa(cos(60)cos(θ) + sin(60)sin(θ))
IbVc (cos(60)cos(θ) - sin(60)sin(θ))
– Ib(Va+Vc)0.5cos(θ) + Ib(Vc-Va) 0.866sin(θ)
• Assuming
– Assume Vb = Va = Vc
– And, they are exactly 120° apart
• Pb = Ib(2Vb)(0.5cosθ) = IbVbcosθ
Slide 24
Blondel’s Theorem
• If Va ≠ Vb ≠ Vc then the error is
• %Error =
-Ib{(Va+Vc)/(2Vb) - (Va-Vc) 0.866sin(θ)/(Vbcos(θ))
How big is this in reality? If
Va=117, Vb=120, Vc=119, PF=1 then E=-1.67%
Va=117, Vb=116, Vc=119, PF=.866 then E=-1.67%
Slide 25
Blondel’s Theorem
Condition % V % I Phase A Phase B
non-
Blondel
Imb Imb V φvan I φian V φvbn I φibn
% Err
All balanced 0 0 120 0 100 0 120 180 100 180 0.00%
Unbalanced voltages PF=1 18% 0% 108 0 100 0 132 180 100 180 0.00%
Unbalanced current PF=1 0% 18% 120 0 90 0 120 180 110 180 0.00%
Unbalanced V&I PF=1 5% 18% 117 0 90 0 123 180 110 180 -0.25%
Unbalanced V&I PF=1 8% 18% 110 0 90 0 120 180 110 180 -0.43%
Unbalanced V&I PF=1 8% 50% 110 0 50 0 120 180 100 180 -1.43%
Unbalanced V&I PF=1 18% 40% 108 0 75 0 132 180 125 180 -2.44%
Unbalanced voltages
PF≠1 PFa = PFb
18% 0% 108 0 100 30 132 180 100 210 0.00%
Unbalanced current
PF≠1 PFa = PFb
0% 18% 120 0 90 30 120 180 110 210 0.00%
Unbalanced V&I
PF≠1 PFa = PFb
18% 18% 108 0 90 30 132 180 110 210 -0.99%
Unbalanced V&I
PF≠1 PFa = PFb
18% 40% 108 0 75 30 132 180 125 210 -2.44%
Unbalanced voltages
PF≠1 PFa ≠ PFb
18% 0% 108 0 100 60 132 180 100 210 -2.61%
Unbalanced current
PF≠1 PFa ≠ PFb
0% 18% 120 0 90 60 120 180 110 210 0.00%
Unbalanced V&I
PF≠1 PFa ≠ PFb
18% 18% 108 0 90 60 132 180 110 210 -3.46%
Unbalanced V&I
PF≠1 PFa ≠ PFb
18% 40% 108 0 75 60 132 180 125 210 -4.63%
Power Measurements Handbook
Slide 26
Site Verification: Why should we invest our
limited meter service resources here
• These customers represent a
disproportionately large amount of the overall
revenue for every utility in North America.
• For some utilities the ten percent of their
customers who have transformer rated
metering services can represent over 70% of
their overall revenue.
• While these numbers will vary from utility to
utility the basic premise should be the same
for all utilities regarding where Meter Services
should focus their efforts
• This is perhaps one of the larger benefits that
AMI can provide for our Utilities – more time
to spend on C&I metering and less on
residential
Easy Answer: Money.
Slide 27
Potential list of tasks to be completed during a Site
Veriification of a Transformer Rated Metering SIte
• Double check the meter number, the location the test result and the meter record
• Perform a visual safety inspection of the site. This includes utility and customer equipment. Things
to look for include intact down ground on pole, properly attached enclosure, unwanted voltage on
enclosure, proper trimming and site tidiness (absence of discarded seals, etc.)
• Visually inspect for energy diversions (intentional and not). This includes broken or missing wires,
jumpers, open test switch, unconnected wires and foreign objects on meters or other metering
equipment. Broken or missing wires can seriously cause the under measurement of energy. A
simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the registration on either 3
element or 2 element metering, respectively.
• Visually check lightning arrestors and transformers for damage or leaks.
• Check for proper grounding and bonding of metering equipment. Poor grounding and bonding
practices may result in inaccurate measurements that go undetected for long periods of time.
Implementing a single point ground policy and practice can reduce or eliminate this type of issue.
• Burden test CTs and voltage check PTs.
Slide 28
Site Verification Checklist (cont)
• Verify service voltage. Stuck regulator or seasonal capacitor can impact service voltage.
• Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires,
loose connections, etc.
• Confirm we have a Blondel compliant metering set up
• Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs not cross
wired. Be sure CTs are grounded in one location (test switch) only.
• Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps
using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage).
• Check rotation by closing in one phase at a time at the test switch and observing the phase meter for
forward rotation. If forward rotation is not observed measurements may be significantly impacted as
the phases are most likely cancelling each other out.
• Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing
compensation (line and/or transformer losses) the compensation should be verified either through
direct testing at the site or by examining recorded pulse data.
• Loss compensation is generally a very small percentage of the overall measurement and would not
be caught under utilities normal high/low checks. However, the small percentages when applied to
large loads or generation can really add up overtime. Billing adjustments can easily be in the $million
range if not caught early.
Slide 29
Site Verification Checklist (cont)
• Verify metering vectors. Traditionally this has been done using instruments such as a circuit
analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and
values using meter manufacturer software or meter displays. Many of these desired values are
programmed into the meters Alternate/Utility display. Examining these values can provide much
information about the metering integrity. It may also assist in determining if unbalanced loads are
present and if CTs are sized properly. The vendor software generally has the ability to capture both
diagnostic and vector information electronically. These electronic records should be kept in the
meter shop for future comparisons.
• If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for
totalization they also should be verified vs. the known load on the meter. If present test/inspect
isolation relays/pulse splitters for things like blown fuses to ensure they are operating properly.
• Verify meter information including meter multiplier, serial number, dials/decimals, Mp, Ke, Primary
Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on
measured/reported values.
• Verify CT shunts are all opened.
• Look for signs of excessive heat on the meter base e.g.
melted plastic or discoloration related to heat
Slide 30
Periodic Site Inspections…..
….Can Discover or Prevent:
•Billing Errors
•Bad Metering set-up
•Detect Current Diversion
•Identify Potential Safety Issues
•Metering Issues (issues not
related to meter accuracy)
•AMR/AMI Communications Issues
•The need for Unscheduled Truck Rolls
due to Undetected Field Related Issues
•Discrepancies between what is believed to
be at a given site versus the actual setup
and equipment at the site
Slide 31
Questions and Discussion
Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
Tom.Lawton@tescometering.com
Cell: 215-688-0298
This presentation can also be found under Meter Conferences
and Schools on the TESCO web site: www.tesco-advent.com

More Related Content

PPT
Transformer Rated Metering Site Verification
PPT
Transformer Rated Metering
PPT
Transformer Rated Metering Site Verification
PPT
Transformer Rated Metering 09.27.17
PPT
Introduction to Transformer Rated Metering
PPT
Burden Testing, Theory, and Practice
PPTX
Introduction to CTs and PTs
PDF
TESCO Tuesday: Harmonics
Transformer Rated Metering Site Verification
Transformer Rated Metering
Transformer Rated Metering Site Verification
Transformer Rated Metering 09.27.17
Introduction to Transformer Rated Metering
Burden Testing, Theory, and Practice
Introduction to CTs and PTs
TESCO Tuesday: Harmonics

What's hot (20)

PPT
Site Verification for Self-Contained Hot Socket Detection
PPTX
Introduction to Transformer Rated Metering
PDF
TESCO Tuesday: Ratio, Burden and Admittance
PPTX
TESCO Tuesday: Transformer-Rated & Self-Contained Metering Fundamentals
PPTX
Introduction to CTs and PTs
PPTX
Meter Forms: Wiring and Uses
PPT
TESCO Tuesday: Test Switch Operation & Accessories
PPTX
CT Testing: Theory and Practice
PPTX
Ratio, Burden, and Admittance Testing
PPTX
Hands-On Transformer Rated Polyphase Meter Testing
PPTX
Advanced Polyphase Metering
PDF
TESCO Tuesday: CT Testing: Theory and Practice
PPTX
21st Century Power Measurements
PPTX
Communicating to Your Meters
DOCX
LAB report basic dc meter design
PPT
PPTX
Introduction to Self-Contained Metering
PPTX
Electronics measurements and instrumentation basics
PPTX
Introduction to Transformer Rated Metering
PPTX
Theory of AC and DC Meter Testing
Site Verification for Self-Contained Hot Socket Detection
Introduction to Transformer Rated Metering
TESCO Tuesday: Ratio, Burden and Admittance
TESCO Tuesday: Transformer-Rated & Self-Contained Metering Fundamentals
Introduction to CTs and PTs
Meter Forms: Wiring and Uses
TESCO Tuesday: Test Switch Operation & Accessories
CT Testing: Theory and Practice
Ratio, Burden, and Admittance Testing
Hands-On Transformer Rated Polyphase Meter Testing
Advanced Polyphase Metering
TESCO Tuesday: CT Testing: Theory and Practice
21st Century Power Measurements
Communicating to Your Meters
LAB report basic dc meter design
Introduction to Self-Contained Metering
Electronics measurements and instrumentation basics
Introduction to Transformer Rated Metering
Theory of AC and DC Meter Testing
Ad

Similar to Introduction to Transformer Rated Metering (20)

PPT
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
PPTX
PPTX
PPT
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
PDF
TESCO Tuesday: Metering Testing by Form
PPT
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
PPT
Instrument Transformer Testing
PPT
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
PDF
TESCO Tuesday: Meter Testing in the Field
PPT
Instrument Transformer Testing in the Shop and Field
PPTX
Introduction to Instrument Transformers
PPTX
Verifying Transformer Rated Service Installations
PPTX
PPTX
Intro to Polyphase Metering - Tom Lawton_5-3-2023.pptx
PPT
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
PPTX
PDF
Power transformer maintenance
PDF
Power transformer maintenance
PPTX
CT Testing - Theory and Practice
PPT
Site Verification - Protocols & Tools for Complex Metering Installations
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
TESCO Tuesday: Metering Testing by Form
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
TESCO Tuesday: Meter Testing in the Field
Instrument Transformer Testing in the Shop and Field
Introduction to Instrument Transformers
Verifying Transformer Rated Service Installations
Intro to Polyphase Metering - Tom Lawton_5-3-2023.pptx
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Power transformer maintenance
Power transformer maintenance
CT Testing - Theory and Practice
Site Verification - Protocols & Tools for Complex Metering Installations
Ad

Recently uploaded (20)

PDF
Univ-Connecticut-ChatGPT-Presentaion.pdf
PDF
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
PDF
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
PDF
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
PPTX
The various Industrial Revolutions .pptx
PPTX
1. Introduction to Computer Programming.pptx
PDF
Assigned Numbers - 2025 - Bluetooth® Document
PPTX
Final SEM Unit 1 for mit wpu at pune .pptx
PPTX
Tartificialntelligence_presentation.pptx
PDF
A contest of sentiment analysis: k-nearest neighbor versus neural network
PPTX
OMC Textile Division Presentation 2021.pptx
PPTX
TLE Review Electricity (Electricity).pptx
PDF
Getting Started with Data Integration: FME Form 101
PDF
NewMind AI Weekly Chronicles - August'25-Week II
PPTX
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
PDF
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf
PDF
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
PPT
What is a Computer? Input Devices /output devices
PDF
STKI Israel Market Study 2025 version august
PDF
gpt5_lecture_notes_comprehensive_20250812015547.pdf
Univ-Connecticut-ChatGPT-Presentaion.pdf
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
The various Industrial Revolutions .pptx
1. Introduction to Computer Programming.pptx
Assigned Numbers - 2025 - Bluetooth® Document
Final SEM Unit 1 for mit wpu at pune .pptx
Tartificialntelligence_presentation.pptx
A contest of sentiment analysis: k-nearest neighbor versus neural network
OMC Textile Division Presentation 2021.pptx
TLE Review Electricity (Electricity).pptx
Getting Started with Data Integration: FME Form 101
NewMind AI Weekly Chronicles - August'25-Week II
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
What is a Computer? Input Devices /output devices
STKI Israel Market Study 2025 version august
gpt5_lecture_notes_comprehensive_20250812015547.pdf

Introduction to Transformer Rated Metering

  • 1. Slide 1 10/02/2012 Slide 1 Introduction to Transformer Rated Metering Prepared by Tom Lawton,TESCO For Southeastern Electricity Metering Association (SEMA) Tuesday, November 7, 2017 10:15 a.m.
  • 2. Slide 2 Topics we will be covering • The Basics- Differences Between Self Contained and Transformer or Instrument Rated Meter Sites • Transformer Rated Meter Forms • Test Switches and CT’s • Blondel’s Theorem and why this matters to us in metering • Meter Accuracy Testing in the Field • Checking the Health of your CT’s and PT’s • Site Verification and not just meter testing
  • 3. Slide 3 Self Contained Metering •Typically found in residential metering •Meters are capable of handling the direct incoming amperage •Meter is connected directly to the load being measured •Meter is part of the circuit •When the meter is removed from the socket, power to the customer is interrupted
  • 4. Slide 4 Transformer Rated Metering • Meter measures scaled down representation of the load. • Scaling is accomplished by the use of external current transformers (CTs) and sometimes voltage transformers or PTs). • The meter is NOT part of the circuit • When the meter is removed from the socket, power to the customer is not effected.
  • 5. Slide 5 9S Meter Installation with 400:5 CT’s 400A 400A 400A LOAD 5A 5A 5A SOURCE PHASE A PHASE B PHASE C The Basic Components
  • 6. Slide 6 Typical Connections Typical Connections for Common Transformer (Instrument) Rated Meter Forms
  • 7. Slide 7 TESCO/Georgia Power 2017 Caribbean Meter School Fundamentals of Polyphase Field Meter Testing and Site Verification  Full Load  Light Load  Power Factor Meter Accuracy Testing Meter Accuracy Testing in a Nutshell
  • 8. Slide 8 The Importance of CT Testing in the Field • One transformer in three wired backwards will give the customer a bill of 1/3rd the actual bill. • One broken wire to a single transformer will give the customer a bill of 2/3rd the actual bill • One dual ratio transformer inappropriately marked in the billing system as 400:5 instead of 800:5 provides a bill that is ½ of the actual bill. And the inverse will give a bill double of what should have been sent. Both are lose-lose situations for the utility.
  • 9. Slide 9 The Importance of CT Testing in the Field (cont) •Cross Phasing (wiring errors) •Loose or Corroded Connections •CT Mounted Backwards •CT’s with Shorted Turns •Wrong Selection of Dual Ratio CT •Detect Magnetized CT’s •Burden Failure in Secondary Circuit •Open or Shorted Secondary •Mislabeled CT’s •Ensures all Shorting Blocks have been Removed
  • 10. Slide 10 Testing at Transformer Rated Sites Meter Accuracy Full Load Light Load Power Factor CT Health Burden Testing Ratio Testing Admittance Testing Site Verification
  • 11. Slide 11 Fundamentals of Polyphase Field Meter Testing and Site Verification Functionality with Burden Present on the Secondary Loop PHASE A • Some burden will always be present – junctions, meter coils, test switches, cables, etc. • CT’s must be able to maintain an accurate ratio with burden on the secondary.
  • 12. Slide 12 Fundamentals of Polyphase Field Meter Testing and Site Verification Functionality with Burden Present on the Secondary Loop Example Burden Spec: 0.3% @ B0.1, B0.2, B0.5 or There should be less than the 0.3% change in secondary current from initial (“0” burden) reading, when up to 0.5Ohms of burden is applied Fundamentals of Polyphase Field Meter Testing and Site Verification
  • 13. Slide 13 Fundamentals of Polyphase Field Meter Testing and Site Verification Current Transformers Conceptual Rtepresentation Real, with core losses Ideal. No losses
  • 14. Slide 14 Fundamentals of Polyphase Field Meter Testing and Site Verification Functionality with Burden Present on the Secondary Loop 0.3% @ B0.1, B0.2, B0.5 0.0000 1.0000 2.0000 3.0000 4.0000 5.0000 6.0000 0 2 4 6 8 Initial Reading = 5Amps 0.3% x 5A = 0.015A 5A – 0.015 = 4.985A Burden Reading 0 5.0000 0.1 4.9999 0.2 4.9950 0.5 4.9900 1 4.9800 2 4.9500 4 4.0000 8 0.8000
  • 15. Slide 15 Ratio of Primary Current to Secondary Current PHASE A SOURCE LOAD 400A 400A 400A 5A5A Calculate Ratio Fundamentals of Polyphase Field Meter Testing and Site Verification
  • 16. Slide 16 Three Phase Power Blondel’s Theorem The theory of polyphase watthour metering was first set forth on a scientific basis in 1893 by Andre E. Blondel, engineer and mathematician. His theorem applies to the measurement of real power in a polyphase system of any number of wires. The theorem is as follows: - If energy is supplied to any system of conductors through N wires, the total power in the system is given by the algebraic sum of the readings of N wattmeters, so arranged that each of the N wires contains one current coil, the corresponding voltage coil being connected between that wire and some common point. If this common point is on one of the N wires, the measurement may be made by the use of N-1 wattmeters.
  • 17. Slide 17 Three Phase Power Blondel’s Theorem • Simply – We can measure the power in a N wire system by measuring the power in N-1 conductors. • For example, in a 4-wire, 3-phase system we need to measure the power in 3 circuits.
  • 18. Slide 18 Three Phase Power Blondel’s Theorem • If a meter installation meets Blondel’s Theorem then we will get accurate power measurements under all circumstances. • If a metering system does not meet Blondel’s Theorem then we will only get accurate measurements if certain assumptions are met.
  • 19. Slide 19 Blondel’s Theorem • Three wires • Two voltage measurements with one side common to Line 2 • Current measurements on lines 1 & 3. This satisfies Blondel’s Theorem.
  • 20. Slide 20 Blondel’s Theorem • Four wires • Two voltage measurements to neutral • Current measurements on lines 1 & 3. How about line 2? This DOES NOT satisfy Blondel’s Theorem.
  • 21. Slide 21 Blondel’s Theorem • In the previous example: – What are the “ASSUMPTIONS”? – When do we get errors? • What would the “Right Answer” be? • What did we measure? )cos()cos()cos( cccbbbaaasys IVIVIVP θθθ ++= )]cos()cos([)]cos()cos([ bbcccbbaaasys IIVIIVP θθθθ −+−=
  • 22. Slide 22 Blondel’s Theorem • Phase B power would be: – P = Vb Ib cosθ • But we aren’t measuring Vb • What we are measuring is: – IbVacos(60- θ) + IbVccos(60+ θ) • cos(α + β) = cos(α)cos(β) - sin(α)sin(β) • cos(α - β) = cos(α)cos(β) + sin(α)sin(β) • So
  • 23. Slide 23 Blondel’s Theorem • Pb = Ib Va cos(60- θ) + Ib Vc cos(60+ θ) • Applying the trig identity – IbVa(cos(60)cos(θ) + sin(60)sin(θ)) IbVc (cos(60)cos(θ) - sin(60)sin(θ)) – Ib(Va+Vc)0.5cos(θ) + Ib(Vc-Va) 0.866sin(θ) • Assuming – Assume Vb = Va = Vc – And, they are exactly 120° apart • Pb = Ib(2Vb)(0.5cosθ) = IbVbcosθ
  • 24. Slide 24 Blondel’s Theorem • If Va ≠ Vb ≠ Vc then the error is • %Error = -Ib{(Va+Vc)/(2Vb) - (Va-Vc) 0.866sin(θ)/(Vbcos(θ)) How big is this in reality? If Va=117, Vb=120, Vc=119, PF=1 then E=-1.67% Va=117, Vb=116, Vc=119, PF=.866 then E=-1.67%
  • 25. Slide 25 Blondel’s Theorem Condition % V % I Phase A Phase B non- Blondel Imb Imb V φvan I φian V φvbn I φibn % Err All balanced 0 0 120 0 100 0 120 180 100 180 0.00% Unbalanced voltages PF=1 18% 0% 108 0 100 0 132 180 100 180 0.00% Unbalanced current PF=1 0% 18% 120 0 90 0 120 180 110 180 0.00% Unbalanced V&I PF=1 5% 18% 117 0 90 0 123 180 110 180 -0.25% Unbalanced V&I PF=1 8% 18% 110 0 90 0 120 180 110 180 -0.43% Unbalanced V&I PF=1 8% 50% 110 0 50 0 120 180 100 180 -1.43% Unbalanced V&I PF=1 18% 40% 108 0 75 0 132 180 125 180 -2.44% Unbalanced voltages PF≠1 PFa = PFb 18% 0% 108 0 100 30 132 180 100 210 0.00% Unbalanced current PF≠1 PFa = PFb 0% 18% 120 0 90 30 120 180 110 210 0.00% Unbalanced V&I PF≠1 PFa = PFb 18% 18% 108 0 90 30 132 180 110 210 -0.99% Unbalanced V&I PF≠1 PFa = PFb 18% 40% 108 0 75 30 132 180 125 210 -2.44% Unbalanced voltages PF≠1 PFa ≠ PFb 18% 0% 108 0 100 60 132 180 100 210 -2.61% Unbalanced current PF≠1 PFa ≠ PFb 0% 18% 120 0 90 60 120 180 110 210 0.00% Unbalanced V&I PF≠1 PFa ≠ PFb 18% 18% 108 0 90 60 132 180 110 210 -3.46% Unbalanced V&I PF≠1 PFa ≠ PFb 18% 40% 108 0 75 60 132 180 125 210 -4.63% Power Measurements Handbook
  • 26. Slide 26 Site Verification: Why should we invest our limited meter service resources here • These customers represent a disproportionately large amount of the overall revenue for every utility in North America. • For some utilities the ten percent of their customers who have transformer rated metering services can represent over 70% of their overall revenue. • While these numbers will vary from utility to utility the basic premise should be the same for all utilities regarding where Meter Services should focus their efforts • This is perhaps one of the larger benefits that AMI can provide for our Utilities – more time to spend on C&I metering and less on residential Easy Answer: Money.
  • 27. Slide 27 Potential list of tasks to be completed during a Site Veriification of a Transformer Rated Metering SIte • Double check the meter number, the location the test result and the meter record • Perform a visual safety inspection of the site. This includes utility and customer equipment. Things to look for include intact down ground on pole, properly attached enclosure, unwanted voltage on enclosure, proper trimming and site tidiness (absence of discarded seals, etc.) • Visually inspect for energy diversions (intentional and not). This includes broken or missing wires, jumpers, open test switch, unconnected wires and foreign objects on meters or other metering equipment. Broken or missing wires can seriously cause the under measurement of energy. A simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the registration on either 3 element or 2 element metering, respectively. • Visually check lightning arrestors and transformers for damage or leaks. • Check for proper grounding and bonding of metering equipment. Poor grounding and bonding practices may result in inaccurate measurements that go undetected for long periods of time. Implementing a single point ground policy and practice can reduce or eliminate this type of issue. • Burden test CTs and voltage check PTs.
  • 28. Slide 28 Site Verification Checklist (cont) • Verify service voltage. Stuck regulator or seasonal capacitor can impact service voltage. • Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires, loose connections, etc. • Confirm we have a Blondel compliant metering set up • Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs not cross wired. Be sure CTs are grounded in one location (test switch) only. • Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage). • Check rotation by closing in one phase at a time at the test switch and observing the phase meter for forward rotation. If forward rotation is not observed measurements may be significantly impacted as the phases are most likely cancelling each other out. • Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing compensation (line and/or transformer losses) the compensation should be verified either through direct testing at the site or by examining recorded pulse data. • Loss compensation is generally a very small percentage of the overall measurement and would not be caught under utilities normal high/low checks. However, the small percentages when applied to large loads or generation can really add up overtime. Billing adjustments can easily be in the $million range if not caught early.
  • 29. Slide 29 Site Verification Checklist (cont) • Verify metering vectors. Traditionally this has been done using instruments such as a circuit analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and values using meter manufacturer software or meter displays. Many of these desired values are programmed into the meters Alternate/Utility display. Examining these values can provide much information about the metering integrity. It may also assist in determining if unbalanced loads are present and if CTs are sized properly. The vendor software generally has the ability to capture both diagnostic and vector information electronically. These electronic records should be kept in the meter shop for future comparisons. • If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for totalization they also should be verified vs. the known load on the meter. If present test/inspect isolation relays/pulse splitters for things like blown fuses to ensure they are operating properly. • Verify meter information including meter multiplier, serial number, dials/decimals, Mp, Ke, Primary Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on measured/reported values. • Verify CT shunts are all opened. • Look for signs of excessive heat on the meter base e.g. melted plastic or discoloration related to heat
  • 30. Slide 30 Periodic Site Inspections….. ….Can Discover or Prevent: •Billing Errors •Bad Metering set-up •Detect Current Diversion •Identify Potential Safety Issues •Metering Issues (issues not related to meter accuracy) •AMR/AMI Communications Issues •The need for Unscheduled Truck Rolls due to Undetected Field Related Issues •Discrepancies between what is believed to be at a given site versus the actual setup and equipment at the site
  • 31. Slide 31 Questions and Discussion Tom Lawton TESCO – The Eastern Specialty Company Bristol, PA Tom.Lawton@tescometering.com Cell: 215-688-0298 This presentation can also be found under Meter Conferences and Schools on the TESCO web site: www.tesco-advent.com