STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
GENERAL SAFETY
1. PERSONAL PROTECTIVE EQUIPMENT
2. EMERGENCY
In case of an emergency, stop the equipment by pressing the red emergency stop button (see picture).
All employees should be familiar with the location of the emergency stop buttons on the equipment they operate.
Scope: The purpose of the procedure is to illustrate how to SET-UP AND RUN the Eyelet Machine Safely
and Efficiently, while minimizing machine downtime during changeovers.
Emergency Stop
“E-Stop” Button
3.6mm 9.6mm
“SMALL” “LARGE” eyelets
Die sets and Drums are labelled “LARGE” &“SMALL”
SAFETY SENSOR AND GUARDING
Page 2 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
3 STEP SETUP OF MACHINE
1-Release spring, depress the track
switch and remove the eyelets from the
track
2-Remove the spring loaded clamp and drum
3-Quick release spring loaded clamp
5 MIN SETUP
CHANGEOVER
Quick Connect Drum
Page 3 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
Place the material flat onto the table
& align with the ruler and back stop
Adjust the back stop
position for depth
Easy Die changeover
2-OPERATION
SPRING LOADED WASHER ARM
Page 4 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
GOOD ROLLOVER QUALITY
Page 5 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
MATERIAL –EYELET IDENTIFICATION
COLOR CODED MATERIAL BINS FOR DIFFERENT SIZES
Page 6 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
3-TROUBLESHOOTING:
Page 7 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
Page 8 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
Page 9 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
FLYWHEELBRAKE HOOPPER DRUM
MECHANICAL TRACK
Page 10 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
Page 11 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
B-01 Pedal Support
B -02 Lower Treadle Rod
B -03 Connector
B -04 Upper Treadle Rod
B 05 Pedal
B -06 Frame
B -07 Pedal Bolt
B -08 Spacing Washer
B -09 Working Plate
B -10 Hollow Inner Screw
B -11 T-Sleeve
B -12 Die Set
B -13 Ring Nut
A-10 Motor Plate
A-14 Motor
A-15 Flywheel Cover
FINAL ASSEMBLY PARTS
Page 12 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
HOPPER COMPLETE SET EXPLODED VIEW
Page 13 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
Page 14 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
Page 15 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
SUGGESTED PREVENTATIVE MAINTENANCE FREQUENCY
Page 16 of 16
STANDARD OPERATING PROCEDURE
CUSTOM EYELET MACHINE 3/6/8MM
Created by : Julian Kalac Revision Level 1 Department PACKAGING
Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
SUGGESTED REGULAR MACHINE MAINTENANCE (MONTHLY)

More Related Content

PDF
Jishu Hozen or Autonomous Maintenance
PPT
010 bmw tpm management training
PPT
Tpmjishu
PPTX
TPM Overview and AM Workshop
PPTX
One Point Lesson (OPL) Basic presentation
PPTX
AUTONOMOUS MAINTENANCE
PPT
My machine camp
PPT
Assembly Line Balancing
Jishu Hozen or Autonomous Maintenance
010 bmw tpm management training
Tpmjishu
TPM Overview and AM Workshop
One Point Lesson (OPL) Basic presentation
AUTONOMOUS MAINTENANCE
My machine camp
Assembly Line Balancing

What's hot (20)

PDF
TPM for lean manufacturing chp4 step of “jlshu hozen “activities
PDF
Weekly welding machine checklist
PPTX
Training module 4 m change
PPTX
PPTX
Autonomous Maintenance (Jishu Hozen) by Ketan Kumar (Raavinnovate)
PPT
Plant maintenance
PDF
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
PPT
ODP
Autonomous maintenance ppt
PPTX
Root Cause Analysis and Accident Investigation
PPT
LOTO Training.ppt
PPTX
Total Productive Maintenance (Tpm) EVERTS 21Aug2018
PPTX
PPT
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
PPTX
Jishu hozen
PPTX
Poka yoke hindi
PDF
HSE Monthly Performance .pdf
PPTX
Change Management - 4 m change
PPT
SBS - SMED Training (Set Up Reduction)
PPTX
5S Training
TPM for lean manufacturing chp4 step of “jlshu hozen “activities
Weekly welding machine checklist
Training module 4 m change
Autonomous Maintenance (Jishu Hozen) by Ketan Kumar (Raavinnovate)
Plant maintenance
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
Autonomous maintenance ppt
Root Cause Analysis and Accident Investigation
LOTO Training.ppt
Total Productive Maintenance (Tpm) EVERTS 21Aug2018
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
Jishu hozen
Poka yoke hindi
HSE Monthly Performance .pdf
Change Management - 4 m change
SBS - SMED Training (Set Up Reduction)
5S Training
Ad

Similar to Custom Lean Eyelet machine SOP with 5 min changeover (11)

PPTX
Presentasi pekerjaan mekanikal elektrikal
PDF
John deere tractors 5065 e tractor (north america) service repair manual (tm9...
PDF
John deere tractors 5055 e tractor (north america) service repair manual (tm9...
PDF
John deere tractors 5065 e tractor (north america) service repair manual (tm9...
PDF
John deere tractors 5075 e tractor (north america) service repair manual (tm9...
PDF
John deere tractors 5075 e tractor (north america) service repair manual (tm9...
PDF
Jupa_SolidCitric_products
PPTX
Forward revrese pressure not ok
PPTX
LTAS-FLM-PowerPoint 2011 04_21.pptx
PDF
IRJET- Inbuilt Motor Operated Screw Jack and Automatic Tyre Inflation System
PDF
Jcb 801 gravemaster mini excavator service repair manual
Presentasi pekerjaan mekanikal elektrikal
John deere tractors 5065 e tractor (north america) service repair manual (tm9...
John deere tractors 5055 e tractor (north america) service repair manual (tm9...
John deere tractors 5065 e tractor (north america) service repair manual (tm9...
John deere tractors 5075 e tractor (north america) service repair manual (tm9...
John deere tractors 5075 e tractor (north america) service repair manual (tm9...
Jupa_SolidCitric_products
Forward revrese pressure not ok
LTAS-FLM-PowerPoint 2011 04_21.pptx
IRJET- Inbuilt Motor Operated Screw Jack and Automatic Tyre Inflation System
Jcb 801 gravemaster mini excavator service repair manual
Ad

More from Julian Kalac P.Eng (20)

PDF
2025 JULIAN KALAC Lean Six Sigma improvements in SDLC, IT , Audit and FINANCE...
PDF
2025- LEAN 6 SIGMA IMPROVEMENTS MFG SCM WAREHOUSE DISTRIBUTION.pdf
PDF
CTC Vacation Forfeit Purchase Po;licy.pdf
PDF
6-SIGMA ENGINEERING DEPLOYMENT PROGRAM.pdf
PDF
2023-AI POWERED KPI DASHBOARD Julian Kalac.pdf
PDF
0-FINAL ARB Funding Compliance Report FINAL - Copy.pdf
PDF
2023-Overview of-LEAN basics in Software Development.pdf
PDF
2025 Gen-AI inventive solution Automated SOC report processing by Julian Ka...
PDF
2023 Julian Kalac CTC ITGC User Access Testing Improvement.pdf
PDF
Design tolerances using Six Sigma Statistical tolerances
PDF
SIX SIGMA IMPROVES OEE performance from 20% to 39.1%
PDF
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
PDF
Batch & Queue vs Lean Continuous Flow
PDF
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
PDF
Design for Six Sigma in Automotive
PDF
1000 Ton Transfer Press Risk Assessment
PDF
Lean logistics
PDF
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PDF
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
PDF
Live wire testing lock out tag out safe work procedure
2025 JULIAN KALAC Lean Six Sigma improvements in SDLC, IT , Audit and FINANCE...
2025- LEAN 6 SIGMA IMPROVEMENTS MFG SCM WAREHOUSE DISTRIBUTION.pdf
CTC Vacation Forfeit Purchase Po;licy.pdf
6-SIGMA ENGINEERING DEPLOYMENT PROGRAM.pdf
2023-AI POWERED KPI DASHBOARD Julian Kalac.pdf
0-FINAL ARB Funding Compliance Report FINAL - Copy.pdf
2023-Overview of-LEAN basics in Software Development.pdf
2025 Gen-AI inventive solution Automated SOC report processing by Julian Ka...
2023 Julian Kalac CTC ITGC User Access Testing Improvement.pdf
Design tolerances using Six Sigma Statistical tolerances
SIX SIGMA IMPROVES OEE performance from 20% to 39.1%
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
Batch & Queue vs Lean Continuous Flow
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
Design for Six Sigma in Automotive
1000 Ton Transfer Press Risk Assessment
Lean logistics
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
Live wire testing lock out tag out safe work procedure

Recently uploaded (20)

PPT
Project quality management in manufacturing
PPTX
Geodesy 1.pptx...............................................
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
UNIT 4 Total Quality Management .pptx
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
web development for engineering and engineering
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
DOCX
573137875-Attendance-Management-System-original
PPT
Mechanical Engineering MATERIALS Selection
PPTX
additive manufacturing of ss316l using mig welding
PDF
composite construction of structures.pdf
PPTX
Construction Project Organization Group 2.pptx
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
CH1 Production IntroductoryConcepts.pptx
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PPTX
Lecture Notes Electrical Wiring System Components
PPT
introduction to datamining and warehousing
PPTX
Sustainable Sites - Green Building Construction
Project quality management in manufacturing
Geodesy 1.pptx...............................................
Safety Seminar civil to be ensured for safe working.
UNIT 4 Total Quality Management .pptx
Automation-in-Manufacturing-Chapter-Introduction.pdf
CYBER-CRIMES AND SECURITY A guide to understanding
web development for engineering and engineering
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
573137875-Attendance-Management-System-original
Mechanical Engineering MATERIALS Selection
additive manufacturing of ss316l using mig welding
composite construction of structures.pdf
Construction Project Organization Group 2.pptx
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
CH1 Production IntroductoryConcepts.pptx
R24 SURVEYING LAB MANUAL for civil enggi
Lecture Notes Electrical Wiring System Components
introduction to datamining and warehousing
Sustainable Sites - Green Building Construction

Custom Lean Eyelet machine SOP with 5 min changeover

  • 1. Page 1 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac GENERAL SAFETY 1. PERSONAL PROTECTIVE EQUIPMENT 2. EMERGENCY In case of an emergency, stop the equipment by pressing the red emergency stop button (see picture). All employees should be familiar with the location of the emergency stop buttons on the equipment they operate. Scope: The purpose of the procedure is to illustrate how to SET-UP AND RUN the Eyelet Machine Safely and Efficiently, while minimizing machine downtime during changeovers. Emergency Stop “E-Stop” Button 3.6mm 9.6mm “SMALL” “LARGE” eyelets Die sets and Drums are labelled “LARGE” &“SMALL” SAFETY SENSOR AND GUARDING
  • 2. Page 2 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac 3 STEP SETUP OF MACHINE 1-Release spring, depress the track switch and remove the eyelets from the track 2-Remove the spring loaded clamp and drum 3-Quick release spring loaded clamp 5 MIN SETUP CHANGEOVER Quick Connect Drum
  • 3. Page 3 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac Place the material flat onto the table & align with the ruler and back stop Adjust the back stop position for depth Easy Die changeover 2-OPERATION SPRING LOADED WASHER ARM
  • 4. Page 4 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac GOOD ROLLOVER QUALITY
  • 5. Page 5 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac MATERIAL –EYELET IDENTIFICATION COLOR CODED MATERIAL BINS FOR DIFFERENT SIZES
  • 6. Page 6 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac 3-TROUBLESHOOTING:
  • 7. Page 7 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
  • 8. Page 8 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
  • 9. Page 9 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac FLYWHEELBRAKE HOOPPER DRUM MECHANICAL TRACK
  • 10. Page 10 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
  • 11. Page 11 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac B-01 Pedal Support B -02 Lower Treadle Rod B -03 Connector B -04 Upper Treadle Rod B 05 Pedal B -06 Frame B -07 Pedal Bolt B -08 Spacing Washer B -09 Working Plate B -10 Hollow Inner Screw B -11 T-Sleeve B -12 Die Set B -13 Ring Nut A-10 Motor Plate A-14 Motor A-15 Flywheel Cover FINAL ASSEMBLY PARTS
  • 12. Page 12 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac HOPPER COMPLETE SET EXPLODED VIEW
  • 13. Page 13 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
  • 14. Page 14 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac
  • 15. Page 15 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac SUGGESTED PREVENTATIVE MAINTENANCE FREQUENCY
  • 16. Page 16 of 16 STANDARD OPERATING PROCEDURE CUSTOM EYELET MACHINE 3/6/8MM Created by : Julian Kalac Revision Level 1 Department PACKAGING Date Created July 13, 2015 Revision Date: N/A P.Eng Julian Kalac SUGGESTED REGULAR MACHINE MAINTENANCE (MONTHLY)