A Study on Risk Assessment in Construction Projects K. Jayasudha1, Dr. B. Vidivelli2 1 Research Scholar, Department of Civil and Structural Engineering, Annamalai University, Chidambaram. 2 Professor, Department of Civil and Structural Engineering, Annamalai University, Chidambaram 
I. INTRODUCTION 
Construction companies and firms, such as the government, consultants and contractors, normally face different kinds of risks (e.g., environmental, physical, political, social and economic risks) during construction. However, most of them do not predict risks when they are considering bids and tenders. Construction risk is generally perceived as events that influence project objectives, i.e., cost, time and quality. In project management terms, the most serious effects of risk can be summarised as follows: 1. Failure to keep within the cost estimate. 2. Failure to achieve the required completion date. 3. Failure to achieve the required quality and operational requirements. This study aims to better understand the risk identification process and other risk processes. Risk identification is the first process in risk management. Therefore, this study focuses on risk identification because it is important to know how the players in the construction industry handle risk identification. Without having any perspective on or approach for risk identification, construction participants cannot make appropriate decisions in other risk management processes. This study evaluates risk identification by better understanding the processes and guidelines related to the risks in large and infrastructure construction projects, so that project risk management can be more effective. It has already been recognised that a clear understanding of the risks born by each participant leads to better risk allocation. The objective of this study is to find means of identifying risk management and other processes that can be utilised and to make new suggestions on the use of these risk management methods. It is of particular interest to find the means to manage risks that are the most effectively managed with the co-operation of several project participants. II. Methodology To achieve the objectives of this research, questionnaires were deemed to be the most effective tool for gathering information. These questions helped identify any projects that should definitely not be undertaken by the parties and those which, although risky, should be examined further after a more rigorous examination of the potential sources of risk. The questionnaire was designed based on the knowledge of government, consultant, or contractor in large or infrastructure construction projects; the questions were meant to identify their method of risk identification and possible effects of those risks. The general methodology of this study relies largely on the survey questionnaire which will be collected from the various multi project construction contractors and project manager of different sizes by mail 
Abstract: Risks are very common in construction sector. Risk management includes identifying risks, assessing risks either quantitatively or qualitatively, choosing the appropriate method for handling the risks, and then monitoring and documenting risks. By identifying risks in an early stage of planning and assessing their relative importance, project managers can identify methods used to reduce risks and allocate the best people to mitigate them. Thus, this research focuses on risk identification, as opposed to other processes of risk management. "Brain-storming sessions" is the most popular method used frequently to identify the risks in projects as deduced from a questionnaire survey from participants in large construction projects. Time and cost management need to be fully integrated with the identification process. Time constraints and project managers with sufficient experience are critical when identifying the level of risk for large and/or complex projects. The most considerable types of risk in construction projects are financial risks, construction risks, and demand or product risks. 
Keywords: Risk, Risk identification techniques, Risk management, and Construction Projects.
A Study on Risk Assessment in Construction Projects 
| IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss.9| Sept. 2014 | 21| 
or by personnel meeting. A thorough literature review was initially conducted to identify the risk factors that 
affect the performance of construction industry as a whole. This study has adopted the more general and broad 
definition of risk as presented by Shen et al (2001) on china's construction joint ventures and more risk factors 
from other literature. Also some interviews with industrial practitioners were conducted to produce to check 
of questionnaires. 
III. QUESTIONNAIRE STRUCTURE AND DESIGN 
. The questionnaire was tested with a pilot survey for clarity, ease of use, value of the information that 
could be gathered. The questionnaire survey is divided into two parts. The first part consists of general 
information like type of company, experience, value of their project etc., and the second part consists of the 
construction risk factors for evaluation. 
Risk factor for this study classified into eight categories, namely: financial risk, legal risk, 
management risk, market risk, policy & political risk, technical risk, environmental risk, social risk. 
The survey questionnaire survey is designed to probe the cross-sectional behavioral pattern of 
construction risks construction industry. The questionnaire was prepared for the pilot survey was formulated by 
seeing the relevant literatures in the area of construction risk. The interviewer was free to ask additional 
questions that focused on issues arising during the course of the interview. The freedom to follow the 
interviewee, to ask for clarifications, and to focus on the specify projects, risk practices and knowledge, made 
the interviews insightful 
3.1 Risk Rating 
A Likert scale of 1-5 was used in the questionnaire. A Likert scale is a type of psychometric response 
scale questionnaire, and is the most widely used scale in survey research. When responding to a Likert 
questionnaire item, respondents specify their level of agreement to a statement. The scale is named after Rensis 
Likert, who published a report describing its use. The respondents were required to indicate the relative 
critically/effectiveness of each of the probability of risk factors and their impact to the management. 
3.2 Design of Survey 
The respondents were requested to judge the significance or "expected loss" of each risk. There are many 
criteria that respondents may need to consider. One alternative approach adopted by previous researches is to 
consider two attributes for each risk: the probability level of risk occurrence, denoted by o; and the degree of 
impact or the level of loss if the risk occurs denoted by p. The same type of evaluation is followed in this study 
also. Therefore, risk significance, denoted as RS, can be described as the function of the two attributes RS=f 
(, ). 
By applying this approach, the respondents were asked to respond to the two attributes for each risk. For 
considering a, the respondents were required to judge the probability level of risk occurrence by selecting one 
from among five levels namely, very small, small, normal, large and very large. For considering p, the 
respondents were required to judge the degree of impact if the risk concerned occurs, by selecting one from 
among five grades namely, very low, low. and medium, high and very high. 
3.3 Analysis of Survey 
To assess the relative significance among risks, previous literatures study suggests establishing a risk 
significance index by calculating the significance score for each risk. For calculating the significance score is 
to multiply the probability of occurrence by the degree of impact Thus, the significance score of each risk 
assessed by each respondent can be obtained through the model 
i 
j 
i 
j 
i 
p S   
Where Si = significance score assessed by respondent j for risk i; a, = probability of occurrence of risk 
i, assessed by respondent j; and p, = degree of impact of risk i, assessed by respondent j. By averaging scores 
from all responses, it is possible to get an average significance score for each risk, and this average score is 
called the risk index score and is used to rank among all risks. The model for the calculation of risk index 
score can be written 
T 
S 
RS 
T 
i 
i 
j 
i 
 
 1
A Study on Risk Assessment in Construction Projects 
| IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss.9| Sept. 2014 | 22| 
Where RS1 = index score for risk i; and S1 = significance score assessed by respondent j for risk I and T=Total number of responses. To calculate S', the five scales for o and (3, this will be converted into numerical (Likert scale) scales. 3.4 Pilot Survey A pilot questionnaire survey and follow-up interviews with local contractors was conducted. The purpose was to identify the factors out of the 68 factors that applied overseas could also apply to the construction industry. The small number interviews and the structure of the questionnaire in die pilot study does not allow for statistical analysis. Responses to the interviews have been used to identify consistent themes, common practices, and insight provided by active and influential project participants that would provide additional guidance and assistance to the research team. The survey results formed the basis of modifying the questionnaire for the subsequent full-scale survey. The pilot study attempts to short-list locally relevant factors. The criteria for a shortlisting are that the chosen factors are relevant in the local construction industry. As a result, only important and relevant factors can be chosen for inclusion in the full-scale survey in the second phase research. IV. Risk Identification And Risk Identification Technique The risk identification phase as being either one of the most important stages within the risk management process, the risk identification phase into three categories. 1. The Risk identification conducted only by a risk analyst and based exclusively in his practice, knowledge and capacity. 2. The Risk identification was conducted through the interview of the risk analyst with one or many members of the project staff in order to analyze the reviewed data and the project life cycle based on the knowledge and expert of the people interviewed. 3. The Risk identification in which the risk analyst guides one or many work groups applying the risk identification techniques. 4.1 Risk Indentification Techniques 1. Brainstorming – An idea generation group technique is divided in two phases. (i) idea generation phase, in which participant generate as more ideas as possible (ii) idea selection phase, the ideas are filtered, remaining only those approved by the entire group 2. Delphi Technique – Delphi is a technique to obtain an opinion consensus about future events from a group of experts. It is supported by structured knowledge, experience and creativity from an expert 3. Interview/ Expert judgment – Unstructured, semi structured or structured interviews individually or collectively conducted with a set of experienced project members, specialist or project 4. Checklist – It consists of a list of item that are marked as yes or no , could be used by an individual project team members, a group or in an interview. 5. Influence Diagram – It is a graphical representation containing nodes representing the decision variables of a problem. A traditional influence diagram is formed by three types of nodes: utility, decision and informational. The causal relationship occurs between utility and chance nodes and represents a probabilistic dependence. 6. Flowchart – Graphical tool that shows the steps of a process. This technique is applied for a better comprehension of the risks or the elements interrelation 7. Cause-and-Effect Diagrams – These are also called Ishikawa diagrams or fishbone diagram, illustrate how various factor might be linked to potential problems or effects. The diagram is designed by listing the effect on the right sides and the causes on the left sides. There are categorized for each effect, and the main causes must be grouped according to these categories . V. Conclusions 
This paper is based on a literature review on the risk assessment methods. The risk assessments approaches are applied in various areas and the problems solve. It was found that the currently used methods for risk assessment are Brainstorming, checklist, Flowchart, Delphi method, Risk significant index method. Each method of risk assessment has their limitation therefore this paper attempt to formulate integrated risk assessment tools. It was observed that currently used risk assessment methods can be integrated into new approach that can aid the decision makers applying the risk assessment effectively. The specifications for
A Study on Risk Assessment in Construction Projects 
| IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss.9| Sept. 2014 | 23| 
identifying project risk that have been particularised for construction projects have been presented from diverse points of view (from government, consultants and contractors) and construction companies and firms that may be helping the process of dealing with the project in the planning and construction phases. The process can also be adapted to identify the level of risk for a particular project. The brain-storming sessions and analysis of historical data for similar projects were found to be the most preferred methods of risk identification in the construction industry. The risks associated with construction projects included financial risks (project funding problem), construction risks and demand/ product risks. These risks commonly prevent the completion of construction project objectives. REFERENCES [1] R.C.Walke et al. “An approach to risk quantification in construction projects” International Journal of Engineering Science and Technology Vol. 3 No. 9 September 2011 .pp 6846-6855. [2] L. Y. Shen,1 George W. C. Wu,2 and Catherine S. K. Ng3. Risk assessment for construction joint venture in chinaJournal of construction Engineering and management Vol. 127 No. 1 January/ February 2001 pp. 76-81. [3] Wenzhe Tang1; Maoshan Qiang2; Colin F. Duffield3; David M. Young4; and Youmei Lu5. Risk management in the Chinese construction industry. Journal of construction Engineering and Management ASCE/ DECEMBER 2007 [4] Dr Patrick. X.W. Zou1, Dr Guomin Zhang2 and Professor Jia-Yuan Wang3 1 and 2: Faculty of Built Environment, University of New South Wales, Sydney 2052, Australia;3: College of Architecture and Civil Engineering, Shenzhen University, Shenzhen, P.R. China. Identified Key Risks in Construction Projects: Life Cycle and Stake Holder Perspectives. [5] Akintoye A.S and MacLeod, M.J. (1997). Risk analysis and management in construction, International Journal of project Management. Vol 15, February 1997, pages 31-38. [6] Ossama A.Abdou (Asst.Prof. Dept. of Civil and Arch. Engg.Drexel University) Managing Construction Journal of Architectural Engineering, Vol 2, No.1 March 1996, pp. 3- 10. [7] Matins Claudia Garrido, Morano Cassia Andra Ruotolo, Fereira Miguel Luiz Riberio and Haddad Assed Naked. Risk Identification Techniques Knowledge and Application in the Brazilian Construction Vol. 2(11), pp. 242-252, November2011 [8] Chapman R.J. (2001) The Controlling Influences on Effective Risk Identification and Assessment for Construction Design Management, International Journal of Project Management. Vol 19.Issue 3, pp. 147-160. [9] Al-Bahar, J.F. and Crandall, K.C. (1990). Systematic risk management approach for construction project. Journal of Construction Engineering and Management, 116(3): 533–546. [10] Artto, K.A. (1999). Development of World-Class Practices in Project Companies. In The Future of Project Management, Project Management Institute Research Series. Newtown Square, PA: Project Management Institute (PMI), 127–137. [11] Kendrick, T. (2009). Identifying and Managing Project Risk: Essential Tools for Failure-Proofing Your Project. 2nd Edition. New York: AMACOM Div. American Management Association. [12] Project Management Institute. (2004). A Guide to the Project Management Body of Knowledge. Newtown Square, Pennsylvania: PMI.

More Related Content

PDF
IRJET- Projects in Constructions due to Inadequate Risk Management
PDF
Risk Management in Construction Project
PDF
Risk Management in High Rise Construction Projects: A Review
PDF
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
PDF
A study of various factors affecting risk management techniques in constructi...
PDF
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
PPT
“Construction Risk Management”
PPT
Construction project risk management
IRJET- Projects in Constructions due to Inadequate Risk Management
Risk Management in Construction Project
Risk Management in High Rise Construction Projects: A Review
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
A study of various factors affecting risk management techniques in constructi...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
“Construction Risk Management”
Construction project risk management

What's hot (20)

PDF
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
DOCX
2.11 risk management 1
PDF
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
PPT
043 Integrating Risk Management
PDF
Analysis, perception and aspects of risk management in the construction secto...
PDF
Establishing risk management factors for construction projects in iraq
PDF
IRJET- Risk Management using Primavera Software for Residential Sector
PPT
Risk Management
PDF
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
PDF
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
PDF
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
PDF
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
PDF
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
POTX
Risk and uncertainty in construction projects
PDF
Software Project Risk Management Practice in Oman
PPT
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
PDF
A Qualitative approach for analysing Causes and Effects of Construction Risks
PDF
IRJET- Risk Management in Residential Project by Primavera Software
PPTX
Project mngmnt risks3.2
PPT
Technical Risk Management
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
2.11 risk management 1
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
043 Integrating Risk Management
Analysis, perception and aspects of risk management in the construction secto...
Establishing risk management factors for construction projects in iraq
IRJET- Risk Management using Primavera Software for Residential Sector
Risk Management
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
Risk and uncertainty in construction projects
Software Project Risk Management Practice in Oman
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
A Qualitative approach for analysing Causes and Effects of Construction Risks
IRJET- Risk Management in Residential Project by Primavera Software
Project mngmnt risks3.2
Technical Risk Management
Ad

Viewers also liked (20)

PPT
Risk Assessment
PPT
Risk Assessment
PDF
Participatory mapping and LGU decision support tools for Disaster Risk Reduct...
PPTX
Disaster management
PDF
Evaluation of Mechanical Properties of Sintered Hot Upset Forged Square Cros...
PDF
Propabilistic Analysis of a Man-Machine System Operating Subject To Different...
PDF
Investigation of the Role of Bulkhead and Crack Stopper Strap in the Fail-Saf...
PDF
Ct3210321037
PDF
ANN Based Prediction Model as a Condition Monitoring Tool for Machine Tools
PDF
CFD Analysis of Heat Transfer and Flow Characteristics in A 3D Cubic Enclosure
PDF
Fatigue Analysis of Acetylene converter reactor
PDF
Pathogenic Bacteria in Corals from Veracruz Reef System National Park
PDF
A Study on Mathematical Statistics to Evaluate Relationship between Attributes
PDF
Application of Weighted Centroid Approach in Base Station Localization for Mi...
PDF
Energy Based Analysis of a Thermal Power Station for Energy Efficiency Improv...
PDF
Data Mining Techniques in Higher Education an Empirical Study for the Univer...
PDF
CNC PART PROGRAMMING AND COST ANALYSIS ON VERTICAL MACHINING CENTRE (VTC)
PDF
Ak2418751879
PDF
Fd2427822788
PDF
Cz3210711074
Risk Assessment
Risk Assessment
Participatory mapping and LGU decision support tools for Disaster Risk Reduct...
Disaster management
Evaluation of Mechanical Properties of Sintered Hot Upset Forged Square Cros...
Propabilistic Analysis of a Man-Machine System Operating Subject To Different...
Investigation of the Role of Bulkhead and Crack Stopper Strap in the Fail-Saf...
Ct3210321037
ANN Based Prediction Model as a Condition Monitoring Tool for Machine Tools
CFD Analysis of Heat Transfer and Flow Characteristics in A 3D Cubic Enclosure
Fatigue Analysis of Acetylene converter reactor
Pathogenic Bacteria in Corals from Veracruz Reef System National Park
A Study on Mathematical Statistics to Evaluate Relationship between Attributes
Application of Weighted Centroid Approach in Base Station Localization for Mi...
Energy Based Analysis of a Thermal Power Station for Energy Efficiency Improv...
Data Mining Techniques in Higher Education an Empirical Study for the Univer...
CNC PART PROGRAMMING AND COST ANALYSIS ON VERTICAL MACHINING CENTRE (VTC)
Ak2418751879
Fd2427822788
Cz3210711074
Ad

Similar to A Study on Risk Assessment in Construction Projects (20)

PDF
International Journal of Engineering Research and Development
PDF
Critical Factors Influencing to Management Risk in Construction Projects
PDF
10120140506004 2
PDF
10120140506004 2
PDF
B0363010015
PDF
J1303045360
PDF
Risk Severity Framework for a BOT Highway Project
PDF
Risk Management Appraisal - A tool for successful Infrastructure project
PDF
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
PDF
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
PPTX
Risk and Its Management in the Kuwait Construction Industry |2020
PDF
A fuzzy ahp model in risk ranking
PDF
A fuzzy ahp model in risk ranking
PDF
Risk Management in Medium Sized Commercial Buildings
PDF
The Identification of Risks and its Criticality in the Nigeria Construction I...
PDF
Risk Assessment for Building Construction Sites in Myanmar
PDF
Risk Management Methodologies in Construction Industries
PDF
IRJET - A Study on Identification of Risks at Various Phases of Road Const...
DOCX
RISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docx
PDF
IRJET-Qualitative Risk Analysis for Construction Projects
International Journal of Engineering Research and Development
Critical Factors Influencing to Management Risk in Construction Projects
10120140506004 2
10120140506004 2
B0363010015
J1303045360
Risk Severity Framework for a BOT Highway Project
Risk Management Appraisal - A tool for successful Infrastructure project
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
Risk and Its Management in the Kuwait Construction Industry |2020
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
Risk Management in Medium Sized Commercial Buildings
The Identification of Risks and its Criticality in the Nigeria Construction I...
Risk Assessment for Building Construction Sites in Myanmar
Risk Management Methodologies in Construction Industries
IRJET - A Study on Identification of Risks at Various Phases of Road Const...
RISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docx
IRJET-Qualitative Risk Analysis for Construction Projects

More from IJMER (20)

PDF
A Study on Translucent Concrete Product and Its Properties by Using Optical F...
PDF
Developing Cost Effective Automation for Cotton Seed Delinting
PDF
Study & Testing Of Bio-Composite Material Based On Munja Fibre
PDF
Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)
PDF
Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...
PDF
Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...
PDF
Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...
PDF
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...
PDF
Static Analysis of Go-Kart Chassis by Analytical and Solid Works Simulation
PDF
High Speed Effortless Bicycle
PDF
Integration of Struts & Spring & Hibernate for Enterprise Applications
PDF
Microcontroller Based Automatic Sprinkler Irrigation System
PDF
On some locally closed sets and spaces in Ideal Topological Spaces
PDF
Intrusion Detection and Forensics based on decision tree and Association rule...
PDF
Natural Language Ambiguity and its Effect on Machine Learning
PDF
Evolvea Frameworkfor SelectingPrime Software DevelopmentProcess
PDF
Material Parameter and Effect of Thermal Load on Functionally Graded Cylinders
PDF
Studies On Energy Conservation And Audit
PDF
An Implementation of I2C Slave Interface using Verilog HDL
PDF
Discrete Model of Two Predators competing for One Prey
A Study on Translucent Concrete Product and Its Properties by Using Optical F...
Developing Cost Effective Automation for Cotton Seed Delinting
Study & Testing Of Bio-Composite Material Based On Munja Fibre
Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)
Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...
Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...
Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...
Static Analysis of Go-Kart Chassis by Analytical and Solid Works Simulation
High Speed Effortless Bicycle
Integration of Struts & Spring & Hibernate for Enterprise Applications
Microcontroller Based Automatic Sprinkler Irrigation System
On some locally closed sets and spaces in Ideal Topological Spaces
Intrusion Detection and Forensics based on decision tree and Association rule...
Natural Language Ambiguity and its Effect on Machine Learning
Evolvea Frameworkfor SelectingPrime Software DevelopmentProcess
Material Parameter and Effect of Thermal Load on Functionally Graded Cylinders
Studies On Energy Conservation And Audit
An Implementation of I2C Slave Interface using Verilog HDL
Discrete Model of Two Predators competing for One Prey

Recently uploaded (20)

PDF
Cryptography and Network Security-Module-I.pdf
PPTX
PRASUNET_20240614003_231416_0000[1].pptx
PPTX
ai_satellite_crop_management_20250815030350.pptx
PPTX
Feature types and data preprocessing steps
PPTX
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
PDF
Soil Improvement Techniques Note - Rabbi
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PDF
Unit I -OPERATING SYSTEMS_SRM_KATTANKULATHUR.pptx.pdf
PPTX
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PPTX
Measurement Uncertainty and Measurement System analysis
PPTX
Module 8- Technological and Communication Skills.pptx
PDF
Unit1 - AIML Chapter 1 concept and ethics
PPTX
wireless networks, mobile computing.pptx
PDF
Design of Material Handling Equipment Lecture Note
PPTX
Software Engineering and software moduleing
PDF
UEFA_Carbon_Footprint_Calculator_Methology_2.0.pdf
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
PDF
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf
Cryptography and Network Security-Module-I.pdf
PRASUNET_20240614003_231416_0000[1].pptx
ai_satellite_crop_management_20250815030350.pptx
Feature types and data preprocessing steps
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
Soil Improvement Techniques Note - Rabbi
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Unit I -OPERATING SYSTEMS_SRM_KATTANKULATHUR.pptx.pdf
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
Measurement Uncertainty and Measurement System analysis
Module 8- Technological and Communication Skills.pptx
Unit1 - AIML Chapter 1 concept and ethics
wireless networks, mobile computing.pptx
Design of Material Handling Equipment Lecture Note
Software Engineering and software moduleing
UEFA_Carbon_Footprint_Calculator_Methology_2.0.pdf
"Array and Linked List in Data Structures with Types, Operations, Implementat...
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf

A Study on Risk Assessment in Construction Projects

  • 1. International OPEN ACCESS Journal Of Modern Engineering Research (IJMER) | IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss.9| Sept. 2014 | 20| A Study on Risk Assessment in Construction Projects K. Jayasudha1, Dr. B. Vidivelli2 1 Research Scholar, Department of Civil and Structural Engineering, Annamalai University, Chidambaram. 2 Professor, Department of Civil and Structural Engineering, Annamalai University, Chidambaram I. INTRODUCTION Construction companies and firms, such as the government, consultants and contractors, normally face different kinds of risks (e.g., environmental, physical, political, social and economic risks) during construction. However, most of them do not predict risks when they are considering bids and tenders. Construction risk is generally perceived as events that influence project objectives, i.e., cost, time and quality. In project management terms, the most serious effects of risk can be summarised as follows: 1. Failure to keep within the cost estimate. 2. Failure to achieve the required completion date. 3. Failure to achieve the required quality and operational requirements. This study aims to better understand the risk identification process and other risk processes. Risk identification is the first process in risk management. Therefore, this study focuses on risk identification because it is important to know how the players in the construction industry handle risk identification. Without having any perspective on or approach for risk identification, construction participants cannot make appropriate decisions in other risk management processes. This study evaluates risk identification by better understanding the processes and guidelines related to the risks in large and infrastructure construction projects, so that project risk management can be more effective. It has already been recognised that a clear understanding of the risks born by each participant leads to better risk allocation. The objective of this study is to find means of identifying risk management and other processes that can be utilised and to make new suggestions on the use of these risk management methods. It is of particular interest to find the means to manage risks that are the most effectively managed with the co-operation of several project participants. II. Methodology To achieve the objectives of this research, questionnaires were deemed to be the most effective tool for gathering information. These questions helped identify any projects that should definitely not be undertaken by the parties and those which, although risky, should be examined further after a more rigorous examination of the potential sources of risk. The questionnaire was designed based on the knowledge of government, consultant, or contractor in large or infrastructure construction projects; the questions were meant to identify their method of risk identification and possible effects of those risks. The general methodology of this study relies largely on the survey questionnaire which will be collected from the various multi project construction contractors and project manager of different sizes by mail Abstract: Risks are very common in construction sector. Risk management includes identifying risks, assessing risks either quantitatively or qualitatively, choosing the appropriate method for handling the risks, and then monitoring and documenting risks. By identifying risks in an early stage of planning and assessing their relative importance, project managers can identify methods used to reduce risks and allocate the best people to mitigate them. Thus, this research focuses on risk identification, as opposed to other processes of risk management. "Brain-storming sessions" is the most popular method used frequently to identify the risks in projects as deduced from a questionnaire survey from participants in large construction projects. Time and cost management need to be fully integrated with the identification process. Time constraints and project managers with sufficient experience are critical when identifying the level of risk for large and/or complex projects. The most considerable types of risk in construction projects are financial risks, construction risks, and demand or product risks. Keywords: Risk, Risk identification techniques, Risk management, and Construction Projects.
  • 2. A Study on Risk Assessment in Construction Projects | IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss.9| Sept. 2014 | 21| or by personnel meeting. A thorough literature review was initially conducted to identify the risk factors that affect the performance of construction industry as a whole. This study has adopted the more general and broad definition of risk as presented by Shen et al (2001) on china's construction joint ventures and more risk factors from other literature. Also some interviews with industrial practitioners were conducted to produce to check of questionnaires. III. QUESTIONNAIRE STRUCTURE AND DESIGN . The questionnaire was tested with a pilot survey for clarity, ease of use, value of the information that could be gathered. The questionnaire survey is divided into two parts. The first part consists of general information like type of company, experience, value of their project etc., and the second part consists of the construction risk factors for evaluation. Risk factor for this study classified into eight categories, namely: financial risk, legal risk, management risk, market risk, policy & political risk, technical risk, environmental risk, social risk. The survey questionnaire survey is designed to probe the cross-sectional behavioral pattern of construction risks construction industry. The questionnaire was prepared for the pilot survey was formulated by seeing the relevant literatures in the area of construction risk. The interviewer was free to ask additional questions that focused on issues arising during the course of the interview. The freedom to follow the interviewee, to ask for clarifications, and to focus on the specify projects, risk practices and knowledge, made the interviews insightful 3.1 Risk Rating A Likert scale of 1-5 was used in the questionnaire. A Likert scale is a type of psychometric response scale questionnaire, and is the most widely used scale in survey research. When responding to a Likert questionnaire item, respondents specify their level of agreement to a statement. The scale is named after Rensis Likert, who published a report describing its use. The respondents were required to indicate the relative critically/effectiveness of each of the probability of risk factors and their impact to the management. 3.2 Design of Survey The respondents were requested to judge the significance or "expected loss" of each risk. There are many criteria that respondents may need to consider. One alternative approach adopted by previous researches is to consider two attributes for each risk: the probability level of risk occurrence, denoted by o; and the degree of impact or the level of loss if the risk occurs denoted by p. The same type of evaluation is followed in this study also. Therefore, risk significance, denoted as RS, can be described as the function of the two attributes RS=f (, ). By applying this approach, the respondents were asked to respond to the two attributes for each risk. For considering a, the respondents were required to judge the probability level of risk occurrence by selecting one from among five levels namely, very small, small, normal, large and very large. For considering p, the respondents were required to judge the degree of impact if the risk concerned occurs, by selecting one from among five grades namely, very low, low. and medium, high and very high. 3.3 Analysis of Survey To assess the relative significance among risks, previous literatures study suggests establishing a risk significance index by calculating the significance score for each risk. For calculating the significance score is to multiply the probability of occurrence by the degree of impact Thus, the significance score of each risk assessed by each respondent can be obtained through the model i j i j i p S   Where Si = significance score assessed by respondent j for risk i; a, = probability of occurrence of risk i, assessed by respondent j; and p, = degree of impact of risk i, assessed by respondent j. By averaging scores from all responses, it is possible to get an average significance score for each risk, and this average score is called the risk index score and is used to rank among all risks. The model for the calculation of risk index score can be written T S RS T i i j i   1
  • 3. A Study on Risk Assessment in Construction Projects | IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss.9| Sept. 2014 | 22| Where RS1 = index score for risk i; and S1 = significance score assessed by respondent j for risk I and T=Total number of responses. To calculate S', the five scales for o and (3, this will be converted into numerical (Likert scale) scales. 3.4 Pilot Survey A pilot questionnaire survey and follow-up interviews with local contractors was conducted. The purpose was to identify the factors out of the 68 factors that applied overseas could also apply to the construction industry. The small number interviews and the structure of the questionnaire in die pilot study does not allow for statistical analysis. Responses to the interviews have been used to identify consistent themes, common practices, and insight provided by active and influential project participants that would provide additional guidance and assistance to the research team. The survey results formed the basis of modifying the questionnaire for the subsequent full-scale survey. The pilot study attempts to short-list locally relevant factors. The criteria for a shortlisting are that the chosen factors are relevant in the local construction industry. As a result, only important and relevant factors can be chosen for inclusion in the full-scale survey in the second phase research. IV. Risk Identification And Risk Identification Technique The risk identification phase as being either one of the most important stages within the risk management process, the risk identification phase into three categories. 1. The Risk identification conducted only by a risk analyst and based exclusively in his practice, knowledge and capacity. 2. The Risk identification was conducted through the interview of the risk analyst with one or many members of the project staff in order to analyze the reviewed data and the project life cycle based on the knowledge and expert of the people interviewed. 3. The Risk identification in which the risk analyst guides one or many work groups applying the risk identification techniques. 4.1 Risk Indentification Techniques 1. Brainstorming – An idea generation group technique is divided in two phases. (i) idea generation phase, in which participant generate as more ideas as possible (ii) idea selection phase, the ideas are filtered, remaining only those approved by the entire group 2. Delphi Technique – Delphi is a technique to obtain an opinion consensus about future events from a group of experts. It is supported by structured knowledge, experience and creativity from an expert 3. Interview/ Expert judgment – Unstructured, semi structured or structured interviews individually or collectively conducted with a set of experienced project members, specialist or project 4. Checklist – It consists of a list of item that are marked as yes or no , could be used by an individual project team members, a group or in an interview. 5. Influence Diagram – It is a graphical representation containing nodes representing the decision variables of a problem. A traditional influence diagram is formed by three types of nodes: utility, decision and informational. The causal relationship occurs between utility and chance nodes and represents a probabilistic dependence. 6. Flowchart – Graphical tool that shows the steps of a process. This technique is applied for a better comprehension of the risks or the elements interrelation 7. Cause-and-Effect Diagrams – These are also called Ishikawa diagrams or fishbone diagram, illustrate how various factor might be linked to potential problems or effects. The diagram is designed by listing the effect on the right sides and the causes on the left sides. There are categorized for each effect, and the main causes must be grouped according to these categories . V. Conclusions This paper is based on a literature review on the risk assessment methods. The risk assessments approaches are applied in various areas and the problems solve. It was found that the currently used methods for risk assessment are Brainstorming, checklist, Flowchart, Delphi method, Risk significant index method. Each method of risk assessment has their limitation therefore this paper attempt to formulate integrated risk assessment tools. It was observed that currently used risk assessment methods can be integrated into new approach that can aid the decision makers applying the risk assessment effectively. The specifications for
  • 4. A Study on Risk Assessment in Construction Projects | IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss.9| Sept. 2014 | 23| identifying project risk that have been particularised for construction projects have been presented from diverse points of view (from government, consultants and contractors) and construction companies and firms that may be helping the process of dealing with the project in the planning and construction phases. The process can also be adapted to identify the level of risk for a particular project. The brain-storming sessions and analysis of historical data for similar projects were found to be the most preferred methods of risk identification in the construction industry. The risks associated with construction projects included financial risks (project funding problem), construction risks and demand/ product risks. These risks commonly prevent the completion of construction project objectives. REFERENCES [1] R.C.Walke et al. “An approach to risk quantification in construction projects” International Journal of Engineering Science and Technology Vol. 3 No. 9 September 2011 .pp 6846-6855. [2] L. Y. Shen,1 George W. C. Wu,2 and Catherine S. K. Ng3. Risk assessment for construction joint venture in chinaJournal of construction Engineering and management Vol. 127 No. 1 January/ February 2001 pp. 76-81. [3] Wenzhe Tang1; Maoshan Qiang2; Colin F. Duffield3; David M. Young4; and Youmei Lu5. Risk management in the Chinese construction industry. Journal of construction Engineering and Management ASCE/ DECEMBER 2007 [4] Dr Patrick. X.W. Zou1, Dr Guomin Zhang2 and Professor Jia-Yuan Wang3 1 and 2: Faculty of Built Environment, University of New South Wales, Sydney 2052, Australia;3: College of Architecture and Civil Engineering, Shenzhen University, Shenzhen, P.R. China. Identified Key Risks in Construction Projects: Life Cycle and Stake Holder Perspectives. [5] Akintoye A.S and MacLeod, M.J. (1997). Risk analysis and management in construction, International Journal of project Management. Vol 15, February 1997, pages 31-38. [6] Ossama A.Abdou (Asst.Prof. Dept. of Civil and Arch. Engg.Drexel University) Managing Construction Journal of Architectural Engineering, Vol 2, No.1 March 1996, pp. 3- 10. [7] Matins Claudia Garrido, Morano Cassia Andra Ruotolo, Fereira Miguel Luiz Riberio and Haddad Assed Naked. Risk Identification Techniques Knowledge and Application in the Brazilian Construction Vol. 2(11), pp. 242-252, November2011 [8] Chapman R.J. (2001) The Controlling Influences on Effective Risk Identification and Assessment for Construction Design Management, International Journal of Project Management. Vol 19.Issue 3, pp. 147-160. [9] Al-Bahar, J.F. and Crandall, K.C. (1990). Systematic risk management approach for construction project. Journal of Construction Engineering and Management, 116(3): 533–546. [10] Artto, K.A. (1999). Development of World-Class Practices in Project Companies. In The Future of Project Management, Project Management Institute Research Series. Newtown Square, PA: Project Management Institute (PMI), 127–137. [11] Kendrick, T. (2009). Identifying and Managing Project Risk: Essential Tools for Failure-Proofing Your Project. 2nd Edition. New York: AMACOM Div. American Management Association. [12] Project Management Institute. (2004). A Guide to the Project Management Body of Knowledge. Newtown Square, Pennsylvania: PMI.