This document summarizes a case study of soil improvement works using deep dynamic compaction and rapid impact compaction techniques at a site near Dammam, Saudi Arabia. Two soil investigations identified loose granular soils up to 10m deep requiring compaction to meet bearing capacity, settlement, and liquefaction criteria for structures and roads. A strategy was developed to use dynamic compaction and rapid impact compaction independently and together to treat 180,000m2 within the required 6-month timeframe. Trial works showed the techniques could achieve the criteria and improve 104,000m2 and 76,000m2, respectively, allowing completion in under 5 months.