Legal framework under Electricity Act 2003
The Section 42 (1) of the Electricity Act 2003 provides that it shall be the duty of a
Distribution Licensee to develop and maintain an efficient coordinated and economical
distribution system in his area of supply and to supply electricity in accordance with
the provisions contained in the Act and the Distribution Licensee Standards of
Performance issued by the Commission.
The Distribution Code ensures that the Distribution Licensee comply with the
requirement of section 42 (1) of the Act read with Section 86 sub-section 1
clause (h) and (i) of the Act.
8/7/2023
2
Framework of Distribution Code
8/7/2023 3
Management of
Distribution Code
Distribution
Planning Code
Distribution
System Planning &
Security Standard
Connectivity
Conditions
Operating Code
Metering and
Protection Code
Cross boundary
safety code
Incident/accident
reporting
Management of Distribution Code
8/7/2023
4
Distribution Code Review Panel
Members of the Panel
Distribution Licensee,
Transmission Utility, SLDC,
Generators, Open Access
Consumers, Industrial,
Agricultural, Domestic and
Commercial Consumers & Such
other member as the Commission
may direct and find appropriate
Commission shall develop a list
of potential candidates to serve
on the Distribution Code
Review Panel, which reflects a
balance of the various interest
groups in consultation with the
Distribution Licensee.
Functions of the
Review Panel
Technical Expertise / Review and
Revisions required from time to
time / Scrutiny of Code / Provide
guidance / Examination of the
problems of Users
Method of managing Distribution Code, pursuing of any changes / modifications
required and the responsibilities of the Distribution Licensees and the Users/
Consumers in this regard.
Distribution Planning Code
8/7/2023
5
Planning
Policy
Extension or
reinforcement or
capacity
enhancement of the
Distribution System
based on
requirement of the
User(s).
Introduction of new
technology
DRE/EVs/BESS etc.
Load data
load curves
database
Asset mapping
consumer indexing
feeder metering
DTR metering
Load
forecasting
5-year plan
Peak Demand
Assessment
Hourly demand
assessment
Energy
consumption
assessment
Use of appropriate
modern forecasting
tools
Technical &
Design
Criteria
Electricity usage by
Consumers.
Implementation of
appropriate load
forecast program.
Energy Audit
Create
responsibility
centers for energy
audit.
Develop action plan
for reduction of
losses.
Capex investments.
Suitable
improvements in
governance.
To enable the planning, design and construction of the Distribution System for a safe
and economical operation with the specified degree of reliability conforming to the
following standards:
Distribution System Planning & Security
Standard
Quality of power
supply
Load forecast
Planning procedure
& Planning
standards.
Service area of a
distribution
network.
Reliability analysis.
Committee on
Design,
Construction &
Maintenance
Practices
Security Standards
Preventive
Maintenance
Maintenance
Records
Energy
Conservation
8/7/2023
6
Specifies the guidelines for planning methodology of the Distribution System
Connectivity Conditions
The design and construction of all the equipment connected to the Distribution System should be as per Indian
Standard Specifications or appropriate IEC / IEEE or other International Standards.
Discom is required to specify the Connection Point/ Interface Point and the supply voltage, along with the
metering and protection requirements for all New Connection as per provisions of the Electricity Supply Code
The operation of the Distribution System shall be in accordance with the "Distribution System Operating Standard"
under Power System Management & Operation Standard as prescribed by authority under Electricity Act 2003
Connection Point/ Interface Point - Connection to Transmission System shall be governed by the relevant clauses
of Central / State Grid Code as the case may be. For HT/EHT and LT Consumers connection to the Distribution
System shall be as per provisions mentioned in the Electricity Supply Code.
Other Procedures like Applications for Connections to The System / Acceptance or Rejection of Application
for Connection / Connection Agreements shall be as per provisions mentioned in the Electricity Supply Code.
8/7/2023
7
Specify the minimum technical and design criteria, which shall be complied by any
agency connected to, or seeking connection to the Distribution System
Operating Code
8/7/2023 8
Demand Estimation Outage Planning Contingency Planning
Demand Side
Management
Interface with Small
Generating Plant
including CPPs
Operational
Communication
Monitoring and Control
of voltage, frequency
and power factor.
Safety Co-ordination.
Maintenance and
testing
Tools and spares
Human Resource
Development and
Training
GIS or GPS based
information system
Procedures and practices to be followed for a safe and efficient operation of the Distribution System by the
Distribution Licensee and by the Users of the Distribution System of their electrical plant and lines which are
connected to the Distribution Licensee’s system.
Metering and Protection Code (1/2)
8/7/2023 9
• 66 / 33 kV bus voltage; 33 / 11 kV bus voltage; 66 / 33 / 11 kV incoming /
outgoing current in each phase and each circuit.
• PT currents in each phase; HT outgoing feeder current in each phase.
• Power factor measurement; Load survey meters having memory duration of at
least 45 days for all the incoming and outgoing feeders.
• Facility to record energy in MWH and frequency at interval of 15 minutes at
point of connection with Transmission Licensee.
Operational
Metering at Grid
substation
• At each point of interconnection between the Distribution and
Transmission Systems in accordance with the Central / State Grid
Code
• At the Connection Points/ Interface Points between the User’s system
and the Distribution System and shall be governed by the provision in
the Distribution Services Agreement.
Tariff and
Commercial
Metering
Specifies the procedure for metering in Distribution System with respect to operational
metering as well as tariff and commercial metering. This section also specifies the
general guidelines for protection of Distribution system.
Metering and Protection Code (2/2)
• Active & Reactive energy Import/Export
• Meters shall conform to the relevant IEC or IS specifications
• Main and check meters shall be provided at all Connection Points/
Interface Points.
Measurement Of
Energy Import/ Export
• Adequate protection for all electrical equipment.
• Example: Distribution System: - For Power Transformers of HV
class differential protection shall be provided for rating >10 MVA
along with backup time lag over current and earth fault protection
with directional feature for parallel operation.
Protection System
• Adequate precaution against fire hazards to all apparatus in the
System conforming to the relevant IS Specifications and/or
provisions under other relevant rules as amended from time to
time.
Fire Protection
8/7/2023
10
Cross boundary safety code
Nomination of
Control Persons
(CP)
For work to be
carried out by User
or Discom, the CPs
shall directly
contact his
counterpart
CPs shall establish &
maintain necessary
precautions for
carrying out the
required work
After work
completion, the CP
shall assess
requirement /
removal of safety
precautions
Discom & Users
shall develop
written procedure
for Cross Boundary
Safety Protocols
8/7/2023
11
Objective of this section is to achieve an agreement on the principles of safety when
working across a control boundary between the Distribution Licensee and the Users
The Distribution Licensee and all the Users (comprising Generation Companies, Transmission
Licensees and consumers having load above 1MW or dedicated line) shall nominate suitably
authorized and technically qualified persons to be responsible for the co-ordination of safety across
their boundary. These persons shall be referred to as "Control Persons".
8/7/2023
12
Incident/Accident Reporting
Major Incident or Accident Reporting & Reporting
Procedure
• Discom shall send preliminary report to the
Commission on all significant Incidents in the Area of
Supply, which results in interruption to service /
substantial damage to equipment / loss of life /
significant injury to human beings.
• Reporting to be done within one week of its occurrence
followed by a detailed report within one month
Procedure of major incident / accident reporting (which occur in Distribution System)
by User to Licensee and Licensee to User and Commission
REPORT:
Location of the incident, Date and time, Plant or
Equipment involved, Nature of incident
(electrical or non-electrical), Supplies
interrupted and the duration, System
Parameters (Voltage, Frequency, Load,
Generation) etc. …
Thank You

More Related Content

PDF
Guidelines on Interfacing Requirements.pdf
PDF
Draft MERC Net Metering for Solar Rooftop Regulations,2015
PPTX
Grid standards and acts electrical safety
PDF
guidelines_GUIDELINES FOR DISTRIBUTION UTILITIES FOR DEVELOPMENT OF DISTRIBUT...
PPTX
Final_NFE,May23-Lenin-CEA-Safety- Regulations PPT.pptx
PDF
DERC Renewable energy Net Metering Regulations 2014
PPT
PPTX
Guidelines on Interfacing Requirements.pdf
Draft MERC Net Metering for Solar Rooftop Regulations,2015
Grid standards and acts electrical safety
guidelines_GUIDELINES FOR DISTRIBUTION UTILITIES FOR DEVELOPMENT OF DISTRIBUT...
Final_NFE,May23-Lenin-CEA-Safety- Regulations PPT.pptx
DERC Renewable energy Net Metering Regulations 2014

Similar to Distribution Code (Framework).pdf (20)

PPTX
Renewable energy and grid integration energy transition
PPT
Concept Of Grid Code Anilpatil Session Iii
PDF
Sop english final20_01_2005 msedcl
PDF
Cerc communication regulations, 2017 ppt
PPTX
NPTI 15th batch Indian electricity grid code (IEGC)
PPT
IEGC_PPT_SLDC.ppt
PDF
Transformer
PPTX
OPEN ACCESS REGULATION
PPTX
CEA _Grid Connectivity Standards 23092019.pptx
PDF
Safety+manual
PPT
Indian electricity grid code presentation
PPTX
1.0 General Operations & Maintenance Strategies for improving Safety of lines...
PDF
Transmission line loadability improvement using facts device
PDF
ENTSO-E Draft Network Code for Operational Security
PDF
Review on Different Techniques for Differential Protection of Power Transformer
PPT
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
PPTX
PHILIPPINE-DISTRIBUTION-CODE (1).pptxhsgsgsgsgsgzgsgsgsg
PPTX
GROUP-9-Residential-Electricity-Consumer.pptx
PDF
RERC Net metering Regulations 2015
PPTX
Connectivity
Renewable energy and grid integration energy transition
Concept Of Grid Code Anilpatil Session Iii
Sop english final20_01_2005 msedcl
Cerc communication regulations, 2017 ppt
NPTI 15th batch Indian electricity grid code (IEGC)
IEGC_PPT_SLDC.ppt
Transformer
OPEN ACCESS REGULATION
CEA _Grid Connectivity Standards 23092019.pptx
Safety+manual
Indian electricity grid code presentation
1.0 General Operations & Maintenance Strategies for improving Safety of lines...
Transmission line loadability improvement using facts device
ENTSO-E Draft Network Code for Operational Security
Review on Different Techniques for Differential Protection of Power Transformer
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
PHILIPPINE-DISTRIBUTION-CODE (1).pptxhsgsgsgsgsgzgsgsgsg
GROUP-9-Residential-Electricity-Consumer.pptx
RERC Net metering Regulations 2015
Connectivity
Ad

Recently uploaded (20)

PPTX
UNIT - 3 Total quality Management .pptx
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PPT
Occupational Health and Safety Management System
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PPTX
Current and future trends in Computer Vision.pptx
PDF
PPT on Performance Review to get promotions
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PPTX
Nature of X-rays, X- Ray Equipment, Fluoroscopy
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS
PPTX
Artificial Intelligence
PDF
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PPTX
introduction to high performance computing
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
UNIT - 3 Total quality Management .pptx
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
Occupational Health and Safety Management System
III.4.1.2_The_Space_Environment.p pdffdf
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Current and future trends in Computer Vision.pptx
PPT on Performance Review to get promotions
R24 SURVEYING LAB MANUAL for civil enggi
Nature of X-rays, X- Ray Equipment, Fluoroscopy
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS
Artificial Intelligence
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
introduction to high performance computing
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
Ad

Distribution Code (Framework).pdf

  • 2. Legal framework under Electricity Act 2003 The Section 42 (1) of the Electricity Act 2003 provides that it shall be the duty of a Distribution Licensee to develop and maintain an efficient coordinated and economical distribution system in his area of supply and to supply electricity in accordance with the provisions contained in the Act and the Distribution Licensee Standards of Performance issued by the Commission. The Distribution Code ensures that the Distribution Licensee comply with the requirement of section 42 (1) of the Act read with Section 86 sub-section 1 clause (h) and (i) of the Act. 8/7/2023 2
  • 3. Framework of Distribution Code 8/7/2023 3 Management of Distribution Code Distribution Planning Code Distribution System Planning & Security Standard Connectivity Conditions Operating Code Metering and Protection Code Cross boundary safety code Incident/accident reporting
  • 4. Management of Distribution Code 8/7/2023 4 Distribution Code Review Panel Members of the Panel Distribution Licensee, Transmission Utility, SLDC, Generators, Open Access Consumers, Industrial, Agricultural, Domestic and Commercial Consumers & Such other member as the Commission may direct and find appropriate Commission shall develop a list of potential candidates to serve on the Distribution Code Review Panel, which reflects a balance of the various interest groups in consultation with the Distribution Licensee. Functions of the Review Panel Technical Expertise / Review and Revisions required from time to time / Scrutiny of Code / Provide guidance / Examination of the problems of Users Method of managing Distribution Code, pursuing of any changes / modifications required and the responsibilities of the Distribution Licensees and the Users/ Consumers in this regard.
  • 5. Distribution Planning Code 8/7/2023 5 Planning Policy Extension or reinforcement or capacity enhancement of the Distribution System based on requirement of the User(s). Introduction of new technology DRE/EVs/BESS etc. Load data load curves database Asset mapping consumer indexing feeder metering DTR metering Load forecasting 5-year plan Peak Demand Assessment Hourly demand assessment Energy consumption assessment Use of appropriate modern forecasting tools Technical & Design Criteria Electricity usage by Consumers. Implementation of appropriate load forecast program. Energy Audit Create responsibility centers for energy audit. Develop action plan for reduction of losses. Capex investments. Suitable improvements in governance. To enable the planning, design and construction of the Distribution System for a safe and economical operation with the specified degree of reliability conforming to the following standards:
  • 6. Distribution System Planning & Security Standard Quality of power supply Load forecast Planning procedure & Planning standards. Service area of a distribution network. Reliability analysis. Committee on Design, Construction & Maintenance Practices Security Standards Preventive Maintenance Maintenance Records Energy Conservation 8/7/2023 6 Specifies the guidelines for planning methodology of the Distribution System
  • 7. Connectivity Conditions The design and construction of all the equipment connected to the Distribution System should be as per Indian Standard Specifications or appropriate IEC / IEEE or other International Standards. Discom is required to specify the Connection Point/ Interface Point and the supply voltage, along with the metering and protection requirements for all New Connection as per provisions of the Electricity Supply Code The operation of the Distribution System shall be in accordance with the "Distribution System Operating Standard" under Power System Management & Operation Standard as prescribed by authority under Electricity Act 2003 Connection Point/ Interface Point - Connection to Transmission System shall be governed by the relevant clauses of Central / State Grid Code as the case may be. For HT/EHT and LT Consumers connection to the Distribution System shall be as per provisions mentioned in the Electricity Supply Code. Other Procedures like Applications for Connections to The System / Acceptance or Rejection of Application for Connection / Connection Agreements shall be as per provisions mentioned in the Electricity Supply Code. 8/7/2023 7 Specify the minimum technical and design criteria, which shall be complied by any agency connected to, or seeking connection to the Distribution System
  • 8. Operating Code 8/7/2023 8 Demand Estimation Outage Planning Contingency Planning Demand Side Management Interface with Small Generating Plant including CPPs Operational Communication Monitoring and Control of voltage, frequency and power factor. Safety Co-ordination. Maintenance and testing Tools and spares Human Resource Development and Training GIS or GPS based information system Procedures and practices to be followed for a safe and efficient operation of the Distribution System by the Distribution Licensee and by the Users of the Distribution System of their electrical plant and lines which are connected to the Distribution Licensee’s system.
  • 9. Metering and Protection Code (1/2) 8/7/2023 9 • 66 / 33 kV bus voltage; 33 / 11 kV bus voltage; 66 / 33 / 11 kV incoming / outgoing current in each phase and each circuit. • PT currents in each phase; HT outgoing feeder current in each phase. • Power factor measurement; Load survey meters having memory duration of at least 45 days for all the incoming and outgoing feeders. • Facility to record energy in MWH and frequency at interval of 15 minutes at point of connection with Transmission Licensee. Operational Metering at Grid substation • At each point of interconnection between the Distribution and Transmission Systems in accordance with the Central / State Grid Code • At the Connection Points/ Interface Points between the User’s system and the Distribution System and shall be governed by the provision in the Distribution Services Agreement. Tariff and Commercial Metering Specifies the procedure for metering in Distribution System with respect to operational metering as well as tariff and commercial metering. This section also specifies the general guidelines for protection of Distribution system.
  • 10. Metering and Protection Code (2/2) • Active & Reactive energy Import/Export • Meters shall conform to the relevant IEC or IS specifications • Main and check meters shall be provided at all Connection Points/ Interface Points. Measurement Of Energy Import/ Export • Adequate protection for all electrical equipment. • Example: Distribution System: - For Power Transformers of HV class differential protection shall be provided for rating >10 MVA along with backup time lag over current and earth fault protection with directional feature for parallel operation. Protection System • Adequate precaution against fire hazards to all apparatus in the System conforming to the relevant IS Specifications and/or provisions under other relevant rules as amended from time to time. Fire Protection 8/7/2023 10
  • 11. Cross boundary safety code Nomination of Control Persons (CP) For work to be carried out by User or Discom, the CPs shall directly contact his counterpart CPs shall establish & maintain necessary precautions for carrying out the required work After work completion, the CP shall assess requirement / removal of safety precautions Discom & Users shall develop written procedure for Cross Boundary Safety Protocols 8/7/2023 11 Objective of this section is to achieve an agreement on the principles of safety when working across a control boundary between the Distribution Licensee and the Users The Distribution Licensee and all the Users (comprising Generation Companies, Transmission Licensees and consumers having load above 1MW or dedicated line) shall nominate suitably authorized and technically qualified persons to be responsible for the co-ordination of safety across their boundary. These persons shall be referred to as "Control Persons".
  • 12. 8/7/2023 12 Incident/Accident Reporting Major Incident or Accident Reporting & Reporting Procedure • Discom shall send preliminary report to the Commission on all significant Incidents in the Area of Supply, which results in interruption to service / substantial damage to equipment / loss of life / significant injury to human beings. • Reporting to be done within one week of its occurrence followed by a detailed report within one month Procedure of major incident / accident reporting (which occur in Distribution System) by User to Licensee and Licensee to User and Commission REPORT: Location of the incident, Date and time, Plant or Equipment involved, Nature of incident (electrical or non-electrical), Supplies interrupted and the duration, System Parameters (Voltage, Frequency, Load, Generation) etc. …