Introduction to FIDIC Conditions
of contract
Dr. Mirosław J. Skibniewski,
A.J. Clark Chair Professor
 New tendency in contracts worldwide
dokumen.tips_fidic-power-point-presentation.pdf
OUTLINE
1. What is FIDIC?
2. Characteristics of FIDIC Conditions of
Contract
3. Application Prospect of FIDIC
Conditions of Contract
4. New development of FIDIC Conditions of
contract
What is FIDIC?
 Management is a kind of science which needs
continuous summarizing, to experience development
and innovations through practice.
 In the contract for international engineering projects,
the function of Conditions of Contract is of greatest
importance providing the rights, obligation and
responsibility for the parties concerned in the
Contract execution.
 During the past half century, the International
Federation of Consulting Engineers (FIDIC) has
devoted itself to the compilation of management
documents for all kinds of projects, among which
the FIDIC Conditions of Contract are of the
highest influence and are the most popular
application.
 The first edition of FIDIC Conditions of Contract
for Works of Civil Engineering Construction (use
“Red Book” in the following) was compiled in 1957,
and later its second, third, and fourth edition were
issued in 1963, 1977, and 1987 respectively.
 But these editions were mostly compiled in the
reference of the related documents of the
Institution of Civil Engineers (ICE). The FIDIC
and European International Contractors (EIC)
entrusted the University of Reading in 1966 to
summarize the experience and to draw lessons
from the application of the former documents.
 With the investigation of the governments,
employers, contractors and consulting engineers
all over the world about their application of the
“Red Book”, 204 findings reports were returned.
According to the findings, the FIDIC Contract
Committee organized a group of experts to
compile the new Contract Condition models to be
applied in the 21stcentury.
 The test edition of these models was published in
1998, and FIDIC solicited opinions throughout
the world for additional time to publish the
official texts in 1999.
 Now FIDIC condition of contract has been
applied worldwide, especially in the projects
invested by World Bank, Asia Development Bank,
Africa Development Bank etc.
The new models include :
FIDIC Conditions of Contract for Construction, the (New Red Book)
FIDIC Conditions of Contract for Plant and Design/Build, the
(New Yellow Book)
FIDIC Conditions of Contract for EPC Turnkey Projects, the
(Silver Book)
FIDIC Short Form of Contract, the (Green Book)
FIDIC Conditions of Contract (new edition) raised a
higher requirement to the Parties concerned in the area
of contract management
dokumen.tips_fidic-power-point-presentation.pdf
2. Characteristics of FIDIC
Conditions of Contract
 Unification of Terms and Clause
 The new edition was drafted as the “New Red Book”, the “New
Yellow Book” and the “Silver Book” by a workgroup under the
leadership of the FIDIC Contract Committee. The contract form
was not influenced by the former ICE framework, which was
included in all 20 clauses. So if the clauses content could be
unified, it would be under the same titles and expressions. In
these three books, more than 80% of the content was consistent,
and 85% of the definitions and expressions were the same. It is
of great help for the users to understand them completely, saving
study time.
 Wider Application
 When these new Conditions of Contract were drafted, FIDIC
tried its best so the Conditions could be applied under not only
the Customary Law (i.e. Anglo-American Law System), but also
Civil Law. To pursue this, the contract working group had an
attorney present to review the clauses, so that they could be
applied under the two laws noted above. The new edition also
shows more flexibility and adaptability. For example, in the old
edition, the conditional performance guarantee was necessary,
which the World Bank had different opinions of. While in the
new edition, the guarantee forms were set by Particular
Conditions which can be applied giving the employers better
flexibility.
 Applicability under Various Project Delivery and
Contracting System
1. The “New Red Book” can be used in any kind of Engineering
Construction Contract.
2. The “New Yellow Book” applies to the lump sum contract project
where the Contractor takes participation in the design work.
3. The “Silver Book” applies to the turnkey projects of
infrastructures or large-scale factories, where the Contractor
takes on more work and risk while the Employer’s participation
is small (private financing or government financing), but it is
strictly defined upon the investment and construction period.
4. The “Green Book” can be used in all kinds of small-scale projects.
5. Altogether, these four Contract Conditions can be applied to
nearly every kind of project, expect for that of managing
contracting or simply consulting or designing
 High-quality Provisions and Logical Clause
Sequencing
 Compared with the original “Red Book”, the “New Red Book” has
163 clauses, nearly 40% being freshly compiled. An additional
40% were modified and given supplements. Only 20% were kept
intact. The old edition adopted ICE’s disorderly style bit in the
clause sequence, while in the new edition, the related sub-clauses
are put into one clause when possible, and convenient to the
users.
 More Specific Provisions concerning the Rights
and Obligations of the Contract Parties
 Taking the clause of Employer’s default as an example, we can
see that in contrast to the “Red Book”,” three points are added
into the “New Red Book”: two of them are concerned with
payment. The above shows the strict requirements for the
Employer. However, the Contractor shall institute a quality
assurance system and submit to the Engineer to audit any aspect
of the system before execution. Monthly progress reports shall be
prepared by the Contractor to submit to the Engineer every
month, otherwise, the payment won’t be given. Any kind of bribe
can result in Contractor’s default. All of the above are high
requirements for the Contractor.
 Changes in the Preparing Style
 General Conditions in the former edition were fairly concise;
some recommendable clauses were given Particular Conditions.
While in the new edition, there is a way around the regulations
being that the General Conditions are relatively comprehensive
and detailed. An example would be advanced payment and
adjustment formula. The new edition writers believe that it is
more convenient for the users to delete the clauses they do not
need than to write them in the “Particular Conditions” by
themselves.
 Concise Language
 The language and sentence structures in the new edition are
rather easy to understand, and a great help to the people whose
native language is not English.
3. Application Prospect of FIDIC
Conditions of Contract
 The traditional project management mode, which is
universal in the world, has been applied in most of the
engineering project management cases in the world.
 The new edition has many advanced ideas and
regulations such as standardizing of the Contract
words and expressions, clearer and stricter claim
procedure, and emphasis on the protection of
intellectual property rights
 To Solve the Problem of Back Payment using
World Wide Experience for Reference
 It is reported that the back payment and debt between the
engineering units in China have added up to 280 billion (RMB),
which is mostly Employer’s (government included) default to
the Contractor. The problem has greatly influenced the
construction corporations that their economic strength were
weakened. The market needs a legal system to provide a
guarantee for free and fair competition.
 Since the problems of the Employer’s financial vacancy
or Contractor financing are originating worldwide, the
relative clauses and regulations are added into FIDIC
Conditions of Contract.
1. Employer’s financial arrangement. The Employer shall submit
within 28 days after receiving any request from the Contractor
reasonable evidence that financial arrangement has been made. If
the Employer intends to make any material change to his financial
arrangement, he shall give notice to the Contractor with detailed
particulars.
1. If the Employer fails to execute in accordance with this clause,
the Contractor may, after giving a 21 days’ notice to the
Employer, suspend the work or reduce production output as a
kind of warning; if the Contractor does not receive any
reasonable financial arrangement certificate within 42 days
after giving the warning, he shall be entitled to terminate the
Contract, for it is the Employer’s default. Also the Contractor
can get all the compensation earned on the condition of
Employer’s default.
2. It is defined in the clause of payment how to handle the
problem when the Employer has the payment delayed. If
the Contractor does not receive payment (in accordance
with the Interim Payment Certificate) within 56 days after
submitting monthly statement to the Engineer at the
beginning of the month, the Contractor shall be entitled to
receive interest compounded monthly on the amount
unpaid during the period of delay. These financing changes
shall be calculated at the annual rate of 3 percentage points
above the discount rate of central bank in the country of
the currency of payment. If the Contractor does not receive
payment with in 42 days after the expiry of the above 56
days, he shall be entitled to terminate the Contract.
3. Contractor Financed Project’s execution. It is specially set up in
the Particular Conditions an Example Provisions for Contractor
Finance, which defines that if it is Contractor financing and he
has committed to the project, the Employer shall deliver a bank
payment guarantee to the Contractor within 28 days after both
parties have entered into the Contract Agreement. If the
Contractor does not receive the guarantee, the Engineer shall
not issue the notice to commence. It is defined in the guarantee
that if the Employer fails to make payment in full by the date 14
days after the expiry of the period specified in the contract as
that within which such payment should have been made, the
Contractor shall been entitled to demand for payment from the
bank with a certificate, Contractor’s signatures which must be
authenticated by his bankers or by a notary public.
 To Carry out the General Contracting Mode of
Design/Build and EPC Turnkey Enthusiastically
 FIDIC makes out the “New Yellow Book” and
“Silver Book” independently in addition to
meet the development tendency of
international project management mode.
 According to the statistics and forecast of the American
Design/Build Institution, the market share’s change
tendency of American main engineering construction
mode during 1985 to 2015 is shown in the Tab. 1.
 To Make Clear the Position of the Construction
Supervising Engineer, Raise Their Working
Responsibility, and Open up New Regions of Work
 In the “New Red Book”, it needs the Engineer to be timelier, and
more explicit in solving the problems than before. It pays more
respect to the position and the authority of the Engineer, such as,
without the consent of the Contractor, the Employer shall not be
entitled to exchange the Engineer or impose further restriction on
the Engineer’s authority which has been specified in the contract.
 Engineer’s authority includes:
 Making it clear that the Engineer belongs to “Employer’s
Personnel”, while there is no stress that he is an independent
party.
 When the Engineer makes a decision, there will be no more
stress on impartiality, but he is still required to be fair.
 If the Contractor and Employer have a heated dispute, there
will be no need for the Engineer to mediate before either party
applies for arbitration. So the Dispute Adjudication Board
(DAB) has been set up to solve the problem
 The mode of Engineer’s supervising is also applied in the “New
Yellow Book”, while the responsibilities of Engineer are the same
on the whole with what is said in the “New Red Book”, that is,
the Engineer should manage not only the construction, but in
designing, including reviewing and approving the qualification of
the designer and sub-designer, Contractor’s design documents,
participating in the discussion of the design, and instructing the
Contractor to prepare further Documents. But any Engineer’s
review, approval, or consent of the Contractor’s documents shall
not relieve the Contractor from any obligation or responsibility.
 To Prepare the MODEL of Short Form Contract
 Many small scale and large scale projects can use simple
techniques such as in residential areas, also need a contract. So
we shall compile a short form of contract in reference to FIDIC
“Green Book”. It is necessary to be fairly flexible in the mode and
requirements of management.
 To Improve the Mediation Methods for Dispute
 The new edition takes the experience of USA and World Bank in
solving the construction dispute, which results in DAB to
mediate the dispute. The most outstanding merit of DAB is that
it is composed of three experts who are chosen, approved and
paid for by both parties.
 These experts go to site to solve the dispute occurring between
the two parties after commencing construction work. While in
the FIDIC “Red Book”, the Engineer is required to mediate the
problem which he can not handle. It is hard to be impartial
because the Engineer is the Employer’s employee, so very often
the contradiction will still be unsolved after a long time.
New development of FIDIC conditions of contract
--Design-Build Operate Contract
It was published on
September 2007,
Gold Book
 New DBO document for long-term contract
 Background
 The DBO approach to contracting combines design,
construction, and long-term operation (and maintenance) of
a facility into one single contract awarded to a single
contractor (who will usually be a joint venture or consortium
representing all the disciplines and skills called for in a DBO
arrangement. Public private partnerships, PPPs, are this
arrangement).
 DBO’s advantages
 Time: With possibilities to overlap some design and build
activities it will be possible to minimize delays and optimize
the smooth flow of construction activities.
 Financial: With cost restraints and commitments and other
risks being carried by the Contractor, there is less risk of
price over-runs.
 Quality: With the Contractor responsible for 20 years
operation, he has an interest to design and build quality plant
with low operation and maintenance costs. Not only will the
plant be ‘fit for purpose’ but it will be built to last.
 Basically the success of a true DBO contract depends on the
commitment of the Contractor to the complete project - and
the best way to do that is to cover the whole design-build and
the operation elements in a single contract. That is why
FIDIC chose a single long term Performance Security with a
substantial reduction in value on completion of the design-
build – but with an on-going commitment by the Contract to
perform and complete the operation service.
 The format of a DBO arrangement can be based on either a
‘green field’ scenario (D-B-O), or on a ‘brown field’ scenario
(O-D-B). Either is quite common, however the contractual
requirements and procedures are quite different.
 FIDIC has chosen to produce a document based on the DBO
green field scenario, with a Guide (which will be published in
2008) containing guidelines on the changes necessary to
cover a brown field arrangement, in which FIDIC Yellow
Book for the DB is the basement.
 The other important factor considered in DBO document is
the length of the operation period, since the conditions
suitable for long-term operation are not necessarily suitable
for a short-term operation. From the experience of the DBO
members it was decided that the most useful period to
consider was 20 years operation – again giving guidelines in
the Guide if a shorter period would be required
 Risk control in DBO contract
 DBO can be viewed as a complete method in PPPs. This method
is a long-term process including procurement, construction,
operation, and transfer, in which high risk should be pay the
most attention to.
 About PPPs: A wide spectrum of options is available for the
delivery of public infrastructure and services, ranging from
direct provision by the government to outright privatization,
with increasing responsibilities, risks, commitment, and rewards
transferred from the government to the private sector.
 For example, supply and service contracts usually have a short
duration. In such contracts, the private contractor performs
specified tasks (e.g., material/ equipment supplies, works
construction and facilities maintenance) whereas it is not
directly responsible for providing related services. In a lease-
and-operate contract, the private contractor operates and
maintains the facilities at its own risk against the payment of a
lease fee. In a build-operate-transfer (BOT) project, the private
contractor is also responsible for building and financing the
project and it has to transfer project facilities in operational
conditions and free of costs to the government at the end of the
concession term. In divestiture, the ownership of existing assets
and the responsibility for future expansion and upkeep are
transferred to the private contractor, in addition to financing and
carrying out the investments required to meet the obligations
specified in the contract and/or a general regulatory framework.
Successful PPPs
Best Value for Money
Needs for PPPs
The problem of
public sector budget
restraint
Non recourse or limited
recourse public funding
public money tied
up in capital investment
High public service costs
More infrastructure
facility need from society
Procurement
Improving procurement process
Standardization of tender
documents and contract
Maintaining competitive
environment for best offer
Strong private consortium
Appropriate risk
allocation and
risk sharing
Available
financial market
Commitment/responsibility
of public/private sectors
Thorough and realistic
cost/benefit assessment
Well-organized public agency
Favorable legal framework and
transparency in the procurement
Political support
Design and building
Innovative design,
reengineering, avoiding
over specification, and use
of new material and technique
Identification and classification
of skills needed
Sound economic policy
Multi-benefit objectives
operation
Transfer management
Post-transfer
Appropriate
PPP schemes
Contract
management
Payment
management
Cost
management
Technology
transfer
Tariff/toll, price
adjustment mechanism
Facility management
Environment
friendly
Payment
management
Contract
management
Cost
management
Training of new
employees
Provisions for selling
project facilities to the
concessionaire or further
extension on concession
Transfer price
Standards of
project facilities
upon transfer
Intellectual
property rights
Facility
management
Project
renew
Project
renew
 The whole process of a PPP (DBO) project and key issues are should in
following figure.
 Lots of risks have been identified as followed:
It comes from L. Bing et al. (2005) The allocation of risk in PPP/PFI construction projects in the UK,
International Journal of Project Management, 23: 25–35.
dokumen.tips_fidic-power-point-presentation.pdf
 Therefore, a new DBO contract should handle
these risks to pursue the successful projects.
FIDIC has designed new clause to deal the risks
in DBO contract:
 Restructured Clauses 17 – 19 (Clause 17: Risk Allocation, Clause
18: Exceptional Risks, Clause 19: Insurance)
 Identified the Risks to be carried by each Party
 Differentiated between Risks during the Design-Build Period
and Operation Service Period
 Classified the Risks into Commercial Risks and Risks of Damage
 Taken away the term Force Majeure
 The structure of employer and contractor in
DBO document
 The new DBO document format
 The format of the new document follows the traditional format
and layout of previous FIDIC documents, with 20 clauses, and,
where appropriate, using the same terminology and definitions
which are found in the other documents.
 The document will have General Conditions, Particular
Conditions, flow charts and sample forms – just like the other
FIDIC documents, and a Guide which will include, amongst
other things, guidelines on how to change the clauses if it is
required to have a document for a ‘brown field’ situation, or an
operation period significantly different to the previous method
adopted in other FIDIC contract.

More Related Content

PDF
FIDIC Red Book (PEC 2019).pdf
PPT
Fidic law1
PDF
The working of the Dispute Adjudication Board (DAB)
PPTX
Fidic.pptx
PPT
12953021.ppt
PDF
PEC Contract Management under the FIDIC Red Book Training Presentation 2019.pdf
PPTX
Ppt on fidic claims
PDF
FIDIC Presentation-2016.pdf
FIDIC Red Book (PEC 2019).pdf
Fidic law1
The working of the Dispute Adjudication Board (DAB)
Fidic.pptx
12953021.ppt
PEC Contract Management under the FIDIC Red Book Training Presentation 2019.pdf
Ppt on fidic claims
FIDIC Presentation-2016.pdf

Similar to dokumen.tips_fidic-power-point-presentation.pdf (20)

PDF
Fidic contract
PPT
FIDIC.RICS CPD Event Singapore 2012.ppt
PPTX
400618115-180522-FIDIC-2017-Edition-Workshop-May-2018.pptx
PPTX
GROUP 6 - FIDIC Conditions of Contract.pptx
PPT
FIDIC.RICS CPD Event Singapore 2012/.ppt
PPT
Awareness PPT - Fidic_slide_s_show 2015.ppt
PDF
A Contractor s Guide to the FIDIC Conditions of Contract 1st Edition Michael ...
PDF
The International Federation of Consulting Engineers.pdf
PDF
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
PDF
ICE-Learned-Event-Dubai-event for understanding contract management
DOCX
07 cl-assignment-syafiq-qy-macy-huiyong-deric
PDF
the arts of contarcb t amangeemnt and law
PDF
Fidic contracts management introduction
PDF
The FIDIC Forms of Contract Nael G. Bunni
PDF
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
PDF
FIDIC intro author eng. mohammed fadlalla
PDF
A Contractors Guide To The Fidic Conditions Of Contract 1st Edition Michael D...
PDF
Ss training fidic moustafa ismail 2017 _ lec. 1
PDF
459185713 Advanced FIDIC 2019 - Dushanbe 2019
PDF
Fidic db-yellow-book
Fidic contract
FIDIC.RICS CPD Event Singapore 2012.ppt
400618115-180522-FIDIC-2017-Edition-Workshop-May-2018.pptx
GROUP 6 - FIDIC Conditions of Contract.pptx
FIDIC.RICS CPD Event Singapore 2012/.ppt
Awareness PPT - Fidic_slide_s_show 2015.ppt
A Contractor s Guide to the FIDIC Conditions of Contract 1st Edition Michael ...
The International Federation of Consulting Engineers.pdf
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
ICE-Learned-Event-Dubai-event for understanding contract management
07 cl-assignment-syafiq-qy-macy-huiyong-deric
the arts of contarcb t amangeemnt and law
Fidic contracts management introduction
The FIDIC Forms of Contract Nael G. Bunni
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
FIDIC intro author eng. mohammed fadlalla
A Contractors Guide To The Fidic Conditions Of Contract 1st Edition Michael D...
Ss training fidic moustafa ismail 2017 _ lec. 1
459185713 Advanced FIDIC 2019 - Dushanbe 2019
Fidic db-yellow-book
Ad

Recently uploaded (20)

PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PPTX
Amdahl’s law is explained in the above power point presentations
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PPTX
Module 8- Technological and Communication Skills.pptx
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PDF
Design Guidelines and solutions for Plastics parts
PDF
Soil Improvement Techniques Note - Rabbi
PPTX
Management Information system : MIS-e-Business Systems.pptx
PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PDF
ChapteR012372321DFGDSFGDFGDFSGDFGDFGDFGSDFGDFGFD
PPTX
Information Storage and Retrieval Techniques Unit III
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
PDF
Abrasive, erosive and cavitation wear.pdf
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PPTX
CyberSecurity Mobile and Wireless Devices
PDF
August -2025_Top10 Read_Articles_ijait.pdf
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
Amdahl’s law is explained in the above power point presentations
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
Module 8- Technological and Communication Skills.pptx
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Design Guidelines and solutions for Plastics parts
Soil Improvement Techniques Note - Rabbi
Management Information system : MIS-e-Business Systems.pptx
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
ChapteR012372321DFGDSFGDFGDFSGDFGDFGDFGSDFGDFGFD
Information Storage and Retrieval Techniques Unit III
Exploratory_Data_Analysis_Fundamentals.pdf
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
Abrasive, erosive and cavitation wear.pdf
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
CyberSecurity Mobile and Wireless Devices
August -2025_Top10 Read_Articles_ijait.pdf
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Ad

dokumen.tips_fidic-power-point-presentation.pdf

  • 1. Introduction to FIDIC Conditions of contract Dr. Mirosław J. Skibniewski, A.J. Clark Chair Professor
  • 2.  New tendency in contracts worldwide
  • 4. OUTLINE 1. What is FIDIC? 2. Characteristics of FIDIC Conditions of Contract 3. Application Prospect of FIDIC Conditions of Contract 4. New development of FIDIC Conditions of contract
  • 5. What is FIDIC?  Management is a kind of science which needs continuous summarizing, to experience development and innovations through practice.  In the contract for international engineering projects, the function of Conditions of Contract is of greatest importance providing the rights, obligation and responsibility for the parties concerned in the Contract execution.
  • 6.  During the past half century, the International Federation of Consulting Engineers (FIDIC) has devoted itself to the compilation of management documents for all kinds of projects, among which the FIDIC Conditions of Contract are of the highest influence and are the most popular application.
  • 7.  The first edition of FIDIC Conditions of Contract for Works of Civil Engineering Construction (use “Red Book” in the following) was compiled in 1957, and later its second, third, and fourth edition were issued in 1963, 1977, and 1987 respectively.
  • 8.  But these editions were mostly compiled in the reference of the related documents of the Institution of Civil Engineers (ICE). The FIDIC and European International Contractors (EIC) entrusted the University of Reading in 1966 to summarize the experience and to draw lessons from the application of the former documents.
  • 9.  With the investigation of the governments, employers, contractors and consulting engineers all over the world about their application of the “Red Book”, 204 findings reports were returned. According to the findings, the FIDIC Contract Committee organized a group of experts to compile the new Contract Condition models to be applied in the 21stcentury.
  • 10.  The test edition of these models was published in 1998, and FIDIC solicited opinions throughout the world for additional time to publish the official texts in 1999.  Now FIDIC condition of contract has been applied worldwide, especially in the projects invested by World Bank, Asia Development Bank, Africa Development Bank etc.
  • 11. The new models include : FIDIC Conditions of Contract for Construction, the (New Red Book) FIDIC Conditions of Contract for Plant and Design/Build, the (New Yellow Book) FIDIC Conditions of Contract for EPC Turnkey Projects, the (Silver Book) FIDIC Short Form of Contract, the (Green Book) FIDIC Conditions of Contract (new edition) raised a higher requirement to the Parties concerned in the area of contract management
  • 13. 2. Characteristics of FIDIC Conditions of Contract  Unification of Terms and Clause  The new edition was drafted as the “New Red Book”, the “New Yellow Book” and the “Silver Book” by a workgroup under the leadership of the FIDIC Contract Committee. The contract form was not influenced by the former ICE framework, which was included in all 20 clauses. So if the clauses content could be unified, it would be under the same titles and expressions. In these three books, more than 80% of the content was consistent, and 85% of the definitions and expressions were the same. It is of great help for the users to understand them completely, saving study time.
  • 14.  Wider Application  When these new Conditions of Contract were drafted, FIDIC tried its best so the Conditions could be applied under not only the Customary Law (i.e. Anglo-American Law System), but also Civil Law. To pursue this, the contract working group had an attorney present to review the clauses, so that they could be applied under the two laws noted above. The new edition also shows more flexibility and adaptability. For example, in the old edition, the conditional performance guarantee was necessary, which the World Bank had different opinions of. While in the new edition, the guarantee forms were set by Particular Conditions which can be applied giving the employers better flexibility.
  • 15.  Applicability under Various Project Delivery and Contracting System 1. The “New Red Book” can be used in any kind of Engineering Construction Contract. 2. The “New Yellow Book” applies to the lump sum contract project where the Contractor takes participation in the design work. 3. The “Silver Book” applies to the turnkey projects of infrastructures or large-scale factories, where the Contractor takes on more work and risk while the Employer’s participation is small (private financing or government financing), but it is strictly defined upon the investment and construction period. 4. The “Green Book” can be used in all kinds of small-scale projects. 5. Altogether, these four Contract Conditions can be applied to nearly every kind of project, expect for that of managing contracting or simply consulting or designing
  • 16.  High-quality Provisions and Logical Clause Sequencing  Compared with the original “Red Book”, the “New Red Book” has 163 clauses, nearly 40% being freshly compiled. An additional 40% were modified and given supplements. Only 20% were kept intact. The old edition adopted ICE’s disorderly style bit in the clause sequence, while in the new edition, the related sub-clauses are put into one clause when possible, and convenient to the users.
  • 17.  More Specific Provisions concerning the Rights and Obligations of the Contract Parties  Taking the clause of Employer’s default as an example, we can see that in contrast to the “Red Book”,” three points are added into the “New Red Book”: two of them are concerned with payment. The above shows the strict requirements for the Employer. However, the Contractor shall institute a quality assurance system and submit to the Engineer to audit any aspect of the system before execution. Monthly progress reports shall be prepared by the Contractor to submit to the Engineer every month, otherwise, the payment won’t be given. Any kind of bribe can result in Contractor’s default. All of the above are high requirements for the Contractor.
  • 18.  Changes in the Preparing Style  General Conditions in the former edition were fairly concise; some recommendable clauses were given Particular Conditions. While in the new edition, there is a way around the regulations being that the General Conditions are relatively comprehensive and detailed. An example would be advanced payment and adjustment formula. The new edition writers believe that it is more convenient for the users to delete the clauses they do not need than to write them in the “Particular Conditions” by themselves.
  • 19.  Concise Language  The language and sentence structures in the new edition are rather easy to understand, and a great help to the people whose native language is not English.
  • 20. 3. Application Prospect of FIDIC Conditions of Contract  The traditional project management mode, which is universal in the world, has been applied in most of the engineering project management cases in the world.  The new edition has many advanced ideas and regulations such as standardizing of the Contract words and expressions, clearer and stricter claim procedure, and emphasis on the protection of intellectual property rights
  • 21.  To Solve the Problem of Back Payment using World Wide Experience for Reference  It is reported that the back payment and debt between the engineering units in China have added up to 280 billion (RMB), which is mostly Employer’s (government included) default to the Contractor. The problem has greatly influenced the construction corporations that their economic strength were weakened. The market needs a legal system to provide a guarantee for free and fair competition.
  • 22.  Since the problems of the Employer’s financial vacancy or Contractor financing are originating worldwide, the relative clauses and regulations are added into FIDIC Conditions of Contract. 1. Employer’s financial arrangement. The Employer shall submit within 28 days after receiving any request from the Contractor reasonable evidence that financial arrangement has been made. If the Employer intends to make any material change to his financial arrangement, he shall give notice to the Contractor with detailed particulars.
  • 23. 1. If the Employer fails to execute in accordance with this clause, the Contractor may, after giving a 21 days’ notice to the Employer, suspend the work or reduce production output as a kind of warning; if the Contractor does not receive any reasonable financial arrangement certificate within 42 days after giving the warning, he shall be entitled to terminate the Contract, for it is the Employer’s default. Also the Contractor can get all the compensation earned on the condition of Employer’s default.
  • 24. 2. It is defined in the clause of payment how to handle the problem when the Employer has the payment delayed. If the Contractor does not receive payment (in accordance with the Interim Payment Certificate) within 56 days after submitting monthly statement to the Engineer at the beginning of the month, the Contractor shall be entitled to receive interest compounded monthly on the amount unpaid during the period of delay. These financing changes shall be calculated at the annual rate of 3 percentage points above the discount rate of central bank in the country of the currency of payment. If the Contractor does not receive payment with in 42 days after the expiry of the above 56 days, he shall be entitled to terminate the Contract.
  • 25. 3. Contractor Financed Project’s execution. It is specially set up in the Particular Conditions an Example Provisions for Contractor Finance, which defines that if it is Contractor financing and he has committed to the project, the Employer shall deliver a bank payment guarantee to the Contractor within 28 days after both parties have entered into the Contract Agreement. If the Contractor does not receive the guarantee, the Engineer shall not issue the notice to commence. It is defined in the guarantee that if the Employer fails to make payment in full by the date 14 days after the expiry of the period specified in the contract as that within which such payment should have been made, the Contractor shall been entitled to demand for payment from the bank with a certificate, Contractor’s signatures which must be authenticated by his bankers or by a notary public.
  • 26.  To Carry out the General Contracting Mode of Design/Build and EPC Turnkey Enthusiastically  FIDIC makes out the “New Yellow Book” and “Silver Book” independently in addition to meet the development tendency of international project management mode.
  • 27.  According to the statistics and forecast of the American Design/Build Institution, the market share’s change tendency of American main engineering construction mode during 1985 to 2015 is shown in the Tab. 1.
  • 28.  To Make Clear the Position of the Construction Supervising Engineer, Raise Their Working Responsibility, and Open up New Regions of Work  In the “New Red Book”, it needs the Engineer to be timelier, and more explicit in solving the problems than before. It pays more respect to the position and the authority of the Engineer, such as, without the consent of the Contractor, the Employer shall not be entitled to exchange the Engineer or impose further restriction on the Engineer’s authority which has been specified in the contract.
  • 29.  Engineer’s authority includes:  Making it clear that the Engineer belongs to “Employer’s Personnel”, while there is no stress that he is an independent party.  When the Engineer makes a decision, there will be no more stress on impartiality, but he is still required to be fair.  If the Contractor and Employer have a heated dispute, there will be no need for the Engineer to mediate before either party applies for arbitration. So the Dispute Adjudication Board (DAB) has been set up to solve the problem
  • 30.  The mode of Engineer’s supervising is also applied in the “New Yellow Book”, while the responsibilities of Engineer are the same on the whole with what is said in the “New Red Book”, that is, the Engineer should manage not only the construction, but in designing, including reviewing and approving the qualification of the designer and sub-designer, Contractor’s design documents, participating in the discussion of the design, and instructing the Contractor to prepare further Documents. But any Engineer’s review, approval, or consent of the Contractor’s documents shall not relieve the Contractor from any obligation or responsibility.
  • 31.  To Prepare the MODEL of Short Form Contract  Many small scale and large scale projects can use simple techniques such as in residential areas, also need a contract. So we shall compile a short form of contract in reference to FIDIC “Green Book”. It is necessary to be fairly flexible in the mode and requirements of management.
  • 32.  To Improve the Mediation Methods for Dispute  The new edition takes the experience of USA and World Bank in solving the construction dispute, which results in DAB to mediate the dispute. The most outstanding merit of DAB is that it is composed of three experts who are chosen, approved and paid for by both parties.  These experts go to site to solve the dispute occurring between the two parties after commencing construction work. While in the FIDIC “Red Book”, the Engineer is required to mediate the problem which he can not handle. It is hard to be impartial because the Engineer is the Employer’s employee, so very often the contradiction will still be unsolved after a long time.
  • 33. New development of FIDIC conditions of contract --Design-Build Operate Contract It was published on September 2007, Gold Book
  • 34.  New DBO document for long-term contract  Background  The DBO approach to contracting combines design, construction, and long-term operation (and maintenance) of a facility into one single contract awarded to a single contractor (who will usually be a joint venture or consortium representing all the disciplines and skills called for in a DBO arrangement. Public private partnerships, PPPs, are this arrangement).
  • 35.  DBO’s advantages  Time: With possibilities to overlap some design and build activities it will be possible to minimize delays and optimize the smooth flow of construction activities.  Financial: With cost restraints and commitments and other risks being carried by the Contractor, there is less risk of price over-runs.  Quality: With the Contractor responsible for 20 years operation, he has an interest to design and build quality plant with low operation and maintenance costs. Not only will the plant be ‘fit for purpose’ but it will be built to last.
  • 36.  Basically the success of a true DBO contract depends on the commitment of the Contractor to the complete project - and the best way to do that is to cover the whole design-build and the operation elements in a single contract. That is why FIDIC chose a single long term Performance Security with a substantial reduction in value on completion of the design- build – but with an on-going commitment by the Contract to perform and complete the operation service.
  • 37.  The format of a DBO arrangement can be based on either a ‘green field’ scenario (D-B-O), or on a ‘brown field’ scenario (O-D-B). Either is quite common, however the contractual requirements and procedures are quite different.  FIDIC has chosen to produce a document based on the DBO green field scenario, with a Guide (which will be published in 2008) containing guidelines on the changes necessary to cover a brown field arrangement, in which FIDIC Yellow Book for the DB is the basement.
  • 38.  The other important factor considered in DBO document is the length of the operation period, since the conditions suitable for long-term operation are not necessarily suitable for a short-term operation. From the experience of the DBO members it was decided that the most useful period to consider was 20 years operation – again giving guidelines in the Guide if a shorter period would be required
  • 39.  Risk control in DBO contract  DBO can be viewed as a complete method in PPPs. This method is a long-term process including procurement, construction, operation, and transfer, in which high risk should be pay the most attention to.  About PPPs: A wide spectrum of options is available for the delivery of public infrastructure and services, ranging from direct provision by the government to outright privatization, with increasing responsibilities, risks, commitment, and rewards transferred from the government to the private sector.
  • 40.  For example, supply and service contracts usually have a short duration. In such contracts, the private contractor performs specified tasks (e.g., material/ equipment supplies, works construction and facilities maintenance) whereas it is not directly responsible for providing related services. In a lease- and-operate contract, the private contractor operates and maintains the facilities at its own risk against the payment of a lease fee. In a build-operate-transfer (BOT) project, the private contractor is also responsible for building and financing the project and it has to transfer project facilities in operational conditions and free of costs to the government at the end of the concession term. In divestiture, the ownership of existing assets and the responsibility for future expansion and upkeep are transferred to the private contractor, in addition to financing and carrying out the investments required to meet the obligations specified in the contract and/or a general regulatory framework.
  • 41. Successful PPPs Best Value for Money Needs for PPPs The problem of public sector budget restraint Non recourse or limited recourse public funding public money tied up in capital investment High public service costs More infrastructure facility need from society Procurement Improving procurement process Standardization of tender documents and contract Maintaining competitive environment for best offer Strong private consortium Appropriate risk allocation and risk sharing Available financial market Commitment/responsibility of public/private sectors Thorough and realistic cost/benefit assessment Well-organized public agency Favorable legal framework and transparency in the procurement Political support Design and building Innovative design, reengineering, avoiding over specification, and use of new material and technique Identification and classification of skills needed Sound economic policy Multi-benefit objectives operation Transfer management Post-transfer Appropriate PPP schemes Contract management Payment management Cost management Technology transfer Tariff/toll, price adjustment mechanism Facility management Environment friendly Payment management Contract management Cost management Training of new employees Provisions for selling project facilities to the concessionaire or further extension on concession Transfer price Standards of project facilities upon transfer Intellectual property rights Facility management Project renew Project renew  The whole process of a PPP (DBO) project and key issues are should in following figure.
  • 42.  Lots of risks have been identified as followed: It comes from L. Bing et al. (2005) The allocation of risk in PPP/PFI construction projects in the UK, International Journal of Project Management, 23: 25–35.
  • 44.  Therefore, a new DBO contract should handle these risks to pursue the successful projects. FIDIC has designed new clause to deal the risks in DBO contract:  Restructured Clauses 17 – 19 (Clause 17: Risk Allocation, Clause 18: Exceptional Risks, Clause 19: Insurance)  Identified the Risks to be carried by each Party  Differentiated between Risks during the Design-Build Period and Operation Service Period  Classified the Risks into Commercial Risks and Risks of Damage  Taken away the term Force Majeure
  • 45.  The structure of employer and contractor in DBO document
  • 46.  The new DBO document format  The format of the new document follows the traditional format and layout of previous FIDIC documents, with 20 clauses, and, where appropriate, using the same terminology and definitions which are found in the other documents.  The document will have General Conditions, Particular Conditions, flow charts and sample forms – just like the other FIDIC documents, and a Guide which will include, amongst other things, guidelines on how to change the clauses if it is required to have a document for a ‘brown field’ situation, or an operation period significantly different to the previous method adopted in other FIDIC contract.