Driving Innovative IT Metrics
Focusing on the CONDITIONS for Success
© 2013 Joe Hessmiller
1
2
© 2013 Joe Hessmiller
Schedule Check
You Are
Here
Joe Hessmiller
• Over 30 years in IT; analyst, programmer, technical
training manager, project manager, user interface
designer, project management consultant, consulting
sales and marketing manager.
• Worked with dozens of IT managers from Fortune 50
corporations and large government agencies.
• Current focus on software project risk management,
specifically, identifying, monitoring and use of project
risk “early warning signs”.
3
© 2013 Joe Hessmiller
1. To establish the need for monitoring the
metrics that really matter.
2. To identify the types of metrics that really
matter.
3. Show how a familiar framework can be
adapted for metrics identification (and
communication).
4. Give you enough to use back at your office to
improve your metrics program.
4
© 2013 Joe Hessmiller
Objectives of Session
Agenda
1. The Innovative Metrics Opportunity
2. Why Do These Opportunities Still Exist?
3. What Metrics Should We Monitor?
4. Working With Conditions Data
5. Developing Innovative Metrics for Your
Organization
5
© 2013 Joe Hessmiller
Part One
The Innovative Metrics
Opportunity
(in Project Management)
6
© 2013 Joe Hessmiller
7
• Despite Everything
We’ve Tried, Project
Success Rates Little
Changed in 30 Years
– McKinsey (17% threaten)
– IBM (40% met 10X range)
– KPMG (70% orgs)
– Standish CHAOS Report
Source: http://calleam.com/WTPF/?page_id=1445
The Innovative Metrics
Opportunity
8
• There Is Plenty of Opportunity for
Improving Project Success Rates
Source:
http://versionone.com/assets/img/files/ChaosMa
nifesto2013.pdf
Source:
http://versionone.com/assets/img/files/ChaosMa
nifesto2013.pdf
The Innovative Metrics
Opportunity
9
• Strategic Opportunity to Increase
Market Competitiveness
Organizations with a mature PMO outperform those
with an immature PMO by:
28% for on-time project delivery;
24% for on-budget delivery; and
20% for meeting original goals and business
intent of projects. Source: www.metier.com,
According to PMI
The Innovative Metrics
Opportunity
10
Source: Paul D. Nielsen, “About Us: From Director and CEO Paul D.
Nielsen,” Carnegie Mellon Software Engineering Institute,
http://www.sei.cmu.edu/about/message/
• Operational Opportunity to Address
Causes of Largest Project Cost
Component
According to the Carnegie Mellon Software Engineering
Institute, “Data indicate that 60-80% of the cost of software
development is in rework.”
The Innovative Metrics
Opportunity
Part Two
Why Do These “Opportunities”
Still Exist?
11
© 2013 Joe Hessmiller
12
• The “99% Complete”
Syndrome
– Everything is Fine…Everything is
Fine…
– Oh, Oh, SURPRISE! We‟re in Trouble!
• The real challenge to
successful software project
management is:
– having the information
– that is very DIFFICULT to collect,
analyze and act on
– in time to make a difference.
What
You
Know
What
You
Don‟t
Know…
but
Need
To
Know
Why Do These Opportunities
Still Exist?
13
• It‟s DIFFICULT to Have Project Managers
Who Can Predict the Future
Source:
http://versionone.com/assets
/img/files/ChaosManifesto20
13.pdf
Why Do These Opportunities
Still Exist?
14
• It‟s DIFFICULT to find project managers
who can keep everyone on the same
accurate, relevant and timely page.
Source:
http://versionone.com/assets
/img/files/ChaosManifesto20
13.pdf
Why Do These Opportunities
Still Exist?
15
• It‟s DIFFICULT to Trust the Service
Providers You Rely On When You Can‟t
Verify Their Behavior/Performance
Source:
http://versionone.com/assets
/img/files/ChaosManifesto20
13.pdf
Why Do These Opportunities
Still Exist?
SO…What Does an Innovative
Project Manager Need to Do?
16
• Address these DIFFICULT Project
Management Challenges
• By Having the Data That‟s Really
Needed to Be Successful
Part Three
What Metrics Should We
Monitor?
17
© 2013 Joe Hessmiller
What Metrics Should We
Monitor?
• Tracking Progress
–Backward Looking
• Managing Risk
–Forward Looking
18
© 2013 Joe Hessmiller
Tracking Progress
Looking Backward
• Volume
• Quality
• Cost
19
© 2013 Joe Hessmiller
What did we do?
• Alignment of IT Investments to Business Strategy
• Cumulative Business Value of IT Investment
• IT Spend Ratio – New Versus Maintenance
• Critical Business Services
– Customer Satisfaction
– Service Level Performance
• Operational Health
– Outages
– Security Incidents
– Project Success Rate
– Average Defect Rate
Source: Craig Symons, Forrester Research, 4-4-08
20
© 2013 Joe Hessmiller
Tracking Progress
Looking Backward – Enterprise Level
21
© 2013 Joe Hessmiller
http://www.slideshare.net/anandsubramaniam/project-metrics-measures
Tracking Progress
Looking Backward – Project Level
22
© 2013 Joe Hessmiller
Managing Risk
Looking Forward – Experts Agree on EWS
What should we do?
Managing Risk
Looking Forward – Kappelman Research
• Kappelman
Research
– Derived List of
• Six People Factors
• Six Process Factors
• For In-process
Audits
23
24
© 2013 Joe Hessmiller
Managing Risk
Looking Forward – Dominant Dozen
• Project
Management
Institute
– 10 Knowledge Areas
– Things You Should
Know
– Things You Should
Do
• For Gate Audits
25
Managing Risk
Looking Forward – Practitioners Too
• In Addition to Traditional
–Key Performance Status
• What To Collect
–Key Performance Conditions
• Intra-process Conditions
• Inter-process Conditions
–Key Process/Practice Compliance
26
© 2013 Joe Hessmiller
Summary: What Metrics Should
We Monitor?
• How Collect
–Intuition
–MBWA
–Survey Software
–Purpose Designed
Software
27
© 2013 Joe Hessmiller
What Metrics Should We
Monitor?
• Pattern Recognition
– Correlations Between Outcomes and
Precedent Conditions
• Feedback Loops
– Correlations Drive KPI Algorithms
Need to Collect the Data for the Insights
28
© 2013 Joe Hessmiller
The Future: PMBD
Project Management Big Data
Part Four
Working with Conditions Data
(The Four Missing Metrics)
29
© 2013 Joe Hessmiller
Three Important CONDITIONS to Monitor
• Expectations Management
• Sponsor Involvement
• Process Compliance
To Minimize Project Risk Factor
• Rework Probability
At 40% of total project costs, Rework is the leading cause of
projects running over budget and beyond schedule.
30
© 2013 Joe Hessmiller
Managing Risk
ESPR “The Missing Metrics”
The Four Missing Metrics
• SMART – Are expectations clear?
• SMPL – Is sponsor engaged?
• PAL - Are processes being
followed?
• PRPL – Are causes of
Rework being avoided?
31
© 2013 Joe Hessmiller
SMART
Level
Tracks the clarity of
assignments. The higher
the SMART Level, the
higher the level of
understanding of what is
expected. Therefore,
less Rework and less
management intervention
required.
The SMART Level
0.0
20.0
40.0
60.0
80.0
100.0
120.0
SMART Index
Upper Control Limit
Lower Control Limit
The SMART Level
32
© 2013 Joe Hessmiller
SMART
Level
Metric derived from
participant feedback on the
perceived
Specificity, Measurability, Ach
ievability, Relevancy and
Timeframes for their
assignments/deliverables.
SMART Index
Week
SMART
Index
Upper
Control
Limit
Lower
Control
Limit
Specific Measurable Achievable Relevant
Time-
Based
8/10/2010 76.3 100 75 75 50 80 100 95
8/17/2010 76.3 100 75 75 50 80 100 90
8/24/2010 75.0 100 75 75 50 80 95 95
8/31/2010 82.5 100 75 80 70 85 95 95
9/7/2010 83.8 100 75 80 70 85 100 95
9/14/2010 82.5 100 75 90 70 85 85 90
9/21/2010 87.5 100 75 90 90 80 90 90
9/28/2010 92.5 100 75 100 90 80 100 90
10/5/2010 88.8 100 75 100 90 75 90 95
10/12/2010 86.3 100 75 90 90 75 90 95
10/19/2010 87.5 100 75 90 90 75 95 85
10/26/2010 88.8 100 75 90 90 80 95 85
11/2/2010 92.5 100 75 95 95 80 100 90
11/9/2010 92.5 100 75 95 90 85 100 95
11/16/2010 93.8 100 75 100 90 85 100 95
11/23/2010 93.8 100 75 100 100 85 90 100
11/30/2010 93.8 100 75 100 100 80 95 95
12/7/2010 88.8 100 75 90 90 85 90 90
12/14/2010 92.5 100 75 90 90 90 100 95
12/21/2010 95.0 100 75 95 95 95 95 95
12/28/2010 92.5 100 75 90 80 100 100 100
Components of the SMART
Level
The SMART Level
33
© 2013 Joe Hessmiller
SMART
Level
Looks like this project was
back under control once the
Relevance of the
assignments were made
clear to the staff.
40.0
50.0
60.0
70.0
80.0
90.0
100.0
110.0
SMART Index
Upper Control Limit
Lower Control Limit
Specific
Measurable
Achievable
Relevant
Time-Based
The SMART Level
SMART Level Influencers
34
© 2013 Joe Hessmiller
SMPL
Line
Tracks the
participation level of
the senior
management and/or
sponsor.
The SMPL Line
Senior Management Participation Level
Attention
Needed
0.0
20.0
40.0
60.0
80.0
100.0
120.0
SMPL
Upper Control Limit
Lower Control Limit
35
© 2013 Joe Hessmiller
SMPL
Line
In this example, the
level of participation in
meetings, surveys, an
d other activities is
compared to the
planned participation
by senior
management
Senior Management Participation Level
Components of the SMPL Line
36
© 2013 Joe Hessmiller
SMPL
Line
In this example, the
components of the
SMPL are shown
separately to identify
individual areas
needing improvement.
Senior Management Participation Level
0.0
20.0
40.0
60.0
80.0
100.0
120.0
SMPL
Upper Control Limit
Lower Control Limit
Status Meeting
Attendenace Rate
APO Response Rate
Decisions
Made/Delegated Rate
SMPL Line Influences
37
© 2013 Joe Hessmiller
PAL
Measures likely level of
process adherence
based on conditions that
would tend to lead to
„short cuts‟ on process..
Process Adherence Likelihood
38
© 2013 Joe Hessmiller
PAL
This table shows how
problems with EVA
lead to likely
abandonment of
process until project
gets back on track.
May be OK, must be
identified to be
managed.
Process Adherence Likelihood
Components of PAL Line
39
© 2013 Joe Hessmiller
PAL
This illustrates the various
components of PAL.
PAL Line Influences
40
© 2013 Joe Hessmiller
Project Rework Probability Level
PRPL
Line
Tracks the „probability‟
of Rework based on
changes in the
conditions that are
known to cause
Rework.
0.0
5.0
10.0
15.0
20.0
25.0
PRPL
Upper Control Limit
Lower Control Limit
Attention
Needed
The PRPL Line
41
© 2013 Joe Hessmiller
PRPL
Line
SME
Involvement, Team
Confidence
Level, Technical
Capability and
Requirements
Stability are
components of PRPL
Line.
Project Rework Probability Level (PRPL)
Week PRPL
Upper
Control
Limit
Lower
Control
Limit
SME
Involvement
Technical
Capability
Requirements
Stability
Confidence
Level
8/10/2010 5.0 20 0 100 100 80 100
8/17/2010 10.0 20 0 80 100 80 100
8/24/2010 12.5 20 0 80 100 80 90
8/31/2010 22.5 20 0 70 90 70 80
9/7/2010 17.5 20 0 80 90 70 90
9/14/2010 16.3 20 0 80 90 75 90
9/21/2010 11.3 20 0 80 90 85 100
9/28/2010 23.8 20 0 80 60 85 80
10/5/2010 23.8 20 0 80 60 85 80
10/12/2010 23.8 20 0 80 60 85 80
10/19/2010 18.8 20 0 65 90 85 85
10/26/2010 21.3 20 0 70 90 70 85
11/2/2010 16.3 20 0 80 90 70 95
11/9/2010 16.3 20 0 80 90 70 95
11/16/2010 16.3 20 0 80 80 80 95
11/23/2010 16.3 20 0 80 80 80 95
11/30/2010 17.5 20 0 80 80 80 90
12/7/2010 12.5 20 0 80 90 80 100
12/14/2010 8.8 20 0 85 90 90 100
12/21/2010 5.0 20 0 90 100 90 100
12/28/2010 0.0 20 0 100 100 100 100
Project Rework Probability Level
Components of PRPL Line
42
© 2013 Joe Hessmiller
PRPL
Line
SME
Involvement, Team
Confidence
Level, Technical
Capability and
Requirements
Stability influence
rework probability.
Project Rework Probability Level
0.0
20.0
40.0
60.0
80.0
100.0
120.0
PRPL
Upper Control Limit
Lower Control Limit
SME Involvement
Confidence Level
Technical Capability
Requirements Stability
PRPL Line Influences
43
© 2013 Joe Hessmiller
Part Five
Developing Innovative Metrics
for Your Organization
44
© 2013 Joe Hessmiller
Five “C”s of Effective Metrics
• Connected to important goals (G-Q-M)
• Complete so that all the factors important to
achieving the goal are included
• Current so that they reflect current goals
• Communicated so that they drive behavior
• Calibrated so that values are comparable
across organizations and over time.
Source: Bob Lewis, InfoWorld, 12-28-11
45
© 2013 Joe Hessmiller
A Gauge for Every Condition
Automotive Engineers Long Ago Defined
the Critical Measures for Safe, Effective
Engine Operation.
46
© 2013 Joe Hessmiller
The Basic Automobile
Dashboard
Automotive Gauge
Odometer
Clock
Fuel Level
Speedometer
Tachometer
Oil Pressure
Oil Temperature
Water Pressure
Water Temperature
Voltmeter
47
© 2013 Joe Hessmiller
What Questions Are We
Asking?
Automotive Gauge Asks the Question
Odometer
How far have we gone?
Clock How much time has it taken?
Fuel Level How far can we go?
Speedometer How fast are we going now?
Tachometer How intensely is engine working?
Oil Pressure Do we have enough „lubrication‟ to keep parts
working well together?
Oil Temperature How smooth are interactions?
Water Pressure Do we have enough coolant to keep the engine
producing?
Water Temperature How effective is the coolant in keeping the
engine cool?
Voltmeter Is enough energy being applied to the other
important systems?
48
© 2013 Joe Hessmiller
The Basic Measures
Automotive Gauge Asks the Question To Measure
Odometer How far? Deliverables Delivered
Clock How long? Duration
Fuel Level How much further? Input Units Available
Speedometer How fast? Deliverables per Unit of Time
Tachometer How intensely? Effort Intensity
Oil Pressure Do we have enough lubrication to
smooth interactions?
Supply of Lubricant to Smooth Interaction
Between Components
Oil Temperature How smooth are interactions? Ability of Lubricant to smooth Interaction
Between Components
Water Pressure Do we have enough coolant to keep the
engine producing?
Supply of Coolant to dissipate excess
engine heat
Water Temperature How effective is the coolant in keeping
the engine cool?
Ability of Coolant to dissipate engine heat
Voltmeter Is enough energy being applied to the
other important systems?
Ability to Support other Control and
Comfort Systems
49
© 2013 Joe Hessmiller
Comparative Metrics
To Measure
Automotive
Metric IT Metric
Deliverables Delivered Miles Service Level Achieved, Function Point Delivered
Duration Hour Hour
Input Units Available Gallons Resource Hour
Deliverables per Unit of Time Miles Per Hour Earned Value Per Clock Hour
Effort Intensity RPM Hours Worked Per Week/Available Hours
Supply of Lubricant to Smooth
Interaction Between Components
PSI Stakeholder Interaction Satisfaction
Ability of Lubricant to Smooth Interaction
Between Components
Degrees Number of Open Issues from Stakeholder Interactions
Supply of Coolant to dissipate excess
engine heat
PSI Duration to Close Issues/Number of Issues
Ability of Coolant to dissipate engine
heat
Degrees Number of Escalated Issues
Ability to Support other Control and
Comfort Systems
Volts On Time Process Deliverables (Status, Reporting, Training)
50
© 2013 Joe Hessmiller
The More Complex the Project
Environment…
51
© 2013 Joe Hessmiller
• To establish the need for monitoring the metrics
that really matter.
• To identify the types of metrics that really
matter.
• Show how familiar framework can be adapted
for metrics identification (and communication).
• Give you enough to use back at your office to
improve your metrics program.
52
© 2013 Joe Hessmiller
Objective of Session

More Related Content

PPTX
Measurement of Project Management Success
PPTX
The metrics that matter using scalability metrics for project planning of a d...
PPT
Webinar: Metrics Management - Be Careful What You Wish For!
PDF
Quality Metrics
PDF
Why meaning matters - Outcomes, Benefits, CSFs, KPIs, Metrics and Measures
PPT
Methods for evaluating project performance
PPT
Project performance tracking analysis and reporting
PDF
Monitor and Control Process Group - Part One
Measurement of Project Management Success
The metrics that matter using scalability metrics for project planning of a d...
Webinar: Metrics Management - Be Careful What You Wish For!
Quality Metrics
Why meaning matters - Outcomes, Benefits, CSFs, KPIs, Metrics and Measures
Methods for evaluating project performance
Project performance tracking analysis and reporting
Monitor and Control Process Group - Part One

What's hot (16)

PDF
Benchmarking Project Schedules
PPTX
project management information system
PDF
InfinityQS_Quality Metrics Survival Handbook final_042413
PPT
Project Integration Management
PDF
Pmbok 5th planning process group part three
PPTX
Project: Monitoring
PDF
Pmbok 5th planning process group part two
PDF
PMBOK 5th Planning Process Group Part One
PPT
Project Management
PPTX
Measurement of project quality performance
PPT
Dmaic
PPT
1.2 workflow and_process_redesign
 
PDF
Pmbok 5th executing process group
PDF
Project cost management PMBOK 5th Edition
PDF
Risk management overview
PPTX
08 projectqualitymanagement
Benchmarking Project Schedules
project management information system
InfinityQS_Quality Metrics Survival Handbook final_042413
Project Integration Management
Pmbok 5th planning process group part three
Project: Monitoring
Pmbok 5th planning process group part two
PMBOK 5th Planning Process Group Part One
Project Management
Measurement of project quality performance
Dmaic
1.2 workflow and_process_redesign
 
Pmbok 5th executing process group
Project cost management PMBOK 5th Edition
Risk management overview
08 projectqualitymanagement
Ad

Viewers also liked (9)

DOCX
Pm 0015 – quantitative methods in project management winter 2014
PPT
Software metrics
PPTX
Managing project performance: alignment of Agile and traditional metrics
PPT
Quantitative Project Risk Analysis
PDF
PMO Performance Measurement and Metrics - Kendrick
PDF
The Metrics of Project Management Performance and PMBOK
PPT
Quantitative approach 1
PPT
Quantitative techniques introduction 19 pages
PPTX
The Three Things You Need to Know to Transform Any Size Organization Into an ...
Pm 0015 – quantitative methods in project management winter 2014
Software metrics
Managing project performance: alignment of Agile and traditional metrics
Quantitative Project Risk Analysis
PMO Performance Measurement and Metrics - Kendrick
The Metrics of Project Management Performance and PMBOK
Quantitative approach 1
Quantitative techniques introduction 19 pages
The Three Things You Need to Know to Transform Any Size Organization Into an ...
Ad

Similar to Driving Innovative IT Metrics (Project Management Institute Presentation) (20)

PPTX
Driving Innovative IT Metrics (Project Management Institute Presentation)
PPTX
Ba process plan- IGATE Global Solutions LTD
PPTX
Project Brief template.pptx
PDF
The Seven Enablers & Constraints Of IT Service Management - Research Update 2011
PDF
The 7 enablers and constraints of itsm 2011 v1 final
PPTX
Maximize your Lean ROI
PPTX
IT Business Value
PDF
PMO and PPM Best Practices
PPTX
Core Skills for Change Agents
PPT
Jason uyderv pmi 2 16 12
PPTX
SPS Abu Dhabi Communicating The Business Value of SharePoint
PPTX
Learning Six Sigma
PDF
Tools guide
PDF
Betsol | Machine Learning for IT Project Estimates
PPTX
Top Ten Reasons For Project Failure - PMP Webinar
PPT
six-sigma2040.ppt
PPTX
Leading the way in six sigma
PPTX
An Overview of Scenario Planning - Introduction, Overview and Examples
PDF
12 Guidelines For Success in Data Quality Projects
PDF
Self-service Analytic for Business Users-19july2017-final
Driving Innovative IT Metrics (Project Management Institute Presentation)
Ba process plan- IGATE Global Solutions LTD
Project Brief template.pptx
The Seven Enablers & Constraints Of IT Service Management - Research Update 2011
The 7 enablers and constraints of itsm 2011 v1 final
Maximize your Lean ROI
IT Business Value
PMO and PPM Best Practices
Core Skills for Change Agents
Jason uyderv pmi 2 16 12
SPS Abu Dhabi Communicating The Business Value of SharePoint
Learning Six Sigma
Tools guide
Betsol | Machine Learning for IT Project Estimates
Top Ten Reasons For Project Failure - PMP Webinar
six-sigma2040.ppt
Leading the way in six sigma
An Overview of Scenario Planning - Introduction, Overview and Examples
12 Guidelines For Success in Data Quality Projects
Self-service Analytic for Business Users-19july2017-final

More from Joe Hessmiller (8)

PPTX
Comprehensive risk management for a cyber secure organization
PPTX
Tale of the Four Missing Metrics
PPTX
Leadership is Simple. Followership is a Challenge. Lehigh University Guest L...
PPTX
Why Do CIOs Get Fired? A Look at the Numbers and Insights by Joe Hessmiller
PPT
Managing the Evolution of Software Systems: The Old, the New and What's Consi...
PPTX
Automation of Information (Cyber) Security by Joe Hessmiller
PPT
Knowledge Management - It's Not a Good Idea If It Can't Be Implemented by Joe...
PPTX
Estimating the Economic Value of Software Maintenance Improvement by Joe Hess...
Comprehensive risk management for a cyber secure organization
Tale of the Four Missing Metrics
Leadership is Simple. Followership is a Challenge. Lehigh University Guest L...
Why Do CIOs Get Fired? A Look at the Numbers and Insights by Joe Hessmiller
Managing the Evolution of Software Systems: The Old, the New and What's Consi...
Automation of Information (Cyber) Security by Joe Hessmiller
Knowledge Management - It's Not a Good Idea If It Can't Be Implemented by Joe...
Estimating the Economic Value of Software Maintenance Improvement by Joe Hess...

Recently uploaded (20)

PDF
Geopolitics and the Dynamic Competition Framework
PPTX
Ryan Daly Gallardo Prod Management PPT .pptx
PPTX
WORLD TRADE ORAGANIZATION- INSTITUTION TO MANAGE TRADE BETWEEN NATIONS
PPTX
Common Methods of Performance Appraisal.pptx
PDF
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
PDF
How to Present a Project Proposal to Stakeholders for Approval?
PPTX
Lean Thinking: Making Efficiency an Everyday Thing
PDF
Personal-Professional-Development-in-Nursing-1.pdf
PPTX
Human resources planning and job design ppt.
PPTX
Principles & Theories of Mgt-Master in PM.pptx
PPTX
Management and Leadership across diverse culture
PPTX
Spotlight on road Injury in the Philippines
PPTX
HRM mmm presentation pragati pandey.pptx
PPTX
SM_Behavior Based Safety (BBS)_Unit V.pptx
PPTX
Organizing and Staffing, Staffing process.pptx
PPTX
Recruitment and bshiwjwnbshshshshhshvej.ppt
PPTX
management development and careerr planning.pptx
PPT
Operations Management Supply-Chain Management
PPTX
EMOTIONAL INTELLIGENCE IN LEADERSHIP.pptx
PPTX
Organisational behaviour_ managerial applications of perception
Geopolitics and the Dynamic Competition Framework
Ryan Daly Gallardo Prod Management PPT .pptx
WORLD TRADE ORAGANIZATION- INSTITUTION TO MANAGE TRADE BETWEEN NATIONS
Common Methods of Performance Appraisal.pptx
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
How to Present a Project Proposal to Stakeholders for Approval?
Lean Thinking: Making Efficiency an Everyday Thing
Personal-Professional-Development-in-Nursing-1.pdf
Human resources planning and job design ppt.
Principles & Theories of Mgt-Master in PM.pptx
Management and Leadership across diverse culture
Spotlight on road Injury in the Philippines
HRM mmm presentation pragati pandey.pptx
SM_Behavior Based Safety (BBS)_Unit V.pptx
Organizing and Staffing, Staffing process.pptx
Recruitment and bshiwjwnbshshshshhshvej.ppt
management development and careerr planning.pptx
Operations Management Supply-Chain Management
EMOTIONAL INTELLIGENCE IN LEADERSHIP.pptx
Organisational behaviour_ managerial applications of perception

Driving Innovative IT Metrics (Project Management Institute Presentation)

  • 1. Driving Innovative IT Metrics Focusing on the CONDITIONS for Success © 2013 Joe Hessmiller 1
  • 2. 2 © 2013 Joe Hessmiller Schedule Check You Are Here
  • 3. Joe Hessmiller • Over 30 years in IT; analyst, programmer, technical training manager, project manager, user interface designer, project management consultant, consulting sales and marketing manager. • Worked with dozens of IT managers from Fortune 50 corporations and large government agencies. • Current focus on software project risk management, specifically, identifying, monitoring and use of project risk “early warning signs”. 3 © 2013 Joe Hessmiller
  • 4. 1. To establish the need for monitoring the metrics that really matter. 2. To identify the types of metrics that really matter. 3. Show how a familiar framework can be adapted for metrics identification (and communication). 4. Give you enough to use back at your office to improve your metrics program. 4 © 2013 Joe Hessmiller Objectives of Session
  • 5. Agenda 1. The Innovative Metrics Opportunity 2. Why Do These Opportunities Still Exist? 3. What Metrics Should We Monitor? 4. Working With Conditions Data 5. Developing Innovative Metrics for Your Organization 5 © 2013 Joe Hessmiller
  • 6. Part One The Innovative Metrics Opportunity (in Project Management) 6 © 2013 Joe Hessmiller
  • 7. 7 • Despite Everything We’ve Tried, Project Success Rates Little Changed in 30 Years – McKinsey (17% threaten) – IBM (40% met 10X range) – KPMG (70% orgs) – Standish CHAOS Report Source: http://calleam.com/WTPF/?page_id=1445 The Innovative Metrics Opportunity
  • 8. 8 • There Is Plenty of Opportunity for Improving Project Success Rates Source: http://versionone.com/assets/img/files/ChaosMa nifesto2013.pdf Source: http://versionone.com/assets/img/files/ChaosMa nifesto2013.pdf The Innovative Metrics Opportunity
  • 9. 9 • Strategic Opportunity to Increase Market Competitiveness Organizations with a mature PMO outperform those with an immature PMO by: 28% for on-time project delivery; 24% for on-budget delivery; and 20% for meeting original goals and business intent of projects. Source: www.metier.com, According to PMI The Innovative Metrics Opportunity
  • 10. 10 Source: Paul D. Nielsen, “About Us: From Director and CEO Paul D. Nielsen,” Carnegie Mellon Software Engineering Institute, http://www.sei.cmu.edu/about/message/ • Operational Opportunity to Address Causes of Largest Project Cost Component According to the Carnegie Mellon Software Engineering Institute, “Data indicate that 60-80% of the cost of software development is in rework.” The Innovative Metrics Opportunity
  • 11. Part Two Why Do These “Opportunities” Still Exist? 11 © 2013 Joe Hessmiller
  • 12. 12 • The “99% Complete” Syndrome – Everything is Fine…Everything is Fine… – Oh, Oh, SURPRISE! We‟re in Trouble! • The real challenge to successful software project management is: – having the information – that is very DIFFICULT to collect, analyze and act on – in time to make a difference. What You Know What You Don‟t Know… but Need To Know Why Do These Opportunities Still Exist?
  • 13. 13 • It‟s DIFFICULT to Have Project Managers Who Can Predict the Future Source: http://versionone.com/assets /img/files/ChaosManifesto20 13.pdf Why Do These Opportunities Still Exist?
  • 14. 14 • It‟s DIFFICULT to find project managers who can keep everyone on the same accurate, relevant and timely page. Source: http://versionone.com/assets /img/files/ChaosManifesto20 13.pdf Why Do These Opportunities Still Exist?
  • 15. 15 • It‟s DIFFICULT to Trust the Service Providers You Rely On When You Can‟t Verify Their Behavior/Performance Source: http://versionone.com/assets /img/files/ChaosManifesto20 13.pdf Why Do These Opportunities Still Exist?
  • 16. SO…What Does an Innovative Project Manager Need to Do? 16 • Address these DIFFICULT Project Management Challenges • By Having the Data That‟s Really Needed to Be Successful
  • 17. Part Three What Metrics Should We Monitor? 17 © 2013 Joe Hessmiller
  • 18. What Metrics Should We Monitor? • Tracking Progress –Backward Looking • Managing Risk –Forward Looking 18 © 2013 Joe Hessmiller
  • 19. Tracking Progress Looking Backward • Volume • Quality • Cost 19 © 2013 Joe Hessmiller What did we do?
  • 20. • Alignment of IT Investments to Business Strategy • Cumulative Business Value of IT Investment • IT Spend Ratio – New Versus Maintenance • Critical Business Services – Customer Satisfaction – Service Level Performance • Operational Health – Outages – Security Incidents – Project Success Rate – Average Defect Rate Source: Craig Symons, Forrester Research, 4-4-08 20 © 2013 Joe Hessmiller Tracking Progress Looking Backward – Enterprise Level
  • 21. 21 © 2013 Joe Hessmiller http://www.slideshare.net/anandsubramaniam/project-metrics-measures Tracking Progress Looking Backward – Project Level
  • 22. 22 © 2013 Joe Hessmiller Managing Risk Looking Forward – Experts Agree on EWS What should we do?
  • 23. Managing Risk Looking Forward – Kappelman Research • Kappelman Research – Derived List of • Six People Factors • Six Process Factors • For In-process Audits 23
  • 24. 24 © 2013 Joe Hessmiller Managing Risk Looking Forward – Dominant Dozen
  • 25. • Project Management Institute – 10 Knowledge Areas – Things You Should Know – Things You Should Do • For Gate Audits 25 Managing Risk Looking Forward – Practitioners Too
  • 26. • In Addition to Traditional –Key Performance Status • What To Collect –Key Performance Conditions • Intra-process Conditions • Inter-process Conditions –Key Process/Practice Compliance 26 © 2013 Joe Hessmiller Summary: What Metrics Should We Monitor?
  • 27. • How Collect –Intuition –MBWA –Survey Software –Purpose Designed Software 27 © 2013 Joe Hessmiller What Metrics Should We Monitor?
  • 28. • Pattern Recognition – Correlations Between Outcomes and Precedent Conditions • Feedback Loops – Correlations Drive KPI Algorithms Need to Collect the Data for the Insights 28 © 2013 Joe Hessmiller The Future: PMBD Project Management Big Data
  • 29. Part Four Working with Conditions Data (The Four Missing Metrics) 29 © 2013 Joe Hessmiller
  • 30. Three Important CONDITIONS to Monitor • Expectations Management • Sponsor Involvement • Process Compliance To Minimize Project Risk Factor • Rework Probability At 40% of total project costs, Rework is the leading cause of projects running over budget and beyond schedule. 30 © 2013 Joe Hessmiller Managing Risk ESPR “The Missing Metrics”
  • 31. The Four Missing Metrics • SMART – Are expectations clear? • SMPL – Is sponsor engaged? • PAL - Are processes being followed? • PRPL – Are causes of Rework being avoided? 31 © 2013 Joe Hessmiller
  • 32. SMART Level Tracks the clarity of assignments. The higher the SMART Level, the higher the level of understanding of what is expected. Therefore, less Rework and less management intervention required. The SMART Level 0.0 20.0 40.0 60.0 80.0 100.0 120.0 SMART Index Upper Control Limit Lower Control Limit The SMART Level 32 © 2013 Joe Hessmiller
  • 33. SMART Level Metric derived from participant feedback on the perceived Specificity, Measurability, Ach ievability, Relevancy and Timeframes for their assignments/deliverables. SMART Index Week SMART Index Upper Control Limit Lower Control Limit Specific Measurable Achievable Relevant Time- Based 8/10/2010 76.3 100 75 75 50 80 100 95 8/17/2010 76.3 100 75 75 50 80 100 90 8/24/2010 75.0 100 75 75 50 80 95 95 8/31/2010 82.5 100 75 80 70 85 95 95 9/7/2010 83.8 100 75 80 70 85 100 95 9/14/2010 82.5 100 75 90 70 85 85 90 9/21/2010 87.5 100 75 90 90 80 90 90 9/28/2010 92.5 100 75 100 90 80 100 90 10/5/2010 88.8 100 75 100 90 75 90 95 10/12/2010 86.3 100 75 90 90 75 90 95 10/19/2010 87.5 100 75 90 90 75 95 85 10/26/2010 88.8 100 75 90 90 80 95 85 11/2/2010 92.5 100 75 95 95 80 100 90 11/9/2010 92.5 100 75 95 90 85 100 95 11/16/2010 93.8 100 75 100 90 85 100 95 11/23/2010 93.8 100 75 100 100 85 90 100 11/30/2010 93.8 100 75 100 100 80 95 95 12/7/2010 88.8 100 75 90 90 85 90 90 12/14/2010 92.5 100 75 90 90 90 100 95 12/21/2010 95.0 100 75 95 95 95 95 95 12/28/2010 92.5 100 75 90 80 100 100 100 Components of the SMART Level The SMART Level 33 © 2013 Joe Hessmiller
  • 34. SMART Level Looks like this project was back under control once the Relevance of the assignments were made clear to the staff. 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0 SMART Index Upper Control Limit Lower Control Limit Specific Measurable Achievable Relevant Time-Based The SMART Level SMART Level Influencers 34 © 2013 Joe Hessmiller
  • 35. SMPL Line Tracks the participation level of the senior management and/or sponsor. The SMPL Line Senior Management Participation Level Attention Needed 0.0 20.0 40.0 60.0 80.0 100.0 120.0 SMPL Upper Control Limit Lower Control Limit 35 © 2013 Joe Hessmiller
  • 36. SMPL Line In this example, the level of participation in meetings, surveys, an d other activities is compared to the planned participation by senior management Senior Management Participation Level Components of the SMPL Line 36 © 2013 Joe Hessmiller
  • 37. SMPL Line In this example, the components of the SMPL are shown separately to identify individual areas needing improvement. Senior Management Participation Level 0.0 20.0 40.0 60.0 80.0 100.0 120.0 SMPL Upper Control Limit Lower Control Limit Status Meeting Attendenace Rate APO Response Rate Decisions Made/Delegated Rate SMPL Line Influences 37 © 2013 Joe Hessmiller
  • 38. PAL Measures likely level of process adherence based on conditions that would tend to lead to „short cuts‟ on process.. Process Adherence Likelihood 38 © 2013 Joe Hessmiller
  • 39. PAL This table shows how problems with EVA lead to likely abandonment of process until project gets back on track. May be OK, must be identified to be managed. Process Adherence Likelihood Components of PAL Line 39 © 2013 Joe Hessmiller
  • 40. PAL This illustrates the various components of PAL. PAL Line Influences 40 © 2013 Joe Hessmiller
  • 41. Project Rework Probability Level PRPL Line Tracks the „probability‟ of Rework based on changes in the conditions that are known to cause Rework. 0.0 5.0 10.0 15.0 20.0 25.0 PRPL Upper Control Limit Lower Control Limit Attention Needed The PRPL Line 41 © 2013 Joe Hessmiller
  • 42. PRPL Line SME Involvement, Team Confidence Level, Technical Capability and Requirements Stability are components of PRPL Line. Project Rework Probability Level (PRPL) Week PRPL Upper Control Limit Lower Control Limit SME Involvement Technical Capability Requirements Stability Confidence Level 8/10/2010 5.0 20 0 100 100 80 100 8/17/2010 10.0 20 0 80 100 80 100 8/24/2010 12.5 20 0 80 100 80 90 8/31/2010 22.5 20 0 70 90 70 80 9/7/2010 17.5 20 0 80 90 70 90 9/14/2010 16.3 20 0 80 90 75 90 9/21/2010 11.3 20 0 80 90 85 100 9/28/2010 23.8 20 0 80 60 85 80 10/5/2010 23.8 20 0 80 60 85 80 10/12/2010 23.8 20 0 80 60 85 80 10/19/2010 18.8 20 0 65 90 85 85 10/26/2010 21.3 20 0 70 90 70 85 11/2/2010 16.3 20 0 80 90 70 95 11/9/2010 16.3 20 0 80 90 70 95 11/16/2010 16.3 20 0 80 80 80 95 11/23/2010 16.3 20 0 80 80 80 95 11/30/2010 17.5 20 0 80 80 80 90 12/7/2010 12.5 20 0 80 90 80 100 12/14/2010 8.8 20 0 85 90 90 100 12/21/2010 5.0 20 0 90 100 90 100 12/28/2010 0.0 20 0 100 100 100 100 Project Rework Probability Level Components of PRPL Line 42 © 2013 Joe Hessmiller
  • 43. PRPL Line SME Involvement, Team Confidence Level, Technical Capability and Requirements Stability influence rework probability. Project Rework Probability Level 0.0 20.0 40.0 60.0 80.0 100.0 120.0 PRPL Upper Control Limit Lower Control Limit SME Involvement Confidence Level Technical Capability Requirements Stability PRPL Line Influences 43 © 2013 Joe Hessmiller
  • 44. Part Five Developing Innovative Metrics for Your Organization 44 © 2013 Joe Hessmiller
  • 45. Five “C”s of Effective Metrics • Connected to important goals (G-Q-M) • Complete so that all the factors important to achieving the goal are included • Current so that they reflect current goals • Communicated so that they drive behavior • Calibrated so that values are comparable across organizations and over time. Source: Bob Lewis, InfoWorld, 12-28-11 45 © 2013 Joe Hessmiller
  • 46. A Gauge for Every Condition Automotive Engineers Long Ago Defined the Critical Measures for Safe, Effective Engine Operation. 46 © 2013 Joe Hessmiller
  • 47. The Basic Automobile Dashboard Automotive Gauge Odometer Clock Fuel Level Speedometer Tachometer Oil Pressure Oil Temperature Water Pressure Water Temperature Voltmeter 47 © 2013 Joe Hessmiller
  • 48. What Questions Are We Asking? Automotive Gauge Asks the Question Odometer How far have we gone? Clock How much time has it taken? Fuel Level How far can we go? Speedometer How fast are we going now? Tachometer How intensely is engine working? Oil Pressure Do we have enough „lubrication‟ to keep parts working well together? Oil Temperature How smooth are interactions? Water Pressure Do we have enough coolant to keep the engine producing? Water Temperature How effective is the coolant in keeping the engine cool? Voltmeter Is enough energy being applied to the other important systems? 48 © 2013 Joe Hessmiller
  • 49. The Basic Measures Automotive Gauge Asks the Question To Measure Odometer How far? Deliverables Delivered Clock How long? Duration Fuel Level How much further? Input Units Available Speedometer How fast? Deliverables per Unit of Time Tachometer How intensely? Effort Intensity Oil Pressure Do we have enough lubrication to smooth interactions? Supply of Lubricant to Smooth Interaction Between Components Oil Temperature How smooth are interactions? Ability of Lubricant to smooth Interaction Between Components Water Pressure Do we have enough coolant to keep the engine producing? Supply of Coolant to dissipate excess engine heat Water Temperature How effective is the coolant in keeping the engine cool? Ability of Coolant to dissipate engine heat Voltmeter Is enough energy being applied to the other important systems? Ability to Support other Control and Comfort Systems 49 © 2013 Joe Hessmiller
  • 50. Comparative Metrics To Measure Automotive Metric IT Metric Deliverables Delivered Miles Service Level Achieved, Function Point Delivered Duration Hour Hour Input Units Available Gallons Resource Hour Deliverables per Unit of Time Miles Per Hour Earned Value Per Clock Hour Effort Intensity RPM Hours Worked Per Week/Available Hours Supply of Lubricant to Smooth Interaction Between Components PSI Stakeholder Interaction Satisfaction Ability of Lubricant to Smooth Interaction Between Components Degrees Number of Open Issues from Stakeholder Interactions Supply of Coolant to dissipate excess engine heat PSI Duration to Close Issues/Number of Issues Ability of Coolant to dissipate engine heat Degrees Number of Escalated Issues Ability to Support other Control and Comfort Systems Volts On Time Process Deliverables (Status, Reporting, Training) 50 © 2013 Joe Hessmiller
  • 51. The More Complex the Project Environment… 51 © 2013 Joe Hessmiller
  • 52. • To establish the need for monitoring the metrics that really matter. • To identify the types of metrics that really matter. • Show how familiar framework can be adapted for metrics identification (and communication). • Give you enough to use back at your office to improve your metrics program. 52 © 2013 Joe Hessmiller Objective of Session

Editor's Notes

  • #8: Source : McKinsey & Company in conjunction with the University of OxfordType of survey : Study on large scale IT ProjectsDate : 2012A study of 5,400 large scale IT projects (projects with initial budgets greater than $15M) finds that the well known problems with IT Project Management are persisting. Among the key findings quoted from the report:17 percent of large IT projects go so badly that they can threaten the very existence of the companyOn average, large IT projects run 45 percent over budget and 7 percent over time, while delivering 56 percent less value than predictedSource material - Delivering large-scale IT projects on time, on budget, and on valueSource : IBMType of survey : Survey of 1,500 change management executivesDate : Oct 2008IBM survey in the success / failure rates of “change” projects finds;Only 40% of projects met schedule, budget and quality goalsBest organizations are 10 times more successful than worst organizationsBiggest barriers to success listed as people factors: Changing mindsets and attitudes – 58%. Corporate culture – 49%.  Lack of senior management support – 32%.Underestimation of complexity listed as a factor in 35% of projectsFor source data read – Making change workSource : KPMG (New Zealand)Type of survey : Survey of 100 businesses across a broad cross section of industriesDate : Dec 2010KPMG survey of Project Management practices in New Zealand finds some truly startling results;Survey shows an incredible 70% of organizations have suffered at least one project failure in the prior 12 months!50% of respondents also indicated that their project failed to consistently achieve what they set out to achieve!Reference article - Most Business Experience Project FailureSource material – KPMG Project Management Survey 2010
  • #9: Even if we say that the 39% successful project doers don’t need us, and the 18% failures were doomed from the start…that still leaves 43% who are “challenged”. If just that is the market…it’s a huge market.http://versionone.com/assets/img/files/ChaosManifesto2013.pdf
  • #10: Let’s not dwell on the negative (failure). Let’s focus on the positive…becoming more competitive. Dramatic Opportunity: Those organizations that HAVE developed mature project management offices have become more significantly more consistently reliable. Giving their organizations the ability to out-compete their rivals.http://www.pmsolutions.com/audio/State_of_the_PMO_2012_Research_Report.pdf
  • #11: Then there is the huge cost savings potential from doing things right the first time because enough time was taken to do it right…or to cancel the project that isn’t possible at this time or worth it knowing the challenges.http://public.dhe.ibm.com/common/ssi/ecm/en/ras14021usen/RAS14021USEN.PDF