Quantitative Project Risk Analysis
1
Intaver Institute Inc.
303, 6707, Elbow Drive S.W.,
Calgary AB Canada T2V 0E5
www.intaver.com
Agenda
• Introduction
• Part One
– Project Decision Framework
– Quantitative Analysis within Project Risk Management
• Part Two
– Practical Exercises
• Q and A
2
Introduction
Who is Intaver Institute?
– Formed 2002
– Group of risk, economic, and decision analysis experts
– All to some extent were involved in developing software
tools for these fields
3
Problem
• Many IT projects were late or over budget
• No readily available tools for the analysis of project
schedules, the provided similar analysis as the ones they were
developing for other industries
• Decision analysis processes including quantitative analysis
widely used in many industries, but not project management
– Many project manager don’t believe in benefits of quantitative
methods
– Most methods and tools remain relatively complex, require special
training, and expensive
4
Vision: Quantitative project
analysis for the rest of us
1. Develop application
– No specialist training required to get started
– Easier to use and understand
– Relatively inexpensive
1. Provide project decision analysis training and consulting to support
application
5© Intaver Institute 2009
Part One: Project Decisions Framework and
Quantitative Analysis
• Project Decision Analysis
• Quantitative Project Risk Analysis and Management
6
Project Decision Analysis
• Successful projects are the result of good decisions
• Structure decision analysis
– Well defined process founded in decision analysis science
– Applicable to project management
– Provides framework that will improve project decisions
7
Decision Analysis vs. PMBOK
• Decision analysis not in conflict with PMBOK
• Can be easily integrated (as needed) into current PM
Risk Analysis Pyramid
8
Quantitative
Analysis
Qualitative Analysis
Risk Management Planning
© Intaver Institute 2009
8
Quantitative Estimates
• Uncertainties
– 3pt estimates
– Distributions
• Risk events
– Chance
– Outcome
– Result
– Moment of risk
9© Intaver Institute 2009
Types of uncertainties
• Duration
• Cost
• Start and Finish Times
• Lags
• Rates and Resource Allocation
• Entered as 3 pt estimate
10© Intaver Institute 2009
Types of Risk
• Task
• Resource
• Global (project or local)
11© Intaver Institute 2009
Risks or uncertainties?
• Use uncertainties in cases where you have historical data that
is both strong and analogous
• Use uncertainties in cases where you have some historical
data and strong expert opinion (experts have consensus)
• Use risk events when little historical data exists to back up
expert opinion
• Use risk events on higher risk projects
• You can use a combination of risk events and uncertainties
12
Risk or uncertainties
• Risk events are less prone to the effects of human biases and
heuristics
• Easier to recall effect of risk events on projects
13
Event Based Analysis
• Risk event estimates less affected by heuristics and biases
• Risk events estimates easier to obtain via relative frequency analysis
• Event based analysis of causes of project uncertainty
– Sensitivity analysis can be done to identify critical risks
– Uncertainties require additional root cause analysis to identify critical risks
14
Modeling Risk Events
• Chance - % chance that the risk will occur
• Outcome – relative % or fixed (e.g. % cost increase, Fixed
delay)
• Result - 15%
• Example Fire: 20% Chance of a Fixed Delay of 14 days
• Risks can have mutually exclusive alternatives
15
Monte Carlo Analysis
• Statistical sampling
• Runs many simulations of a project that produces
probabilistic distributions of particular results (cost, duration,
finish time, etc.)
• Gaining popularity as size and power of hardware and
software improve
16
Project Risk Analysis
• Create project schedule
• Define project uncertainties
• Define project risks
• Perform Monte Carlo Simulations
• Analyze results
17
RiskyProject Workflow
WBS
Resources
Costs
Risk List
RiskyProject Analysis
Results of Analysis
• Project outcomes with and without risks and uncertainties
• Sensitivity analysis
• Cost analysis
• Identifying critical risks and uncertainties
• Success rates
20
Project Summary
21
Main Project
Parameters with and
without risks
Probabilistic results
Result Gantt Chart
22
White bars represent
original project
schedule (no risks)
Blue bars represent
project schedule
with risks
Because of risks, project duration has
significantly increased
Detailed Results of Analysis
23
Move the slider to determine the
chance that project will be within
budget
Get detailed
statistical data
You may export this
data to other software
it graphic or text
formats
Detailed results can be shown for each tasks
or whole project for cost, duration, start
time, finish time, and income.
Cost Analysis
You may compare
cash flow with (blue
line) and without (red
line) risks
Cash flow is generated based on
fixed and variables cost and
income associated with tasks
and resources
Crucial Tasks
Crucial tasks have the
most affect on the
project schedule
Green bars represent tasks
uncertainties in which almost
not affecting project schedule
Crucial tasks for project cost and
duration can be different
Critical Risks
Tornado chart shows the risks
that have the most affect on
the project schedule
Critical risks need to be
mitigated first
Project Dashboard 3x3
3 most important project
parameters (cost, duration,
and finish time)
3 most crucial tasks
3 most critical risks
Project Dashboard 3x3
is a condensed view for
most important results
of analysis
Risk Chart
The risk chart shows risk uncertainty for tasks versus duration or cost
This task has low
duration but high
risk
These tasks have
balanced risk versus
duration ratio.
Success Rate
The deadline is
causing calculation of
the task in 86% of
cases
A task can be canceled if it reaches a task or a project deadline or if it is affected
by risk with a “Cancel task” outcome.
This task is affected by
one of many risks with
impact “Cancel task” Success rate is calculated
based on number of
times the task is not
canceled
Tracking
This task is 100%
completed (green bar)
For each task at any moment you may enter how much work has been completed
This task is partially
completed (yellow
bar)
Risky project automatically
adjust probability of risks for
partially completed tasks
Tracking Results
New project forecast is done each time actual project data is
entered
Original (baseline)
project duration
Actual project
duration
Low, base, and
high forecast
Intaver Institute
32
Intaver Institute performs project risk management, risk
analysis, and decision analysis training and consulting
Download a trial version of RiskyProject at:
http://www.intaver.com/index-downloads.html (version 2.1)
White papers, presentations : http://www.intaver.com/index-
whitepapers.html
Courses: http://www.intaver.com/riskyproject_training.html
Future Reading
Lev Virine and Michael Trumper
Project Decisions:
The Art and Science
Management Concepts, Vienna, VA, 2007
Lev Virine and Michael Trumper
Project Think:
Why Good Managers Make Poor Project Choices
Gower, 2013

More Related Content

PPTX
Oil and Gas Risk Analysis
PPTX
Vendor management
PDF
Section 02 Work Packages
PPTX
Risk Management
PPT
Creating and Implementing an Effective Port Facility Security Plan
PPS
Earned Value Management
PPTX
Levels of health care and health care settings
PPTX
Murabaha INTRODUCTION
Oil and Gas Risk Analysis
Vendor management
Section 02 Work Packages
Risk Management
Creating and Implementing an Effective Port Facility Security Plan
Earned Value Management
Levels of health care and health care settings
Murabaha INTRODUCTION

What's hot (20)

PPTX
Projectriskmanagement pmbok5
PPTX
11.4 Perform Quantitative Risk Analysis
PDF
Step by step guide on project risk management
PPT
PMI-RMP Exam Prep Presentation
PDF
Project Risk Management - PMBOK5
PPTX
Project Risk Management
PPTX
Presentation on Project Risk Management
PPTX
Risk management
PPT
Risk management: Principles, methodologies and techniques
PPTX
Risk management
PPT
Episode 25 : Project Risk Management
PPTX
Project Risk Management - PMBOK6
PDF
Risk Management module PowerPoint Presentation Slides
PPTX
Project risk management
PPT
Project risk management
PPT
project risk management
PPT
Risk-management
PDF
Risk Analysis : PMP- Project Risk Management
PDF
Project Risk Management
PDF
Risk management
Projectriskmanagement pmbok5
11.4 Perform Quantitative Risk Analysis
Step by step guide on project risk management
PMI-RMP Exam Prep Presentation
Project Risk Management - PMBOK5
Project Risk Management
Presentation on Project Risk Management
Risk management
Risk management: Principles, methodologies and techniques
Risk management
Episode 25 : Project Risk Management
Project Risk Management - PMBOK6
Risk Management module PowerPoint Presentation Slides
Project risk management
Project risk management
project risk management
Risk-management
Risk Analysis : PMP- Project Risk Management
Project Risk Management
Risk management
Ad

Viewers also liked (19)

PDF
Qualitative & Quantitative Analysis
PDF
Quantitative Risk Analysis - Preventing Project cost escalation
DOCX
Pm 0015 – quantitative methods in project management winter 2014
PPTX
Driving Innovative IT Metrics (Project Management Institute Presentation)
PPT
Software metrics
PDF
Adding quantitative risk analysis your Swiss Army Knife
PPTX
The metrics that matter using scalability metrics for project planning of a d...
PPT
Project Risk Analysis in Aerospace Industry
PDF
Full Risk management and new products developme
PPTX
Managing employee risk
PDF
Infoempresa
PPTX
Managing project performance: alignment of Agile and traditional metrics
PDF
The future of bank risk management full report
PDF
PMO Performance Measurement and Metrics - Kendrick
PPT
Top Five Ideas -- Statistics for Project Management
PDF
Synopsis on inventory_management_system
PPTX
Third Party Vendor Contract – Risk Management
PDF
Earning value from risk (v4 full charts)
PDF
Measurement, Qualitative vs Quantitative Methods, and other Cool Stuff
Qualitative & Quantitative Analysis
Quantitative Risk Analysis - Preventing Project cost escalation
Pm 0015 – quantitative methods in project management winter 2014
Driving Innovative IT Metrics (Project Management Institute Presentation)
Software metrics
Adding quantitative risk analysis your Swiss Army Knife
The metrics that matter using scalability metrics for project planning of a d...
Project Risk Analysis in Aerospace Industry
Full Risk management and new products developme
Managing employee risk
Infoempresa
Managing project performance: alignment of Agile and traditional metrics
The future of bank risk management full report
PMO Performance Measurement and Metrics - Kendrick
Top Five Ideas -- Statistics for Project Management
Synopsis on inventory_management_system
Third Party Vendor Contract – Risk Management
Earning value from risk (v4 full charts)
Measurement, Qualitative vs Quantitative Methods, and other Cool Stuff
Ad

Similar to Quantitative Project Risk Analysis (20)

PPTX
Quantitative Project Risk Analysis
PPTX
RiskyProject Software
PPTX
Risk Event Modeling and Event Chains
PPT
Project Risk Analysis with Risk Event and Event Chain
PPTX
RiskyProject Software Version 7.2
PDF
Perform quantitative risk analysis
PPT
Chapter 2.ppt
PPTX
Summary Ch 5-7 Rita Mucahy Book Project.pptx
PDF
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
PPTX
RiskyProject Enterprise
PDF
Project management part 3
PPT
Project Management Unit 3 Lecture 3.3 (1).ppt
PPTX
Risk Identification and analysis Presentation (2).pptx
PDF
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
PPTX
Software project plannings
PPTX
Software project plannings
PPTX
Ppt.pptx
PDF
unit plan for project building in s/w.pdf
PDF
Essentials of Entry Level Project Management - Rev A
PPT
4-ProjectPlanning.ppt
Quantitative Project Risk Analysis
RiskyProject Software
Risk Event Modeling and Event Chains
Project Risk Analysis with Risk Event and Event Chain
RiskyProject Software Version 7.2
Perform quantitative risk analysis
Chapter 2.ppt
Summary Ch 5-7 Rita Mucahy Book Project.pptx
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
RiskyProject Enterprise
Project management part 3
Project Management Unit 3 Lecture 3.3 (1).ppt
Risk Identification and analysis Presentation (2).pptx
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Software project plannings
Software project plannings
Ppt.pptx
unit plan for project building in s/w.pdf
Essentials of Entry Level Project Management - Rev A
4-ProjectPlanning.ppt

More from Intaver Insititute (20)

PPTX
How Risk Events and Uncertainties can affect your project
PPTX
Project risk analysis in Construction Industry
PPT
Risk Analysis of Linear Projects
PPTX
Project Cost Risk Analysis - Reporting
PPTX
Project Cost Analysis
PPT
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
PPT
Risk Analysis of Linear Projects
PPTX
Smart Monte Carlo: Tricks for schedule risk analysis.
PPT
Risk Resilient Projects and Project Portfolios
PPT
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
PPTX
RiskyProject 7
PPTX
Quantiative Risk Analysis for the Aerospace Industry
PPTX
Monte Carlo and Schedule Risk Analysis
PPTX
Estimates in Project Management
PPTX
Project Management: Adaptive management
PPTX
Decision framing in Project Management
PDF
Risky projectpresentation rus
PDF
Risky project Cloud presentation rus
PDF
Risky projectenterpriseriskmanagement
PDF
Risky Project Lite vs. Professional
How Risk Events and Uncertainties can affect your project
Project risk analysis in Construction Industry
Risk Analysis of Linear Projects
Project Cost Risk Analysis - Reporting
Project Cost Analysis
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Risk Analysis of Linear Projects
Smart Monte Carlo: Tricks for schedule risk analysis.
Risk Resilient Projects and Project Portfolios
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
RiskyProject 7
Quantiative Risk Analysis for the Aerospace Industry
Monte Carlo and Schedule Risk Analysis
Estimates in Project Management
Project Management: Adaptive management
Decision framing in Project Management
Risky projectpresentation rus
Risky project Cloud presentation rus
Risky projectenterpriseriskmanagement
Risky Project Lite vs. Professional

Recently uploaded (20)

PPTX
20250228 LYD VKU AI Blended-Learning.pptx
PDF
Electronic commerce courselecture one. Pdf
PDF
Modernizing your data center with Dell and AMD
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PPT
Teaching material agriculture food technology
PDF
Encapsulation_ Review paper, used for researhc scholars
PPTX
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
PDF
Machine learning based COVID-19 study performance prediction
PDF
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
PPTX
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PDF
Chapter 3 Spatial Domain Image Processing.pdf
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PPTX
Big Data Technologies - Introduction.pptx
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
20250228 LYD VKU AI Blended-Learning.pptx
Electronic commerce courselecture one. Pdf
Modernizing your data center with Dell and AMD
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
Agricultural_Statistics_at_a_Glance_2022_0.pdf
Teaching material agriculture food technology
Encapsulation_ Review paper, used for researhc scholars
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
Machine learning based COVID-19 study performance prediction
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
Mobile App Security Testing_ A Comprehensive Guide.pdf
The Rise and Fall of 3GPP – Time for a Sabbatical?
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
Chapter 3 Spatial Domain Image Processing.pdf
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Per capita expenditure prediction using model stacking based on satellite ima...
Big Data Technologies - Introduction.pptx
“AI and Expert System Decision Support & Business Intelligence Systems”

Quantitative Project Risk Analysis

  • 1. Quantitative Project Risk Analysis 1 Intaver Institute Inc. 303, 6707, Elbow Drive S.W., Calgary AB Canada T2V 0E5 www.intaver.com
  • 2. Agenda • Introduction • Part One – Project Decision Framework – Quantitative Analysis within Project Risk Management • Part Two – Practical Exercises • Q and A 2
  • 3. Introduction Who is Intaver Institute? – Formed 2002 – Group of risk, economic, and decision analysis experts – All to some extent were involved in developing software tools for these fields 3
  • 4. Problem • Many IT projects were late or over budget • No readily available tools for the analysis of project schedules, the provided similar analysis as the ones they were developing for other industries • Decision analysis processes including quantitative analysis widely used in many industries, but not project management – Many project manager don’t believe in benefits of quantitative methods – Most methods and tools remain relatively complex, require special training, and expensive 4
  • 5. Vision: Quantitative project analysis for the rest of us 1. Develop application – No specialist training required to get started – Easier to use and understand – Relatively inexpensive 1. Provide project decision analysis training and consulting to support application 5© Intaver Institute 2009
  • 6. Part One: Project Decisions Framework and Quantitative Analysis • Project Decision Analysis • Quantitative Project Risk Analysis and Management 6
  • 7. Project Decision Analysis • Successful projects are the result of good decisions • Structure decision analysis – Well defined process founded in decision analysis science – Applicable to project management – Provides framework that will improve project decisions 7 Decision Analysis vs. PMBOK • Decision analysis not in conflict with PMBOK • Can be easily integrated (as needed) into current PM
  • 8. Risk Analysis Pyramid 8 Quantitative Analysis Qualitative Analysis Risk Management Planning © Intaver Institute 2009 8
  • 9. Quantitative Estimates • Uncertainties – 3pt estimates – Distributions • Risk events – Chance – Outcome – Result – Moment of risk 9© Intaver Institute 2009
  • 10. Types of uncertainties • Duration • Cost • Start and Finish Times • Lags • Rates and Resource Allocation • Entered as 3 pt estimate 10© Intaver Institute 2009
  • 11. Types of Risk • Task • Resource • Global (project or local) 11© Intaver Institute 2009
  • 12. Risks or uncertainties? • Use uncertainties in cases where you have historical data that is both strong and analogous • Use uncertainties in cases where you have some historical data and strong expert opinion (experts have consensus) • Use risk events when little historical data exists to back up expert opinion • Use risk events on higher risk projects • You can use a combination of risk events and uncertainties 12
  • 13. Risk or uncertainties • Risk events are less prone to the effects of human biases and heuristics • Easier to recall effect of risk events on projects 13
  • 14. Event Based Analysis • Risk event estimates less affected by heuristics and biases • Risk events estimates easier to obtain via relative frequency analysis • Event based analysis of causes of project uncertainty – Sensitivity analysis can be done to identify critical risks – Uncertainties require additional root cause analysis to identify critical risks 14
  • 15. Modeling Risk Events • Chance - % chance that the risk will occur • Outcome – relative % or fixed (e.g. % cost increase, Fixed delay) • Result - 15% • Example Fire: 20% Chance of a Fixed Delay of 14 days • Risks can have mutually exclusive alternatives 15
  • 16. Monte Carlo Analysis • Statistical sampling • Runs many simulations of a project that produces probabilistic distributions of particular results (cost, duration, finish time, etc.) • Gaining popularity as size and power of hardware and software improve 16
  • 17. Project Risk Analysis • Create project schedule • Define project uncertainties • Define project risks • Perform Monte Carlo Simulations • Analyze results 17
  • 20. Results of Analysis • Project outcomes with and without risks and uncertainties • Sensitivity analysis • Cost analysis • Identifying critical risks and uncertainties • Success rates 20
  • 21. Project Summary 21 Main Project Parameters with and without risks Probabilistic results
  • 22. Result Gantt Chart 22 White bars represent original project schedule (no risks) Blue bars represent project schedule with risks Because of risks, project duration has significantly increased
  • 23. Detailed Results of Analysis 23 Move the slider to determine the chance that project will be within budget Get detailed statistical data You may export this data to other software it graphic or text formats Detailed results can be shown for each tasks or whole project for cost, duration, start time, finish time, and income.
  • 24. Cost Analysis You may compare cash flow with (blue line) and without (red line) risks Cash flow is generated based on fixed and variables cost and income associated with tasks and resources
  • 25. Crucial Tasks Crucial tasks have the most affect on the project schedule Green bars represent tasks uncertainties in which almost not affecting project schedule Crucial tasks for project cost and duration can be different
  • 26. Critical Risks Tornado chart shows the risks that have the most affect on the project schedule Critical risks need to be mitigated first
  • 27. Project Dashboard 3x3 3 most important project parameters (cost, duration, and finish time) 3 most crucial tasks 3 most critical risks Project Dashboard 3x3 is a condensed view for most important results of analysis
  • 28. Risk Chart The risk chart shows risk uncertainty for tasks versus duration or cost This task has low duration but high risk These tasks have balanced risk versus duration ratio.
  • 29. Success Rate The deadline is causing calculation of the task in 86% of cases A task can be canceled if it reaches a task or a project deadline or if it is affected by risk with a “Cancel task” outcome. This task is affected by one of many risks with impact “Cancel task” Success rate is calculated based on number of times the task is not canceled
  • 30. Tracking This task is 100% completed (green bar) For each task at any moment you may enter how much work has been completed This task is partially completed (yellow bar) Risky project automatically adjust probability of risks for partially completed tasks
  • 31. Tracking Results New project forecast is done each time actual project data is entered Original (baseline) project duration Actual project duration Low, base, and high forecast
  • 32. Intaver Institute 32 Intaver Institute performs project risk management, risk analysis, and decision analysis training and consulting Download a trial version of RiskyProject at: http://www.intaver.com/index-downloads.html (version 2.1) White papers, presentations : http://www.intaver.com/index- whitepapers.html Courses: http://www.intaver.com/riskyproject_training.html
  • 33. Future Reading Lev Virine and Michael Trumper Project Decisions: The Art and Science Management Concepts, Vienna, VA, 2007 Lev Virine and Michael Trumper Project Think: Why Good Managers Make Poor Project Choices Gower, 2013

Editor's Notes

  • #7: Bring out parking lot questions
  • #13: So what should we use.
  • #15: Risks are separated from the schedule and cost. When we use distributions, we set “boundaries” on them. Risk events less effected as we do not know the statistical outcome until Monte Carlo is run. Less conscious or unconscious “gaming” of estimates.