Risk Adjusted Project Schedules
Intaver Institute Inc.
400, 7015 Macleod Trail S.W, Calgary, AB, Canada
Tel: +1(403)692-2252
www.intaver.com
Objectives
• Goal to create realistic or “credible” project plans
• Identify and manage critical risks
• Monte Carlo risk analysis
• Calculate model and risk appropriate schedule margin and
contingency reserve
Risk adjusted project plans allow projects to
withstand impact of foreseen and unforeseen
circumstances
www.intaver.com Intaver Institute Inc.
Sources of Risk
www.intaver.com Intaver Institute Inc.
Discrete Risks
•Risk events that can directly impact project objectives Technical, Schedule,
Cost.
•Characterized by probability of occurrence and impacts and period of exposure
(sunrise and sunset)
•Are “reducible” – they can be managed or eliminated give sufficient effort
Uncertainties
•Natural variance caused by randomness in all processes
•Characterized using statistical distributions that capture most likely and
boundary estimates (Low and High)
•Are “irreducible” – they cannot be reduced
Building Risk Adjusted Plans
www.intaver.com Intaver Institute Inc.
1 Create WBS. WBS is primarily developed using Scope of Work.
2 Create Integrated Management Plan. IMP provides high level
structure for program deliverables, technical measures of success
as well as cost and schedule estimates
3 Analyze and manage risks. Identify, assess, and manage reducible
risks for every WBS item in the plan.
Manage Discrete Risks
www.intaver.com Intaver Institute Inc.
1. Identify Risks
o What events could impact key objectives
1. What are the impacts?
o Assess the impact of a risk event occurring on technical, cost
and schedule measures.
1. What can you do about it?
o What is your risk strategy: Avoid, Transfer, Mitigate, or Accept
o If mitigate, create mitigation plan with activities that will reduce
probability and impact.
o Residual risk (cost, schedule) added to contingency reserve
Assign Risks to WBS
www.intaver.com Intaver Institute Inc.
Drag selected risk and drop it on the
task; define risk probabilities and
impacts
Assess Risks
www.intaver.com Intaver Institute Inc.
Risks are initially assessed using Risk Matrix or Risk
Register Prioritization
Risk Planning
www.intaver.com Intaver Institute Inc.
• Mitigation activities for each risk are
modeled to waterfall chart
• Mitigation activities are added to the
schedule with associated dates, costs
and durations
• Successful completion of mitigation
activities in schedule are tracked and
updated in risk register.
Contingency and Management Reserves
www.intaver.com Intaver Institute Inc.
• Contingency and Margin cover “known unknowns”
o Residual risk from known risks (manageable)
o Natural variance in project performance (unmanageable)
o Does not cover scope changes
• Management Reserves cover unknown unknowns
o Risks not previously identified, etc.
Managing Irreducible Risk
www.intaver.com Intaver Institute Inc.
• Modeling irreducible risk is used to develop Schedule
margins for the Program
• Uncertainties are modeled using 3 pt. estimates (L, ML, H)
• Use all available information including SME opinion,
previous analogous projects
• Uncertainty should be added to all tasks in relation to their
known and forecasted level of uncertainty.
Monte Carlo is Essential
www.intaver.com Intaver Institute Inc.
Monte Carlo Simulations
Contingency and Management Reserves
www.intaver.com Intaver Institute Inc.
$Cost
Time
Contingency
Margin
MR
P80
P80
x
x
Unmanaged Risks and Contingency
www.intaver.com Intaver Institute Inc.
• Impact of unmanaged and
residual risks added to
contingency
• Contingency is difference
between baseline and level
of confidence P-?
• Calculated with Monte Carlo
simulation
Residual risk
www.intaver.com Intaver Institute Inc.
$
Pre-Mitigation
Original
Estimates
With Risk
CR
$
Post-Mitigation
Margin
Pre-Mitigation Post-Mitigation
Residual risk is accounted for in contingency and margin
Schedule Margin
www.intaver.com Intaver Institute Inc.
• Deterministic Plan = 330 days
• With uncertainties and residual
risk P80 = 353 days
• Schedule Margin = P80 – DP =
33 days
Schedule Margin
www.intaver.com Intaver Institute Inc.
Margin is added directly to the schedule to
provide buffers for key deliverables.
Cost Contingency
www.intaver.com Intaver Institute Inc.
Forecasts for cost and schedule now account for
risks and uncertainties and are integrated into plan
Max
P50
Low
When is this appropriate?
www.intaver.com Intaver Institute Inc.
• Always perform risk management as appropriate for the
size and importance of your project.
• Scale with Project
– Small, Routine: Qualitative
– Large, Complex: Quantitative (Monte Carlo)
• Set thresholds
– US Federal
– $20M Perform EV and RM evidenced by reports
– $50 Certified EV and RM systems
Summary
www.intaver.com Intaver Institute Inc.
Program managers can increase confidence of
successfully delivering programs on time and budget
by:
•Managing and controlling risks (reducible)
•Accounting for uncertainties and residual risk
integrating sufficient schedule margin and
management reserves
•This creates a project plan that is….
Risk adjusted plans and protects key program objectivesRisk adjusted plans and protects key program objectives

More Related Content

PPTX
Monte Carlo and Schedule Risk Analysis
PPTX
Smart Monte Carlo: Tricks for schedule risk analysis.
PPT
Risk Analysis of Linear Projects
PPTX
How Risk Events and Uncertainties can affect your project
PPT
Risk Resilient Projects and Project Portfolios
PPTX
Project Cost Risk Analysis - Reporting
PPTX
Project risk analysis in Construction Industry
PPT
Concepts and best practices for the risk register in primavera risk analysis
Monte Carlo and Schedule Risk Analysis
Smart Monte Carlo: Tricks for schedule risk analysis.
Risk Analysis of Linear Projects
How Risk Events and Uncertainties can affect your project
Risk Resilient Projects and Project Portfolios
Project Cost Risk Analysis - Reporting
Project risk analysis in Construction Industry
Concepts and best practices for the risk register in primavera risk analysis

What's hot (20)

PPT
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
PPT
RiskyProject for Oil and Gas Industry
PPT
Monte Carlo Schedule Risk Analysis
PPTX
Risk reserve management model
PDF
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
PPT
Concepts and best practices for the risk register in primavera risk analysis
PDF
Introduction to primavera risk analysis ppt
PPS
Pert master risk analysis tool
PPTX
Project monitoring & Earned Value Analysis
PPTX
Quantitative Project Risk Analysis
PDF
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
PDF
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
PPTX
Project Auditing
DOCX
Job Duties in Current Position
PPSX
Process implementation for project risk management
PDF
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
PDF
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
PDF
AACE Cost Engineering Journal ce15-01
PPT
Budgeting and cost estimation
PDF
Risk management and assessment
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
RiskyProject for Oil and Gas Industry
Monte Carlo Schedule Risk Analysis
Risk reserve management model
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
Concepts and best practices for the risk register in primavera risk analysis
Introduction to primavera risk analysis ppt
Pert master risk analysis tool
Project monitoring & Earned Value Analysis
Quantitative Project Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Project Auditing
Job Duties in Current Position
Process implementation for project risk management
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
AACE Cost Engineering Journal ce15-01
Budgeting and cost estimation
Risk management and assessment
Ad

Similar to Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules (20)

PPT
RiskyProject Software
PDF
Risky projectenterpriseriskmanagement
PPT
Quantitative Project Risk Analysis
PPTX
Risk Event Modeling and Event Chains
PPT
Project Risk Analysis with Risk Event and Event Chain
PPTX
Oil and Gas Risk Analysis
PPTX
Lecture 6 Managing risk.pptx
PPTX
Implementing Ways to Limit Risk (Risk Mitigation)
PPT
Risky project Enterprise
PPTX
RiskyProject Software
PPT
Sameer Mitter Bournemouth - What do understand by Risk management
PDF
Project Controls Expo 18th Nov 2014 - "Practical Applications of a Risk Manag...
PPTX
RiskyProject Enterprise
PPTX
Risk based thinking
PDF
Enterprise Risk Management and Analysis with RiskyProject
PPTX
RiskyProject Software Version 7.2
PPT
Risky projectcloudpresentation
PPTX
Risk management
PPTX
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
PPTX
Risk management
RiskyProject Software
Risky projectenterpriseriskmanagement
Quantitative Project Risk Analysis
Risk Event Modeling and Event Chains
Project Risk Analysis with Risk Event and Event Chain
Oil and Gas Risk Analysis
Lecture 6 Managing risk.pptx
Implementing Ways to Limit Risk (Risk Mitigation)
Risky project Enterprise
RiskyProject Software
Sameer Mitter Bournemouth - What do understand by Risk management
Project Controls Expo 18th Nov 2014 - "Practical Applications of a Risk Manag...
RiskyProject Enterprise
Risk based thinking
Enterprise Risk Management and Analysis with RiskyProject
RiskyProject Software Version 7.2
Risky projectcloudpresentation
Risk management
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Risk management
Ad

More from Intaver Insititute (12)

PPTX
Project Cost Analysis
PPT
Risk Analysis of Linear Projects
PPTX
RiskyProject 7
PPTX
Quantiative Risk Analysis for the Aerospace Industry
PPTX
Estimates in Project Management
PPTX
Project Management: Adaptive management
PPTX
Decision framing in Project Management
PDF
Risky projectpresentation rus
PDF
Risky project Cloud presentation rus
PDF
Risky Project Lite vs. Professional
PPT
Adaptive Project Management
PPT
Decision Framing in Project Decision-Making
Project Cost Analysis
Risk Analysis of Linear Projects
RiskyProject 7
Quantiative Risk Analysis for the Aerospace Industry
Estimates in Project Management
Project Management: Adaptive management
Decision framing in Project Management
Risky projectpresentation rus
Risky project Cloud presentation rus
Risky Project Lite vs. Professional
Adaptive Project Management
Decision Framing in Project Decision-Making

Recently uploaded (20)

PDF
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
PDF
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
PDF
The-Power-of-Communication (1).pdf......
PDF
40.-Rizal-And-Philippine-Identity-Formation.pdf
PDF
CISSP - Domain 7: Security Operations - InfoSec Institute
PDF
The Cyber SwarmShield by Stéphane Nappo
PDF
CHAPTER 15- Manageement of Nursing Educational Institutions- Staffing and st...
PPTX
Mangeroal Finance for Strategic Management
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PDF
CISSP Domain 5: Identity and Access Management (IAM)
PPTX
Chapter Three for international political
PPT
Claims and Adjustment Business_Communication.pptx.ppt
PPTX
Course Overview of the Course Titled.pptx
PPTX
School Annual day Presentation, Logo, Animation
PDF
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
PDF
Features of Effective decision making in Management
PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PPTX
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
PPTX
Effective_communication._(strategy).pptx
PPTX
Human Resources management _HR structure
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
The-Power-of-Communication (1).pdf......
40.-Rizal-And-Philippine-Identity-Formation.pdf
CISSP - Domain 7: Security Operations - InfoSec Institute
The Cyber SwarmShield by Stéphane Nappo
CHAPTER 15- Manageement of Nursing Educational Institutions- Staffing and st...
Mangeroal Finance for Strategic Management
_ISO_Presentation_ISO 9001 and 45001.pptx
CISSP Domain 5: Identity and Access Management (IAM)
Chapter Three for international political
Claims and Adjustment Business_Communication.pptx.ppt
Course Overview of the Course Titled.pptx
School Annual day Presentation, Logo, Animation
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
Features of Effective decision making in Management
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
Effective_communication._(strategy).pptx
Human Resources management _HR structure

Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules

  • 1. Risk Adjusted Project Schedules Intaver Institute Inc. 400, 7015 Macleod Trail S.W, Calgary, AB, Canada Tel: +1(403)692-2252 www.intaver.com
  • 2. Objectives • Goal to create realistic or “credible” project plans • Identify and manage critical risks • Monte Carlo risk analysis • Calculate model and risk appropriate schedule margin and contingency reserve Risk adjusted project plans allow projects to withstand impact of foreseen and unforeseen circumstances www.intaver.com Intaver Institute Inc.
  • 3. Sources of Risk www.intaver.com Intaver Institute Inc. Discrete Risks •Risk events that can directly impact project objectives Technical, Schedule, Cost. •Characterized by probability of occurrence and impacts and period of exposure (sunrise and sunset) •Are “reducible” – they can be managed or eliminated give sufficient effort Uncertainties •Natural variance caused by randomness in all processes •Characterized using statistical distributions that capture most likely and boundary estimates (Low and High) •Are “irreducible” – they cannot be reduced
  • 4. Building Risk Adjusted Plans www.intaver.com Intaver Institute Inc. 1 Create WBS. WBS is primarily developed using Scope of Work. 2 Create Integrated Management Plan. IMP provides high level structure for program deliverables, technical measures of success as well as cost and schedule estimates 3 Analyze and manage risks. Identify, assess, and manage reducible risks for every WBS item in the plan.
  • 5. Manage Discrete Risks www.intaver.com Intaver Institute Inc. 1. Identify Risks o What events could impact key objectives 1. What are the impacts? o Assess the impact of a risk event occurring on technical, cost and schedule measures. 1. What can you do about it? o What is your risk strategy: Avoid, Transfer, Mitigate, or Accept o If mitigate, create mitigation plan with activities that will reduce probability and impact. o Residual risk (cost, schedule) added to contingency reserve
  • 6. Assign Risks to WBS www.intaver.com Intaver Institute Inc. Drag selected risk and drop it on the task; define risk probabilities and impacts
  • 7. Assess Risks www.intaver.com Intaver Institute Inc. Risks are initially assessed using Risk Matrix or Risk Register Prioritization
  • 8. Risk Planning www.intaver.com Intaver Institute Inc. • Mitigation activities for each risk are modeled to waterfall chart • Mitigation activities are added to the schedule with associated dates, costs and durations • Successful completion of mitigation activities in schedule are tracked and updated in risk register.
  • 9. Contingency and Management Reserves www.intaver.com Intaver Institute Inc. • Contingency and Margin cover “known unknowns” o Residual risk from known risks (manageable) o Natural variance in project performance (unmanageable) o Does not cover scope changes • Management Reserves cover unknown unknowns o Risks not previously identified, etc.
  • 10. Managing Irreducible Risk www.intaver.com Intaver Institute Inc. • Modeling irreducible risk is used to develop Schedule margins for the Program • Uncertainties are modeled using 3 pt. estimates (L, ML, H) • Use all available information including SME opinion, previous analogous projects • Uncertainty should be added to all tasks in relation to their known and forecasted level of uncertainty.
  • 11. Monte Carlo is Essential www.intaver.com Intaver Institute Inc. Monte Carlo Simulations
  • 12. Contingency and Management Reserves www.intaver.com Intaver Institute Inc. $Cost Time Contingency Margin MR P80 P80 x x
  • 13. Unmanaged Risks and Contingency www.intaver.com Intaver Institute Inc. • Impact of unmanaged and residual risks added to contingency • Contingency is difference between baseline and level of confidence P-? • Calculated with Monte Carlo simulation
  • 14. Residual risk www.intaver.com Intaver Institute Inc. $ Pre-Mitigation Original Estimates With Risk CR $ Post-Mitigation Margin Pre-Mitigation Post-Mitigation Residual risk is accounted for in contingency and margin
  • 15. Schedule Margin www.intaver.com Intaver Institute Inc. • Deterministic Plan = 330 days • With uncertainties and residual risk P80 = 353 days • Schedule Margin = P80 – DP = 33 days
  • 16. Schedule Margin www.intaver.com Intaver Institute Inc. Margin is added directly to the schedule to provide buffers for key deliverables.
  • 17. Cost Contingency www.intaver.com Intaver Institute Inc. Forecasts for cost and schedule now account for risks and uncertainties and are integrated into plan Max P50 Low
  • 18. When is this appropriate? www.intaver.com Intaver Institute Inc. • Always perform risk management as appropriate for the size and importance of your project. • Scale with Project – Small, Routine: Qualitative – Large, Complex: Quantitative (Monte Carlo) • Set thresholds – US Federal – $20M Perform EV and RM evidenced by reports – $50 Certified EV and RM systems
  • 19. Summary www.intaver.com Intaver Institute Inc. Program managers can increase confidence of successfully delivering programs on time and budget by: •Managing and controlling risks (reducible) •Accounting for uncertainties and residual risk integrating sufficient schedule margin and management reserves •This creates a project plan that is…. Risk adjusted plans and protects key program objectivesRisk adjusted plans and protects key program objectives