What Is RiskyProject?
• Project Scheduling
• Risk Register
• Quantitative risk analysis using Monte Carlo simulations
• Project performance measurement
RiskyProject is Windows-based project risk
management software.
Risky Project gives you a simple answer to a
common question: What will happen to your
project if certain risks occur?
The Project Management Problem
• Budget
• Schedule
• Quality
• Safety
• Technology
• Other measures
Projects
consistently
fail to meet:
The Project Management Problem
Reasons
• Human psychological limits
• Inadequate training
• Poor processes
• others
4
The Project Management Problem
Key Project Management Issues
• How to estimate project duration or cost?
• What are the most critical risks and how to mitigate them?
• How to measure project performance?
• How to make an informed decision about future course of
the project?
The RiskyProject Solution
Project risk management made simple
• RiskyProject is consistent with PMI PMBOK. Risky
Project supports the full project risk
management process.
• RiskyProject is very easy to use. RiskyProject is
uses a scheduling interface similar to other
project popular project management tools.
• RiskyProject has low implementation and
support costs. Compared with the comparative
products, RiskyProject provides unmatched value
The RiskyProject Solution
Project risk management for Project
Managers
• Provide state of art quantitative project risk management
tools
• Low cost
• Ease of implementation
• Limited initial training required
• Scalable
7
RiskyProject Features
• Full scheduling engine with costs and resources
• Full risk register that links to project schedules
• Quantitative and qualitative analysis
• Easy to use quantitative schedule risk analysis based on risk
events
• Probabilistic cash flow analysis
• Project tracking with risks and uncertainties
• Integration with Microsoft Project, Primavera, or other project
management software
• Optional decision tree analysis
• Analysis of critical risk events, which need to be mitigated first
RiskyProject Features (Continued)
• Product lifecycle management
• Risk templates
• Probabilistic and conditional branching
• Managing mitigation plans
• “What if “ analysis
• Advanced reporting tools
• Risk event correlations
• Multiple statistical distributions and distribution fitting
9
RiskyProject uses common PM
artifacts
• WBS
• Resources
• Costs
• Risk Register or Risk Lists
RiskyProject Workflow
RiskyProject Workflow
RiskyProject’s workflow is compatible with PMI, Prince II, and other risk
management processes
Define Project Schedule
You may also import project schedules from other scheduling tools, such as Microsoft
Project or Oracle Primavera.
Enter resources, cost and
income for each task
Enter complete WBS, as it is
done in other project
management software
Risk Register
Pre mitigation
Probability, Impact, and
Score
Post mitigation
Probability, Impact, and
Score
Separate opened and
closed risks, risk, issues,
lessons learned
Separate threats or
opportunities
Risk register view
Risk Form
Risk description and
status
Cost of Risk
Management Strategy
Review Timeline
Double-click on a risk to view or modify Risk Information
Qualitative Risk Analysis: Define Risk Probabilities and
Impacts
If no schedule is attached, qualitative risk assessments can be performed
Outcome Types are now
qualitative
Outcomes for risk categories are
qualitative and are based on risk matrix
settings
Mitigation Waterfall Chart
Track total cost, expected reductions in probability or impact and dates for
mitigation plans
Compare actual and planned
mitigation efforts
Risk Reviews and Risk History
All risk reviews with details can be saved and tracked in system
Information about risk reviews
Next review timing
Assign Risks to Tasks and Resources
Define risk chance, outcome and result. Risks can
have mutually exclusive outcomes, different
outcomes of the same risk
Drag and drop risk on particular
task or group of tasks
If schedule is attached, quantitative risk assessments is performed
Statistical Distributions
In addition to risk events you may define
uncertainties as statistical distributions for:
• task cost
• task start time
• task duration
• income associated with task
If you enter only the low, base and high cost,
duration, start time and income, RiskyProject
will generate statistical distribution based on
this data
Monte Carlo Simulation
When your project schedule and risk breakdown structure is
ready, click here to perform Monte Carlo simulations
Result Gantt Chart
White bars represent original
project schedule (no risks)
Blue bars represent risk
adjusted project schedule (with
risks and uncertainties)
Compare original project schedule and result of analysis
Results of Risk Analysis
Project Summary: project duration,
cost, and finish time with and
without risks
Results of analysis for
project cost, finish time,
and duration
Double click on any chart to view detailed information
The meters show project risk score
for cost and duration
Detailed Results of Analysis
Move the slider to determine the
chance that project will be within
budget
Get detailed statistical
data
Data can be exported as an
image or text
Detailed results can be shown for each task or
project for cost, duration, start time, finish time,
and income.
Cost vs Schedule Scatter Plot
Move the slider to determine the
chance of meeting both schedule and
budget
Base
Estimate indicated by
yellow dot
This plot is often
referred to as
the “Bull’s eye”
or “Football”
chart
Cost Analysis
Project cost with risks (blue line)
Cost chart is generated based on fixed and
variables cost and income associated with tasks
and resources
Project cost without risks (red line)
Probabilistic Cash Flow Analysis
Cash flow with risks (blue bars)
Cash flow is generated based on fixed and
variables cost and income associated with tasks
and resources
Project cost without risks (red line)
Sensitivity Analysis
Tornado chart shows risks or other parameters that have
the most affect on the project schedule
Prioritize critical task or risks
Crucial Tasks
Crucial tasks have the most effect
on the project schedule
Crucial tasks for project cost and duration can be
different
Crucial tasks are red
Risk Chart
Risk chart shows task duration and versus risk, associated
with task
This task has low duration but
high risk
These tasks have balanced risk
versus duration ratio.
Risk Matrix
Risk Probability, Impact and
Score for the current schedule
30
The arrow represents risk
mitigation
Project Dashboard 3x3
3 most important project parameters (cost,
duration, and finish time)
3 most crucial tasks
3 most critical risks
Project Dashboard 3x3 is a condensed view of the most important
results of analysis
Project Tracking
This task is 100% completed (green bar)
For each task at any moment you may enter how much work has been completed
This task is partially completed
(yellow bar)
Risky project automatically adjusts the probability
of risks for partially completed tasks
Tracking Results
New project forecast is done each time actual project data is entered.
Original (baseline) project duration
Actual project performance
Low, base, and high forecast
•Risk Register allows you to compare pre and post mitigation risk
scores for different baselines
View mitigation efforts
Select pre and post mitigation
baselines to view on risk
register
Pre and post mitigation
risk scores
Advanced Project Risk Management
• View results for each baseline
• Select the working schedule that you will use to manage
the project
Compare different baselines
Select the current schedule
Compare results for each
baseline
Advanced Project Risk Management
Advanced Project Risk Management
• Model different scenarios when project activities are uncertain
• Calculate Expected Value of project given uncertainties in project activities
Conditional and Probabilistic Branching
Run alternative project
branches probabilistically
• Model non working days due to weather
Advanced Project Risk Management
Weather Calendar
Non working days due to
weather
Weather calendar settings:
number of non-working days
due to weather each month
Integration with Scheduling Software
RiskyProject’s Add –in installed on the Microsoft Project ribbon allows users move projects
seamlessly into RiskyProject
RiskyProject can import schedules from Oracle Primavera and other project
management software.
Microsoft Project
RiskyProject Add-in for
Microsoft Project

More Related Content

PPTX
Quantitative Project Risk Analysis
PDF
MG6088 SOFTWARE PROJECT MANAGEMENT
PDF
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
PPT
Pressman ch-25-risk-management
PPTX
Using Risk Analysis and Simulation in Project Management
PPT
Risk Management by Roger Pressman
PDF
Primavera Monte Carlo[1]
PPTX
Spm unit iii-risk-intro
Quantitative Project Risk Analysis
MG6088 SOFTWARE PROJECT MANAGEMENT
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Pressman ch-25-risk-management
Using Risk Analysis and Simulation in Project Management
Risk Management by Roger Pressman
Primavera Monte Carlo[1]
Spm unit iii-risk-intro

What's hot (20)

PDF
Estimation guidelines and templates
PPTX
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
PDF
Perform quantitative risk analysis
PPTX
Risk Adjusted Estimating Techniques
DOCX
Building Risk Tolerance into the Program Plan and Schedule
PPT
Iwsm2014 defining technical risk in software development (vard antinyan)
PPTX
RMMM-Risk Management,Mitigation and Monitoring.
PPT
Risk Management In Software Product Development
PPT
Good Risk Software and Why a Spreadsheet will not DO IT!
PPTX
Lecture 03 Software Risk Management
DOC
Cis 500 assignment 6 vo ip part 4 (risk register)
PDF
A NEW MATHEMATICAL RISK MANAGEMENT MODEL FOR AGILE SOFTWARE DEVELOPMENT METHO...
PDF
Risk Assessment
PPTX
New Quality Tools
PDF
Earned Value Management for Design and Construction Project
PDF
Thesis Presentation_LocNguyen
PDF
SEPG_2010_RiskKnowItAll_REV2
PDF
Risk Management Software Implementation Guide eBook
PPT
Unit 7
PDF
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Estimation guidelines and templates
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Perform quantitative risk analysis
Risk Adjusted Estimating Techniques
Building Risk Tolerance into the Program Plan and Schedule
Iwsm2014 defining technical risk in software development (vard antinyan)
RMMM-Risk Management,Mitigation and Monitoring.
Risk Management In Software Product Development
Good Risk Software and Why a Spreadsheet will not DO IT!
Lecture 03 Software Risk Management
Cis 500 assignment 6 vo ip part 4 (risk register)
A NEW MATHEMATICAL RISK MANAGEMENT MODEL FOR AGILE SOFTWARE DEVELOPMENT METHO...
Risk Assessment
New Quality Tools
Earned Value Management for Design and Construction Project
Thesis Presentation_LocNguyen
SEPG_2010_RiskKnowItAll_REV2
Risk Management Software Implementation Guide eBook
Unit 7
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Ad

Similar to RiskyProject Software (20)

PPTX
RiskyProject Software Version 7.2
PPT
Quantitative Project Risk Analysis
PPTX
RiskyProject Enterprise
PPTX
Risk Event Modeling and Event Chains
PPT
Project Risk Analysis with Risk Event and Event Chain
PPT
8 project planning
PPT
9 project planning
PPT
112 risk- metrics for risk reduction
PPT
5 The Logical Framework - a short course for NGOs
PPT
RiskyProject Software
PPT
Project Planning
PPT
Planning.ppt
PPT
5-ProjPlanning.ppt
PPT
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
PPT
Project-Planning
PDF
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
PPT
5-ProjPlanning.ppthhjjjjhhhjjjjhgyhhjhggg
PDF
Introduction to Qualitative Risk Analysis for the PMP.pdf
PDF
unit plan for project building in s/w.pdf
RiskyProject Software Version 7.2
Quantitative Project Risk Analysis
RiskyProject Enterprise
Risk Event Modeling and Event Chains
Project Risk Analysis with Risk Event and Event Chain
8 project planning
9 project planning
112 risk- metrics for risk reduction
5 The Logical Framework - a short course for NGOs
RiskyProject Software
Project Planning
Planning.ppt
5-ProjPlanning.ppt
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
Project-Planning
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
5-ProjPlanning.ppthhjjjjhhhjjjjhgyhhjhggg
Introduction to Qualitative Risk Analysis for the PMP.pdf
unit plan for project building in s/w.pdf
Ad

More from Intaver Insititute (20)

PPTX
How Risk Events and Uncertainties can affect your project
PPTX
Project risk analysis in Construction Industry
PPT
Risk Analysis of Linear Projects
PPTX
Project Cost Risk Analysis - Reporting
PPTX
Project Cost Analysis
PPT
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
PPT
Risk Analysis of Linear Projects
PPTX
Smart Monte Carlo: Tricks for schedule risk analysis.
PPT
Risk Resilient Projects and Project Portfolios
PPT
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
PPTX
RiskyProject 7
PPTX
Oil and Gas Risk Analysis
PPTX
Quantiative Risk Analysis for the Aerospace Industry
PPTX
Monte Carlo and Schedule Risk Analysis
PPTX
Estimates in Project Management
PPTX
Project Management: Adaptive management
PPTX
Decision framing in Project Management
PDF
Risky projectpresentation rus
PDF
Risky project Cloud presentation rus
PDF
Risky projectenterpriseriskmanagement
How Risk Events and Uncertainties can affect your project
Project risk analysis in Construction Industry
Risk Analysis of Linear Projects
Project Cost Risk Analysis - Reporting
Project Cost Analysis
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Risk Analysis of Linear Projects
Smart Monte Carlo: Tricks for schedule risk analysis.
Risk Resilient Projects and Project Portfolios
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
RiskyProject 7
Oil and Gas Risk Analysis
Quantiative Risk Analysis for the Aerospace Industry
Monte Carlo and Schedule Risk Analysis
Estimates in Project Management
Project Management: Adaptive management
Decision framing in Project Management
Risky projectpresentation rus
Risky project Cloud presentation rus
Risky projectenterpriseriskmanagement

Recently uploaded (20)

PDF
How to Choose the Right IT Partner for Your Business in Malaysia
PDF
Upgrade and Innovation Strategies for SAP ERP Customers
PDF
How to Migrate SBCGlobal Email to Yahoo Easily
PDF
How Creative Agencies Leverage Project Management Software.pdf
PDF
Wondershare Filmora 15 Crack With Activation Key [2025
PDF
Claude Code: Everyone is a 10x Developer - A Comprehensive AI-Powered CLI Tool
PDF
Odoo Companies in India – Driving Business Transformation.pdf
PDF
Which alternative to Crystal Reports is best for small or large businesses.pdf
PDF
Audit Checklist Design Aligning with ISO, IATF, and Industry Standards — Omne...
PPT
Introduction Database Management System for Course Database
PPTX
CHAPTER 2 - PM Management and IT Context
PPTX
Online Work Permit System for Fast Permit Processing
PDF
Navsoft: AI-Powered Business Solutions & Custom Software Development
PPTX
ManageIQ - Sprint 268 Review - Slide Deck
PPTX
Operating system designcfffgfgggggggvggggggggg
PDF
T3DD25 TYPO3 Content Blocks - Deep Dive by André Kraus
PDF
Addressing The Cult of Project Management Tools-Why Disconnected Work is Hold...
PDF
Digital Strategies for Manufacturing Companies
PPTX
Agentic AI Use Case- Contract Lifecycle Management (CLM).pptx
PPTX
CHAPTER 12 - CYBER SECURITY AND FUTURE SKILLS (1) (1).pptx
How to Choose the Right IT Partner for Your Business in Malaysia
Upgrade and Innovation Strategies for SAP ERP Customers
How to Migrate SBCGlobal Email to Yahoo Easily
How Creative Agencies Leverage Project Management Software.pdf
Wondershare Filmora 15 Crack With Activation Key [2025
Claude Code: Everyone is a 10x Developer - A Comprehensive AI-Powered CLI Tool
Odoo Companies in India – Driving Business Transformation.pdf
Which alternative to Crystal Reports is best for small or large businesses.pdf
Audit Checklist Design Aligning with ISO, IATF, and Industry Standards — Omne...
Introduction Database Management System for Course Database
CHAPTER 2 - PM Management and IT Context
Online Work Permit System for Fast Permit Processing
Navsoft: AI-Powered Business Solutions & Custom Software Development
ManageIQ - Sprint 268 Review - Slide Deck
Operating system designcfffgfgggggggvggggggggg
T3DD25 TYPO3 Content Blocks - Deep Dive by André Kraus
Addressing The Cult of Project Management Tools-Why Disconnected Work is Hold...
Digital Strategies for Manufacturing Companies
Agentic AI Use Case- Contract Lifecycle Management (CLM).pptx
CHAPTER 12 - CYBER SECURITY AND FUTURE SKILLS (1) (1).pptx

RiskyProject Software

  • 1. RiskyProject Project Risk Management Software Intaver Institute Inc. 303, 6707, Elbow Drive S.W, Calgary, AB, Canada Tel: +1 (403) 692-2252 Fax: +1 (403) 459-4533 www.intaver.com 4280 East Tamiami Trail, 302-M, Naples Florida, 34112, USA Tel: +1(510) 984 3527
  • 2. What Is RiskyProject? • Project Scheduling • Risk Register • Quantitative risk analysis using Monte Carlo simulations • Project performance measurement RiskyProject is Windows-based project risk management software. Risky Project gives you a simple answer to a common question: What will happen to your project if certain risks occur?
  • 3. The Project Management Problem • Budget • Schedule • Quality • Safety • Technology • Other measures Projects consistently fail to meet:
  • 4. The Project Management Problem Reasons • Human psychological limits • Inadequate training • Poor processes • others 4
  • 5. The Project Management Problem Key Project Management Issues • How to estimate project duration or cost? • What are the most critical risks and how to mitigate them? • How to measure project performance? • How to make an informed decision about future course of the project?
  • 6. The RiskyProject Solution Project risk management made simple • RiskyProject is consistent with PMI PMBOK. Risky Project supports the full project risk management process. • RiskyProject is very easy to use. RiskyProject is uses a scheduling interface similar to other project popular project management tools. • RiskyProject has low implementation and support costs. Compared with the comparative products, RiskyProject provides unmatched value
  • 7. The RiskyProject Solution Project risk management for Project Managers • Provide state of art quantitative project risk management tools • Low cost • Ease of implementation • Limited initial training required • Scalable 7
  • 8. RiskyProject Features • Full scheduling engine with costs and resources • Full risk register that links to project schedules • Quantitative and qualitative analysis • Easy to use quantitative schedule risk analysis based on risk events • Probabilistic cash flow analysis • Project tracking with risks and uncertainties • Integration with Microsoft Project, Primavera, or other project management software • Optional decision tree analysis • Analysis of critical risk events, which need to be mitigated first
  • 9. RiskyProject Features (Continued) • Product lifecycle management • Risk templates • Probabilistic and conditional branching • Managing mitigation plans • “What if “ analysis • Advanced reporting tools • Risk event correlations • Multiple statistical distributions and distribution fitting 9
  • 10. RiskyProject uses common PM artifacts • WBS • Resources • Costs • Risk Register or Risk Lists RiskyProject Workflow
  • 11. RiskyProject Workflow RiskyProject’s workflow is compatible with PMI, Prince II, and other risk management processes
  • 12. Define Project Schedule You may also import project schedules from other scheduling tools, such as Microsoft Project or Oracle Primavera. Enter resources, cost and income for each task Enter complete WBS, as it is done in other project management software
  • 13. Risk Register Pre mitigation Probability, Impact, and Score Post mitigation Probability, Impact, and Score Separate opened and closed risks, risk, issues, lessons learned Separate threats or opportunities Risk register view
  • 14. Risk Form Risk description and status Cost of Risk Management Strategy Review Timeline Double-click on a risk to view or modify Risk Information
  • 15. Qualitative Risk Analysis: Define Risk Probabilities and Impacts If no schedule is attached, qualitative risk assessments can be performed Outcome Types are now qualitative Outcomes for risk categories are qualitative and are based on risk matrix settings
  • 16. Mitigation Waterfall Chart Track total cost, expected reductions in probability or impact and dates for mitigation plans Compare actual and planned mitigation efforts
  • 17. Risk Reviews and Risk History All risk reviews with details can be saved and tracked in system Information about risk reviews Next review timing
  • 18. Assign Risks to Tasks and Resources Define risk chance, outcome and result. Risks can have mutually exclusive outcomes, different outcomes of the same risk Drag and drop risk on particular task or group of tasks If schedule is attached, quantitative risk assessments is performed
  • 19. Statistical Distributions In addition to risk events you may define uncertainties as statistical distributions for: • task cost • task start time • task duration • income associated with task If you enter only the low, base and high cost, duration, start time and income, RiskyProject will generate statistical distribution based on this data
  • 20. Monte Carlo Simulation When your project schedule and risk breakdown structure is ready, click here to perform Monte Carlo simulations
  • 21. Result Gantt Chart White bars represent original project schedule (no risks) Blue bars represent risk adjusted project schedule (with risks and uncertainties) Compare original project schedule and result of analysis
  • 22. Results of Risk Analysis Project Summary: project duration, cost, and finish time with and without risks Results of analysis for project cost, finish time, and duration Double click on any chart to view detailed information The meters show project risk score for cost and duration
  • 23. Detailed Results of Analysis Move the slider to determine the chance that project will be within budget Get detailed statistical data Data can be exported as an image or text Detailed results can be shown for each task or project for cost, duration, start time, finish time, and income.
  • 24. Cost vs Schedule Scatter Plot Move the slider to determine the chance of meeting both schedule and budget Base Estimate indicated by yellow dot This plot is often referred to as the “Bull’s eye” or “Football” chart
  • 25. Cost Analysis Project cost with risks (blue line) Cost chart is generated based on fixed and variables cost and income associated with tasks and resources Project cost without risks (red line)
  • 26. Probabilistic Cash Flow Analysis Cash flow with risks (blue bars) Cash flow is generated based on fixed and variables cost and income associated with tasks and resources Project cost without risks (red line)
  • 27. Sensitivity Analysis Tornado chart shows risks or other parameters that have the most affect on the project schedule Prioritize critical task or risks
  • 28. Crucial Tasks Crucial tasks have the most effect on the project schedule Crucial tasks for project cost and duration can be different Crucial tasks are red
  • 29. Risk Chart Risk chart shows task duration and versus risk, associated with task This task has low duration but high risk These tasks have balanced risk versus duration ratio.
  • 30. Risk Matrix Risk Probability, Impact and Score for the current schedule 30 The arrow represents risk mitigation
  • 31. Project Dashboard 3x3 3 most important project parameters (cost, duration, and finish time) 3 most crucial tasks 3 most critical risks Project Dashboard 3x3 is a condensed view of the most important results of analysis
  • 32. Project Tracking This task is 100% completed (green bar) For each task at any moment you may enter how much work has been completed This task is partially completed (yellow bar) Risky project automatically adjusts the probability of risks for partially completed tasks
  • 33. Tracking Results New project forecast is done each time actual project data is entered. Original (baseline) project duration Actual project performance Low, base, and high forecast
  • 34. •Risk Register allows you to compare pre and post mitigation risk scores for different baselines View mitigation efforts Select pre and post mitigation baselines to view on risk register Pre and post mitigation risk scores Advanced Project Risk Management
  • 35. • View results for each baseline • Select the working schedule that you will use to manage the project Compare different baselines Select the current schedule Compare results for each baseline Advanced Project Risk Management
  • 36. Advanced Project Risk Management • Model different scenarios when project activities are uncertain • Calculate Expected Value of project given uncertainties in project activities Conditional and Probabilistic Branching Run alternative project branches probabilistically
  • 37. • Model non working days due to weather Advanced Project Risk Management Weather Calendar Non working days due to weather Weather calendar settings: number of non-working days due to weather each month
  • 38. Integration with Scheduling Software RiskyProject’s Add –in installed on the Microsoft Project ribbon allows users move projects seamlessly into RiskyProject RiskyProject can import schedules from Oracle Primavera and other project management software. Microsoft Project RiskyProject Add-in for Microsoft Project