Risk Analysis of Linear Projects
Intaver Institute Inc.
www.intaver.com
Linear Project Software
http://www.turbo-chart.com
What Are the Linear Projects?
• In linear projects activities are associated with certain locations.
• They are usually construction projects, where each activities have
location attributes addition to duration, cost, and other attributes of
traditional project schedules.
• Examples of linear projects are high-rise buildings, tunnels, pipelines,
and roads
What Are The Location Charts?
Location
Time
Activities
Why Linear Projects Are Delayed or Over Budget?
London Crossrail Project
Originally planned to open in
2018
As of January 2020, it is expected
that the central section will open
in summer 2021.
Risk Adjusted Location Charts
• Time location charts could be presented for original project schedule
and risks-adjusted project schedule.
• Risk adjusted project schedule is a result of project risk analysis
• Comparing risk adjusted project schedule and original project
schedule helps to determine how risks would affect your project.
How Risk Analysis is Performed
Risks are assigned to certain activities
Software for Risk Adjusted Location Charts
Project Risk Analysis is
performed by RiskyProject
software (www.intaver.com).
Time location charts are
presented by Turbo-Chart
software (www.turbo-chart.com).

More Related Content

PPT
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
PPTX
Oil and Gas Risk Analysis
PPTX
Project Cost Risk Analysis - Reporting
PPTX
How Risk Events and Uncertainties can affect your project
PPTX
Smart Monte Carlo: Tricks for schedule risk analysis.
PPTX
Monte Carlo and Schedule Risk Analysis
PPTX
Project risk analysis in Construction Industry
PPT
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Oil and Gas Risk Analysis
Project Cost Risk Analysis - Reporting
How Risk Events and Uncertainties can affect your project
Smart Monte Carlo: Tricks for schedule risk analysis.
Monte Carlo and Schedule Risk Analysis
Project risk analysis in Construction Industry
Project Risk Analysis and Risk Management Software RiskyProject version 7.1

What's hot (20)

PPT
Risk Resilient Projects and Project Portfolios
PPTX
Project Cost Analysis
PPT
Concepts and best practices for the risk register in primavera risk analysis
PPT
RiskyProject for Oil and Gas Industry
PPT
Concepts and best practices for the risk register in primavera risk analysis
PPT
Monte Carlo Schedule Risk Analysis
PDF
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
PPTX
Quantitative Project Risk Analysis
PDF
Introduction to primavera risk analysis ppt
PPS
Pert master risk analysis tool
PDF
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
PDF
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
DOC
Cis 500 assignment 6 vo ip part 4 (risk register)
PDF
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
PPTX
Risk Management
PDF
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
PPTX
Risk reserve management model
PPT
Budgeting and cost estimation
DOCX
Cost estimation method
PPTX
Total Cost Management - Synergy between Cost Estimating and Project Controls
Risk Resilient Projects and Project Portfolios
Project Cost Analysis
Concepts and best practices for the risk register in primavera risk analysis
RiskyProject for Oil and Gas Industry
Concepts and best practices for the risk register in primavera risk analysis
Monte Carlo Schedule Risk Analysis
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
Quantitative Project Risk Analysis
Introduction to primavera risk analysis ppt
Pert master risk analysis tool
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Cis 500 assignment 6 vo ip part 4 (risk register)
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
Risk Management
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
Risk reserve management model
Budgeting and cost estimation
Cost estimation method
Total Cost Management - Synergy between Cost Estimating and Project Controls
Ad

Similar to Risk Analysis of Linear Projects (20)

PDF
DOCX
Vocational training report l&t
DOCX
Construction management
PPTX
PRO-& OPER MGT UNIT V.pptklk58427ghfewtrx
DOCX
Running head PMPM .docx
PPTX
Project Management (2).pptxxxxxxxxxxxxxx
PPT
project management -04.ppt
PPTX
4.1 Project Implementation Planning (1).pptx
PDF
Project controls function
PPT
09 lecture project scheduling 1
DOCX
2017 Updated CV - Essam Harby
DOC
Project 27663255255255781771777166162666
PDF
PDF
Tracking a Typical Apartment Construction using Earned Value Management
PPTX
PM-5 chapter project management (1).pptx
PPTX
PM-chapter 00005 project management.pptx
DOCX
Project PlanGroup 2The Data Center Project PlanProj.docx
PPTX
PMNM101 Lesson 2 2022.pptx
PPTX
RiskyProject Software Version 7.2
PDF
Table of Contents (TOC) to define Enterprise Architecture roadmaps - process_...
Vocational training report l&t
Construction management
PRO-& OPER MGT UNIT V.pptklk58427ghfewtrx
Running head PMPM .docx
Project Management (2).pptxxxxxxxxxxxxxx
project management -04.ppt
4.1 Project Implementation Planning (1).pptx
Project controls function
09 lecture project scheduling 1
2017 Updated CV - Essam Harby
Project 27663255255255781771777166162666
Tracking a Typical Apartment Construction using Earned Value Management
PM-5 chapter project management (1).pptx
PM-chapter 00005 project management.pptx
Project PlanGroup 2The Data Center Project PlanProj.docx
PMNM101 Lesson 2 2022.pptx
RiskyProject Software Version 7.2
Table of Contents (TOC) to define Enterprise Architecture roadmaps - process_...
Ad

More from Intaver Insititute (17)

PPT
Risk Analysis of Linear Projects
PPTX
RiskyProject 7
PPTX
RiskyProject Software
PPTX
RiskyProject Enterprise
PPTX
Risk Event Modeling and Event Chains
PPTX
Quantiative Risk Analysis for the Aerospace Industry
PPTX
Estimates in Project Management
PPTX
Project Management: Adaptive management
PPTX
Decision framing in Project Management
PDF
Risky projectpresentation rus
PDF
Risky project Cloud presentation rus
PDF
Risky projectenterpriseriskmanagement
PDF
Risky Project Lite vs. Professional
PDF
Enterprise Risk Management and Analysis with RiskyProject
PPT
Risky projectcloudpresentation
PPT
Adaptive Project Management
PPT
Decision Framing in Project Decision-Making
Risk Analysis of Linear Projects
RiskyProject 7
RiskyProject Software
RiskyProject Enterprise
Risk Event Modeling and Event Chains
Quantiative Risk Analysis for the Aerospace Industry
Estimates in Project Management
Project Management: Adaptive management
Decision framing in Project Management
Risky projectpresentation rus
Risky project Cloud presentation rus
Risky projectenterpriseriskmanagement
Risky Project Lite vs. Professional
Enterprise Risk Management and Analysis with RiskyProject
Risky projectcloudpresentation
Adaptive Project Management
Decision Framing in Project Decision-Making

Recently uploaded (20)

PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
PPTX
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
PDF
Laughter Yoga Basic Learning Workshop Manual
PPT
Data mining for business intelligence ch04 sharda
PDF
Unit 1 Cost Accounting - Cost sheet
PPTX
Amazon (Business Studies) management studies
PDF
Training And Development of Employee .pdf
PDF
Chapter 5_Foreign Exchange Market in .pdf
PDF
MSPs in 10 Words - Created by US MSP Network
PDF
Nidhal Samdaie CV - International Business Consultant
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PPTX
Business Ethics - An introduction and its overview.pptx
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
DOCX
Business Management - unit 1 and 2
PDF
A Brief Introduction About Julia Allison
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
Laughter Yoga Basic Learning Workshop Manual
Data mining for business intelligence ch04 sharda
Unit 1 Cost Accounting - Cost sheet
Amazon (Business Studies) management studies
Training And Development of Employee .pdf
Chapter 5_Foreign Exchange Market in .pdf
MSPs in 10 Words - Created by US MSP Network
Nidhal Samdaie CV - International Business Consultant
Belch_12e_PPT_Ch18_Accessible_university.pptx
Business Ethics - An introduction and its overview.pptx
HR Introduction Slide (1).pptx on hr intro
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
unit 1 COST ACCOUNTING AND COST SHEET
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
Business Management - unit 1 and 2
A Brief Introduction About Julia Allison

Risk Analysis of Linear Projects

  • 1. Risk Analysis of Linear Projects Intaver Institute Inc. www.intaver.com Linear Project Software http://www.turbo-chart.com
  • 2. What Are the Linear Projects? • In linear projects activities are associated with certain locations. • They are usually construction projects, where each activities have location attributes addition to duration, cost, and other attributes of traditional project schedules. • Examples of linear projects are high-rise buildings, tunnels, pipelines, and roads
  • 3. What Are The Location Charts? Location Time Activities
  • 4. Why Linear Projects Are Delayed or Over Budget? London Crossrail Project Originally planned to open in 2018 As of January 2020, it is expected that the central section will open in summer 2021.
  • 5. Risk Adjusted Location Charts • Time location charts could be presented for original project schedule and risks-adjusted project schedule. • Risk adjusted project schedule is a result of project risk analysis • Comparing risk adjusted project schedule and original project schedule helps to determine how risks would affect your project.
  • 6. How Risk Analysis is Performed Risks are assigned to certain activities
  • 7. Software for Risk Adjusted Location Charts Project Risk Analysis is performed by RiskyProject software (www.intaver.com). Time location charts are presented by Turbo-Chart software (www.turbo-chart.com).

Editor's Notes

  • #2: Today we are going to take a high level look at why and how risk analysis is performed on Linear Projects. This video is brought to you in partnership o Intaver Institute and Linear Project Software.
  • #3: While all projects occur on locations, the key aspect of linear projects is how it adds a distance dimension to each activity. Linear projects with this distance dimension include high-rise buildings (vertical) or roads, pipelines, and railways (horizontal). The distance element and underlying risk it entails are not well represented in traditional scheduling tools such as Gantt charts. Gantt charts lack the ability to visualize the distance element of each activity.
  • #4: Traditional representations of a high-rise building project schedules use Gantt or Bar charts with time for the one axis. The another axis represents a form of Work Breakdown Structure. Location Based Scheduling allocates quantities to the locations defined in the LBS and takes into consideration resourcing required to complete these works, including production rates, crew sizing, logic between tasks and any requirements for splitting or buffering works. This technique allows managers to identify potential risks that can arise due to complexities that can arise due to onsite work conflicts, resource constraints, etc.
  • #5: The reasons for linear projects running over budget and schedule are well documented and almost always are due to errors in judgement and subsequent errors in decision making. Here is an example of one of the very large linear projects: London Crossrail. Originally planned to be opened in 2018, it is currently expected that the central section will start operation in summer 2021. One of the key methods used to minimize the impact of management biases is risk analysis and risk management.
  • #6: Risk adjusted location charts provide a reality check on the feasibility of the schedule to complete on time and budget. Running a quantitative Monte Carlo risk analysis on the schedule and comparing the results with the current plan, not only provides a more realistic forecast for when a project could be completed, but also identify the critical phases in the project that have the most risk.
  • #7: A Monte Carlo risk analysis is performed on the schedule first importing the schedule into the Monte Carlo simulation software. The data includes activity parameters such as Start Time, Finish Time, Durations, Resources etc. Then risks with probabilities and schedule and cost impacts such can be assigned to activities. At this point a simulation is run and probabilities of meeting specific objectives can be determined. The results of this analysis can be exported back into the location based chart which allows a visual comparison of the current schedule vs the more realistic “risk adjusted” schedule.
  • #8: Thank you for watching this video on why Risk Analysis and Location based charts. If you have questions regarding this video or the software tools used. Please feel free to contact either Intaver Institute or Linear Project Software for more information or to schedule a demonstration.