Project Planning 3 The Logical Framework
Overview of this session Review project cycle The LFA process The Logical Framework Preparing LF Using LF to guide M&E
Generic Project Cycle Identification Appraisal Negotiation and Approval Implementation & Monitoring  Evaluation
Project Cycle Stages: Identification  Appraisal Negotiation and Approval Implementation and Monitoring Evaluation and Closure
 
Developing the Logical Framework
Logical Framework Approach   In German: ZOPP (Zielorientierte Projektplanung) In English: GOPP- Goal Oriented Project Planning OOPP- Objective Oriented Project Planning
Organisations Using the Logframe USAID, USA GTZ, Germany DfID, Great-Britain NORAD, Norway DANIDA, Denmark AUSAID, Australia Intercooperation, Switzerland Ministry of Foreign Affairs, France DGCD, Belgium European Commission DGCS - Min. of For. Aff., Italy ICAX - Min. of Industry, Spain SIDA, Sweden UNIDO, Vienna FINNIDA - Min. of For. Aff., Finland HELLASCO, Greece WWF Int. Federation of Red Cross UNDP FAO
Logical Framework Approach   “  a quality-based understanding of planning..  based  on a participatory and transparent .. planning process,  aimed  towards the needs of partners and target groups, in which the key elements of a project are  agreed  on step by step, in teams, with those concerned, and recorded transparently ”   (GTZ, 2005)
Logical Framework Approach provides a systematic structure for identification, planning, and management of projects  developed in a workshop setting  with principal interest groups.
  Advantages of the logical framework Problems are analysed systematically The objectives are clear, logical and measurable The risks and conditions for success of a project are taken into account There is an objective basis for monitoring  and evaluation Your project proposal will be coherent
The logical framework approach Decide what you will do Problem  Objectives Strategy Decide how you will do it Logframe Activity planning Resources planning Analysis phase Planning phase
The logical framework approach Problem analysis : stakeholders, problems, constraints, opportunities, causes and effects. Analysis of objectives : objectives from the problems, relationships from means to ends. Analysis of the strategy : identify the different strategies to achieve objectives (overall objectives and project purpose or specific objective).   Analysis phase
The logical framework approach Logframe :  define the project structure, test its logic and set measurable objectives, determine means and cost. Activity planning :  plan sequence of activities, time, main stages in the process, responsibility. Resources planning :  from the activities, develop inputs and budget. Planning phase
Logical Framework Approach The output is a planning matrix, the  logical project framework, which:  summarizes and structures the main elements of a project ,  and: highlights logical linkages between intended inputs, planned activities and expected results . (GTZ)
Pre-project planning In-house exercise by agency  Participatory Action Research Situation Analysis  Stakeholder Analysis Problem Identification: Problem Tree Objectives Analysis Alternatives Analysis
Problem Tree
Stakeholder Analysis  Secondary Primary Participation Influence on project Importance to Project Key Interests Stakeholders
Project Planning Matrix (PPM) Logframe, Logical Framework (Analysis), LFA Table 4 rows and 4 columns: “4x4 matrix” Ensures clear statement of objectives (distinction between purpose and objectives) Introduces indicators of progress Focuses attention on the assumptions and risks involved
Activity-Oriented Logical Framework MOVs Indicators  “Milestones” Activities (Inputs) MOVs Indicators Outputs MOVs Indicators Purpose Assumptions Risks  MOVs Means of Verification   Indicators Objectively Verifiable Indicators (OVIs) Goal
What makes the Logical Framework “logical” and how does this help plan a project?
Assumptions Something we take to be true. We expect it will happen e.g. we expect the sun to rise each morning assumption: the sun will be in the sky every day This is a safe assumption Assumption: “we can buy from Thailand supplies like pickups” Is this safe?
‘ Logic Model’ The core of the Logical Framework is the "logic model".   This takes the form of a series of statements: If these Activities are done, and these Assumptions are true, then these Outputs will be delivered  If these Outputs are delivered, and these Assumptions a r e   t r u e , then this Purpose will be achieved.  If this Purpose is achieved, and these Assumptions a r e   t r u e , then this Goal will be achieved.
Logic of the Framework INPUTS ACTIVITIES OUTPUTS PURPOSE GOAL Activities lead to outputs IF… Outputs lead to Purpose IF… Purpose leads to Goal IF… ASSUMPTIONS   We must make some assumptions “ IF …. THEN ….”
Logic of the Framework Overall objective Results Activities + + + Assumptions Assumptions Assumptions Conditions Project Purpose
Take a break
Writing a Log Frame
Exercise Choose a project Volunteer(s) to write on flip chart We will write a Logframe as we go Just one sample point in each box Write when you see
Step One Top Down Write the  Goal Purpose Outputs Activities Inputs
Logframe  Step One Goal  also   Development Objective, Development Purpose or effective objective  A high ideal, resulting from development vision Fits the wider context of the programme structure Beyond control of project but project contributes directly to it
Logframe  Step One Purpose (Objective) Statement of specific achievement for the project Within project scope Should be realistic given available resources Should be measurable: who will be reached, what will change, when and where it will occur Verbs:  decrease, increase, improve, enhance, strengthen…   Adjectives for measurable change:  more, longer, greater…
Logframe  Step One Outputs – specific project outputs Activities – the project strategy Inputs – what is needed (include a summary of the budget)
Step Two Work Across Measurable Indicators Means of Verification
Indicators and Verification Measurable Indicators QQT: Quality, Quantity and Timing  what, how much, when Don’t confuse indicators with outputs Output –TBAs trained in new method Indicator - number of TBAs correctly using new method Means of Verification How will you measure the indicator Step Two
Step Three Work Up Assumptions and Risks All the external factors out of your control
Assumptions and Risks  Step Three Assumption: “we can get permission to visit villages 6 times” Is this a safe assumption? If not, it becomes a Risk. A Risk requires analysis: Is it likely? How much will it impact our project? Contingency Plan
Logical Framework  Basic Principles It should be concise. Normally not more than two sides of paper.  It should be a free-standing document - clear when you read it for the first time.  Avoid acronyms, jargon &c.  If beneficiaries are included in the project, they should also help design the Logical Framework.  It is a basis for monitoring and evaluation later.  So it must be kept under regular review and amended whenever the project changes course.
CATWOE  Test C ustomer for the project (Who pays?) A gents for the project (who does what?) T ransformation the project intends to achieve W orldview or major assumption of the change (development hypothesis) O wner of the project (who are the beneficiaries) E nvironmental Constraints (natural, social, political, economic) facing the project
A New Method  you may see Results -Oriented Logical Framework Results-Based Management (RBM) modify the logical framework to be more "results-oriented" and less input-oriented.  Change some columns
Results-Oriented  Logical Framework  More detail on a PMF (next slide) Outputs Resources Outcome Purpose Indicators Impact Goal Assumptions/ Risk Performance Measurement Expected Results Narrative Summary
Performance Monitoring Framework Method of Verification Performance Indicator Output Outcome
Discussion Questions and follow ups Feedback
Thank you GrKuN
Produced by Tony Hobbs Health Unlimited,  Ratanakiri, Cambodia www.healthunlimited.org With the support of  Australian Volunteers International www.australianvolunteers.com © 2009 HU. Use with Acknowledgement

More Related Content

PPTX
Introduction to the Logical Framework Approach
PPT
Logical Framework And Project Proposal
PPT
Logical framework
PPTX
Logical framework approach DR.MADHUR VERMA PGIMS ROHTAK
PPTX
Logical framework
PDF
Logical framework analysis
PDF
Logical framework
PPT
Log frame-analysis
Introduction to the Logical Framework Approach
Logical Framework And Project Proposal
Logical framework
Logical framework approach DR.MADHUR VERMA PGIMS ROHTAK
Logical framework
Logical framework analysis
Logical framework
Log frame-analysis

What's hot (20)

PPT
Monitoring and evaluation (2)
PPT
Lfa Logical Framework Analysis
PPT
7 M&E: Indicators
PPT
Capacity Development For Monitoring And Evaluation
PPTX
Monitoring And Evaluation Presentation
PPTX
Monitoring and Evaluation for Project management.
PPT
6 M&E - Monitoring and Evaluation of Aid Projects
PPTX
Monitoring and evaluation frameworks logical framework
PPTX
Monitoring And Evaluation
PPT
Project monitoring and evaluation by Samuel Obino Mokaya
PPTX
M&E Plan
PPTX
An Introduction to Project Management
PDF
Basics of Monitoring & Evaluation
PPTX
Difference between monitoring and evaluation
PPTX
Results Based Monitoring and Evaluation
PPT
Presentation Training on Result Based Management (RBM) for M&E Staff
PPTX
Monitoring and Evaluation
ODP
Project evaluation
PPTX
Project monitoring
DOCX
Project M&E (unit 1-4)
Monitoring and evaluation (2)
Lfa Logical Framework Analysis
7 M&E: Indicators
Capacity Development For Monitoring And Evaluation
Monitoring And Evaluation Presentation
Monitoring and Evaluation for Project management.
6 M&E - Monitoring and Evaluation of Aid Projects
Monitoring and evaluation frameworks logical framework
Monitoring And Evaluation
Project monitoring and evaluation by Samuel Obino Mokaya
M&E Plan
An Introduction to Project Management
Basics of Monitoring & Evaluation
Difference between monitoring and evaluation
Results Based Monitoring and Evaluation
Presentation Training on Result Based Management (RBM) for M&E Staff
Monitoring and Evaluation
Project evaluation
Project monitoring
Project M&E (unit 1-4)
Ad

Viewers also liked (20)

PPT
3 Project Cycle and Planning (4-6 hours)
PPTX
How To Write Af Good Project
PPTX
The six phase comprehensive project life cycle model-2013
PPT
Project Planning Basics - Everything you need to start managing a project
PPTX
Project characteristics
PPT
Public Health Dentistry
PPTX
Different types of wbs structures
PDF
Mini-Training: Using root-cause analysis for problem management
PDF
Lfa problem tree analysis
PPT
Swot analysis in project management
PPTX
Project management & Network analysis
PPTX
Tools for Problem Indentification and Analysis
PDF
Understanding logframe ___problem_tree_analysis_____by_dr_malik_khalid_mehmoo...
PPT
Introduction To Problem Analysis
PPT
Problem Analysis
PPT
4 Project Pre-Planning & Stakeholder Analysis
PPT
Project Planning
PPTX
HRBA & Gender Mainstreaming
PDF
6 Characteristics of a Project
3 Project Cycle and Planning (4-6 hours)
How To Write Af Good Project
The six phase comprehensive project life cycle model-2013
Project Planning Basics - Everything you need to start managing a project
Project characteristics
Public Health Dentistry
Different types of wbs structures
Mini-Training: Using root-cause analysis for problem management
Lfa problem tree analysis
Swot analysis in project management
Project management & Network analysis
Tools for Problem Indentification and Analysis
Understanding logframe ___problem_tree_analysis_____by_dr_malik_khalid_mehmoo...
Introduction To Problem Analysis
Problem Analysis
4 Project Pre-Planning & Stakeholder Analysis
Project Planning
HRBA & Gender Mainstreaming
6 Characteristics of a Project
Ad

Similar to 5 The Logical Framework - a short course for NGOs (20)

PPTX
Logical Framework Approach lecture -10.pptx
PPT
PDF
Developing a Logical Framework Guide, Developmental Public Administration, De...
PPT
The Logical Framework Approach
PPT
DOCX
Logical framework analysis of projects.docx
PPTX
Logical Framework Approach in Project planning.pptx
PDF
Logical framework
PDF
Monitoring and Evaluation of Project Under Project Management
DOC
3 proj plan handouts
DOC
Project Planning module 5 Handout
PDF
The logical framework matrix approach (LFMA)
PPT
Shaping Ideas – LogFrame Workshop at the oikos Winter School 2008
PPT
Martin on Maximising Impact
PDF
Training-on-Logical-Framework-Approach-Monitoring-and-Evaluation-Framework-an...
PPT
lecture about project management: Logical Framework.ppt
PPTX
Logical framework for development projects
PPTX
Agriculture Extension evaluation and impact
DOC
Logical framework guide
PPT
Logical framework-and-project-proposal-119679674017067-2
Logical Framework Approach lecture -10.pptx
Developing a Logical Framework Guide, Developmental Public Administration, De...
The Logical Framework Approach
Logical framework analysis of projects.docx
Logical Framework Approach in Project planning.pptx
Logical framework
Monitoring and Evaluation of Project Under Project Management
3 proj plan handouts
Project Planning module 5 Handout
The logical framework matrix approach (LFMA)
Shaping Ideas – LogFrame Workshop at the oikos Winter School 2008
Martin on Maximising Impact
Training-on-Logical-Framework-Approach-Monitoring-and-Evaluation-Framework-an...
lecture about project management: Logical Framework.ppt
Logical framework for development projects
Agriculture Extension evaluation and impact
Logical framework guide
Logical framework-and-project-proposal-119679674017067-2

More from Tony (20)

DOC
Policy & Procedure Manual (sample)
PDF
Rights Advocacy in Ratanakiri - health exchange news
PDF
Remote solar project Ecogeneration Magazine
PDF
Population Indicators Handout
DOC
Watsan training sample proposal
DOC
Module 8 presenter notes
DOC
M&E handout for module 8
DOC
Exercise: Watsan logframe with blanks
DOC
Progress Reporting - notes
DOC
Exercise cards - logframe components
DOCX
Ten rules of project risk management
DOC
Issues Risklog
PDF
A Guide to Logical Framework Analysis
DOC
Stakeholder Analysis
DOC
Project Planning module 5 presenter notes
DOC
Project management terms
DOC
3 proj plan notes
PPT
11 Problem Solving
PPTX
10 Project Proposal Writing
PPT
8 M&E: Data Sources
Policy & Procedure Manual (sample)
Rights Advocacy in Ratanakiri - health exchange news
Remote solar project Ecogeneration Magazine
Population Indicators Handout
Watsan training sample proposal
Module 8 presenter notes
M&E handout for module 8
Exercise: Watsan logframe with blanks
Progress Reporting - notes
Exercise cards - logframe components
Ten rules of project risk management
Issues Risklog
A Guide to Logical Framework Analysis
Stakeholder Analysis
Project Planning module 5 presenter notes
Project management terms
3 proj plan notes
11 Problem Solving
10 Project Proposal Writing
8 M&E: Data Sources

Recently uploaded (20)

PDF
How to Get Funding for Your Trucking Business
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
Types of control:Qualitative vs Quantitative
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PPT
Data mining for business intelligence ch04 sharda
PDF
Nidhal Samdaie CV - International Business Consultant
PDF
Dr. Enrique Segura Ense Group - A Self-Made Entrepreneur And Executive
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PPTX
5 Stages of group development guide.pptx
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
PDF
Unit 1 Cost Accounting - Cost sheet
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PPTX
Amazon (Business Studies) management studies
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
How to Get Funding for Your Trucking Business
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
Types of control:Qualitative vs Quantitative
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
DOC-20250806-WA0002._20250806_112011_0000.pdf
Data mining for business intelligence ch04 sharda
Nidhal Samdaie CV - International Business Consultant
Dr. Enrique Segura Ense Group - A Self-Made Entrepreneur And Executive
WRN_Investor_Presentation_August 2025.pdf
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
5 Stages of group development guide.pptx
Reconciliation AND MEMORANDUM RECONCILATION
COST SHEET- Tender and Quotation unit 2.pdf
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
Unit 1 Cost Accounting - Cost sheet
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
Roadmap Map-digital Banking feature MB,IB,AB
Amazon (Business Studies) management studies
Power and position in leadershipDOC-20250808-WA0011..pdf
Belch_12e_PPT_Ch18_Accessible_university.pptx

5 The Logical Framework - a short course for NGOs

  • 1. Project Planning 3 The Logical Framework
  • 2. Overview of this session Review project cycle The LFA process The Logical Framework Preparing LF Using LF to guide M&E
  • 3. Generic Project Cycle Identification Appraisal Negotiation and Approval Implementation & Monitoring Evaluation
  • 4. Project Cycle Stages: Identification Appraisal Negotiation and Approval Implementation and Monitoring Evaluation and Closure
  • 5.  
  • 7. Logical Framework Approach In German: ZOPP (Zielorientierte Projektplanung) In English: GOPP- Goal Oriented Project Planning OOPP- Objective Oriented Project Planning
  • 8. Organisations Using the Logframe USAID, USA GTZ, Germany DfID, Great-Britain NORAD, Norway DANIDA, Denmark AUSAID, Australia Intercooperation, Switzerland Ministry of Foreign Affairs, France DGCD, Belgium European Commission DGCS - Min. of For. Aff., Italy ICAX - Min. of Industry, Spain SIDA, Sweden UNIDO, Vienna FINNIDA - Min. of For. Aff., Finland HELLASCO, Greece WWF Int. Federation of Red Cross UNDP FAO
  • 9. Logical Framework Approach “ a quality-based understanding of planning.. based on a participatory and transparent .. planning process, aimed towards the needs of partners and target groups, in which the key elements of a project are agreed on step by step, in teams, with those concerned, and recorded transparently ” (GTZ, 2005)
  • 10. Logical Framework Approach provides a systematic structure for identification, planning, and management of projects developed in a workshop setting with principal interest groups.
  • 11. Advantages of the logical framework Problems are analysed systematically The objectives are clear, logical and measurable The risks and conditions for success of a project are taken into account There is an objective basis for monitoring and evaluation Your project proposal will be coherent
  • 12. The logical framework approach Decide what you will do Problem Objectives Strategy Decide how you will do it Logframe Activity planning Resources planning Analysis phase Planning phase
  • 13. The logical framework approach Problem analysis : stakeholders, problems, constraints, opportunities, causes and effects. Analysis of objectives : objectives from the problems, relationships from means to ends. Analysis of the strategy : identify the different strategies to achieve objectives (overall objectives and project purpose or specific objective). Analysis phase
  • 14. The logical framework approach Logframe : define the project structure, test its logic and set measurable objectives, determine means and cost. Activity planning : plan sequence of activities, time, main stages in the process, responsibility. Resources planning : from the activities, develop inputs and budget. Planning phase
  • 15. Logical Framework Approach The output is a planning matrix, the logical project framework, which: summarizes and structures the main elements of a project , and: highlights logical linkages between intended inputs, planned activities and expected results . (GTZ)
  • 16. Pre-project planning In-house exercise by agency Participatory Action Research Situation Analysis Stakeholder Analysis Problem Identification: Problem Tree Objectives Analysis Alternatives Analysis
  • 18. Stakeholder Analysis Secondary Primary Participation Influence on project Importance to Project Key Interests Stakeholders
  • 19. Project Planning Matrix (PPM) Logframe, Logical Framework (Analysis), LFA Table 4 rows and 4 columns: “4x4 matrix” Ensures clear statement of objectives (distinction between purpose and objectives) Introduces indicators of progress Focuses attention on the assumptions and risks involved
  • 20. Activity-Oriented Logical Framework MOVs Indicators “Milestones” Activities (Inputs) MOVs Indicators Outputs MOVs Indicators Purpose Assumptions Risks MOVs Means of Verification Indicators Objectively Verifiable Indicators (OVIs) Goal
  • 21. What makes the Logical Framework “logical” and how does this help plan a project?
  • 22. Assumptions Something we take to be true. We expect it will happen e.g. we expect the sun to rise each morning assumption: the sun will be in the sky every day This is a safe assumption Assumption: “we can buy from Thailand supplies like pickups” Is this safe?
  • 23. ‘ Logic Model’ The core of the Logical Framework is the "logic model". This takes the form of a series of statements: If these Activities are done, and these Assumptions are true, then these Outputs will be delivered If these Outputs are delivered, and these Assumptions a r e t r u e , then this Purpose will be achieved. If this Purpose is achieved, and these Assumptions a r e t r u e , then this Goal will be achieved.
  • 24. Logic of the Framework INPUTS ACTIVITIES OUTPUTS PURPOSE GOAL Activities lead to outputs IF… Outputs lead to Purpose IF… Purpose leads to Goal IF… ASSUMPTIONS We must make some assumptions “ IF …. THEN ….”
  • 25. Logic of the Framework Overall objective Results Activities + + + Assumptions Assumptions Assumptions Conditions Project Purpose
  • 27. Writing a Log Frame
  • 28. Exercise Choose a project Volunteer(s) to write on flip chart We will write a Logframe as we go Just one sample point in each box Write when you see
  • 29. Step One Top Down Write the Goal Purpose Outputs Activities Inputs
  • 30. Logframe Step One Goal also Development Objective, Development Purpose or effective objective A high ideal, resulting from development vision Fits the wider context of the programme structure Beyond control of project but project contributes directly to it
  • 31. Logframe Step One Purpose (Objective) Statement of specific achievement for the project Within project scope Should be realistic given available resources Should be measurable: who will be reached, what will change, when and where it will occur Verbs: decrease, increase, improve, enhance, strengthen… Adjectives for measurable change: more, longer, greater…
  • 32. Logframe Step One Outputs – specific project outputs Activities – the project strategy Inputs – what is needed (include a summary of the budget)
  • 33. Step Two Work Across Measurable Indicators Means of Verification
  • 34. Indicators and Verification Measurable Indicators QQT: Quality, Quantity and Timing what, how much, when Don’t confuse indicators with outputs Output –TBAs trained in new method Indicator - number of TBAs correctly using new method Means of Verification How will you measure the indicator Step Two
  • 35. Step Three Work Up Assumptions and Risks All the external factors out of your control
  • 36. Assumptions and Risks Step Three Assumption: “we can get permission to visit villages 6 times” Is this a safe assumption? If not, it becomes a Risk. A Risk requires analysis: Is it likely? How much will it impact our project? Contingency Plan
  • 37. Logical Framework Basic Principles It should be concise. Normally not more than two sides of paper. It should be a free-standing document - clear when you read it for the first time. Avoid acronyms, jargon &c. If beneficiaries are included in the project, they should also help design the Logical Framework. It is a basis for monitoring and evaluation later. So it must be kept under regular review and amended whenever the project changes course.
  • 38. CATWOE Test C ustomer for the project (Who pays?) A gents for the project (who does what?) T ransformation the project intends to achieve W orldview or major assumption of the change (development hypothesis) O wner of the project (who are the beneficiaries) E nvironmental Constraints (natural, social, political, economic) facing the project
  • 39. A New Method you may see Results -Oriented Logical Framework Results-Based Management (RBM) modify the logical framework to be more "results-oriented" and less input-oriented. Change some columns
  • 40. Results-Oriented Logical Framework More detail on a PMF (next slide) Outputs Resources Outcome Purpose Indicators Impact Goal Assumptions/ Risk Performance Measurement Expected Results Narrative Summary
  • 41. Performance Monitoring Framework Method of Verification Performance Indicator Output Outcome
  • 42. Discussion Questions and follow ups Feedback
  • 44. Produced by Tony Hobbs Health Unlimited, Ratanakiri, Cambodia www.healthunlimited.org With the support of Australian Volunteers International www.australianvolunteers.com © 2009 HU. Use with Acknowledgement

Editor's Notes

  • #2: NEED: Handout - BOND Guidance Notes No4, Flip chart, prepare example Objective Tree (/problem tree) (from previous session), Handout list of terms
  • #8: Developed by USAID in 1960s to be developed by various UN agencies, then adopted by GTZ in 1980s but now optional. In widespread use by the larger donor organizations, partially because of the orderly structuring and documentation of information and its demand for more skill in use DFID require it
  • #10: Developed by US Army, NASA then USAID in 1960s, later developed by various UN agencies, then adopted by GTZ in 1980s but now optional. In widespread use by the larger donor organizations, partially because of the orderly structuring and documentation of information and its demand for more skill in use DFID require it
  • #12: Problems are analysed systematically The objectives are clearly formulated, logical and measurable, The risks and conditions for success of a project are taken into account There is an objective basis for monitoring and evaluation => hence the whole project proposal is coherent
  • #13: See next 2 slides for detail
  • #14: Problem analysis : identifying stakeholders, their key problems, constraints and opportunities, determining cause and effect relationships. Analysis of objectives : developing objectives from the identified problems, identifying the relationships between the means and the ends. Analysis of the strategy : identifying the different strategies to achieve objectives, determining the major objectives (overall objectives and project purpose or specific objective).
  • #15: Logframe : defining the project structure, testing its internal logic and formulating objectives in measurable terms, determining means and cost. Activity planning : determining the sequence and the relation between the activities, estimating their duration , setting the main stages in the process, assigning responsibility. Resources planning : from the activity schedule, developing the input schedule and the budget.
  • #17: We have covered this topic as part of the project cycle, but we can run a session specially on pre-planning at any time.
  • #18: The technique is an integral part of the ZOPP approach assists in analysing an existing situation by identifying the major problems and their main causal relationships
  • #19: May also use a ranking exercise
  • #20: Helps to cintrol scope creep
  • #21: How do you fill in/prepare a logframe? This is the first style of Logframe – activity oriented. Then introduced results oriented
  • #23: What if war breaks out? Trade bans?
  • #24: Again, it is the application of science and scientific principles to non-scientific situations in the real world.
  • #25: What sort of assumptions?
  • #30: These are the levels of the Objective Tree
  • #31: Sometimes Supergoal is introduced (ie global). Donors often see the goal as a national level policy objective.
  • #32: Measurable: who will be reached, what change will be achieved, the period in which it will be achieved and where it will occur
  • #36: NB: Be careful in preparation of risks and assumptions!!
  • #38: Do you know what “&c” means? No? Then it shouldn’t be here! All jargon too.
  • #39: All this information should be in the Logframe
  • #40: With the advent of Results-Based Management (RBM), there was a need to modify the logical framework so as to render it more "results-oriented" and less input-oriented.
  • #41: Means of Verification has been pushed out. A PMF Performance Monitoring Framework is prepared to accompany this type of LFA which will go into detail about MOVs for indicators and milestones etc.