SlideShare a Scribd company logo
9
Most read
16
Most read
17
Most read
Project Auditing
SHOWAIB AHMED CHOWDHURY
Lecturer
Department of Building Engineering & Construction
Management
Rajshahi University of Engineering & Technology(RUET)
Introduction
Project assurance is a fundamental part of effective project
governance.
The project audit is the means to provide that assurance and enables
the sponsor to have confidence that the governance is working and that
the project is being managed as intended.
In this lesson, we will try,
to demonstrate how to plan and undertake a comprehensive audit of a
project, thereby providing that assurance.
to explain the role of an auditor, how it could be planned and
undertaken, the degrees of assurance that can be given, and how
project audits can be aligned to organizational governance.
The three main roles involved in project audits are:
Role Description
Organization board/audit committee/
sponsor/other stakeholders
Those who schedulethe projectauditand
receive the audit findings
Project team
Those whose project is being audited, with
whom the auditors interact
Project auditor(s)
Those who undertake the audit, and report its
findings and make recommendations
For any audit to be successful and provide value to all parties, these
three main roles must work together and understand each other’s
function in the process.
What is project auditing?
According to the Chartered Institute of Internal Auditors,
‘an independent, objective assurance and consulting activity designed
to add value and improve an organization's operations.
It helps an organization accomplish its objectives by bringing a
systematic, disciplined approach to evaluate and improve the
effectiveness of risk management, control, and governance processes’.
In any audit, the auditor(s) perceives and recognizes the propositions
before them for examination, collects evidence, evaluates the same,
and on this basis formulates an opinion on the adequacy of controls
within the activity being audited.
Principles of project audit
Project audit should be:
independent, and supported in this by the organization board;
accountable within a governance and reporting system;
planned and coordinated as part of the organization's
management system;
risk-based, against an independent risk evaluation;
able to allow the impact of identified weaknesses to be
reported and addressed, by follow-up and escalation.
Why do we need project audits?
• The giving of assurance to project stakeholders, including the
organization board, through providing assessment of the likelihood of
the project achieving its objectives, is a fundamental aspect of project
governance
• This assurance will cover the identification and management of risk,
evaluation of opportunities, and actions being taken to realize those
benefits on which approval of the business case was based.
• Assurance also seeks evidence of effective controls and opportunities
to increase the likelihood of success of the project
So, Throughout the phases of a project there should be provision for
independent audit to give assurance to key stakeholders including the
project sponsor and executive board, of the likelihood that the objectives
of the project will be achieved.
The audit will cover the following elements :
• Project definition and requirements management;
• Project organization and governance;
• Risks management;
• Commercial, procurement and commissioning;
• Configuration management, project change controls;
• Project planning and scheduling;
• Performance and benefits management;
• Stakeholder management and communications;
• Organizational capability and culture;
• Social responsibility and sustainability.
Project audit process
Step 1: Planning the audit
• Audit prioritization: Project audits should be planned on the basis of risks to the organization
and to the project.
• Choosing the audit team: The audit team should have access to specialist technical skills e.g.
quality assurance, and should bear in mind the organization's appetite for integrated assurance.
• Information gathering:
Background information Results
1 Project name/reference
2 Brief description of the objectives of the project
3 Project value (total)/(this year)
4 Appropriate (outline or full) business case approved/ date/value
5 Agreed project audit scope, objectives and name/ reference
6
Project governance arrangements including project sponsor,
projectmanager and projectteam
7 Project management arrangements
8 Project phase (Inception, Feasibility, Development, Delivery, Close-out)
9 Overview ofproject controls includingchange controls
10
Project Management Plan (PMP) and Project Initiation Document (PID)
approved date
11 Project audit team details
12 Organization policies andprocedures tobeusedas basis for project audit
13
Extent ofPMO support required including management, cost and
financial reports
14
Risks from corporate and project risk registers, and additional risks from
discussion with stakeholders
15 Project and organization risk management and mitigation measures
16 Integration with other assurance providers
17 Alignment of project with corporate strategy
18 Risk-based audit programmed and schedule
19 Audit reporting details including timetable
20 Significant stakeholders (including their influence and interest)
21 Communications strategy
22 Arrangements tohandovertonextphase,stageor client ofproject
• Risk assessing of a project: This should be carried out by discussion with
stakeholders on risks that they have identified but which have not been
included in the formal register; and on the auditor’s own experience and
discussion with the project team.
• The project audit programme: The audit team should identify the risks
to the project, and the controls and tests which are derived from these. The
different phases of the project life cycle should lead to audit programmed
and tests appropriate to those phases, and to the nature of the project.
2. Fieldwork : The audit team should gather information and
documentation, and talk to key stakeholders including (as appropriate)
members of the project team, the procurement function and the supply chain.
• Elements for review:
 Project definition and requirements management
 Project organization and governance
 Risks management
 Commercial, procurement and commissioning
 Project planning and scheduling
 Performance and benefits management
 Stakeholder management and communications
 Organizational capability and culture
 Social responsibility and sustainability
3. Evaluation and reporting
 Evaluation
• The basic idea is to use a grading score to rank each audited element
and indicate the extent to which the project has performed.
• One method of grading used extensively to measure performance is
the ‘traffic light’ system of three ratings: red/amber/green (RAG).
• During project audits it may be more appropriate to use four or five
ratings, with additional definitions and next steps.
• Definitions of RAG will depend on project and reporting
requirements.
 Reporting
 Individual organizations have their own reporting requirements,
including who should receive the report, who has responsibility for
responding to it, and who will be tasked with implementing its
findings and recommendations.
As some of the content of the report may be commercially or
otherwise sensitive, this should be borne in mind in circulation and
distribution of draft and final reports.
Following a close-out meeting with auditees, the preliminary report
should be prepared and internally reviewed before issue to those
auditees and other stakeholders for comment on findings and
recommendations.
The final report, which should contain the evaluation rating based on
the responses received, should be distributed in accordance with the
requirements of the agreed audit plan. The final report should also be
4. Follow-up
• Follow-up is the final element of the audit process, in which the audit
team confirms that the sponsor and project team have implemented the
agreed actions to address identified project risks and issues.
• This can be confirmed by monitoring the implementation process, or
by accepting a formal statement from the sponsor or project team that
the recommended actions have been carried out.
5. Benefits evaluation
• Where the scope of the project audit included evaluation or auditing of
outcomes on which approval of the business case was, a separate audit
process will be required.
• This will seek to compare recorded benefit outcomes against those
proposed in the business case through the use of defined benefit
measures, normally by quantitative methods.
6. Legacy and lessons learned
• The results of project audits can provide valuable reference
points for the organisation’s legacy and lessons learned
process. The audit team should be aware of the organisation’s
requirements for confidentiality if involved in the legacy and
lessons learned process.
• The organization may operate a legacy programme, to capture
the intellectual capital within a project before the project
team is disbanded.
• Prepare a mid-term audit report for a building construction project
which have a budgeted cost at TK. 1000000 with a total project
duration 8 months, Also consider at the time of mid-term 40%
construction work is completed at a cost of TK 600000.
Solution:
Auditor:
Audit-Team:
Date of Audit:
Project Audited:
Project Manager:
Introduction:
General Analysis of the project by EVM:
Budget at completion(BAC) : 1000000TK
Completion Period: 8 months
Actual cost(AC): 600000TK
Earned Value(EV)= 40% * 1000000 = 400000TK
Planned Value(PV)= 50% * 1000000 = 500000TK
Cost Variance, CV= EV-AC = -200000TK
Schedule Variance, SV= EV-PV= -100000TK
Cost Performance Index, CPI= EV/AC= 0.67<1
Schedule Performance Index, SPI= EV/PV= 0.8<1
• Current Status:
• Future Projection:
• Critical Management issues:
• Risk Analysis and Risk Management:

More Related Content

PPTX
Evolution of project management
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
PPTX
Fidic conditions of contract presentation
PPSX
Projectmanagement 130721095616-phpapp01
PPTX
contract administration PPT
PDF
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PPTX
Construction Project Management ppt
PPTX
5 phases of project management
Evolution of project management
Extension of time (E.O.T) By Ahmed Ibarhim
Fidic conditions of contract presentation
Projectmanagement 130721095616-phpapp01
contract administration PPT
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
Construction Project Management ppt
5 phases of project management

What's hot (20)

PPTX
Construction Project Management
PPSX
Pmp presentation chapter 1 to 7
PPTX
Construction management
PPT
3. construction planning. construction project management
PPTX
Presentation on FIDIC red book
PDF
Extension of Time (EoT) in Construction Project presentation
PDF
Primavera p6 18.8 planning and scheduling guide r3
PPTX
Project management
PPTX
Construction contract
PPT
Project control
PPT
Project management planning
PPTX
Project communication management
PPT
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
PPTX
10.3 Monitor Communication
PDF
Construction Project Management
PDF
Project Management Professional (PMP)
PPTX
Construction project management
PPTX
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
PPTX
Ppt on fidic claims
PPTX
Project Scheduling
Construction Project Management
Pmp presentation chapter 1 to 7
Construction management
3. construction planning. construction project management
Presentation on FIDIC red book
Extension of Time (EoT) in Construction Project presentation
Primavera p6 18.8 planning and scheduling guide r3
Project management
Construction contract
Project control
Project management planning
Project communication management
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
10.3 Monitor Communication
Construction Project Management
Project Management Professional (PMP)
Construction project management
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
Ppt on fidic claims
Project Scheduling
Ad

Similar to Project Auditing (20)

PPT
Project auditing
PPT
2 a. project auditing
PPTX
Project Auditing
PPT
Project audit
PPT
Project Auditing.ppt
PPT
PROJECT AUDIT- METHODS OF EVALUATION AND ASSESSMENT.
DOCX
project of audit
PPTX
Project Auditing
PPTX
Project management unit 5(1)
PDF
a-guide-to-project-auditing.pdf
PDF
How to survive a Project Management Audit Dec 2-2014
PPT
Swati Katba
PPT
Final Class Presentation on Project Audit and Closure.ppt
PPTX
GROUP-4-PRESENTATION-FINAL.pptx
PDF
How to do a Project Audit
PDF
Delivering Assurance - Audit, Mark Reilly, APM ASSURANCE SIG conference
PPTX
Project: Monitoring
PPTX
Is your project not going well this will help you get it back on track
PDF
How to audit for success webinar
PDF
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
Project auditing
2 a. project auditing
Project Auditing
Project audit
Project Auditing.ppt
PROJECT AUDIT- METHODS OF EVALUATION AND ASSESSMENT.
project of audit
Project Auditing
Project management unit 5(1)
a-guide-to-project-auditing.pdf
How to survive a Project Management Audit Dec 2-2014
Swati Katba
Final Class Presentation on Project Audit and Closure.ppt
GROUP-4-PRESENTATION-FINAL.pptx
How to do a Project Audit
Delivering Assurance - Audit, Mark Reilly, APM ASSURANCE SIG conference
Project: Monitoring
Is your project not going well this will help you get it back on track
How to audit for success webinar
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
Ad

More from BECM, RUET, Bangladesh (6)

PPTX
BECM 4103: Lecture 2 On site human waste management
PPTX
Introduction to environmental sanitation
PPTX
Introduction to sustainability
PPTX
Project monitoring & Earned Value Analysis
PPTX
Risk analysis
PPTX
Project monitoring lecture 1
BECM 4103: Lecture 2 On site human waste management
Introduction to environmental sanitation
Introduction to sustainability
Project monitoring & Earned Value Analysis
Risk analysis
Project monitoring lecture 1

Recently uploaded (20)

PPTX
bas. eng. economics group 4 presentation 1.pptx
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Welding lecture in detail for understanding
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
Well-logging-methods_new................
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
additive manufacturing of ss316l using mig welding
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
Structs to JSON How Go Powers REST APIs.pdf
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
bas. eng. economics group 4 presentation 1.pptx
Mechanical Engineering MATERIALS Selection
Welding lecture in detail for understanding
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Well-logging-methods_new................
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
additive manufacturing of ss316l using mig welding
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
Internet of Things (IOT) - A guide to understanding
Structs to JSON How Go Powers REST APIs.pdf
Operating System & Kernel Study Guide-1 - converted.pdf
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx

Project Auditing

  • 1. Project Auditing SHOWAIB AHMED CHOWDHURY Lecturer Department of Building Engineering & Construction Management Rajshahi University of Engineering & Technology(RUET)
  • 2. Introduction Project assurance is a fundamental part of effective project governance. The project audit is the means to provide that assurance and enables the sponsor to have confidence that the governance is working and that the project is being managed as intended. In this lesson, we will try, to demonstrate how to plan and undertake a comprehensive audit of a project, thereby providing that assurance. to explain the role of an auditor, how it could be planned and undertaken, the degrees of assurance that can be given, and how project audits can be aligned to organizational governance.
  • 3. The three main roles involved in project audits are: Role Description Organization board/audit committee/ sponsor/other stakeholders Those who schedulethe projectauditand receive the audit findings Project team Those whose project is being audited, with whom the auditors interact Project auditor(s) Those who undertake the audit, and report its findings and make recommendations For any audit to be successful and provide value to all parties, these three main roles must work together and understand each other’s function in the process.
  • 4. What is project auditing? According to the Chartered Institute of Internal Auditors, ‘an independent, objective assurance and consulting activity designed to add value and improve an organization's operations. It helps an organization accomplish its objectives by bringing a systematic, disciplined approach to evaluate and improve the effectiveness of risk management, control, and governance processes’. In any audit, the auditor(s) perceives and recognizes the propositions before them for examination, collects evidence, evaluates the same, and on this basis formulates an opinion on the adequacy of controls within the activity being audited.
  • 5. Principles of project audit Project audit should be: independent, and supported in this by the organization board; accountable within a governance and reporting system; planned and coordinated as part of the organization's management system; risk-based, against an independent risk evaluation; able to allow the impact of identified weaknesses to be reported and addressed, by follow-up and escalation.
  • 6. Why do we need project audits? • The giving of assurance to project stakeholders, including the organization board, through providing assessment of the likelihood of the project achieving its objectives, is a fundamental aspect of project governance • This assurance will cover the identification and management of risk, evaluation of opportunities, and actions being taken to realize those benefits on which approval of the business case was based. • Assurance also seeks evidence of effective controls and opportunities to increase the likelihood of success of the project So, Throughout the phases of a project there should be provision for independent audit to give assurance to key stakeholders including the project sponsor and executive board, of the likelihood that the objectives of the project will be achieved.
  • 7. The audit will cover the following elements : • Project definition and requirements management; • Project organization and governance; • Risks management; • Commercial, procurement and commissioning; • Configuration management, project change controls; • Project planning and scheduling; • Performance and benefits management; • Stakeholder management and communications; • Organizational capability and culture; • Social responsibility and sustainability.
  • 8. Project audit process Step 1: Planning the audit • Audit prioritization: Project audits should be planned on the basis of risks to the organization and to the project. • Choosing the audit team: The audit team should have access to specialist technical skills e.g. quality assurance, and should bear in mind the organization's appetite for integrated assurance. • Information gathering: Background information Results 1 Project name/reference 2 Brief description of the objectives of the project 3 Project value (total)/(this year) 4 Appropriate (outline or full) business case approved/ date/value 5 Agreed project audit scope, objectives and name/ reference 6 Project governance arrangements including project sponsor, projectmanager and projectteam 7 Project management arrangements
  • 9. 8 Project phase (Inception, Feasibility, Development, Delivery, Close-out) 9 Overview ofproject controls includingchange controls 10 Project Management Plan (PMP) and Project Initiation Document (PID) approved date 11 Project audit team details 12 Organization policies andprocedures tobeusedas basis for project audit 13 Extent ofPMO support required including management, cost and financial reports 14 Risks from corporate and project risk registers, and additional risks from discussion with stakeholders 15 Project and organization risk management and mitigation measures 16 Integration with other assurance providers 17 Alignment of project with corporate strategy 18 Risk-based audit programmed and schedule 19 Audit reporting details including timetable 20 Significant stakeholders (including their influence and interest) 21 Communications strategy 22 Arrangements tohandovertonextphase,stageor client ofproject
  • 10. • Risk assessing of a project: This should be carried out by discussion with stakeholders on risks that they have identified but which have not been included in the formal register; and on the auditor’s own experience and discussion with the project team. • The project audit programme: The audit team should identify the risks to the project, and the controls and tests which are derived from these. The different phases of the project life cycle should lead to audit programmed and tests appropriate to those phases, and to the nature of the project.
  • 11. 2. Fieldwork : The audit team should gather information and documentation, and talk to key stakeholders including (as appropriate) members of the project team, the procurement function and the supply chain. • Elements for review:  Project definition and requirements management  Project organization and governance  Risks management  Commercial, procurement and commissioning  Project planning and scheduling  Performance and benefits management  Stakeholder management and communications  Organizational capability and culture  Social responsibility and sustainability
  • 12. 3. Evaluation and reporting  Evaluation • The basic idea is to use a grading score to rank each audited element and indicate the extent to which the project has performed. • One method of grading used extensively to measure performance is the ‘traffic light’ system of three ratings: red/amber/green (RAG). • During project audits it may be more appropriate to use four or five ratings, with additional definitions and next steps. • Definitions of RAG will depend on project and reporting requirements.
  • 13.  Reporting  Individual organizations have their own reporting requirements, including who should receive the report, who has responsibility for responding to it, and who will be tasked with implementing its findings and recommendations. As some of the content of the report may be commercially or otherwise sensitive, this should be borne in mind in circulation and distribution of draft and final reports. Following a close-out meeting with auditees, the preliminary report should be prepared and internally reviewed before issue to those auditees and other stakeholders for comment on findings and recommendations. The final report, which should contain the evaluation rating based on the responses received, should be distributed in accordance with the requirements of the agreed audit plan. The final report should also be
  • 14. 4. Follow-up • Follow-up is the final element of the audit process, in which the audit team confirms that the sponsor and project team have implemented the agreed actions to address identified project risks and issues. • This can be confirmed by monitoring the implementation process, or by accepting a formal statement from the sponsor or project team that the recommended actions have been carried out. 5. Benefits evaluation • Where the scope of the project audit included evaluation or auditing of outcomes on which approval of the business case was, a separate audit process will be required. • This will seek to compare recorded benefit outcomes against those proposed in the business case through the use of defined benefit measures, normally by quantitative methods.
  • 15. 6. Legacy and lessons learned • The results of project audits can provide valuable reference points for the organisation’s legacy and lessons learned process. The audit team should be aware of the organisation’s requirements for confidentiality if involved in the legacy and lessons learned process. • The organization may operate a legacy programme, to capture the intellectual capital within a project before the project team is disbanded.
  • 16. • Prepare a mid-term audit report for a building construction project which have a budgeted cost at TK. 1000000 with a total project duration 8 months, Also consider at the time of mid-term 40% construction work is completed at a cost of TK 600000. Solution: Auditor: Audit-Team: Date of Audit: Project Audited: Project Manager: Introduction:
  • 17. General Analysis of the project by EVM: Budget at completion(BAC) : 1000000TK Completion Period: 8 months Actual cost(AC): 600000TK Earned Value(EV)= 40% * 1000000 = 400000TK Planned Value(PV)= 50% * 1000000 = 500000TK Cost Variance, CV= EV-AC = -200000TK Schedule Variance, SV= EV-PV= -100000TK Cost Performance Index, CPI= EV/AC= 0.67<1 Schedule Performance Index, SPI= EV/PV= 0.8<1
  • 18. • Current Status: • Future Projection: • Critical Management issues: • Risk Analysis and Risk Management: