EXTENSION OF TIME
(E.O.T)
By: Ahmed Ibrahim,PMP,PMI-
RMP,MSc,TOT
1
Professionalengineer
Presentation Objectives
Extension of Time Definition
EOT Triggers
Contractual Completion Date(s)
Primary components
Schedule Integrity
Documentation of Causation
Responsibility Assignment
Concurrency of Delays
Schedule Analysis
Presentation is Everything!
Recap
2
Professionalengineer
Extension of Time Definition
“Is a time which reimbursed by one of the contract
sides to the other as compensation for project events
and conditions, prevented that side from execute
portion of project work .”
3
Professionalengineer
EOT Triggers
 1. An Event Occurred or Will Occur that Causes
Delay
 2. 3 Possible EOT Event Types:
– Owner driven events or risk’s (Time & money)
– Neutral events – risk shared (Time only)
– Concurrent events-risk allocated (Time only)
 3. Causes Delay to the Critical Path.
4
Professionalengineer
Contractual Completion Date(s)
 Types of Contractual Completion Dates:
– „Practical Completion‟ Date
– „Substantial Completion‟ Date
– „Mechanical Completion‟ Date
– „Handover‟ Date
– „Separable Portion‟ Date
 May apply to a Section, or the Entire Project
– Each Section is treated separately
– Multiple EOT Claims May Apply
5
Professionalengineer
Primary components
E.O.T
Claims
Solid Schedule
Critical Path
Delay
Causation
Documentation
Responsibility
assignments
Analysis
technique
Packaging
6
Professionalengineer
Schedule Integrity
 No Open Ends
 Limited Constraints
 All Scope Captured
 Majority of Relationships Types: FS
 No Large Lags: “Float Realistic”
 No Redundant Logic Relationships
 Critical Path Makes Sense
 Critical Path is Continuous
 “Longest Path” Filter Confirmation
7
Professionalengineer
Schedule Integrity
 Obligation of Both the Owner and Contractor
 Contract Must State Schedule Requirements
 Updating Must not Stop after Baseline is Accepted
 Schedule Updates Are Contractual Too!
8
Professionalengineer
Schedule Integrity: How do you
Know?
 Ask for the Electronic Version (Not a PDF)…XER
 Run a Schedule Diagnostic on Baseline & Updates
 Primavera: “Schedule Log” and “Claim Digger”
 Others: Acumen “Fuse”, “Schedule Analyzer Pro” , ”XER
toolkit”
 Also look for..
– Added and/or Deleted Activities
– Increase or Decrease in OD
– Calendar Changes – Schedule Calculation Changes –
9
Professionalengineer
Schedule Integrity: Diagnostic
Tools
10
Professionalengineer
Schedule Integrity: Diagnostic Tools "Claim
Digger”
11
Professionalengineer
Schedule Integrity: Diagnostic Tools “XER
Toolkit”
12
Professionalengineer
Documentation of Causation
 1st: Demonstrate Cause (Documentation)
 2nd: Demonstrate Effect (Schedule Analysis)
 The 3 „R’s – Records, Records, and Records
 Record Type Important but Record Content is A Key!
13
Professionalengineer
Documentation of Causation: Record
Types
 Letters and Emails
 RFI’s
 Hold Registers
 Transmittal Logs
 Progress photographs
 Variation Notices
 Daily Field Reports
 Weekly Progress Reports
 Meeting Minutes
 Drawing Revision Logs
14
Professionalengineer
Documentation of Causation: Record
Content
 Instructions given & received
 Conflicts in plans/specifications
 Weather conditions: Not Just Rain
 Work Stoppage: Time Stopped and Why
 Subcontractors
 Equipment Type Utilized and Number
 Daily Activity of Staff
 Specific Location: Zone Number, Area…etc
 Delays Encountered: Specific Activity
 Material Shortages Create a Standardized Daily
Report Form
15
Professionalengineer
Documentation of Causation: Delay
Examples
 Weather
1-We can not continue in excavation
2-We can not pouring the –
ready mix concrete
16
Professionalengineer
Documentation of Causation: Delay
Examples
 Equipment & Material Problems
1-excavation hydraulic pipe broken again
2-Power generator is down again
17
Professionalengineer
Documentation of Causation: Delay
Examples
 Design issues
 Environmental
 Site accidents
18
Professionalengineer
Responsibility Assignment
 What Does the Contract Say?
– Owner Caused Delays
– Force Majeure Delays
– Neutral Delays-Weather
– Non-Excusable Delays
19
Professionalengineer
Concurrent Delay – Requirements…
 Two or more delays during the “same” time
 Delays unrelated and independent
 Must delay the critical path
 Responsibility of different parties
 Each party bears its own expenses for that delay
 Substantial and not easily curable
20
Professionalengineer
Concurrency: Net Affect Matrix
Delay event Concurrent with Net effect
Owner delay Another delay by owner xxx
Owner delay Another delay by owner xxxx
Contractor delay Force majeure delay xx
Contractor delay
Another contractor
delay
xxxxxx
21
Professionalengineer
Schedule Analysis:
 1.As-Planned vs. As-Built
 2.Windows Analysis
 3.TIA
22
Professionalengineer
As-Planned vs. As-Built
 Comparison of start/finish dates between two schedule
updates
 Purely mathematical-Variance between dates
23
Professionalengineer
As-Planned vs. As-Built
 When should it be used?
-Limited time and money
-No electronic schedules
-Inadequate schedule logic
24
Professionalengineer
As-Planned vs. As-Built
Not Good For:
– Concurrent delays or acceleration
– Critical path changes between updates
– Multiple critical or near-critical paths per update
– Recovering extended overhead costs
– Arbitration or Litigation
25
Professionalengineer
As-Planned vs. As-Built
Pros:
– Easy to understand, explain, and graphically depict
– Technically simple to perform
Data Required:
– Baseline schedule
– As-built schedule
26
Professionalengineer
Windows Analysis
 Quantify loss or gain of time along a float path
 Loss and gains tallied by window
 A “window” is the time period framed between two
revisions:
• The as-planned schedule for the beginning of the
window
• The as-built schedule for the end of the window As-
Planned As- Built
27
Professionalengineer
Windows Analysis
28
Professionalengineer
Windows Analysis
 When Should the Schedule Analysis Method be Used?
– Complex schedules with large critical paths
– Very high delay damages
– Concurrent delays
– Client has the time and budget
– Need graphical depiction of concurrency
 What does the Schedule Analysis Method Best Prove?
– Excusable non-compensable delay
– Excusable compensable delay
– Concurrent delay
29
Professionalengineer
Impacted As-Planned (TIA)
 Insertion of impact activities into a baseline or update schedule
 Integrated into the network logic before, in- between, or after the
activity it affected
 Additive model that simulates the possible effect of actual delay
events to the schedule completion date
 Comparison of IAP schedule and succeeding update to determine
possible acceleration or non-excusable delays
 Comparison of IAP schedule and planned schedule to determine
time extension
30
Professionalengineer
Impacted As-Planned
31
Professionalengineer
Impacted As-Planned
32
Professionalengineer
Presentation
 1. Attach Source Documentation
 2. Graphical Representation
• Schedule Updates: Prior to Impact and After Impact
• Critical Path in Gantt Chart Format with Logic
• Concurrency
 3. Write Up
• Keep it Short and Sweet (Ishikawa , Pareto and time lines)
• Explanation of Impact Event: Timing , Activities , Duration
33
Professionalengineer
Presentation
 4. Cost Impact
• Stand-By Costs of Equipment and Staff Affected
• Don't Claim Costs on Staff That Were Working!
5. Executive Summary at the Beginning
6. Submit Once Impact Event Is Known
7. Submit Again Once Full Impact Understood
34
Professionalengineer
Ishikawa example
Management process and
Procedure
Too much process and unneeded
procedure activities which take
more time
All major and minor decisions by PM
only
Q u a l I t y C o n t r o l P r o c e
PM staff came very late to
project
Material submittals take
unusual review time
Shop drawing submittals
take unusual review time
Open R.F.Is which hold much
works
Delay in issuing (L.O.Is)
Poor Coordination Management
Hold Critical schedule
work areas
Salco work with site
premises
Professionalengineer
Pareto Chart-(20/80)Rule
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
10
20
30
40
50
60
70
80
90
100
Material submittals
review>15days
Shop drawing review
>15days
General Project
Submittals
Issuing LOIs Open RFIs Exceeding project
specifications
Pareto Chart-(20/80)Rule
OCCURRENCES CUMULATIVE PERCENT
Professionalengineer
Summary
• Documentation is Key: Content Must be Consistent
• Schedules Must Be Sound and Accurate
• Don't Ignore Updates
• Choose Your Technique Wisely
• Consider Concurrency
• Present Claim as a Concise Package
• Don't Throw the Kitchen Sink into the Claim
• Resolution time sure will be near to your EOT issue
37
WWW.PROFESSIONALENGINEERS.US
PROFESSIONAL2ENGINEERS@GMAIL.COM
0545821579
Ahmed Ibrahim,MSc,BSc,PMP,PMI-RMP,TOT
Thank
You…
38

More Related Content

PPTX
Construction Delay Analysis, Simplified
PDF
Delay Analysis and Concurrent Delay
PPTX
FIDIC-Relevant to Time Management
PDF
Extension of Time (EoT) in Construction Project presentation
PDF
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
PDF
Delay analysis ... wise after the event.
PDF
Time Impact Analysis
PPTX
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Construction Delay Analysis, Simplified
Delay Analysis and Concurrent Delay
FIDIC-Relevant to Time Management
Extension of Time (EoT) in Construction Project presentation
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Delay analysis ... wise after the event.
Time Impact Analysis
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides

What's hot (20)

PPTX
Eot claims hr__may2012
PPTX
Extension of time Analysis
PDF
Essentials of EOT Claims
PPTX
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
PPTX
Construction Project Management
PPTX
03 Construction Project Planning and Scheduling
PPT
3. construction planning. construction project management
PPTX
Introduction To Primavera (P6)
PPTX
Variations in works contracts
PPTX
Primavera presentation
PPTX
ppt for primevera
PDF
Loading cost in primavera schedule using resources and expenses r01
PDF
Contract payment and variation
PDF
How to prepare recovery or revised schedule rev.2
PDF
Construction Management (1st Lecture)
PDF
Claims
PPTX
Construction contract
PDF
Schedule Updates
PDF
Primavera p6 18.8 planning and scheduling guide r3
PDF
Epc project interdepency and Work Flow- promo
Eot claims hr__may2012
Extension of time Analysis
Essentials of EOT Claims
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
Construction Project Management
03 Construction Project Planning and Scheduling
3. construction planning. construction project management
Introduction To Primavera (P6)
Variations in works contracts
Primavera presentation
ppt for primevera
Loading cost in primavera schedule using resources and expenses r01
Contract payment and variation
How to prepare recovery or revised schedule rev.2
Construction Management (1st Lecture)
Claims
Construction contract
Schedule Updates
Primavera p6 18.8 planning and scheduling guide r3
Epc project interdepency and Work Flow- promo
Ad

Similar to Extension of time (E.O.T) By Ahmed Ibarhim (20)

PPTX
PDF
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
PPTX
2.06 time management 1
PPTX
Pert, cpm & gert
PPT
EO notes Lecture 27 Project Management 2.ppt
PPT
Lecture6
PPT
Schedule_Module_V.10.ppt
PPT
project planning-estimation
PPT
Intro to PM.ppt
PPT
MGT-Ch07.ppt
PPTX
PMNM101 Lesson 2 2022.pptx
PPTX
DOC-20230811-WA0054..pptx busnises plangood
PDF
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
PPTX
C. Site managment chapter 5.pptx
PDF
Project Schedule Management
PDF
Mastering the Critical Path and Mitigation Actions
PPTX
Episode 30 : Project Execution ( Part 1 )
PDF
Group 7_ Claims (Contractor master program and Cause and Effect in Constructi...
PPT
1.7 Project Management basics and techniques.ppt
PPT
lec11.ppt
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
2.06 time management 1
Pert, cpm & gert
EO notes Lecture 27 Project Management 2.ppt
Lecture6
Schedule_Module_V.10.ppt
project planning-estimation
Intro to PM.ppt
MGT-Ch07.ppt
PMNM101 Lesson 2 2022.pptx
DOC-20230811-WA0054..pptx busnises plangood
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
C. Site managment chapter 5.pptx
Project Schedule Management
Mastering the Critical Path and Mitigation Actions
Episode 30 : Project Execution ( Part 1 )
Group 7_ Claims (Contractor master program and Cause and Effect in Constructi...
1.7 Project Management basics and techniques.ppt
lec11.ppt
Ad

More from Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP (13)

PDF
Masar alryadah Arabic profile
PDF
Masar alryadah English profile
PPSX
Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)
PPSX
Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...
PPTX
25 11-big 5- critical success factors for applying (OPM)governance in MENA re...
PPTX
Curcial Factors that affect Cost Management.
PDF
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
PPSX
Pmp taking first attempt public
PPSX
Hbrc professional engineers-presentation
PPTX
الموارد البشريه والانتاجيه والتحفيز
PDF
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
PPT
organization charts....rules
Masar alryadah Arabic profile
Masar alryadah English profile
Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)
Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...
25 11-big 5- critical success factors for applying (OPM)governance in MENA re...
Curcial Factors that affect Cost Management.
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
Pmp taking first attempt public
Hbrc professional engineers-presentation
الموارد البشريه والانتاجيه والتحفيز
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
organization charts....rules

Recently uploaded (20)

PDF
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
PPTX
Chapter Three for international political
PPTX
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
PPT
Claims and Adjustment Business_Communication.pptx.ppt
PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PDF
CISSP - Domain 7: Security Operations - InfoSec Institute
PPTX
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
PDF
The Cyber SwarmShield by Stéphane Nappo
PPTX
MY GOLDEN RULES la regla de oro jhonatan requena
PDF
CISSP Domain 5: Identity and Access Management (IAM)
PDF
CHAPTER 15- Manageement of Nursing Educational Institutions- Staffing and st...
PDF
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PDF
Contemporary management and it's content
PDF
The-Power-of-Communication (1).pdf......
PPTX
Leadership for Industry 4.0 And Industry 5.0
PPTX
Psychological_Contract_Presentation.pptx
PPTX
School Annual day Presentation, Logo, Animation
PPTX
Empowering Project Management Through Servant Leadership - PMI UK.pptx
PDF
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
Chapter Three for international political
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
Claims and Adjustment Business_Communication.pptx.ppt
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
CISSP - Domain 7: Security Operations - InfoSec Institute
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
The Cyber SwarmShield by Stéphane Nappo
MY GOLDEN RULES la regla de oro jhonatan requena
CISSP Domain 5: Identity and Access Management (IAM)
CHAPTER 15- Manageement of Nursing Educational Institutions- Staffing and st...
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
_ISO_Presentation_ISO 9001 and 45001.pptx
Contemporary management and it's content
The-Power-of-Communication (1).pdf......
Leadership for Industry 4.0 And Industry 5.0
Psychological_Contract_Presentation.pptx
School Annual day Presentation, Logo, Animation
Empowering Project Management Through Servant Leadership - PMI UK.pptx
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer

Extension of time (E.O.T) By Ahmed Ibarhim