SlideShare a Scribd company logo
2
Most read
6
Most read
13
Most read
CONTRACT CONDITIONS - II:
VARIATIONS/DEVIATIONS
Dr K M Soni, ADG(Retd.), CPWD,
New Delhi
Variations/Deviations
• Variations or Deviations are the changes from
the scope of work of a contract resulting during
execution of work except duration of the
contract.
• Mostly, Variations or Deviations are considered
the changes from the quantities or items of the
bill of quantities (Schedule of quantities) of a
contract resulting during execution of work as
changes in design, quantity or conditions
ultimately lead to affect BOQ/SOQ.
Variations/Deviations
• Variation/Deviation in quantities of items
• Extra items
• Substituted items
Deviation in Quantities
• These are the deviations or variations from
the quantities taken in Bill of Quantities or
Schedule of Quantities
• These are the items for which rates are
available in the contract
• The deviations/variations may be +ve or –ve
i.e. Quantities may increase or decrease from
the quantities available in BOQ/SOQ
Reasons of Deviations in Quantities
• Wrong assessment or mistake during preparation of detailed
estimate/BOQ/tender documents
• Assessment of quantities without availability of
architectural, structural or MEP drawings.
• Revision of drawings/design
• Revision due to local bye laws or local body agencies
• Revision due to non availability of materials at a particular
time
• Revisions due to client, architect, or engineer and contractor
Rates of Deviations in Quantities
• Rates of such items are available in the contract
• Deviations are +ve or –ve
• Rates can be based on;
• Available in contract for all deviations
• Rates available in the contract upto additional quantities
as mentioned in the contract (deviation limit, described in
percentage) and beyond it, market rates, Schedule rates
+/- quoted percentage, Schedule rates or cost plus basis or
any other method as mentioned in the contract or agreed
upon by the parties.
Extra or Additional items
• Items that are completely new and in addition
to the items contained in the contract
• These are the items other than those available
in BOQ and not covered in the conditions of
contract
• In some contracts, these are the items which are
not available in contract and not taken up in
substitution of items available in BOQ
Reasons of Extra/Additional items
• Left or mistake during preparation of detailed estimate/BOQ/tender
documents
• Specifications not available during preparation of detailed estimate/BOQ
• Non availability of architectural, structural or MEP drawings during
preparation of detailed estimate/tender document
• Revision of drawings/design
• Revision due to local bye laws or local body agencies
• Revision due to non availability of materials at a particular time
• Items not anticipated during preparation of tender documents i.e.
Contingent items
• Revisions due to client, architect, or engineer and contractor
Rates of Extra or Additional Items
• Market rates
• Schedule rates +/- quoted percentage
• Schedule rates
• Cost plus basis or
• Any other method as mentioned in the
contract or agreed upon by the parties.
Substituted item
• Items taken up as partial substitution or in
lieu of items of work available in the contract
• Therefore, the items are basically due to
change of specifications during execution
from those considered during preparation of
detailed estimate/BOQ/tender documents
Reasons of Substituted items
• Specifications/drawings not available during preparation of
detailed estimate/BOQ i.e. Non availability of architectural,
structural or MEP drawings
• Revision of drawings/design/specifications
• Revision due to local bye laws or local body agencies
• Revision due to non availability of materials or non
feasibility of the execution of the item at a particular time
• Revisions due to client, architect, or engineer and contractor
Rates of Substituted Items
• Agreement rates increased or decreased by the
difference in market rates of item substituted
compared to market rates of agreement item
• Market rates
• Schedule rates +/- quoted percentage
• Schedule rates
• Cost plus basis or
• Any other method as mentioned in the contract
or agreed upon by the parties.
Implications of Variations/ Deviations
• Extension of time
• Possible justification of regularisation of delay caused
by the contractor
• Chances of non compatibility of such items with
respect to other services
• Source of Disputes about the rates, time extension,
loss of profit, idle establishment and thus arbitration
• Delayed decisions
• Non approval of items and rates of variations
• Time overrun and cost overrun
Thanks for attending
Dr K M Soni, ADG (Retd.), CPWD, New Delhi
Also available on Youtube: KRISHNA MURARI Soni at
https://www.youtube.com/channel/UC_pPYxk0jI1ayqA5rO6fBOw

More Related Content

PDF
Contract payment and variation
PPTX
Reinforced Concrete Frame Structure
PPTX
Lecture slides5; LINE OF BALANCE PROGRAMMING
PPTX
SOIL NAILING
PPTX
Time management in fidic red book 2017(prmg080 project)
PDF
Assignment - FIDIC Contract
PPTX
Statutory Approvals For Construction Projects In India (Residential & Commerc...
PDF
Construction Monthly Progress Report - June 2011
Contract payment and variation
Reinforced Concrete Frame Structure
Lecture slides5; LINE OF BALANCE PROGRAMMING
SOIL NAILING
Time management in fidic red book 2017(prmg080 project)
Assignment - FIDIC Contract
Statutory Approvals For Construction Projects In India (Residential & Commerc...
Construction Monthly Progress Report - June 2011

What's hot (20)

PPTX
Construction contract
PPT
Construction Claims
PPTX
Fidic Form of Contract.
PPTX
Construction Claims Explained
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
PPTX
Classification of contracts
PDF
Claims 20.1 (Flow chart)
PPSX
Changes in construction
PPTX
Types of contract
PDF
Extension of Time (EoT) in Construction Project presentation
PPT
Construction contracts docuements_08092008
PPTX
TENDER DOCUMENT
PPTX
Construction Documents
PPT
Suspensions and Delays in Construction Contract
PPTX
CONTRACTS AND ITS TYPES
PPTX
Epc contracts.
PDF
Fidic contracts management introduction
PPTX
Contract and Arbitration
DOCX
Procurement Methods
PPTX
Tendering process, Bid Evaluation & Award Process
Construction contract
Construction Claims
Fidic Form of Contract.
Construction Claims Explained
Extension of time (E.O.T) By Ahmed Ibarhim
Classification of contracts
Claims 20.1 (Flow chart)
Changes in construction
Types of contract
Extension of Time (EoT) in Construction Project presentation
Construction contracts docuements_08092008
TENDER DOCUMENT
Construction Documents
Suspensions and Delays in Construction Contract
CONTRACTS AND ITS TYPES
Epc contracts.
Fidic contracts management introduction
Contract and Arbitration
Procurement Methods
Tendering process, Bid Evaluation & Award Process
Ad

Similar to Variations in works contracts (20)

PPTX
CONTRACT ADMINISTRATION Updated.pptx
PPT
TENDERS and Contracts basic syllabus for engineering
PPTX
1. Contracts and Tender.pptx jkbjhvjhcvhgcfgxftxtrjxgjfchchgchgkchgkchkgchgkch
PPTX
Extensions of Time - Contract Management
PPT
Common Interest Repair Issues
PPTX
Legal issues associated with project management and consulting
PPT
Common Interest Repair Issues
PDF
Measure And Pay Contract
PDF
Bid Evaluation
PDF
TOPIC7.pdf
PDF
Procurement Strategies: A Seminar
PDF
Key Components of Cost Estimation in construction
PPTX
Professional practice-1-presentation
DOCX
Turnkey implementation of distribution projects
PPTX
Preparation of boq
PDF
SIA_Scope_of_Service_Matrix-20180814-for_website.pdf
PPT
Change management and dispute resolution
PDF
CCDC2 - A Focus on 3 Topics Using Case Studies
PPTX
Contract Conditions
PPT
ACH 216 Lecture 04b (Bidding) Part 1
CONTRACT ADMINISTRATION Updated.pptx
TENDERS and Contracts basic syllabus for engineering
1. Contracts and Tender.pptx jkbjhvjhcvhgcfgxftxtrjxgjfchchgchgkchgkchkgchgkch
Extensions of Time - Contract Management
Common Interest Repair Issues
Legal issues associated with project management and consulting
Common Interest Repair Issues
Measure And Pay Contract
Bid Evaluation
TOPIC7.pdf
Procurement Strategies: A Seminar
Key Components of Cost Estimation in construction
Professional practice-1-presentation
Turnkey implementation of distribution projects
Preparation of boq
SIA_Scope_of_Service_Matrix-20180814-for_website.pdf
Change management and dispute resolution
CCDC2 - A Focus on 3 Topics Using Case Studies
Contract Conditions
ACH 216 Lecture 04b (Bidding) Part 1
Ad

More from Dr K M SONI (20)

PPTX
Heritage Conservation
PPTX
Project Management
PPTX
You are also a leader
PPTX
Contract Management
PPTX
Contract and agreements
PPTX
Price variation in works contracts
PPTX
Anchors in civil engineering works
PPTX
Advance Payments in Works
PPTX
Earnest Money
PPTX
Deconstruction
PPTX
Geosynthetics
PPTX
Net zero energy building
PPTX
C & D Waste Management
PPTX
EPC and other types of contracts
PPTX
Contract Management
PPTX
EPS Geofoam Blocks
PPTX
Aesthetics and Functionality through Glass
PPTX
EPC Contracts
PPTX
Maintenance Aspects and Services in Architectural Planning
PPT
Safety in Public Works
Heritage Conservation
Project Management
You are also a leader
Contract Management
Contract and agreements
Price variation in works contracts
Anchors in civil engineering works
Advance Payments in Works
Earnest Money
Deconstruction
Geosynthetics
Net zero energy building
C & D Waste Management
EPC and other types of contracts
Contract Management
EPS Geofoam Blocks
Aesthetics and Functionality through Glass
EPC Contracts
Maintenance Aspects and Services in Architectural Planning
Safety in Public Works

Recently uploaded (20)

PPTX
Sustainable Sites - Green Building Construction
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPT
Mechanical Engineering MATERIALS Selection
PDF
PPT on Performance Review to get promotions
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
Geodesy 1.pptx...............................................
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Lecture Notes Electrical Wiring System Components
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPT
Project quality management in manufacturing
PDF
composite construction of structures.pdf
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
Digital Logic Computer Design lecture notes
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Sustainable Sites - Green Building Construction
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Lesson 3_Tessellation.pptx finite Mathematics
Embodied AI: Ushering in the Next Era of Intelligent Systems
bas. eng. economics group 4 presentation 1.pptx
Mechanical Engineering MATERIALS Selection
PPT on Performance Review to get promotions
Foundation to blockchain - A guide to Blockchain Tech
Geodesy 1.pptx...............................................
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Lecture Notes Electrical Wiring System Components
Operating System & Kernel Study Guide-1 - converted.pdf
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Project quality management in manufacturing
composite construction of structures.pdf
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
CYBER-CRIMES AND SECURITY A guide to understanding
Digital Logic Computer Design lecture notes
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx

Variations in works contracts

  • 1. CONTRACT CONDITIONS - II: VARIATIONS/DEVIATIONS Dr K M Soni, ADG(Retd.), CPWD, New Delhi
  • 2. Variations/Deviations • Variations or Deviations are the changes from the scope of work of a contract resulting during execution of work except duration of the contract. • Mostly, Variations or Deviations are considered the changes from the quantities or items of the bill of quantities (Schedule of quantities) of a contract resulting during execution of work as changes in design, quantity or conditions ultimately lead to affect BOQ/SOQ.
  • 3. Variations/Deviations • Variation/Deviation in quantities of items • Extra items • Substituted items
  • 4. Deviation in Quantities • These are the deviations or variations from the quantities taken in Bill of Quantities or Schedule of Quantities • These are the items for which rates are available in the contract • The deviations/variations may be +ve or –ve i.e. Quantities may increase or decrease from the quantities available in BOQ/SOQ
  • 5. Reasons of Deviations in Quantities • Wrong assessment or mistake during preparation of detailed estimate/BOQ/tender documents • Assessment of quantities without availability of architectural, structural or MEP drawings. • Revision of drawings/design • Revision due to local bye laws or local body agencies • Revision due to non availability of materials at a particular time • Revisions due to client, architect, or engineer and contractor
  • 6. Rates of Deviations in Quantities • Rates of such items are available in the contract • Deviations are +ve or –ve • Rates can be based on; • Available in contract for all deviations • Rates available in the contract upto additional quantities as mentioned in the contract (deviation limit, described in percentage) and beyond it, market rates, Schedule rates +/- quoted percentage, Schedule rates or cost plus basis or any other method as mentioned in the contract or agreed upon by the parties.
  • 7. Extra or Additional items • Items that are completely new and in addition to the items contained in the contract • These are the items other than those available in BOQ and not covered in the conditions of contract • In some contracts, these are the items which are not available in contract and not taken up in substitution of items available in BOQ
  • 8. Reasons of Extra/Additional items • Left or mistake during preparation of detailed estimate/BOQ/tender documents • Specifications not available during preparation of detailed estimate/BOQ • Non availability of architectural, structural or MEP drawings during preparation of detailed estimate/tender document • Revision of drawings/design • Revision due to local bye laws or local body agencies • Revision due to non availability of materials at a particular time • Items not anticipated during preparation of tender documents i.e. Contingent items • Revisions due to client, architect, or engineer and contractor
  • 9. Rates of Extra or Additional Items • Market rates • Schedule rates +/- quoted percentage • Schedule rates • Cost plus basis or • Any other method as mentioned in the contract or agreed upon by the parties.
  • 10. Substituted item • Items taken up as partial substitution or in lieu of items of work available in the contract • Therefore, the items are basically due to change of specifications during execution from those considered during preparation of detailed estimate/BOQ/tender documents
  • 11. Reasons of Substituted items • Specifications/drawings not available during preparation of detailed estimate/BOQ i.e. Non availability of architectural, structural or MEP drawings • Revision of drawings/design/specifications • Revision due to local bye laws or local body agencies • Revision due to non availability of materials or non feasibility of the execution of the item at a particular time • Revisions due to client, architect, or engineer and contractor
  • 12. Rates of Substituted Items • Agreement rates increased or decreased by the difference in market rates of item substituted compared to market rates of agreement item • Market rates • Schedule rates +/- quoted percentage • Schedule rates • Cost plus basis or • Any other method as mentioned in the contract or agreed upon by the parties.
  • 13. Implications of Variations/ Deviations • Extension of time • Possible justification of regularisation of delay caused by the contractor • Chances of non compatibility of such items with respect to other services • Source of Disputes about the rates, time extension, loss of profit, idle establishment and thus arbitration • Delayed decisions • Non approval of items and rates of variations • Time overrun and cost overrun
  • 14. Thanks for attending Dr K M Soni, ADG (Retd.), CPWD, New Delhi Also available on Youtube: KRISHNA MURARI Soni at https://www.youtube.com/channel/UC_pPYxk0jI1ayqA5rO6fBOw