SlideShare a Scribd company logo
Time Management In Fidic Red
Book 2017
Project (PRMG-080)
MOHAMED ISMAIL KOTB
AUC ID : 700201232
SUBMITTED TO
Dr. Bahaa el shael
Contents
Fidic Red Book 2017
Project Parties
Agreement or Determination
Time for Completion
Commencement, Delays and Suspension
Sequence of payment
FIDIC and its Dispute Resolution Provisions
Typical Sequence of Dispute
Fidic Red Book 2017
• Design and Engineering (incl. BoQs) is done by Employer or Employer’s
Representative.
• Tenderers fill in their unit prices into the existing BoQs.
• Final amount is not fixed, payments are done based on the real amounts
executed. (Exceptions are available eg: lump-sum conracts).
• Employer carries the risk for contract amount increases.
• The better the design, the flawless the project implementation.
• Tender evaluations are relatively simpler.
Project Parties
Project
Parties
Engineer
• the person named in the
Contract Data appointed
by the Employer to act
as the Engineer for the
purposes of the Contract
Employer
• he person named as the
employer in the Contract
Data and the legal
successors in title to this
person
Contractor
• the person(s) named as
contractor in the Letter
of Tender accepted by
the Employer and the
legal successors in title
of such person(s).
Typical Sequence of Events in Agreement or Determination under
Sub-Clause 3.7
Scenario(1) Agreement is reached within 42 days, error found in the Engineer’s Notice of agreement and corrected
Typical Sequence of Events in Agreement or Determination under
Sub-Clause 3.7
Scenario(2) The Parties’ early advice that agreement cannot be reached and so Engineer’s determination is necessary,
no error in Engineer’s determination.
Typical Sequence of Events in Agreement or Determination under
Sub-Clause 3.7
Scenario(3) No agreement within 42 days, Engineer determines within 42 days, error found in the Engineer’s
determination and corrected.
The Time for Completion Sequence During Contracts for Construction
Commencement, Delays and Suspension(sec-8)
• 8.1 Commencement of Works
• Before the
Commencement Date
not less than 14 days
• Or
• The Commencement
Date shall be within 42
days after the
Contractor receives the
Letter of Acceptance.
Engineer(Notice
the contractor to
commence the
work)
Commence the
work
Contractor
Time for Completion
Time for
completion
Contractor
Whole works
complete with
in
time
Taking over of the
works & section
clause 10.1
8.3Programme
Contractor
• submit an initial
programme for the
execution of the Works
to the Engineer within
28 days after receiving
the Notice
Commencement of
Works.
• submit a revised
programme for the
actual progress of the
Works.
Engineer
• Review the initial
programme and gives
the notice within 21
days after receiving the
initial programme
• Review each revised
programme and gives
the notice within 14
days after receiving a
revised programme
The Contractor shall
submit a revised
programme within 14
days after receiving this
Noticeto the Engineer
Notice of No-objection
• The Contractor shall
proceed in
accordance with the
Programme
Engineer
give the
Notice
Yes
No
Initial programme
initial
programme
Commencement
Date and the
Time for
Completion
the date right of
access to and
possession of
the Site
Execution
strategy
the order of
execution works
timing of each
stage of
Design (if any) Procurement
Submission of
documents
construction,
erection,
installation
nominated
Subcontractor
works
Testing &
inspection
Schedule & WBS
all activities
Logically linked
the earliest,
latest start,
finish dates and
the float
the critical path
Milestones
Revised programme
Revised
programme
Progress
actual progress
to date
Delays
any delay to such
progress
effects of delay
Prosals to
overcome the
effects of any delay
Supporting report
Execution works
Execution
Method
Required recourses
Personnel Equipment
significant
change(s)
8.4 Advance Warning
• The Engineer may request the Contractor to submit a proposal under
Sub-Clause 13.3.2 [Variation by Request for Proposal] to avoid or
minimize the effects of such event(s) or circumstance(s).
8.5 Extension of Time for Completion
• The Contractor shall be entitled subject to Sub-Clause 20.2 [Claims
• For Payment and/or EOT] to Extension of Time if and to the extent
that
• completion for the purposes of Sub-Clause 10.1 [Taking Over the
Works and
• Sections] is or will be delayed by any of the following causes:
Measure works
which increases
the quantity
more than
10%causes a
delay to
completion
Contractor
• Review
measured
quantities
• Increase, but
not decrease
the total EOT
Engineer
8.5 Extension of Time for Completion (EOT)
EOT
Causes
Variation
Unforeseen
climatic
conditions
Unavailabilit
y of labor,
material,or
equipment
Delays
caused by
the employer
Assessed in
accordance
rules and procedures
stated in the Special
Provisions
as appropriate taking
due regard of all
relevant
circumstances).
Concurrent Delay
8.6 Delays Caused by Authorities
DelaysCaused
byAuthorities
Contractor has diligently followed the
procedures laid down by the relevant
legally constituted public authorities
authorities or entities delay or disrupt the
Contractor’s work
delay or disruption was Unforeseeable,
Contractor consider Clause 8.4 (EOT for
completion)
8.7 Rate of Progress
1- slow progress to complete the Works
2- progress has fallen (or will fall) behind the Programme
3- the initial programme has not yet become the Programme
1-instruct the Contractor to submit the revised methods to expedite progress and complete the Works
2-gives a Notice to the Contractor stating otherwise, the Contractor shall adopt these revised methods
1-if these revised methods cause the Employer to incur additional costs, the Employer shall be entitled subject to
Sub-Clause 20.2 [Claims For Payment and/or EOT] to payment of these costs by the Contractor, in addition to Delay
Damages (if any).
2-termination under Sub-Clause 15.2 [Termination for Contractor’s Default] before completion of the Works. These
Delay Damages
Contractor
Engineer
Employer
8.8 Delay Damages
Delay Damages
Contractor
Fails to comply with
Sub-Clause 8.2 [Time
for Completion]
Fraud, gross
negligence,
deliberate default or
reckless misconduct
by the Contractor.
Employer
[Claims ForPayment
and/or EOT] to
payment of Delay
Damages by the
Contractor
Delay Damages shall
be the amount stated
in the Contract Data
paid for every day
between the relevant
Time and relevant
Date of Completion
of the Works
8.9 Employer’s Suspension
• protect, store and
secure such part or all
of the Works against
any deterioration, loss
or damage
Contractor
• instruct to suspend
progress of part or all of
the Works
• state the date and
cause of the suspension
Engineer
8.10 Consequences of Employer’s Suspension
Contractor entitled to EOT, or to
payment of the Cost incurred
• If the Contractor suffers delay and/or incurs
Cost from complying with an Engineer’s
instruction under Sub-Clause 8.9 [Employer’s
Suspension] and/or from resuming the work
under Sub-Clause 8.13 [Resumption of Work]
Contractor not entitled to EOT, or to payment
of the Cost incurred, in making good:
• (a) the consequences of the Contractor’s faulty or defective
• (b) any deterioration, loss or damage caused by the Contractor
8.11 Payment for Plant and Materials after Employer’s
Suspension
Materials which have not
been delivered to Site, if:
the work on Plant, or delivery
of Plant and/or Materials, has
been suspended for more
than 28 days and
the Plant and/or Materials
were scheduled, and ready
for delivery to the Site during
the suspension period
reasonable evidence that the
Plant and/or Materials
comply with the Contract
the Contractor has marked
the Plant and/or Materials as
the Employer’s property in
accordance with the
Engineer’s instructions.
The Contractor shall be
entitled to
payment of the value Plant
and/or Materials which have
not been delivered to Site if
8.12 Prolonged Suspension
Suspension has
continued for more than 84 days
The Contractor may give a Notice
to the Engineer
requesting permission to proceed
If the Engineer does not give a
Notice within 28 days
after receiving the Contractor’s
Notice
the Contractor may agree to a
further suspension in which case
the Parties may agree the EOT
and/or Cost Plus Profit, and/or
payment for suspended Plant
and/or Materials, arising from
the total period of suspension
if the Parties not agree after
giving a (second) Notice to the
Engineer, treat the suspension as
an omission of the affected part
of the Works with immediate
effect including release from any
further obligation to protect,
store and secure
If the suspension affects the
whole of the Works, the
Contractor may give a Notice of
termination
8.13 Resumption of Work
Engineer
• Give Notice to
the contractor
to proceed
the suspended
work
Contractor
• resume work
after receiving
the Notice
from the
Engineer
Engineer
• record any
deterioration,
loss, damage
or defect in
the Works or
Plant or
Materials
during the
suspension
Contractor
• Make good all
such
deterioration,
loss, damage
or defect to
comply with
the Contract
Typical Sequence of payment Events Envisaged in clause 14
FIDIC 1999 and its Dispute Resolution Provisions
FIDIC Procedure for Employer/Contractor’s Claims
28 day Notice of Claim to Engineer
42 day “Fully Detailed Claim”
to Engineer
“Final Claim” 28 days after end of effects
42 days after receipt of claim
Engineer’s Response
Clause 3.5 Engineer to“Agree or Determine”
Clause 20.1
Contractor’s Claims
Clause 3.5
Determinations
Agreement/Determination
given effect unless revised under Clause 20
FIDIC 1999 and its Dispute Resolution Provisions(cont.)
Reference to Dispute Adjudication Board (DAB)
(1 or 3 people)
DAB Decision
within 84 days of reference
“Amicable Settlement” stage
ICC Arbitration
within 56 days after Notice of Dissatisfaction
Clause 20.2
Clause 20.4
Clause 20.5
Clause 20.6
No Notice of Dissatisfaction
within 28 days of Decision
Notice of Dissatisfaction
within 28 days after 84 days of reference
No DAB Decision
within 84 days of reference
Notice of Dissatisfaction
within 28 days of Decision
DAB Decision
final and binding
FIDIC 1999 and its Dispute Resolution Provisions(cont.)
Employer or Engineer gives
notice and particulars to Contractor
Clause 3.5 Engineer to
“Agree or Determine”
Clause 2.5
Employer’s Claims
Clause 3.5
Determinations
Reference to Dispute Adjudication Board (DAB)
(1 or 3 people)
“Amicable Settlement” stage
ICC Arbitration
within 56 days after Notice of Dissatisfaction
Clause 20.5
Clause 20.6
Clauses 20.2 and 20.4
(See previous diagram for
full Clause 20.4 procedure)
Agreement/Determination given
effect unless revised
under Clause 20
FIDIC 2017 and its Dispute Resolution Provisions
Event for Claim
28 day Notice of Claim to
Engineer
(No) the claiming Party shall
not be entitled to any claim
Engineer shall give a Notice
to the claiming Party, within
14 days after receiving the
Notice of Claim
(No) valid Notice
(yes) the other Party
disagrees &review by
the Engineer
Fully Detailed claim
84 days after the event
giving rise to the Claim
the Engineer shall, within
14 days after this time limit
has expired, give a Notice to
the claiming Party
accordingly.
FIDIC 2017 and its Dispute Resolution
Provisions
FIDIC 2017 and its Dispute Resolution Provisions
Typical Sequence of Dispute Events Envisaged in clause 21
Time management in fidic red book 2017(prmg080 project)

More Related Content

PDF
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
PDF
FIDIC variation, claim & dispute - CYLFEx workshop
PPTX
FIDIC-Relevant to Time Management
PDF
Claims 20.1 (Flow chart)
PPTX
Ppt on fidic claims
PDF
Fidic contracts management introduction
PPTX
fidic-flow-chart.pptx
PDF
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC-Relevant to Time Management
Claims 20.1 (Flow chart)
Ppt on fidic claims
Fidic contracts management introduction
fidic-flow-chart.pptx
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5

What's hot (20)

PDF
Training fidic moustafa ismail 2017 _ lec 4
PPT
Fidic flow charts final
PDF
Fidic comparison red yellow - silver book
PDF
Extension of Time (EoT) in Construction Project presentation
PPT
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
PPTX
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
PPTX
Fidic Form of Contract.
PDF
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
PPTX
Fidic conditions of contract presentation
PPT
Fidic law1
PPTX
Cl presentation
PPTX
Lecture 4 - selection of contract forms
PPTX
Construction Claims Explained
PDF
Contract payment and variation
PDF
Claims
PPS
Claims & disputes management
PDF
Delay Analysis and Concurrent Delay
PPSX
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
PPTX
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Training fidic moustafa ismail 2017 _ lec 4
Fidic flow charts final
Fidic comparison red yellow - silver book
Extension of Time (EoT) in Construction Project presentation
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
Fidic Form of Contract.
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Fidic conditions of contract presentation
Fidic law1
Cl presentation
Lecture 4 - selection of contract forms
Construction Claims Explained
Contract payment and variation
Claims
Claims & disputes management
Delay Analysis and Concurrent Delay
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Ad

Similar to Time management in fidic red book 2017(prmg080 project) (20)

PPTX
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
PPTX
A Claim submitted by the contractor during for slides.pptx
PPTX
Suspension and Termination by Contractor Presentation.pptx
PDF
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
PPTX
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
PDF
2 claims under new fidic
PPTX
Tendering clauses of contract
PDF
705150697-FIDIC-Red-vs-Yellow-Book-Index-Comparison.pdf
PPT
Claims in Contract - For FIDIC 1999 .ppt
PDF
Dealing With One Sided Public Contracts- Surviving The Death Star
PPT
Suspensions and Delays in Construction Contract
PPTX
Professional practice 2
DOCX
Cl report final
DOCX
If the Contractor fails to carry out any obligation under the Contract the Em...
PPTX
Professional Practice II - Presentation - Construction Delays & EOT
PPTX
How To Protect Your Construction Business and Legal Interests
PDF
Ss 06 training fidic moustafa ismail 2018 _ lec 6
DOCX
Cl compilation
PDF
Clause 16 suspension
PDF
Sectional completion and partial possession by employer PP2 Coursework 1
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
A Claim submitted by the contractor during for slides.pptx
Suspension and Termination by Contractor Presentation.pptx
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
2 claims under new fidic
Tendering clauses of contract
705150697-FIDIC-Red-vs-Yellow-Book-Index-Comparison.pdf
Claims in Contract - For FIDIC 1999 .ppt
Dealing With One Sided Public Contracts- Surviving The Death Star
Suspensions and Delays in Construction Contract
Professional practice 2
Cl report final
If the Contractor fails to carry out any obligation under the Contract the Em...
Professional Practice II - Presentation - Construction Delays & EOT
How To Protect Your Construction Business and Legal Interests
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Cl compilation
Clause 16 suspension
Sectional completion and partial possession by employer PP2 Coursework 1
Ad

More from mohamed Ismail (20)

PDF
ASCE7-10, SEISMIC ANALYSIS AND DESIGN HANDOUTS
PDF
Anchor Bolt My handouts ACI-318M, CHAPTER-17
PDF
Design_for_RC_short_Column_تصميم_الأعمدة_الخرسانية_القصيرة_Lec_1.pdf
PDF
1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf
PDF
Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...
PDF
Creep Load of concrete_ECP-201_ Ch.4 _Lecture 9.pdf
PDF
Creep of Concrete زحف الخرسانة ECP-201_ Ch.4 _Lecture 8.pdf
PDF
ECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdf
PDF
ECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdf
PDF
ECP-201_ Ch.4 Temprature Load_Lecture 4.pdf
PDF
ECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdf
PDF
ECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdf
PDF
ECP-201_ Ch.4 Live Load_Lecture 1.pdf
PDF
Dead Load -Examples_ شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdf
PDF
ECP-201_ Ch.3 Dead Load_Lecture 1.pdf
PDF
Reliability and LRFD Specification شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...
PDF
Resistance and resistance factor in LRFD شرح الكود المصرى للأحمال ECP-201_ C...
PDF
LRFD Load combination ECP-201_ Ch.2 _Lecture 3.pdf
PDF
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdf
PDF
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdf
ASCE7-10, SEISMIC ANALYSIS AND DESIGN HANDOUTS
Anchor Bolt My handouts ACI-318M, CHAPTER-17
Design_for_RC_short_Column_تصميم_الأعمدة_الخرسانية_القصيرة_Lec_1.pdf
1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf
Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...
Creep Load of concrete_ECP-201_ Ch.4 _Lecture 9.pdf
Creep of Concrete زحف الخرسانة ECP-201_ Ch.4 _Lecture 8.pdf
ECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdf
ECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdf
ECP-201_ Ch.4 Temprature Load_Lecture 4.pdf
ECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdf
ECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdf
ECP-201_ Ch.4 Live Load_Lecture 1.pdf
Dead Load -Examples_ شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdf
ECP-201_ Ch.3 Dead Load_Lecture 1.pdf
Reliability and LRFD Specification شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...
Resistance and resistance factor in LRFD شرح الكود المصرى للأحمال ECP-201_ C...
LRFD Load combination ECP-201_ Ch.2 _Lecture 3.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdf

Recently uploaded (20)

PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PDF
Digital Logic Computer Design lecture notes
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
Lecture Notes Electrical Wiring System Components
DOCX
573137875-Attendance-Management-System-original
PPTX
Welding lecture in detail for understanding
PPTX
bas. eng. economics group 4 presentation 1.pptx
PDF
Well-logging-methods_new................
PPTX
Construction Project Organization Group 2.pptx
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
Structs to JSON How Go Powers REST APIs.pdf
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Digital Logic Computer Design lecture notes
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Lecture Notes Electrical Wiring System Components
573137875-Attendance-Management-System-original
Welding lecture in detail for understanding
bas. eng. economics group 4 presentation 1.pptx
Well-logging-methods_new................
Construction Project Organization Group 2.pptx
CYBER-CRIMES AND SECURITY A guide to understanding
Structs to JSON How Go Powers REST APIs.pdf
Internet of Things (IOT) - A guide to understanding
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Foundation to blockchain - A guide to Blockchain Tech
Embodied AI: Ushering in the Next Era of Intelligent Systems

Time management in fidic red book 2017(prmg080 project)

  • 1. Time Management In Fidic Red Book 2017 Project (PRMG-080) MOHAMED ISMAIL KOTB AUC ID : 700201232 SUBMITTED TO Dr. Bahaa el shael
  • 2. Contents Fidic Red Book 2017 Project Parties Agreement or Determination Time for Completion Commencement, Delays and Suspension Sequence of payment FIDIC and its Dispute Resolution Provisions Typical Sequence of Dispute
  • 3. Fidic Red Book 2017 • Design and Engineering (incl. BoQs) is done by Employer or Employer’s Representative. • Tenderers fill in their unit prices into the existing BoQs. • Final amount is not fixed, payments are done based on the real amounts executed. (Exceptions are available eg: lump-sum conracts). • Employer carries the risk for contract amount increases. • The better the design, the flawless the project implementation. • Tender evaluations are relatively simpler.
  • 4. Project Parties Project Parties Engineer • the person named in the Contract Data appointed by the Employer to act as the Engineer for the purposes of the Contract Employer • he person named as the employer in the Contract Data and the legal successors in title to this person Contractor • the person(s) named as contractor in the Letter of Tender accepted by the Employer and the legal successors in title of such person(s).
  • 5. Typical Sequence of Events in Agreement or Determination under Sub-Clause 3.7 Scenario(1) Agreement is reached within 42 days, error found in the Engineer’s Notice of agreement and corrected
  • 6. Typical Sequence of Events in Agreement or Determination under Sub-Clause 3.7 Scenario(2) The Parties’ early advice that agreement cannot be reached and so Engineer’s determination is necessary, no error in Engineer’s determination.
  • 7. Typical Sequence of Events in Agreement or Determination under Sub-Clause 3.7 Scenario(3) No agreement within 42 days, Engineer determines within 42 days, error found in the Engineer’s determination and corrected.
  • 8. The Time for Completion Sequence During Contracts for Construction
  • 9. Commencement, Delays and Suspension(sec-8) • 8.1 Commencement of Works • Before the Commencement Date not less than 14 days • Or • The Commencement Date shall be within 42 days after the Contractor receives the Letter of Acceptance. Engineer(Notice the contractor to commence the work) Commence the work Contractor
  • 10. Time for Completion Time for completion Contractor Whole works complete with in time Taking over of the works & section clause 10.1
  • 11. 8.3Programme Contractor • submit an initial programme for the execution of the Works to the Engineer within 28 days after receiving the Notice Commencement of Works. • submit a revised programme for the actual progress of the Works. Engineer • Review the initial programme and gives the notice within 21 days after receiving the initial programme • Review each revised programme and gives the notice within 14 days after receiving a revised programme The Contractor shall submit a revised programme within 14 days after receiving this Noticeto the Engineer Notice of No-objection • The Contractor shall proceed in accordance with the Programme Engineer give the Notice Yes No
  • 12. Initial programme initial programme Commencement Date and the Time for Completion the date right of access to and possession of the Site Execution strategy the order of execution works timing of each stage of Design (if any) Procurement Submission of documents construction, erection, installation nominated Subcontractor works Testing & inspection Schedule & WBS all activities Logically linked the earliest, latest start, finish dates and the float the critical path Milestones
  • 13. Revised programme Revised programme Progress actual progress to date Delays any delay to such progress effects of delay Prosals to overcome the effects of any delay Supporting report Execution works Execution Method Required recourses Personnel Equipment significant change(s)
  • 14. 8.4 Advance Warning • The Engineer may request the Contractor to submit a proposal under Sub-Clause 13.3.2 [Variation by Request for Proposal] to avoid or minimize the effects of such event(s) or circumstance(s).
  • 15. 8.5 Extension of Time for Completion • The Contractor shall be entitled subject to Sub-Clause 20.2 [Claims • For Payment and/or EOT] to Extension of Time if and to the extent that • completion for the purposes of Sub-Clause 10.1 [Taking Over the Works and • Sections] is or will be delayed by any of the following causes: Measure works which increases the quantity more than 10%causes a delay to completion Contractor • Review measured quantities • Increase, but not decrease the total EOT Engineer
  • 16. 8.5 Extension of Time for Completion (EOT) EOT Causes Variation Unforeseen climatic conditions Unavailabilit y of labor, material,or equipment Delays caused by the employer Assessed in accordance rules and procedures stated in the Special Provisions as appropriate taking due regard of all relevant circumstances). Concurrent Delay
  • 17. 8.6 Delays Caused by Authorities DelaysCaused byAuthorities Contractor has diligently followed the procedures laid down by the relevant legally constituted public authorities authorities or entities delay or disrupt the Contractor’s work delay or disruption was Unforeseeable, Contractor consider Clause 8.4 (EOT for completion)
  • 18. 8.7 Rate of Progress 1- slow progress to complete the Works 2- progress has fallen (or will fall) behind the Programme 3- the initial programme has not yet become the Programme 1-instruct the Contractor to submit the revised methods to expedite progress and complete the Works 2-gives a Notice to the Contractor stating otherwise, the Contractor shall adopt these revised methods 1-if these revised methods cause the Employer to incur additional costs, the Employer shall be entitled subject to Sub-Clause 20.2 [Claims For Payment and/or EOT] to payment of these costs by the Contractor, in addition to Delay Damages (if any). 2-termination under Sub-Clause 15.2 [Termination for Contractor’s Default] before completion of the Works. These Delay Damages Contractor Engineer Employer
  • 19. 8.8 Delay Damages Delay Damages Contractor Fails to comply with Sub-Clause 8.2 [Time for Completion] Fraud, gross negligence, deliberate default or reckless misconduct by the Contractor. Employer [Claims ForPayment and/or EOT] to payment of Delay Damages by the Contractor Delay Damages shall be the amount stated in the Contract Data paid for every day between the relevant Time and relevant Date of Completion of the Works
  • 20. 8.9 Employer’s Suspension • protect, store and secure such part or all of the Works against any deterioration, loss or damage Contractor • instruct to suspend progress of part or all of the Works • state the date and cause of the suspension Engineer
  • 21. 8.10 Consequences of Employer’s Suspension Contractor entitled to EOT, or to payment of the Cost incurred • If the Contractor suffers delay and/or incurs Cost from complying with an Engineer’s instruction under Sub-Clause 8.9 [Employer’s Suspension] and/or from resuming the work under Sub-Clause 8.13 [Resumption of Work] Contractor not entitled to EOT, or to payment of the Cost incurred, in making good: • (a) the consequences of the Contractor’s faulty or defective • (b) any deterioration, loss or damage caused by the Contractor
  • 22. 8.11 Payment for Plant and Materials after Employer’s Suspension Materials which have not been delivered to Site, if: the work on Plant, or delivery of Plant and/or Materials, has been suspended for more than 28 days and the Plant and/or Materials were scheduled, and ready for delivery to the Site during the suspension period reasonable evidence that the Plant and/or Materials comply with the Contract the Contractor has marked the Plant and/or Materials as the Employer’s property in accordance with the Engineer’s instructions. The Contractor shall be entitled to payment of the value Plant and/or Materials which have not been delivered to Site if
  • 23. 8.12 Prolonged Suspension Suspension has continued for more than 84 days The Contractor may give a Notice to the Engineer requesting permission to proceed If the Engineer does not give a Notice within 28 days after receiving the Contractor’s Notice the Contractor may agree to a further suspension in which case the Parties may agree the EOT and/or Cost Plus Profit, and/or payment for suspended Plant and/or Materials, arising from the total period of suspension if the Parties not agree after giving a (second) Notice to the Engineer, treat the suspension as an omission of the affected part of the Works with immediate effect including release from any further obligation to protect, store and secure If the suspension affects the whole of the Works, the Contractor may give a Notice of termination
  • 24. 8.13 Resumption of Work Engineer • Give Notice to the contractor to proceed the suspended work Contractor • resume work after receiving the Notice from the Engineer Engineer • record any deterioration, loss, damage or defect in the Works or Plant or Materials during the suspension Contractor • Make good all such deterioration, loss, damage or defect to comply with the Contract
  • 25. Typical Sequence of payment Events Envisaged in clause 14
  • 26. FIDIC 1999 and its Dispute Resolution Provisions FIDIC Procedure for Employer/Contractor’s Claims 28 day Notice of Claim to Engineer 42 day “Fully Detailed Claim” to Engineer “Final Claim” 28 days after end of effects 42 days after receipt of claim Engineer’s Response Clause 3.5 Engineer to“Agree or Determine” Clause 20.1 Contractor’s Claims Clause 3.5 Determinations Agreement/Determination given effect unless revised under Clause 20
  • 27. FIDIC 1999 and its Dispute Resolution Provisions(cont.) Reference to Dispute Adjudication Board (DAB) (1 or 3 people) DAB Decision within 84 days of reference “Amicable Settlement” stage ICC Arbitration within 56 days after Notice of Dissatisfaction Clause 20.2 Clause 20.4 Clause 20.5 Clause 20.6 No Notice of Dissatisfaction within 28 days of Decision Notice of Dissatisfaction within 28 days after 84 days of reference No DAB Decision within 84 days of reference Notice of Dissatisfaction within 28 days of Decision DAB Decision final and binding
  • 28. FIDIC 1999 and its Dispute Resolution Provisions(cont.) Employer or Engineer gives notice and particulars to Contractor Clause 3.5 Engineer to “Agree or Determine” Clause 2.5 Employer’s Claims Clause 3.5 Determinations Reference to Dispute Adjudication Board (DAB) (1 or 3 people) “Amicable Settlement” stage ICC Arbitration within 56 days after Notice of Dissatisfaction Clause 20.5 Clause 20.6 Clauses 20.2 and 20.4 (See previous diagram for full Clause 20.4 procedure) Agreement/Determination given effect unless revised under Clause 20
  • 29. FIDIC 2017 and its Dispute Resolution Provisions Event for Claim 28 day Notice of Claim to Engineer (No) the claiming Party shall not be entitled to any claim Engineer shall give a Notice to the claiming Party, within 14 days after receiving the Notice of Claim (No) valid Notice (yes) the other Party disagrees &review by the Engineer Fully Detailed claim 84 days after the event giving rise to the Claim the Engineer shall, within 14 days after this time limit has expired, give a Notice to the claiming Party accordingly.
  • 30. FIDIC 2017 and its Dispute Resolution Provisions
  • 31. FIDIC 2017 and its Dispute Resolution Provisions
  • 32. Typical Sequence of Dispute Events Envisaged in clause 21