An Overview of the FIDIC
FORMS OF CONTRACT
and Contracts Committee
Activities
© www.asia-masters.com
Objectives
• Educational and informative
• Identify and prioritise industry issues
• Assess barriers, opportunities and risks
• Identify potential actions (by FIDIC/CC)
• Identify milestones, success factors and
how to assess or measure progress
2
© www.asia-masters.com
3
Consultancy Agreements
• Client/Consultant Model Services
Agreement, Fourth Edition 2006
• Sub-Consultancy Agreement, First
Edition 1992
• Joint Venture Agreement, First Edition
1992
• Model Representative Agreement, Test
Edition 2004
© www.asia-masters.com
4
The Traditional FIDIC Forms
of Contract
• Conditions of Contract for Works of Civil
Engineering Construction (Red Book)
Fourth Edition 1987
• Conditions of Contract for Electrical and
Mechanical Works including Erection on
Site (Yellow Book) Third Edition 1987
© www.asia-masters.com
5
Basics
• Between Employer and Contractor
• Red Book: payment monthly for work done
• Yellow Book: lump sum on milestones
• Every project is unique
• Guidelines of ’best practice’
• Part I – General Conditions
• Part II – Conditions of Particular Application
© www.asia-masters.com
6
Fair and balanced approach
• Risk is allocated to the party that is best able
to bear and control that risk
• Compensation and time extension allowed
when uncalculated hindrances occur
• ‘Engineer’ whose job is principally to
supervise and monitor the work
– in strict accordance with the Contract to the
satisfaction of the Engineer
– with formal ‘Engineer’s Decision’
© www.asia-masters.com
7
The Orange Book
• Conditions of Contract for Design-Build and
Turnkey (Orange Book) First Edition 1995
• Employer’s Representative
– not required to be impartial
– determine matters fairly, reasonably and in
accordance with the Contract
• Independent dispute adjudication board
• 1996/7 Supplements for use of DAB (R/Y
Books)
© www.asia-masters.com
8
The 1999 Suite of Standard
Conditions of Contract
• Conditions of Contract for Construction - design
by Employer: The Construction Contract (The
New Red Book)
• Conditions of Contract for Plant and Design-Build
- design by Contractor: The Plant and
Design/Build Contract (The New Yellow Book)
• Conditions of Contract for EPC Turnkey Projects:
The EPC/Turnkey Contract (The Silver Book)
• Short Form of Contract: The Short Form (The
Green Book)
• The FIDIC Contracts Guide (2000)
9
Principles behind the
1999 Books
• More consistent wording, with improved
clarity; user-friendly format and layout
• Balance between legal precision and
practicability; compatible with both
common and civil law concepts
• ‘Manuals of good engineering practice’
• Prepared by engineers for practical use
© www.asia-masters.com
10
Principles (continued)
• Traditional role of ‘the Engineer’ to
make impartial determinations modified
to reflect current practice (Red and
Yellow Books)
• ‘Employer’s Representative’ introduced:
must be fair and reasonable (Silver and
Green Books)
11
Principles (continued)
• Distinction between the Books is based
on:
–who does the design?
–who bears the risk for change in
quantities?
• EPC (Silver Book) provides for the
Contractor taking almost all risks (new
for FIDIC)
• Short Form (Green Book) deals with the
wide demand for a simpler form of
contract © www.asia-masters.com
12
Principles (continued)
• Work must continue, regardless of
differences: amicable settlement
encouraged
• Strong financial management: detailed
claims procedures must be followed
© www.asia-masters.com
13
General Remarks on
the 1999 Books
• Suitable for both ‘international’ and
domestic use
• A framework adaptable to suit local law
• More definitions: harmonised, except
for the Short Form
© www.asia-masters.com
14
General Remarks (continued)
• General Conditions not applicable can
be disregarded
• Example Particular Conditions are given
• Adjudication precedes arbitration
© www.asia-masters.com
15
The 1999 Red and Yellow Books
• Emphasis changed to party responsible for
design
• 1999 Yellow Book replaced both 1987 Yellow
Book and Orange Book
• Traditional competitive tendering procedures
• Risk sharing is balanced
• All claims, from either Party, have to follow a
strict procedure
• Engineer is no longer stated to be ‘impartial’:
he ‘shall be deemed to act for the Employer’,
except when fair determinations are required
16
The 1999 Red Book
• For building and engineering works
designed by the Employer
• Needs of modern multi-discipline
contracts recognised
• Partial Contractor design possible
• Valuation and payment based on
remeasurement of quantities, but lump
sum or cost plus could be used
© www.asia-masters.com
17
1999 Red Book (continued)
• No ‘Clause 67’ Engineer’s decision
• If a dispute arises, reference to DAB
• Dispute resolution procedure is:
adjudication (DAB)>>>amicable
settlement >>>arbitration
© www.asia-masters.com
18
The 1999 Yellow Book
• For E&M plant, and for building and
engineering works, designed by the
Contractor
• Needs of modern multi-discipline
contracts recognised
• Partial Employer design: include in
Employer’s Requirements
© www.asia-masters.com
19
1999 Yellow Book (continued)
• Valuation and payment based on lump
sum with payment plan, but
remeasurement possible
• No ‘Clause 67’ Engineer’s decision
• If a dispute arises, reference to DAB
• Dispute resolution procedure is:
adjudication (DAB)>>>amicable
settlement >>>arbitration
© www.asia-masters.com
20
The Silver Book
(EPCT Contract)
• More certain final price and time required
- balance of risk being changed
- privately financed BOT type
• Contractor asked to cover extra risks
• Employer will have to pay more
• Completely new Book - ‘unbalanced’ risk
• BUT full open acceptance of risk picture
• Starting point for BOT type projects
© www.asia-masters.com
21
The Silver Book (continued)
• The EPCT Contract is suitable for:
particularly E&M and process plant
projects
all types of Employers
civil law jurisdictions
where government employer or private
developer wants a fixed price turnkey
basis and two-party approach
• There is an ‘Introductory Note’ of explanation
© www.asia-masters.com
22
Special Features of the
Silver Book
• Responsibility for design lies with Contractor
• Employer’s Requirements usually a
‘performance specification’ (functional basis)
• Contractor carries out all engineering,
procurement, construction, ready for
operation at the ‘turn of a key’
• No Engineer - instead the Employer
• Lump Sum Contract Price (but adjustments in
limited specified cases)
23
Special Features (continued)
• Testing procedures to demonstrate
achievement of specified end result
• Contractor carries majority of risks, so
Employer pays more
• Final price and time should be more certain
• Small number of tenderers with negotiation
• Contractor given freedom to use own
methods
• Has to prove reliability and performance
24
Special Features (continued)
• These Conditions are not suitable in the following
circumstances:
if time or information is insufficient before Contract
signature
if considerable work underground or difficult to
inspect
if Employer intends to supervise closely or control
or review
if an intermediary certifies interim payments
where part of the Works is designed by Employer
for public bidding without negotiations
• For such circumstances P&DB should be used
instead
© www.asia-masters.com
25
The Green Book
(Short Form of Contract)
• US$ 500,000 and six months’ duration
• Simple and repetitive works
• All provisions necessary in 15 clauses
• Language uncomplicated and simple
• Balanced risk sharing - no Engineer
• Design by either party - all types of
construction
• Payment on lump sum or any other basis
© www.asia-masters.com
26
Dredging and Reclamation
• Design by Employer or Contractor
• Valuation – all main methods available
• Engineer required to act “fairly” in
accordance with Contract
• No defects liability on dredging
• Special insurance provisions
• Adjudication by DAB, then arbitration
© www.asia-masters.com
27
Red Book MDB Harmonised
Version
• Based on 1999 Red Book
• Incorporates main common changes
normally required by MDBs, e.g.-
audits, labour provisions, corruption
avoidance, dispute settlement
• Use subject to Licence Agreement
between FIDIC and participating banks
© www.asia-masters.com
28
Design, Build and Operate
Projects
• Conditions of Contract for Design, Build
and Operate Projects (Gold Book), First
Edition 2008
• Assumes ~20-year operation period
• Modern approach to risk and insurance
• Employer’s Representative
• Adjudication by DAB, then arbitration
© www.asia-masters.com
29
Subcontracts
• Conditions of Subcontract for
Construction, Test Edition 2009
• Intended for use with 1999 Red Book
• General Conditions – Particular
Conditions
• Annexes require provision of relevant
information
© www.asia-masters.com
30
Protection of the
Environment
• The Contractor shall take all reasonable
steps to protect the environment (both
on and off the Site) and to limit damage
and nuisance to people and property
resulting from pollution, noise and other
results of his operations
© www.asia-masters.com
31
Environment (continued)
• The Contractor shall ensure that
emissions, surface discharge and
effluent from the Contractor’s activities
shall not exceed the values indicated in
the Specification, and shall not exceed
the values prescribed by applicable
Laws
© www.asia-masters.com
32
Project Phases
• Initiation
• Study and Evaluation
• Design Development
• Detailed Design
• Contracts
• Construction, Manufacture, Shipping,
Installation, Testing and Commissioning
• Operations and Maintenance
© www.asia-masters.com
33
Initiation
• The Concept
• The Big Decisions
• Policy
• Major Choices
© www.asia-masters.com
34
Study and Evaluation
• Feasibility
• Alternatives
• Strategy
• Statutory Requirements
© www.asia-masters.com
35
Design Development/
Detailed Design
• Specifications
• Special Requirements
• Approvals
• Inclusion of results/outcomes from earlier
Project Phases
© www.asia-masters.com
Contracts Committee
• Mandate from Executive Committee
• Members: Christoph Theune/ Zoltán
Záhonyi/Philip Jenkinson
• Special Advisers: Nael Bunni/ Axel Jaeger/
Michael Mortimer-Hawkins/ Chris Seppala/
Chris Wade
• Task Group Leaders and Members
36
© www.asia-masters.com
Contracts Committee Terms of
Reference
• To recommend to the Executive Committee which Conditions of
Contract and related documents should be prepared or updated
by FIDIC
• To assist the Secretariat in establishing Task Groups as
required, to monitor their work at agreed intervals and to carry
out a final review of the documents for submission to the
Executive Committee
• To assist the Secretariat in handling queries on the
interpretation of documents
• To liaise, in conjunction with the Secretariat, with organisations
interested in the FIDIC Conditions of Contract
• To suggest topics and speakers as appropriate for seminars
and workshops
37
© www.asia-masters.com
Current Workload
• TG1 – DBO Form of Contract
• TG2 – Procurement Procedures Guide
• TG4 – Consultancy Agreements
• TG5 – Subcontract Form (Red Book)
• TG6 – Update of 1999 Suite (Yellow Book first)
• TG7 – Update of Dredging Contract (with IADC)
• TG8 – Update of Short Form (Green Book)
• TG9 – YB/SB Subcontract Forms
• TG10 – Tunnelling (proposed, with ITA)
• TG11 – ODB Form of Contract
• Training Courses
38
© www.asia-masters.com

More Related Content

PDF
Fidic contract
PDF
Fidic contracts management introduction
PPTX
FIDIC-Relevant to Time Management
PPTX
#FIDIC Understanding Basics# By SN Panigrahi
PPT
Effective Contract Management
PPTX
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
PPTX
Fidic Form of Contract.
PPTX
Fidic conditions of contract presentation
Fidic contract
Fidic contracts management introduction
FIDIC-Relevant to Time Management
#FIDIC Understanding Basics# By SN Panigrahi
Effective Contract Management
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
Fidic Form of Contract.
Fidic conditions of contract presentation

What's hot (20)

PDF
Training fidic moustafa ismail 2017 _ lec 4
PDF
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
PDF
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
PDF
Claims 20.1 (Flow chart)
PPTX
Tenders, their types and process
PPTX
Ppt on fidic claims
PPT
Fidic law1
PDF
FIDIC variation, claim & dispute - CYLFEx workshop
PPTX
Construction Claims Explained
PDF
Contract payment and variation
PDF
FIDIC Presentation-2016.pdf
PPTX
PPT
Construction contracts docuements_08092008
PPTX
Time management in fidic red book 2017(prmg080 project)
PDF
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
PPTX
A Case Study based on FIDIC and PAM Form 2006
PPS
Claims & disputes management
PDF
Introduction to construction contracts fundamentals
DOCX
Construction lawprint-final-update-21112017
Training fidic moustafa ismail 2017 _ lec 4
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Claims 20.1 (Flow chart)
Tenders, their types and process
Ppt on fidic claims
Fidic law1
FIDIC variation, claim & dispute - CYLFEx workshop
Construction Claims Explained
Contract payment and variation
FIDIC Presentation-2016.pdf
Construction contracts docuements_08092008
Time management in fidic red book 2017(prmg080 project)
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
A Case Study based on FIDIC and PAM Form 2006
Claims & disputes management
Introduction to construction contracts fundamentals
Construction lawprint-final-update-21112017
Ad

Viewers also liked (18)

PDF
Contracts classification
PPT
Fidic flow charts final
DOCX
Risk in FIDIC contracts
PPT
Essaf
PDF
Top10 planning fundamentals...
PDF
time bar clauses
PDF
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
PPS
الإملاء
PDF
Fidic conditions of subcontract agreement
PPSX
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
PPTX
Earned Value Management - Leading & Misleading in Project Control
PDF
EOT Related Cost Compensation Determination
PDF
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
PPTX
Earned Value Analysis - Basic Concepts
PDF
Methods of delay analysis
PPTX
Construction Delay Analysis, Simplified
PDF
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
PDF
A simple example of Earned Value Management (EVM) in action
Contracts classification
Fidic flow charts final
Risk in FIDIC contracts
Essaf
Top10 planning fundamentals...
time bar clauses
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
الإملاء
Fidic conditions of subcontract agreement
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
Earned Value Management - Leading & Misleading in Project Control
EOT Related Cost Compensation Determination
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Earned Value Analysis - Basic Concepts
Methods of delay analysis
Construction Delay Analysis, Simplified
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
A simple example of Earned Value Management (EVM) in action
Ad

Similar to An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activities (20)

PPT
FIDIC.RICS CPD Event Singapore 2012/.ppt
PPT
FIDIC.RICS CPD Event Singapore 2012.ppt
PPTX
Nec3 introduction
PPTX
400618115-180522-FIDIC-2017-Edition-Workshop-May-2018.pptx
PDF
Muckle LLP - Which contract should I be using?
PPTX
05 Contract Management.pptx . DEFINITION
PDF
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
PPTX
Introduction to the Engineering ad Construction Contract
PPT
Renovate Repair Legal Issues Owner View
PDF
Chapter 4 [compatibility mode]
PDF
Chapter 4 [compatibility mode]
PPTX
Building Contracts and CDM regulations
PPTX
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
PPT
Chapter 1- Procurement management
PDF
Contracting strategies for_terminal_construction
PDF
Contracting strategies for_terminal_construction
PDF
NEC4 overview: key changes and impacts - London, September 2017
PPTX
Construction Contracts: Basics of Contracts and Contract Administration
PDF
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
PDF
Infrastructure Projects and Construction contracts in ppp
FIDIC.RICS CPD Event Singapore 2012/.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
Nec3 introduction
400618115-180522-FIDIC-2017-Edition-Workshop-May-2018.pptx
Muckle LLP - Which contract should I be using?
05 Contract Management.pptx . DEFINITION
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Introduction to the Engineering ad Construction Contract
Renovate Repair Legal Issues Owner View
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
Building Contracts and CDM regulations
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
Chapter 1- Procurement management
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
NEC4 overview: key changes and impacts - London, September 2017
Construction Contracts: Basics of Contracts and Contract Administration
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Infrastructure Projects and Construction contracts in ppp

More from Asia Master Training آسيا ماسترز للتدريب والتطوير (20)

PPT
Human Resource Management : The Importance of Effective Strategy and Planning
PPT
Purpose of Contract CloseOuts - Overview Landscape
PPT
Public Meeting - Contract Close-Out - Ground Rules
PPT
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
PPTX
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
PPTX
Microsoft Word 2010 - Technical Skills Training
PPTX
Microsoft® Office Word 2007 Skills & Compentencies Training
PPTX
PPT
Competency Approach to Human Resource Management
PPT
Developing a University-Wide Integrated Employee Core Competency Framework
PPT
Competency-based Management for the DoD-wide Contracting Community
PPT
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
PPT
The Counseling Interview - Principles & Practices
PPT
Behavioral Interview - Selecting Quality Employees for a Quality Organization
PPT
Effective Hiring Practices - Recruiting the Best Person
PPT
Industrial & Organisational Psychology Selecting Employees
Human Resource Management : The Importance of Effective Strategy and Planning
Purpose of Contract CloseOuts - Overview Landscape
Public Meeting - Contract Close-Out - Ground Rules
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
Microsoft Word 2010 - Technical Skills Training
Microsoft® Office Word 2007 Skills & Compentencies Training
Competency Approach to Human Resource Management
Developing a University-Wide Integrated Employee Core Competency Framework
Competency-based Management for the DoD-wide Contracting Community
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
The Counseling Interview - Principles & Practices
Behavioral Interview - Selecting Quality Employees for a Quality Organization
Effective Hiring Practices - Recruiting the Best Person
Industrial & Organisational Psychology Selecting Employees

Recently uploaded (20)

PPTX
Lecture Notes on Family Law - Knowledge Area 5
PPT
Over view on IPR and its components :ppt
PDF
Analysis Childrens act Kenya for the year 2022
PPTX
Ethiopian Law of Contract short note.pptx
PDF
AHRP LB - Quick Look of the Newly-initiated Koperasi Merah Putih (KMP).pdf
PPTX
Income under income Tax Act..pptx Introduction
PPT
Criminal law and civil law under of collage corriculum
PDF
Constitution of India and fundamental rights pdf
PPT
Cyber-Crime-in- India at Present day and Laws
PPT
looking_into_the_crystal_ball - Merger Control .ppt
PDF
Trademark, Copyright, and Trade Secret Protection for Med Tech Startups.pdf
PDF
A SEP and FRAND Overview 13 Aug 2024.pdf
PPTX
2.....FORMULATION OF THE RESEARCH PROBLEM.pptx
PPTX
FFFFFFFFFFFFFFFFFFFFFFTA_012425_PPT.pptx
PDF
Notes to accompany the TMT and FRAND Overview Slides
PDF
The AI & LegalTech Surge Reshaping the Indian Legal Landscape
PDF
OpenAi v. Open AI Summary Judgment Order
PPTX
Ethiopian Civil procedure short note.pptx
PPTX
UDHR & OTHER INTERNATIONAL CONVENTIONS.pptx
PPT
Understanding the Impact of the Cyber Act
Lecture Notes on Family Law - Knowledge Area 5
Over view on IPR and its components :ppt
Analysis Childrens act Kenya for the year 2022
Ethiopian Law of Contract short note.pptx
AHRP LB - Quick Look of the Newly-initiated Koperasi Merah Putih (KMP).pdf
Income under income Tax Act..pptx Introduction
Criminal law and civil law under of collage corriculum
Constitution of India and fundamental rights pdf
Cyber-Crime-in- India at Present day and Laws
looking_into_the_crystal_ball - Merger Control .ppt
Trademark, Copyright, and Trade Secret Protection for Med Tech Startups.pdf
A SEP and FRAND Overview 13 Aug 2024.pdf
2.....FORMULATION OF THE RESEARCH PROBLEM.pptx
FFFFFFFFFFFFFFFFFFFFFFTA_012425_PPT.pptx
Notes to accompany the TMT and FRAND Overview Slides
The AI & LegalTech Surge Reshaping the Indian Legal Landscape
OpenAi v. Open AI Summary Judgment Order
Ethiopian Civil procedure short note.pptx
UDHR & OTHER INTERNATIONAL CONVENTIONS.pptx
Understanding the Impact of the Cyber Act

An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activities

  • 1. 1 RICS Singapore Branch CPD Event 19 June 2012 An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activities © www.asia-masters.com
  • 2. Objectives • Educational and informative • Identify and prioritise industry issues • Assess barriers, opportunities and risks • Identify potential actions (by FIDIC/CC) • Identify milestones, success factors and how to assess or measure progress 2 © www.asia-masters.com
  • 3. 3 Consultancy Agreements • Client/Consultant Model Services Agreement, Fourth Edition 2006 • Sub-Consultancy Agreement, First Edition 1992 • Joint Venture Agreement, First Edition 1992 • Model Representative Agreement, Test Edition 2004 © www.asia-masters.com
  • 4. 4 The Traditional FIDIC Forms of Contract • Conditions of Contract for Works of Civil Engineering Construction (Red Book) Fourth Edition 1987 • Conditions of Contract for Electrical and Mechanical Works including Erection on Site (Yellow Book) Third Edition 1987 © www.asia-masters.com
  • 5. 5 Basics • Between Employer and Contractor • Red Book: payment monthly for work done • Yellow Book: lump sum on milestones • Every project is unique • Guidelines of ’best practice’ • Part I – General Conditions • Part II – Conditions of Particular Application © www.asia-masters.com
  • 6. 6 Fair and balanced approach • Risk is allocated to the party that is best able to bear and control that risk • Compensation and time extension allowed when uncalculated hindrances occur • ‘Engineer’ whose job is principally to supervise and monitor the work – in strict accordance with the Contract to the satisfaction of the Engineer – with formal ‘Engineer’s Decision’ © www.asia-masters.com
  • 7. 7 The Orange Book • Conditions of Contract for Design-Build and Turnkey (Orange Book) First Edition 1995 • Employer’s Representative – not required to be impartial – determine matters fairly, reasonably and in accordance with the Contract • Independent dispute adjudication board • 1996/7 Supplements for use of DAB (R/Y Books) © www.asia-masters.com
  • 8. 8 The 1999 Suite of Standard Conditions of Contract • Conditions of Contract for Construction - design by Employer: The Construction Contract (The New Red Book) • Conditions of Contract for Plant and Design-Build - design by Contractor: The Plant and Design/Build Contract (The New Yellow Book) • Conditions of Contract for EPC Turnkey Projects: The EPC/Turnkey Contract (The Silver Book) • Short Form of Contract: The Short Form (The Green Book) • The FIDIC Contracts Guide (2000)
  • 9. 9 Principles behind the 1999 Books • More consistent wording, with improved clarity; user-friendly format and layout • Balance between legal precision and practicability; compatible with both common and civil law concepts • ‘Manuals of good engineering practice’ • Prepared by engineers for practical use © www.asia-masters.com
  • 10. 10 Principles (continued) • Traditional role of ‘the Engineer’ to make impartial determinations modified to reflect current practice (Red and Yellow Books) • ‘Employer’s Representative’ introduced: must be fair and reasonable (Silver and Green Books)
  • 11. 11 Principles (continued) • Distinction between the Books is based on: –who does the design? –who bears the risk for change in quantities? • EPC (Silver Book) provides for the Contractor taking almost all risks (new for FIDIC) • Short Form (Green Book) deals with the wide demand for a simpler form of contract © www.asia-masters.com
  • 12. 12 Principles (continued) • Work must continue, regardless of differences: amicable settlement encouraged • Strong financial management: detailed claims procedures must be followed © www.asia-masters.com
  • 13. 13 General Remarks on the 1999 Books • Suitable for both ‘international’ and domestic use • A framework adaptable to suit local law • More definitions: harmonised, except for the Short Form © www.asia-masters.com
  • 14. 14 General Remarks (continued) • General Conditions not applicable can be disregarded • Example Particular Conditions are given • Adjudication precedes arbitration © www.asia-masters.com
  • 15. 15 The 1999 Red and Yellow Books • Emphasis changed to party responsible for design • 1999 Yellow Book replaced both 1987 Yellow Book and Orange Book • Traditional competitive tendering procedures • Risk sharing is balanced • All claims, from either Party, have to follow a strict procedure • Engineer is no longer stated to be ‘impartial’: he ‘shall be deemed to act for the Employer’, except when fair determinations are required
  • 16. 16 The 1999 Red Book • For building and engineering works designed by the Employer • Needs of modern multi-discipline contracts recognised • Partial Contractor design possible • Valuation and payment based on remeasurement of quantities, but lump sum or cost plus could be used © www.asia-masters.com
  • 17. 17 1999 Red Book (continued) • No ‘Clause 67’ Engineer’s decision • If a dispute arises, reference to DAB • Dispute resolution procedure is: adjudication (DAB)>>>amicable settlement >>>arbitration © www.asia-masters.com
  • 18. 18 The 1999 Yellow Book • For E&M plant, and for building and engineering works, designed by the Contractor • Needs of modern multi-discipline contracts recognised • Partial Employer design: include in Employer’s Requirements © www.asia-masters.com
  • 19. 19 1999 Yellow Book (continued) • Valuation and payment based on lump sum with payment plan, but remeasurement possible • No ‘Clause 67’ Engineer’s decision • If a dispute arises, reference to DAB • Dispute resolution procedure is: adjudication (DAB)>>>amicable settlement >>>arbitration © www.asia-masters.com
  • 20. 20 The Silver Book (EPCT Contract) • More certain final price and time required - balance of risk being changed - privately financed BOT type • Contractor asked to cover extra risks • Employer will have to pay more • Completely new Book - ‘unbalanced’ risk • BUT full open acceptance of risk picture • Starting point for BOT type projects © www.asia-masters.com
  • 21. 21 The Silver Book (continued) • The EPCT Contract is suitable for: particularly E&M and process plant projects all types of Employers civil law jurisdictions where government employer or private developer wants a fixed price turnkey basis and two-party approach • There is an ‘Introductory Note’ of explanation © www.asia-masters.com
  • 22. 22 Special Features of the Silver Book • Responsibility for design lies with Contractor • Employer’s Requirements usually a ‘performance specification’ (functional basis) • Contractor carries out all engineering, procurement, construction, ready for operation at the ‘turn of a key’ • No Engineer - instead the Employer • Lump Sum Contract Price (but adjustments in limited specified cases)
  • 23. 23 Special Features (continued) • Testing procedures to demonstrate achievement of specified end result • Contractor carries majority of risks, so Employer pays more • Final price and time should be more certain • Small number of tenderers with negotiation • Contractor given freedom to use own methods • Has to prove reliability and performance
  • 24. 24 Special Features (continued) • These Conditions are not suitable in the following circumstances: if time or information is insufficient before Contract signature if considerable work underground or difficult to inspect if Employer intends to supervise closely or control or review if an intermediary certifies interim payments where part of the Works is designed by Employer for public bidding without negotiations • For such circumstances P&DB should be used instead © www.asia-masters.com
  • 25. 25 The Green Book (Short Form of Contract) • US$ 500,000 and six months’ duration • Simple and repetitive works • All provisions necessary in 15 clauses • Language uncomplicated and simple • Balanced risk sharing - no Engineer • Design by either party - all types of construction • Payment on lump sum or any other basis © www.asia-masters.com
  • 26. 26 Dredging and Reclamation • Design by Employer or Contractor • Valuation – all main methods available • Engineer required to act “fairly” in accordance with Contract • No defects liability on dredging • Special insurance provisions • Adjudication by DAB, then arbitration © www.asia-masters.com
  • 27. 27 Red Book MDB Harmonised Version • Based on 1999 Red Book • Incorporates main common changes normally required by MDBs, e.g.- audits, labour provisions, corruption avoidance, dispute settlement • Use subject to Licence Agreement between FIDIC and participating banks © www.asia-masters.com
  • 28. 28 Design, Build and Operate Projects • Conditions of Contract for Design, Build and Operate Projects (Gold Book), First Edition 2008 • Assumes ~20-year operation period • Modern approach to risk and insurance • Employer’s Representative • Adjudication by DAB, then arbitration © www.asia-masters.com
  • 29. 29 Subcontracts • Conditions of Subcontract for Construction, Test Edition 2009 • Intended for use with 1999 Red Book • General Conditions – Particular Conditions • Annexes require provision of relevant information © www.asia-masters.com
  • 30. 30 Protection of the Environment • The Contractor shall take all reasonable steps to protect the environment (both on and off the Site) and to limit damage and nuisance to people and property resulting from pollution, noise and other results of his operations © www.asia-masters.com
  • 31. 31 Environment (continued) • The Contractor shall ensure that emissions, surface discharge and effluent from the Contractor’s activities shall not exceed the values indicated in the Specification, and shall not exceed the values prescribed by applicable Laws © www.asia-masters.com
  • 32. 32 Project Phases • Initiation • Study and Evaluation • Design Development • Detailed Design • Contracts • Construction, Manufacture, Shipping, Installation, Testing and Commissioning • Operations and Maintenance © www.asia-masters.com
  • 33. 33 Initiation • The Concept • The Big Decisions • Policy • Major Choices © www.asia-masters.com
  • 34. 34 Study and Evaluation • Feasibility • Alternatives • Strategy • Statutory Requirements © www.asia-masters.com
  • 35. 35 Design Development/ Detailed Design • Specifications • Special Requirements • Approvals • Inclusion of results/outcomes from earlier Project Phases © www.asia-masters.com
  • 36. Contracts Committee • Mandate from Executive Committee • Members: Christoph Theune/ Zoltán Záhonyi/Philip Jenkinson • Special Advisers: Nael Bunni/ Axel Jaeger/ Michael Mortimer-Hawkins/ Chris Seppala/ Chris Wade • Task Group Leaders and Members 36 © www.asia-masters.com
  • 37. Contracts Committee Terms of Reference • To recommend to the Executive Committee which Conditions of Contract and related documents should be prepared or updated by FIDIC • To assist the Secretariat in establishing Task Groups as required, to monitor their work at agreed intervals and to carry out a final review of the documents for submission to the Executive Committee • To assist the Secretariat in handling queries on the interpretation of documents • To liaise, in conjunction with the Secretariat, with organisations interested in the FIDIC Conditions of Contract • To suggest topics and speakers as appropriate for seminars and workshops 37 © www.asia-masters.com
  • 38. Current Workload • TG1 – DBO Form of Contract • TG2 – Procurement Procedures Guide • TG4 – Consultancy Agreements • TG5 – Subcontract Form (Red Book) • TG6 – Update of 1999 Suite (Yellow Book first) • TG7 – Update of Dredging Contract (with IADC) • TG8 – Update of Short Form (Green Book) • TG9 – YB/SB Subcontract Forms • TG10 – Tunnelling (proposed, with ITA) • TG11 – ODB Form of Contract • Training Courses 38 © www.asia-masters.com