Methods of Delay Analysis 
Requirements and Developments
Katrin Enders
Hill International, London UK
Frankfurt, 29 September 2015
OVERVIEW
Overview – Definition Forensic Schedule Analysis
Approach – Delay Analysis Methodologies pro & cons
Findings    – Choosing a methodology, Fact is King, Guidance 
Conclusions
2
“‘Beware the dark arts’ was the sage advice of Albus
Dumbledore to the young Harry Potter. Besides budding wizards, 
construction clients (at the project or dispute resolution stages), 
contractors and lawyers would be equally well served by this 
advice when it comes to the difficult subject of delay 
analysis"...“delay analysis like Lord Voldamort, comes in many 
guises and it seems there is a spell for every circumstance. ‘What 
would you like conjured … err … proven, sir? Let me just mix up 
some ‘fragnets’, ‘lags’, eye of newt and … hey presto!’”
OVERVIEW – DEFINITION
3
(cited: BEWARE THE DARK ARTS! DELAY ANALYSIS AND THE PROBLEMS WITH RELIANCE ON TECHNOLOGY, David Barry, 2009 )
• FORENSIC SCHEDULE ANALYSIS
• “… refers to the study and investigation of events using CPM or other 
recognized schedule calculation methods for potential use in a legal 
proceeding.” 
• “… the study of how actual events interacted in the context of a 
complex model for the purpose of understanding the significance of a 
specific deviation or series of deviations from some baseline model and 
their role in determining the sequence of tasks within the complex 
network.”
(cited:  AACE® International Recommended Practice No. 29R‐03 FORENSIC SCHEDULE ANALYSIS TCM Framework)
OVERVIEW – DEFINITION
4
APPROACH
Overview – Definition Forensic Schedule Analysis and Nomenclature
Approach – Delay Analysis Methodologies pro & cons
Findings    – Choosing a methodology, Fact is King, Guidance  
Conclusions
5
APPROACH – DELAY ANALYSIS METHODOLOGIES
6
TWO
Types
FOUR
Categories*
TWO
Types
FOUR
Categories*
* See for example the Society of Construction Law “Protocol on Delay and Disruption”, or Association for the Advancement of Cost Engineering Recommended Practice No.29R-03
“Forensic Schedule Analysis”
• As‐planned versus As‐built
• As‐Built But For
LOOKING BACKLOOKING BACK
Retrospective Analyses
LOOKING FORWARDLOOKING FORWARD
Prospective Analyses 
• Time‐Impact Analysis
• Impacted As‐planned 
• is the most basic method of analysis
• is observational – no changes are made to the programme
• straightforward comparison between the planned  vs the actual 
performance of the work
• can only be carried out retrospectively (requires as‐built programme/or at 
least the overall as‐built completion date)
7
Strengths Weakness
• is very simple and therefore 
easy to understand
• can be performed with 
rudimentary base data (e.g. 
when detail and logic of the as‐
planned programme is unavailable,
and no detailed progress records 
other than the overall as‐built 
programme are available)
• Static critical path
• fails to fulfil the fundamental 
requirement to demonstrate the 
causal link between a delay event and 
its alleged effect
• does not deal adequately with 
concurrent delay 
APPROACH – AS‐PLANNED VS AS‐BUILT (APAB) 
Claim
Planned CP
TimescaleActivities
As‐built CP
Compare As‐Planned vs As‐Built
(delays)
Contractual 
Completion 
Date
Actual 
Completion 
Date
(delays and disruptions)
APPROACH – AS‐PLANNED VS AS‐BUILT (APAB) 
APPROACH – IMPACTED AS‐PLANNED (IAP)
9
• is a prospective methodology 
• delay effect is measured by imposing events on a model of the original 
programme (Baseline)
• does not rely on any actual progress that has been made
• requires a robust and reliable original programme that reflects the 
indented sequence and the Scope of Work
Strengths Weakness
• relatively simple to carry out and 
to understand
• No as‐built required (likely choice 
when planned programme is available, 
no significant changes in the sequence 
during the project execution, few 
delaying events, and when there is 
little or no progress records)
• cannot be used for complex projects
• used to quantify potential delays rather 
and actual 
• concurrent delays easily overlooked 
• assumes that the baseline was 
achievable 
• does not take actual progress/ resources 
into account
• not reliable in dispute resolution 
Event
Event
TimescaleActivities
Event
Claim
Event
Event
Event
10
APPROACH – IMPACTED AS‐PLANNED (IAP)
APPROACH – TIME IMPACT ANALYSIS (TIA)
11
• prospective and dynamic method – but can be applied retrospectively
• takes account of progress and timing of delay events on the Works
• requires reliable as‐built data to update the programme (hence, if detailed and 
regular progress data is not available then this method cannot be used)
• a reliable baseline programme is essential (ideally reflects the execution of the 
planned project using sound construction logic) 
• often undertaken in time slices (windows)
Strengths Weakness
• has a proven track‐record in 
forensic application
• preferred method of the SCL
Protocol
• based on a dynamic and changing 
critical path
• demonstrates cause and effect 
• time consuming (to determine the factual 
background and correct logic associated 
with progress records and delay events)
• requires considerable degree of 
expertise and technical knowledge
• hence, difficult to communicate, highly 
complex
Activity 1
Activity 2
Activity 3
Project 
Completion
Date of 
Event
TimescaleActivities
Progress behind 
on this activity. 
Delay to Project 
Completion
Delay to Project 
Completion (2)
Delay Event
• Delay (1) caused by poor progress
• Delay (2) caused by event
• Claim = difference between D (1) and D (2)
12
APPROACH – TIME IMPACT ANALYSIS (TIA)
APPROACH – AS‐BUILT BUT FOR (ABBF)
13
• retrospective method also known as Collapsed As‐built (CAB)
• relies on a detailed reconstruction of the as‐built programme
• normally restricted to after‐the‐event analyses in forensic work
• does have a limited prospective capability (can be used to demonstrate the effect 
of a delay on the completed part of an incomplete project)
• has been proven to be reliable in dispute resolution/ claims
• If done properly can demonstrates effect and cause/ takes account of 
concurrence
Strengths Weakness
• greatest strength for forensic work 
is that it is  fact based (based on as‐
build)
• not reliant upon an as‐planned 
programme 
• complicated method hence, difficult to 
execute and to explain
• difficult to establish a dynamic as‐built 
schedule (as complicated to determine and 
model logic)
• requires detailed as‐build/ progress
records
• Identify Planned Period & As‐built
Planned  
period
Planned 
Completion
As‐built
Actual 
Completion
14
APPROACH – AS‐BUILT BUT FOR (ABBF)
• Identify Delays
Planned
period
As‐built
Planned 
Completion
Actual 
Completion
15
APPROACH – AS‐BUILT BUT FOR (ABBF)
• ‘Zero’ delays
Actual 
CompletionPlanned
period
Planned 
Completion
Actual Completion ‘but for’ 
delays
As‐built
16
APPROACH – AS‐BUILT BUT FOR (ABBF)
• Quantify Claim
Contract
period
As‐built
Contract 
Completion
Culpable or non‐
claimable delays
Claim 
period
Actual Completion 
‘but for’ delays
Actual 
Completion
Extended 
Completion
17
APPROACH – AS‐BUILT BUT FOR (ABBF)
AACEI RP 29R-03: Forensic Schedule Analysis
Table 1 – Nomenclature Correspondence
ADVANTGES & DISADVANTAGES
NOT PREFERENCE … OR PREJUDICE!
APPROACH – NOMENCLATURE
18
FINDINGS
Overview – Definition Forensic Schedule Analysis and Nomenclature
Approach – Delay Analysis Methodologies pro & cons
Findings   – Choosing a methodology, Fact is King, Guidance   
Conclusions
19
Which Method is appropriate, correct, sustainable?
• Legal/Contractual
• What does the jurisdiction/ contract require? (e.g. Concurrency? Likely or Actual delay 
to completion? Delay Analysis Method Specified?)
• What information is available?
• Planned, progress, as‐built (Does a lack of information preclude the use of any of the 
methods?)
• Time and Money
• Do time/cost constraints eliminate certain options? ((During project/After Project, 
Record keeping; Staff available (Engineering/Management),Decision making, Budget)
• Other issues: 
• Proportionality, Type of project, Which party, at what stage is the dispute?
FINDINGS – CHOOSING A METHODOLOGY
20
 Key Facts:
 At least after an event delay becomes a fact and the Other Party/ the Courts are 
interested in what actually happened rather than in what could have happened.
 For an event to affect the completion date it must fall on the critical path of the 
project.
 must consider all relevant facts and evidence regardless of a positive or negative
impact in relation to the issues in question
 Delay Analysis should be based on a calculated approach it can not be impressionistic
 Effect and Cause not Cause and Effect
 Are there facts/ evidence available and accessible to verify the cause?
FINDINGS – FACT IS KING
21
Recommend Guidance:
 AACEI Recommended Practice (http://www.aacei.org/resources/ppg/)
 SCL Protocol (http://www.scl.org.uk/resources)
FINDINGS  – GUIDANCE
22
CONCLUSIONS
Overview – Definition Forensic Schedule Analysis and Nomenclature
Approach – Delay Analysis Methodologies pro & cons
Findings    – Choosing a methodology, Fact is King, Guidance 
Conclusions
23
CONCLUSIONS
24
 Conclusions:
 Delay Analysis comes in many guises all with their 
advantages and disadvantages
 To chose the most suitable method depends on the 
surrounding factors
 Facts and common sense are KING
QUESTIONS
Katrin Enders
Associate Director
Hill International (UK) Ltd
11 Pilgrim Street,
London EC4V 6RN
Office: +44 (0)207 618 1200/ 1262
Mobile: +44 (0)7850722796
www.hillintl.com
25
QUESTIONS PLEASE ?
 4900 Employees worldwide
 100 Offices in 40 countries
 Construction Claims & Consulting Group
 Project Management Group
 NYSE Global Market
 Founded in 1976
 Employers/Contractors
Hill International (D) GmbH
Prinzregentenstraße 20‐22
80538 München
Munich@hillintl.com
Düsseldorf, Germany
Graf‐ Adolf‐ Platz 15
40213 Düsseldorf
Duesseldorf@hillintl.com
Hamburg, Germany
Am Kaiserkai 1
20457 Hamburg
Hill International UK
London, Hill International UK, Ltd.
11 Pilgrim St
London, 
EC4V 6RN
UK
Tel: +44 (0)20 7618 1200
(9 UK Locations)
SERVICES
SERVICES
• Compliance
• Tools and Templates
• Guidelines
• Procedures & Work Flows
• Structures
• In House Seminars
• Open Seminars
• Industry Events
• Coaching / Mentoring
• Workshops
• Delay & Disruption 
Analysis 
• Expert Advisory Services
• Expert Witness Services
• Claims Preparation
• Claims Analysis
• Contract Analysis / 
Drafting
• Time Risk Management
• Procurement Strategy
• Contract Advisory
• Staff Augmentation
• Contract Workshops
• Project Audits
Dispute 
Avoidance
Dispute 
Resolution
Claims 
Consulting
Seminars / 
Coaching / 
Mentoring

More Related Content

PPTX
VERTEX Construction Delays and Forensic Schedule Analyses
PDF
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
PPTX
Quantify Construction Damages related to Delay, disruption, and inefficiencies
PDF
Time Impact Analysis
PPTX
Extension of time Analysis
PDF
Methods of delay analysis
PPTX
Construction Delay Analysis, Simplified
PPTX
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
VERTEX Construction Delays and Forensic Schedule Analyses
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Time Impact Analysis
Extension of time Analysis
Methods of delay analysis
Construction Delay Analysis, Simplified
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...

What's hot (20)

PDF
Essentials of EOT Claims
PDF
Delay Analysis and Concurrent Delay
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
PDF
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
PDF
Favorite Delay Analysis Methodologies Town Hall SEI
PDF
Claims
PDF
Training fidic moustafa ismail 2017 _ lec 4
PDF
Standard Forms of Construction Contracts
PPTX
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
PPT
Fidic flow charts final
PPTX
Extension of time in construction contracts
PPTX
Construction Contracts: Basics of Contracts and Contract Administration
PDF
Delay analysis ... wise after the event.
PDF
Contract payment and variation
PDF
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
PPTX
Earned Value Management - Leading & Misleading in Project Control
PDF
NEC4 overview: key changes and impacts - London, September 2017
PPTX
Forensic schedule analysis acesss
PDF
EOT Related Cost Compensation Determination
PPT
3. construction planning. construction project management
Essentials of EOT Claims
Delay Analysis and Concurrent Delay
Extension of time (E.O.T) By Ahmed Ibarhim
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Favorite Delay Analysis Methodologies Town Hall SEI
Claims
Training fidic moustafa ismail 2017 _ lec 4
Standard Forms of Construction Contracts
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Fidic flow charts final
Extension of time in construction contracts
Construction Contracts: Basics of Contracts and Contract Administration
Delay analysis ... wise after the event.
Contract payment and variation
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
Earned Value Management - Leading & Misleading in Project Control
NEC4 overview: key changes and impacts - London, September 2017
Forensic schedule analysis acesss
EOT Related Cost Compensation Determination
3. construction planning. construction project management
Ad

Recently uploaded (20)

DOCX
573137875-Attendance-Management-System-original
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPT
Project quality management in manufacturing
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
composite construction of structures.pdf
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPTX
Sustainable Sites - Green Building Construction
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
bas. eng. economics group 4 presentation 1.pptx
PDF
PPT on Performance Review to get promotions
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
Geodesy 1.pptx...............................................
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
573137875-Attendance-Management-System-original
Mechanical Engineering MATERIALS Selection
Foundation to blockchain - A guide to Blockchain Tech
Project quality management in manufacturing
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
UNIT-1 - COAL BASED THERMAL POWER PLANTS
composite construction of structures.pdf
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Sustainable Sites - Green Building Construction
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
bas. eng. economics group 4 presentation 1.pptx
PPT on Performance Review to get promotions
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Geodesy 1.pptx...............................................
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
Strings in CPP - Strings in C++ are sequences of characters used to store and...
Ad

Methods of delay analysis