SlideShare a Scribd company logo
4
Most read
5
Most read
10
Most read
CONTRACT
ADMINISTRATION
BY- ARVIND SOLANKI
CONTRACT A contract is a legally binding or valid agreement
between two parties.What is Contract?
CONTRACT
1. offer and acceptance;
2. an intention between the parties to create
binding relations;
3. consideration to be paid for the promise made;
4. legal capacity of the parties to act;
5. genuine consent of the parties; and
6. legality of the agreement.
An agreement that lacks one or more of the
elements listed above is not a valid contract.
Elements of contract
CONSTRUCTION /
BUILDING CONTRACT
A Contract between an Owner (Client) and a
Building Contractor, setting forth the terms under
which construction is to be carried out, the basis of
remuneration, the time scale, and the penalties, if
any, (for failure to comply with terms of the
Contract) is termed as a Building/Construction
Contract.
What is Construction / Building
contract
CONSTRUCTION /
BUILDING
CONTRACT
1. The Contract or Agreement letter.
2. General Conditions of the Contract – these define the legal rights and
obligations of the parties; another way of describing the general conditions is as
the rules by which each party will operate in performing their obligations as set
down under the Contract.
3. Special conditions of Contract – these are an extension to the general
conditions and apply specifically and individually to each project/Contract.
4. Bill of quantities – it lists quantities of the various items and the material to be
included in the Contract. It can also be used as the basis for valuation of
variations and assists the preparation of progress claims. The extent to which the
Owner warrants the completeness of a bill of quantities or a schedule of rates
depends upon the terms of the Contract.
5. All drawings required in building the structure (contract plans including
Architectural and Structural). These include drawings from relevant Consultants.
6. All Specifications – sets out the technical requirements of the work It describes
the project and adds clarity to its drawings; describes the requirements for
materials and workmanship.
7. All other documents considered necessary, for example, Schedule or Annexure to
the Contract completed, all technical schedules, all pricing schedules.
Principle elements of
Construction / Building
contract
ROLE OF CONTRACT
IN PROJECTS
Project is a temporary endeavour undertaken to
create a unique product (such as a building,
conservation of structure, laying a pipeline etc.).
The temporary nature of a project indicates a
defined beginning and end. The end is reached
when project objective have been achieved or when
the project is terminated because its objective
cannot be met.
What is a Project?
ROLE OF CONTRACT
IN PROJECT
When client wish to hire the services of other
agencies to do full or part of project, he offers for
bid. The successful bidder enter into a contract with
client. Project may have many contracts
Contracts a Project?
PROJECT
1. Initiation
2. Planning
3. Execution
4. Monitoring and Control
5. Closure
Phases of Project
PIU’S ROLE
1. Execution
2. Monitoring and Control
3. Closure
Phases where PIU’s has to play
major role
PIU’S ROLE 1. Direct and Manage Project Execution
2. Perform Quality Assurance
3. Distribute Information
Execution Phase
PIU’S ROLE
1. Monitor and Control Project work
2. Perform Integrated Change control
3. Report Performance
4. Identify, Monitor and control Risk
Monitoring and Control Phase
PIU’S ROLE 1. Close project/phase
2. Close Procurements/contractClosure Phase
1.1DIRECT AND MANAGE PROJECT EXECUTION
1. Ask in writing to contractor to submit all statuary documents (and make sure he has
submitted the same)- such as BG(as per GCC 59), Insurances (as per GCC 19) etc.
as per contract agreement.
2. Ask in writing to contractor to submit Project Schedule (and make sure he has
submitted the same) (as per GCC 35).
3. Ask in writing to contractor to mobilise key personal and machinery (as per GCC
15) to meet the time line in contractors submitted schedule.
4. Ask and guide to contractor to prepare a quality control plan based on
specifications in contract agreement.
1.2 PERFORM QUALITY ASSURANCE
1. Ensure that all the test required in specifications are included in Quality control
plan.
2. Maintain Test register and verify the results of test conducted.
3. Ensure frequency of tests are as per specifications.
4. Inspect and verify Material Data Sheet of factory supplied materials. And get the
material stored and applied as per mentioned in material data sheet.
1.3 DISTRIBUTE INFORMATION -IN THE FORM OF MOMS,
PROGRESS REPORTS
1. Write letter to contractor about required Progress, Quality, EHS, extension of BGs and copy to relevant
stakeholders (such as PIU Civil Engineer, PMU Civil Engineer, CGM, APD, PD, TL PMC, TL DSC)
2. Write letter to PMU for approval of Extra Items, Variation statements, Bill verifications and copy to relevant
stakeholders (such as PIU Civil Engineer, PMU Civil Engineer, CGM, PD, TL PMC, TL DSC).
3. Write letter to DSC for required drawings, bill preparation, design submission, quality control issues copy to
relevant stakeholders (such as PIU Civil Engineer, PMU Civil Engineer, CGM, APD, PD, TL PMC,)
4. Issue completion Certificate to Contactor and copy to relevant stakeholders (such as PMU Civil Engineer, CGM,
APD, PD, TL PMC, TL DSC)
5. Circulate MoMs of weekly and monthly review meetings to all participants and copy to relevant stakeholders
(PMU Civil Engineer, CGM, APD, PD, TL PMC).
6. Submit Monthly Progress Report to PMU and copy to relevant stakeholders (such as PMU Civil Engineer, CGM,
APD, PD, TL PMC, TL DSC)
2.1 MONITOR AND CONTROL PROJECT WORK
1. Track each activity of schedule submitted by contractor as described in item 2 of Direct and Manage
Project Execution. Take immediate action as and when you find that there is deviation from
schedule.
2. Check that necessary key personal and equipment are deployed by contractor as described in item
3 of Direct and Manage Project Execution.
3. Evaluate the hazards at site and instruct contractor to maintain safe working environment.
4. Ensure that contractor is complying with all the points given in EMP (Environmental Management
Plan) of contract agreement.
5. Cash flow to be taken from Contractor which should be based on contractor’s schedule (as per GCC
48).
6. Recommendation of Extension of Time has to be as per GCC 36. Please read carefully 36.2 before
recommending EOT.
2.2 PERFORM INTEGRATED CHANGE CONTROL
1. After instruction by PM for variation, contractor has to submit the quotation to
carry out variation (as per GCC 47.2).
2. Contractor’s schedule will be revised to incorporate the variation (as per GCC
47.1)
3. At some cases contract price of an item may be revised due to deviation in from
BOQ quantity (as per GCC 46).
2.3 REPORT PERFORMANCE
1. Monthly Progress reports
2. Environmental Monitoring Report (Every 6 months)
3. Social Safeguard Monitoring Report (Every 6 months)
4. Gender Action Plan (Every 6 months)
5. Any other information feel necessary to be informed
2.4 IDENTIFY, MONITORING AND CONTROL RISK
1. Identify risk due to:
a. Schedule over run
b. Scarcity of a particular material in market
c. Met a sever accident at site
d. Etc etc etc….
2. Monitor the impact of the risk.
3. Control Risk by adopting mitigation actions such as:
1. Liquidated damage clause as per(as per GCC 56)
2. May be substituting of material in subject by any other suitable material or hazing of material
3. Insure that insurance cover has been taken and its date has not expired (as per GCC 19).
3.1 CLOSE PROJECT/ PHASE
1. Check that all the activities has been completed.
2. Make area wise punch list
3. Lebel the key of locks
4. Prepare inventory
5. Complete the works mentioned in punch list.
6. Inspection with client/concessionaire and prepare client’s punch list
7. Rectify as per client’s punch list
8. Record of Handing over the property
9. Issue of completion Certificate (As per GCC 69)
3.2 CLOSE PROCUREMENT/CONTRACT
1. Collect as built drawing/ operation and maintenance Manuals from Contractor
(As per GCC 72).
2. Write and submit lesion learnt during the contract.
THANK YOU

More Related Content

PPTX
contract administration PPT
PDF
contract management, stages of contract management
PPTX
Lecture 4 - selection of contract forms
PPTX
Contracts
PPT
CH-4 Contract Management.ppt
PPTX
Contract management
PDF
The Case for Standard Forms of Construction Contract
contract administration PPT
contract management, stages of contract management
Lecture 4 - selection of contract forms
Contracts
CH-4 Contract Management.ppt
Contract management
The Case for Standard Forms of Construction Contract

What's hot (20)

PPTX
Construction contract
PPTX
FIDIC-Relevant to Time Management
PDF
Fidic contracts management introduction
PPT
Contract Management
PPT
Construction contracts docuements_08092008
PPTX
Contract management general
PPTX
Construction Claims Explained
PPTX
#FIDIC Understanding Basics# By SN Panigrahi
PPTX
Fidic Form of Contract.
PPTX
Overview to contract management
PPT
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
PPTX
Types of contracts
PDF
Standard Forms of Construction Contracts
PPTX
Contract management
PPTX
Construction Contracts: Basics of Contracts and Contract Administration
PDF
Assignment - FIDIC Contract
PPTX
Construction Project Management
PDF
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
PDF
FIDIC variation, claim & dispute - CYLFEx workshop
PDF
Exploration of risks and risk management in construction project delivery
Construction contract
FIDIC-Relevant to Time Management
Fidic contracts management introduction
Contract Management
Construction contracts docuements_08092008
Contract management general
Construction Claims Explained
#FIDIC Understanding Basics# By SN Panigrahi
Fidic Form of Contract.
Overview to contract management
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
Types of contracts
Standard Forms of Construction Contracts
Contract management
Construction Contracts: Basics of Contracts and Contract Administration
Assignment - FIDIC Contract
Construction Project Management
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
FIDIC variation, claim & dispute - CYLFEx workshop
Exploration of risks and risk management in construction project delivery
Ad

Viewers also liked (20)

PPT
Effective contract administration may 2014
PDF
Contract Administration Presentation
PDF
Contract administration iowa AGC
PDF
Nbs specification (updated for contract)
PDF
Contract Administration and Project Management Test Scores
PDF
Contract _RBSC_09.03.15
PPTX
Gcc vs scc
PDF
National structural concrete_specification_for_building_construction
PDF
Contract construction-management142
PPTX
Project Specifications and Building Code
PDF
Alpha Case Study - Contract Administration Sample
PDF
Introduction to GCC 2010 (En)
PPTX
Project Management Theory and Practice
PPT
Project Specifications
PPT
Contract Drafting
PPT
Architectural Professional Practice - Construction Documents
PDF
General technical specification for construction
PPT
Specifications 101
PPTX
SPECIFICATIONS
PPS
Claims & disputes management
Effective contract administration may 2014
Contract Administration Presentation
Contract administration iowa AGC
Nbs specification (updated for contract)
Contract Administration and Project Management Test Scores
Contract _RBSC_09.03.15
Gcc vs scc
National structural concrete_specification_for_building_construction
Contract construction-management142
Project Specifications and Building Code
Alpha Case Study - Contract Administration Sample
Introduction to GCC 2010 (En)
Project Management Theory and Practice
Project Specifications
Contract Drafting
Architectural Professional Practice - Construction Documents
General technical specification for construction
Specifications 101
SPECIFICATIONS
Claims & disputes management
Ad

Similar to CONTRACT ADMINISTRATION- Presentation dated 22.11.16 (20)

PPT
contract_management.ppt
PDF
Green field project making of production plant
PDF
Green field making of production plant.ppt2
DOCX
PMC Proposal.docx
DOCX
PMC .docx
PPTX
Cl presentation
PDF
Contract and Types of Contract
PPT
LEC - 1.ppt most important lecture note and best
 
DOC
Single Proprietorship JD
PPTX
CONTRACT AND CLAIM MANAGEMENT.pptx IN CONSTRUCTION
DOCX
NCIT civil Syllabus 2013-2014
PDF
The Comprehensive Guide to Construction Project Management Process
PDF
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
PDF
SECTION 3 GCC.pdf file of general term and condition
PPSX
Tendering Document for the Procurement of Works
PPTX
CONTRACT MANAGEMENT.pptx
PPTX
¹𝐋𝐞𝐜𝐭 1-2.pptx
PPT
chapter 6 contract management - Copy.ppt
PPT
TENDERS and Contracts basic syllabus for engineering
contract_management.ppt
Green field project making of production plant
Green field making of production plant.ppt2
PMC Proposal.docx
PMC .docx
Cl presentation
Contract and Types of Contract
LEC - 1.ppt most important lecture note and best
 
Single Proprietorship JD
CONTRACT AND CLAIM MANAGEMENT.pptx IN CONSTRUCTION
NCIT civil Syllabus 2013-2014
The Comprehensive Guide to Construction Project Management Process
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
SECTION 3 GCC.pdf file of general term and condition
Tendering Document for the Procurement of Works
CONTRACT MANAGEMENT.pptx
¹𝐋𝐞𝐜𝐭 1-2.pptx
chapter 6 contract management - Copy.ppt
TENDERS and Contracts basic syllabus for engineering

CONTRACT ADMINISTRATION- Presentation dated 22.11.16

  • 2. CONTRACT A contract is a legally binding or valid agreement between two parties.What is Contract?
  • 3. CONTRACT 1. offer and acceptance; 2. an intention between the parties to create binding relations; 3. consideration to be paid for the promise made; 4. legal capacity of the parties to act; 5. genuine consent of the parties; and 6. legality of the agreement. An agreement that lacks one or more of the elements listed above is not a valid contract. Elements of contract
  • 4. CONSTRUCTION / BUILDING CONTRACT A Contract between an Owner (Client) and a Building Contractor, setting forth the terms under which construction is to be carried out, the basis of remuneration, the time scale, and the penalties, if any, (for failure to comply with terms of the Contract) is termed as a Building/Construction Contract. What is Construction / Building contract
  • 5. CONSTRUCTION / BUILDING CONTRACT 1. The Contract or Agreement letter. 2. General Conditions of the Contract – these define the legal rights and obligations of the parties; another way of describing the general conditions is as the rules by which each party will operate in performing their obligations as set down under the Contract. 3. Special conditions of Contract – these are an extension to the general conditions and apply specifically and individually to each project/Contract. 4. Bill of quantities – it lists quantities of the various items and the material to be included in the Contract. It can also be used as the basis for valuation of variations and assists the preparation of progress claims. The extent to which the Owner warrants the completeness of a bill of quantities or a schedule of rates depends upon the terms of the Contract. 5. All drawings required in building the structure (contract plans including Architectural and Structural). These include drawings from relevant Consultants. 6. All Specifications – sets out the technical requirements of the work It describes the project and adds clarity to its drawings; describes the requirements for materials and workmanship. 7. All other documents considered necessary, for example, Schedule or Annexure to the Contract completed, all technical schedules, all pricing schedules. Principle elements of Construction / Building contract
  • 6. ROLE OF CONTRACT IN PROJECTS Project is a temporary endeavour undertaken to create a unique product (such as a building, conservation of structure, laying a pipeline etc.). The temporary nature of a project indicates a defined beginning and end. The end is reached when project objective have been achieved or when the project is terminated because its objective cannot be met. What is a Project?
  • 7. ROLE OF CONTRACT IN PROJECT When client wish to hire the services of other agencies to do full or part of project, he offers for bid. The successful bidder enter into a contract with client. Project may have many contracts Contracts a Project?
  • 8. PROJECT 1. Initiation 2. Planning 3. Execution 4. Monitoring and Control 5. Closure Phases of Project
  • 9. PIU’S ROLE 1. Execution 2. Monitoring and Control 3. Closure Phases where PIU’s has to play major role
  • 10. PIU’S ROLE 1. Direct and Manage Project Execution 2. Perform Quality Assurance 3. Distribute Information Execution Phase
  • 11. PIU’S ROLE 1. Monitor and Control Project work 2. Perform Integrated Change control 3. Report Performance 4. Identify, Monitor and control Risk Monitoring and Control Phase
  • 12. PIU’S ROLE 1. Close project/phase 2. Close Procurements/contractClosure Phase
  • 13. 1.1DIRECT AND MANAGE PROJECT EXECUTION 1. Ask in writing to contractor to submit all statuary documents (and make sure he has submitted the same)- such as BG(as per GCC 59), Insurances (as per GCC 19) etc. as per contract agreement. 2. Ask in writing to contractor to submit Project Schedule (and make sure he has submitted the same) (as per GCC 35). 3. Ask in writing to contractor to mobilise key personal and machinery (as per GCC 15) to meet the time line in contractors submitted schedule. 4. Ask and guide to contractor to prepare a quality control plan based on specifications in contract agreement.
  • 14. 1.2 PERFORM QUALITY ASSURANCE 1. Ensure that all the test required in specifications are included in Quality control plan. 2. Maintain Test register and verify the results of test conducted. 3. Ensure frequency of tests are as per specifications. 4. Inspect and verify Material Data Sheet of factory supplied materials. And get the material stored and applied as per mentioned in material data sheet.
  • 15. 1.3 DISTRIBUTE INFORMATION -IN THE FORM OF MOMS, PROGRESS REPORTS 1. Write letter to contractor about required Progress, Quality, EHS, extension of BGs and copy to relevant stakeholders (such as PIU Civil Engineer, PMU Civil Engineer, CGM, APD, PD, TL PMC, TL DSC) 2. Write letter to PMU for approval of Extra Items, Variation statements, Bill verifications and copy to relevant stakeholders (such as PIU Civil Engineer, PMU Civil Engineer, CGM, PD, TL PMC, TL DSC). 3. Write letter to DSC for required drawings, bill preparation, design submission, quality control issues copy to relevant stakeholders (such as PIU Civil Engineer, PMU Civil Engineer, CGM, APD, PD, TL PMC,) 4. Issue completion Certificate to Contactor and copy to relevant stakeholders (such as PMU Civil Engineer, CGM, APD, PD, TL PMC, TL DSC) 5. Circulate MoMs of weekly and monthly review meetings to all participants and copy to relevant stakeholders (PMU Civil Engineer, CGM, APD, PD, TL PMC). 6. Submit Monthly Progress Report to PMU and copy to relevant stakeholders (such as PMU Civil Engineer, CGM, APD, PD, TL PMC, TL DSC)
  • 16. 2.1 MONITOR AND CONTROL PROJECT WORK 1. Track each activity of schedule submitted by contractor as described in item 2 of Direct and Manage Project Execution. Take immediate action as and when you find that there is deviation from schedule. 2. Check that necessary key personal and equipment are deployed by contractor as described in item 3 of Direct and Manage Project Execution. 3. Evaluate the hazards at site and instruct contractor to maintain safe working environment. 4. Ensure that contractor is complying with all the points given in EMP (Environmental Management Plan) of contract agreement. 5. Cash flow to be taken from Contractor which should be based on contractor’s schedule (as per GCC 48). 6. Recommendation of Extension of Time has to be as per GCC 36. Please read carefully 36.2 before recommending EOT.
  • 17. 2.2 PERFORM INTEGRATED CHANGE CONTROL 1. After instruction by PM for variation, contractor has to submit the quotation to carry out variation (as per GCC 47.2). 2. Contractor’s schedule will be revised to incorporate the variation (as per GCC 47.1) 3. At some cases contract price of an item may be revised due to deviation in from BOQ quantity (as per GCC 46).
  • 18. 2.3 REPORT PERFORMANCE 1. Monthly Progress reports 2. Environmental Monitoring Report (Every 6 months) 3. Social Safeguard Monitoring Report (Every 6 months) 4. Gender Action Plan (Every 6 months) 5. Any other information feel necessary to be informed
  • 19. 2.4 IDENTIFY, MONITORING AND CONTROL RISK 1. Identify risk due to: a. Schedule over run b. Scarcity of a particular material in market c. Met a sever accident at site d. Etc etc etc…. 2. Monitor the impact of the risk. 3. Control Risk by adopting mitigation actions such as: 1. Liquidated damage clause as per(as per GCC 56) 2. May be substituting of material in subject by any other suitable material or hazing of material 3. Insure that insurance cover has been taken and its date has not expired (as per GCC 19).
  • 20. 3.1 CLOSE PROJECT/ PHASE 1. Check that all the activities has been completed. 2. Make area wise punch list 3. Lebel the key of locks 4. Prepare inventory 5. Complete the works mentioned in punch list. 6. Inspection with client/concessionaire and prepare client’s punch list 7. Rectify as per client’s punch list 8. Record of Handing over the property 9. Issue of completion Certificate (As per GCC 69)
  • 21. 3.2 CLOSE PROCUREMENT/CONTRACT 1. Collect as built drawing/ operation and maintenance Manuals from Contractor (As per GCC 72). 2. Write and submit lesion learnt during the contract.