Episode 30 : Project
Execution ( Part 1 )
4.1.2 Systematics
Being used to master the multitude of documents
or activities mentioned in Project structures
 3 examples will describe the application
of these systematics:
 Project manual
 Revision service
 Correspondence system
Project Manual
•To guarantee professional project planning and execution.
•all activities required
for execution within the
framework of a project
& documentation to be
prepared, are arranged
according to an in -
house system.
•planning packages
not feasible for the
present project
have to be deleted
•filing of and access to
documents
made easier
shall be
for the
employees involved by
applying directory
structure for computer
files or a systematics
for the description of
files.
Correspondence system
• Numerous numbers of letters, facsimiles, minutes of
meeting, memoranda are exchanged between employer,
contractor and subcontractors.
• Email correspondence has increased but traditional post
should be retained as written documentation.
• To guarantee clarity and easy access:
incoming or outgoing letter will consecutively
numbered.
document number linked with a filing system or the
systematics of the project manual.
Example:
• Complete outgoing correspondence will be filed in EDP-register called “Project Nam
Correspondence”.
• This register contain 1 sub-register (company’s name) for each company.
• This sub-register contains 3 further sub-registers:
 Letters (denoted as L)
 Facsimiles (denoted as F)
 Minutes of meeting (denoted as M)
• Registers individual documents may named as
COMPANYNAME-001B.DOC
Revision service
Modifications of already existing project documents
The original draft usually gets the revision no. 0 with
each revision numbers are counted up.
The revision line of the respective document indicates
which revision is concerned.
The meticulous tracing of modifications and thus of
revisions is of utmost importance for the execution of
projects
Example
•Sub – contractor informs the project engineer it would be better to
mount the brackets of the heat exchanger 15 cm higher due to
processing reasons.
•Sub - contractor changes the production drawing and sends it to the
plant manufacturer as revision no.1 after the project engineer
gives his approval.
•If the plant manufacturer forgets to furnish the layout planner
with a copy, design in the system layout will be based on revision
0 of the heat exchanger.
•With the latest revision being unnoticed the assembly will end in
disaster.
7
Cost Monitoring
1] Project management is required to prepare a monthly
order report :
forecast in which the looming technical, commercial
or schedule problems.
2] Cost Calculation:
compares the actual costs with the cost objectives of
the preliminary costing of the project.
Significant deviations: cause the problems like
schedule delay, increasing the staff.
3] Claims Management: extra costs will be assessed
addendum negotiations on additions, omissions or
claims
Continue…
Prepare the order report:
•current state of development
meetings
regular project
•function control instrument (detect risks)
•the conflict situation the project management has
to cope with becomes clear.
Time Scheduling/Monitoring of Dates
Execution process in plant manufacturing is made
up of a large number of individual processes. The
beginning of many processes is contingent on
previous activities having been completed with a
certain result.
During the assembly phase, events are the
physical availability of certain equipment and the
completion of assembly work. Thus the
inevitable chronology of processes is
characteristic of the whole process period.
The scheduling of project chronologies and their
explicit depiction are essential objectives of time
scheduling or workflow scheduling.
Time Scheduling/Monitoring of Dates
Missed deadlines will result in liquidated
damages, extended project duration, and directly
increase in employment costs.
Gantt Charts are set up to list the activities one
below the other, resulting in the period of time
required for the completion of the activity from
the beginning and the end of this activity.
The relevant EDP ‐ programs are used for setting
up time schedules and the planning of resources.
Important Time Schedules
Time Schedules
E/MC ‐ Technology
Manufacturing and
assembly of the
piping
Assembly work flow
Project planning
phase
Detail engineering
Commissioning
Procurement of the
components
Erection phase
Framework Time Schedule
Time Schedule for Component Procurement
KKKK6024
Time Schedule for Commissioning
Computers in Plant manufacturing
Office
Applications
Basic software
of system
engineering
Databases
retrieved for
various process
calculations
Spreadsheet
analysis program
Used for all kinds
of
correspondence,
integrated index,
classification
system
CAD/CAE
Project Planning
Phase
‐ plant concept
modeling
‐ Arrangement
of components
in system
‐ piping layout
‐ cost assessment
of piping
packages
Execution Phase
‐ P&ID
‐ layout design
‐ piping plans
CAD/CAE linked to
component
catalogues, 3‐
dimensional
models,
Example:
Computational
FEM/
Pipe Stress
Analysis
Applied on
progress of
stress &
deformation in
branched piping
systems
Components
disassembled
into multitude
of small units
called finite
elements, cover
the modeled
component like
net or skeleton
framing
Process
Simulation
Used for
planning &
layout of
processes in
entire systems /
plant units
Calculation of
procedural basic
operation
mainly in
chemical &
thermal process
engineering
Software in
E/MC‐
technology
Types of
software:
‐ Control loop
‐ Control
technology
(provided by
supplier of
control
equipment)
‐ Preparation of
continuous
function chart
‐ E‐engineering
Others
‐ Databases
‐ Documentation
systems
‐ Time scheduling
‐ maintenance &
repair software
Fluid Dynamics
interference check
•The authority approval provides a secure legal basis for the erection and
operation of process plants
•Approval process :
i) the legitimate interests of the public – i.e. the public in general
ii) the neighbors of the plant to be erected in particular
iii) employees of the operating company – as well as the issues of the plant
operator are examined
iv ) contact the relevant authorities of the respective country in due time
v) commission engineering agencies or a lawyer ’ s office specializing in the
field of authority engineering
•In case a new plant is to be erected and operated, it has to be verified at first
if an authority approval will be required. The statutory regulations and
conditions may vary considerably subject to the respective country.
APPROVAL PLANNING
Procurement
 Initially, component procurement is focused on the components
with the longest delivery times.
 Longer delivery times is considerably higher procurement costs.
 A quotation comparison is necessary to shortlist the
subcontractors.
 The commercial and technical conditions for the plant
manufacturer ’ s order at the subcontractor are also stipulated in
the form of a purchasing contract.
 The consequences of a subcontractor ’ s delay in delivery will be
excessively high costs.
• Long delivery time – have to order in due time.
• In early project phase piping and instrumentation diagrams as well
as detailed layout and piping plans – not yet exist.
• To specify the vessel data, following procedure possible:
– Number of connecting pipes assessed by PFD or with the first draft of
piping and instrumentation diagram.
– Nominal width of connecting pipes assessed – basis of the available
balancing or media data sheets. Doubt case – larger nominal width
chosen.
– Connecting pieces for measuring equipment of vessel approximately
determined. Normal atmospheric vessel – determined quite easily.
– Other nozzle : manhole, overflow pipe, emptying pipe, connection for
sample taking etc.
– All vessel section – additional reserve nozzles (different nominal width)
Vessels
– Position of nozzle – through their function or layout
– the contract with the subcontractor – nozzle modifications with regard
to their position are carried out free of charge and that additional
nozzles can be mounted up to a certain point in time (e.g. release of
production drawings).
• These procedure – at least inquiries to subcontractor in early
time
• The strength – related layout and the warranty regarding
corrosion, vessels do not require further function guaranties.
Vessels
 Pumps may require quite long delivery times
‐ designed by using non commercial materials
 Detailed calculation of the pressure drop requires the exact piping
dimensions & piping routes
 Some plant manufacturers decide to simply “assess” the pumps to
avoid this problem.
‐ the required pump head will be assessed on the basis of the layout and of the
operating data
 Another way of proceeding to avoid the problems:
‐ Preparation of P&ID
‐ Determination of piping classes
‐ Determination of nominal widths & nominal pressures
‐ Fitting concept
Pumps
 Drawing of P&ID is started immediately after the order placing and
parallel to the procurement of the components.
 Basic information
‐ All appliances and machinery, including motors
‐ All pipes or means of transport (conveyor belts)
‐ All pipe installations (valves & fittings) and moulded parts (tees)
 The database is sub‐divided into components or systems to ensure
a certain transparency of the total plant system
Process & Instrumentation Diagram
Thanks for Watching
Please follow me / SAJJAD KHUDHUR ABBAS

More Related Content

PPTX
Episode 32 : Project Execution Part (3)
PPTX
Episode 31 : Project Execution Part (2)
PPTX
Episode 33 : Project Execution Part (4)
PDF
Episode 34 : Project Execution Part (5)
DOCX
ASIF CV - HVAC O & M
PPTX
Episode 28 : Project Management Contract
PPS
Mechanical Completions
PPTX
Episode 22 : PROJECT EXECUTION
Episode 32 : Project Execution Part (3)
Episode 31 : Project Execution Part (2)
Episode 33 : Project Execution Part (4)
Episode 34 : Project Execution Part (5)
ASIF CV - HVAC O & M
Episode 28 : Project Management Contract
Mechanical Completions
Episode 22 : PROJECT EXECUTION

What's hot (19)

PPT
Commissioning and Operations
PPTX
Commissioning of Offshore Installations
DOCX
CV-Shreyas Shah 9.5
DOCX
Mechanical completion
DOC
vijay cv
PDF
110921 commissioning of offshore installations
DOC
Resume_AG
DOC
MS CV May 2016
PPTX
Pcsu chapter 1
PDF
Engineering
PDF
Mohamed elsayed updated
PDF
Detailed engineering-design-phase
DOC
MDK Maintenance Manager 1 7+Year Experience
DOC
Ng Eng Beng CV
PDF
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
PDF
World Class Manufacturing:Plant Start Up and Commissioning Procedure
PDF
PPTX
Episode 7 : iCON Basic Training
Commissioning and Operations
Commissioning of Offshore Installations
CV-Shreyas Shah 9.5
Mechanical completion
vijay cv
110921 commissioning of offshore installations
Resume_AG
MS CV May 2016
Pcsu chapter 1
Engineering
Mohamed elsayed updated
Detailed engineering-design-phase
MDK Maintenance Manager 1 7+Year Experience
Ng Eng Beng CV
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
World Class Manufacturing:Plant Start Up and Commissioning Procedure
Episode 7 : iCON Basic Training
Ad

Viewers also liked (18)

PPTX
Project Execution Methodologies – Rising a Step Further
PPTX
Effective Project Execution
PPTX
Episode 54 : CAPE Problem Formulations
PPT
Episode 36 : What is Powder Technology?
PPTX
Episode 40 : DESIGN EXAMPLE – DILUTE PHASE PNEUMATIC CONVEYING (Part 2)
PPTX
Episode 53 : Computer Aided Process Engineering
PPT
Project Execution
PPT
Episode 37 : SAMPLING
PPT
Episode 35 : Design Approach to Dilute Phase Pneumatic Conveying
PPTX
Episode 57 : Simulation for Design and Analysis
PPTX
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM
PPT
Episode 38 : Bin and Hopper Design
PPT
Project Execution
PPTX
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
PPT
Managing Project Execution
PPSX
7 Steps Project Execution Process
PPTX
Project planning and project work plan
PPSX
Project management
Project Execution Methodologies – Rising a Step Further
Effective Project Execution
Episode 54 : CAPE Problem Formulations
Episode 36 : What is Powder Technology?
Episode 40 : DESIGN EXAMPLE – DILUTE PHASE PNEUMATIC CONVEYING (Part 2)
Episode 53 : Computer Aided Process Engineering
Project Execution
Episode 37 : SAMPLING
Episode 35 : Design Approach to Dilute Phase Pneumatic Conveying
Episode 57 : Simulation for Design and Analysis
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 38 : Bin and Hopper Design
Project Execution
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
Managing Project Execution
7 Steps Project Execution Process
Project planning and project work plan
Project management
Ad

Similar to Episode 30 : Project Execution ( Part 1 ) (20)

PPTX
2.-Introduction-to-Process-Plant-Layout-and-Piping-Design.pptx
PDF
A ROUGH GUIDE TO OFFSHORE PLATFORMS OR FPSO
PDF
OFFSHORE PLATFORM/FPSO PLANT DESIGN-1.pdf
PDF
PEPD MODULE 1.pdf
PPT
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
PDF
Handbook For Process Plant Project Engineers - Peter Watermeyer
PDF
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
PPTX
SWIFT PRESENTATION-RESERVE will blow your mind.pptx
PDF
Handbook for Process Plant Project Engineers 1st Edition Peter Watermeyer
PPTX
Episode 27 : Project Management Costs
PDF
Engineering Company overview and Process Engineer's Role
PPTX
Episode 27 : Project Management Costs
PDF
Chemical plant design & construction 2016
PDF
Process Engineer Training PID.ppt.pdf
PPTX
Chemical Process Diagrams - Copy.Chemical process technology involves the pro...
PDF
Pharmaceutical plant layout
PDF
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
PDF
Note 1.pdf
PPT
chemical plant design lecture notes 1.ppt
PPTX
Presentacion asme seccion viii division 2 2013
2.-Introduction-to-Process-Plant-Layout-and-Piping-Design.pptx
A ROUGH GUIDE TO OFFSHORE PLATFORMS OR FPSO
OFFSHORE PLATFORM/FPSO PLANT DESIGN-1.pdf
PEPD MODULE 1.pdf
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
Handbook For Process Plant Project Engineers - Peter Watermeyer
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
SWIFT PRESENTATION-RESERVE will blow your mind.pptx
Handbook for Process Plant Project Engineers 1st Edition Peter Watermeyer
Episode 27 : Project Management Costs
Engineering Company overview and Process Engineer's Role
Episode 27 : Project Management Costs
Chemical plant design & construction 2016
Process Engineer Training PID.ppt.pdf
Chemical Process Diagrams - Copy.Chemical process technology involves the pro...
Pharmaceutical plant layout
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
Note 1.pdf
chemical plant design lecture notes 1.ppt
Presentacion asme seccion viii division 2 2013

More from SAJJAD KHUDHUR ABBAS (20)

PPTX
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PPTX
Electric cars
PPTX
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
PPTX
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
PPTX
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
PPTX
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
PPTX
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
PPTX
Production of 100 mt distilled monoglyceride (dmg)
PPTX
Episode 66 : Renewable Energy Technologies
PPTX
Episode 65 : Membrane separation processes
PPTX
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
PPTX
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
PPTX
Episode 60 : Pinch Diagram and Heat Integration
PPTX
Episode 59 : Introduction of Process Integration
PPTX
Episode 58 : Tools Integration Examples
PPTX
Episode 56 : Simulation for design and analysis
PPTX
Episode 55 : Conceptual Process Synthesis-Design
PPTX
Episode 52 : Flow sheeting Case Study
PPTX
Episode 51 : Integrated Process Simulation
PPTX
Episode 50 : Simulation Problem Solution Approaches Convergence Techniques S...
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
Electric cars
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
Production of 100 mt distilled monoglyceride (dmg)
Episode 66 : Renewable Energy Technologies
Episode 65 : Membrane separation processes
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 60 : Pinch Diagram and Heat Integration
Episode 59 : Introduction of Process Integration
Episode 58 : Tools Integration Examples
Episode 56 : Simulation for design and analysis
Episode 55 : Conceptual Process Synthesis-Design
Episode 52 : Flow sheeting Case Study
Episode 51 : Integrated Process Simulation
Episode 50 : Simulation Problem Solution Approaches Convergence Techniques S...

Recently uploaded (20)

PPTX
Welding lecture in detail for understanding
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
PPT on Performance Review to get promotions
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPT
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
PPTX
Construction Project Organization Group 2.pptx
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Welding lecture in detail for understanding
R24 SURVEYING LAB MANUAL for civil enggi
Mechanical Engineering MATERIALS Selection
Lecture Notes Electrical Wiring System Components
CYBER-CRIMES AND SECURITY A guide to understanding
Internet of Things (IOT) - A guide to understanding
PPT on Performance Review to get promotions
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Embodied AI: Ushering in the Next Era of Intelligent Systems
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
Construction Project Organization Group 2.pptx
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Model Code of Practice - Construction Work - 21102022 .pdf
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd

Episode 30 : Project Execution ( Part 1 )

  • 1. SAJJAD KHUDHUR ABBAS Ceo , Founder & Head of SHacademy Chemical Engineering , Al-Muthanna University, Iraq Oil & Gas Safety and Health Professional – OSHACADEMY Trainer of Trainers (TOT) - Canadian Center of Human Development Episode 30 : Project Execution ( Part 1 )
  • 2. 4.1.2 Systematics Being used to master the multitude of documents or activities mentioned in Project structures  3 examples will describe the application of these systematics:  Project manual  Revision service  Correspondence system
  • 3. Project Manual •To guarantee professional project planning and execution. •all activities required for execution within the framework of a project & documentation to be prepared, are arranged according to an in - house system. •planning packages not feasible for the present project have to be deleted •filing of and access to documents made easier shall be for the employees involved by applying directory structure for computer files or a systematics for the description of files.
  • 4. Correspondence system • Numerous numbers of letters, facsimiles, minutes of meeting, memoranda are exchanged between employer, contractor and subcontractors. • Email correspondence has increased but traditional post should be retained as written documentation. • To guarantee clarity and easy access: incoming or outgoing letter will consecutively numbered. document number linked with a filing system or the systematics of the project manual.
  • 5. Example: • Complete outgoing correspondence will be filed in EDP-register called “Project Nam Correspondence”. • This register contain 1 sub-register (company’s name) for each company. • This sub-register contains 3 further sub-registers:  Letters (denoted as L)  Facsimiles (denoted as F)  Minutes of meeting (denoted as M) • Registers individual documents may named as COMPANYNAME-001B.DOC
  • 6. Revision service Modifications of already existing project documents The original draft usually gets the revision no. 0 with each revision numbers are counted up. The revision line of the respective document indicates which revision is concerned. The meticulous tracing of modifications and thus of revisions is of utmost importance for the execution of projects
  • 7. Example •Sub – contractor informs the project engineer it would be better to mount the brackets of the heat exchanger 15 cm higher due to processing reasons. •Sub - contractor changes the production drawing and sends it to the plant manufacturer as revision no.1 after the project engineer gives his approval. •If the plant manufacturer forgets to furnish the layout planner with a copy, design in the system layout will be based on revision 0 of the heat exchanger. •With the latest revision being unnoticed the assembly will end in disaster. 7
  • 8. Cost Monitoring 1] Project management is required to prepare a monthly order report : forecast in which the looming technical, commercial or schedule problems. 2] Cost Calculation: compares the actual costs with the cost objectives of the preliminary costing of the project. Significant deviations: cause the problems like schedule delay, increasing the staff. 3] Claims Management: extra costs will be assessed addendum negotiations on additions, omissions or claims
  • 9. Continue… Prepare the order report: •current state of development meetings regular project •function control instrument (detect risks) •the conflict situation the project management has to cope with becomes clear.
  • 10. Time Scheduling/Monitoring of Dates Execution process in plant manufacturing is made up of a large number of individual processes. The beginning of many processes is contingent on previous activities having been completed with a certain result. During the assembly phase, events are the physical availability of certain equipment and the completion of assembly work. Thus the inevitable chronology of processes is characteristic of the whole process period. The scheduling of project chronologies and their explicit depiction are essential objectives of time scheduling or workflow scheduling.
  • 11. Time Scheduling/Monitoring of Dates Missed deadlines will result in liquidated damages, extended project duration, and directly increase in employment costs. Gantt Charts are set up to list the activities one below the other, resulting in the period of time required for the completion of the activity from the beginning and the end of this activity. The relevant EDP ‐ programs are used for setting up time schedules and the planning of resources.
  • 12. Important Time Schedules Time Schedules E/MC ‐ Technology Manufacturing and assembly of the piping Assembly work flow Project planning phase Detail engineering Commissioning Procurement of the components Erection phase
  • 14. Time Schedule for Component Procurement KKKK6024
  • 15. Time Schedule for Commissioning
  • 16. Computers in Plant manufacturing Office Applications Basic software of system engineering Databases retrieved for various process calculations Spreadsheet analysis program Used for all kinds of correspondence, integrated index, classification system CAD/CAE Project Planning Phase ‐ plant concept modeling ‐ Arrangement of components in system ‐ piping layout ‐ cost assessment of piping packages Execution Phase ‐ P&ID ‐ layout design ‐ piping plans CAD/CAE linked to component catalogues, 3‐ dimensional models, Example: Computational FEM/ Pipe Stress Analysis Applied on progress of stress & deformation in branched piping systems Components disassembled into multitude of small units called finite elements, cover the modeled component like net or skeleton framing Process Simulation Used for planning & layout of processes in entire systems / plant units Calculation of procedural basic operation mainly in chemical & thermal process engineering Software in E/MC‐ technology Types of software: ‐ Control loop ‐ Control technology (provided by supplier of control equipment) ‐ Preparation of continuous function chart ‐ E‐engineering Others ‐ Databases ‐ Documentation systems ‐ Time scheduling ‐ maintenance & repair software Fluid Dynamics interference check
  • 17. •The authority approval provides a secure legal basis for the erection and operation of process plants •Approval process : i) the legitimate interests of the public – i.e. the public in general ii) the neighbors of the plant to be erected in particular iii) employees of the operating company – as well as the issues of the plant operator are examined iv ) contact the relevant authorities of the respective country in due time v) commission engineering agencies or a lawyer ’ s office specializing in the field of authority engineering •In case a new plant is to be erected and operated, it has to be verified at first if an authority approval will be required. The statutory regulations and conditions may vary considerably subject to the respective country. APPROVAL PLANNING
  • 18. Procurement  Initially, component procurement is focused on the components with the longest delivery times.  Longer delivery times is considerably higher procurement costs.  A quotation comparison is necessary to shortlist the subcontractors.  The commercial and technical conditions for the plant manufacturer ’ s order at the subcontractor are also stipulated in the form of a purchasing contract.  The consequences of a subcontractor ’ s delay in delivery will be excessively high costs.
  • 19. • Long delivery time – have to order in due time. • In early project phase piping and instrumentation diagrams as well as detailed layout and piping plans – not yet exist. • To specify the vessel data, following procedure possible: – Number of connecting pipes assessed by PFD or with the first draft of piping and instrumentation diagram. – Nominal width of connecting pipes assessed – basis of the available balancing or media data sheets. Doubt case – larger nominal width chosen. – Connecting pieces for measuring equipment of vessel approximately determined. Normal atmospheric vessel – determined quite easily. – Other nozzle : manhole, overflow pipe, emptying pipe, connection for sample taking etc. – All vessel section – additional reserve nozzles (different nominal width) Vessels
  • 20. – Position of nozzle – through their function or layout – the contract with the subcontractor – nozzle modifications with regard to their position are carried out free of charge and that additional nozzles can be mounted up to a certain point in time (e.g. release of production drawings). • These procedure – at least inquiries to subcontractor in early time • The strength – related layout and the warranty regarding corrosion, vessels do not require further function guaranties. Vessels
  • 21.  Pumps may require quite long delivery times ‐ designed by using non commercial materials  Detailed calculation of the pressure drop requires the exact piping dimensions & piping routes  Some plant manufacturers decide to simply “assess” the pumps to avoid this problem. ‐ the required pump head will be assessed on the basis of the layout and of the operating data  Another way of proceeding to avoid the problems: ‐ Preparation of P&ID ‐ Determination of piping classes ‐ Determination of nominal widths & nominal pressures ‐ Fitting concept Pumps
  • 22.  Drawing of P&ID is started immediately after the order placing and parallel to the procurement of the components.  Basic information ‐ All appliances and machinery, including motors ‐ All pipes or means of transport (conveyor belts) ‐ All pipe installations (valves & fittings) and moulded parts (tees)  The database is sub‐divided into components or systems to ensure a certain transparency of the total plant system Process & Instrumentation Diagram
  • 23. Thanks for Watching Please follow me / SAJJAD KHUDHUR ABBAS