SlideShare a Scribd company logo
EET402 -M4-Ktunotes.in.pdf ,NOTES ON ESD
MODULE 4
Downloaded from Ktunotes.in
Module 4
Industrial Power and Lighting Installations (9 hours):
Industrial installations –classifications- Design of electrical distribution systems with main
switch board, sub switch boards and distribution boards with ACBs, MCCBs and MCBs as the
case may be, for feeding power (mainly motors) and lighting loads of small and medium
industries.
Selection of armoured power cables (AYFY, A2XFY, YWY) – calculation of ampacity, voltage
drop, short circuit withstand capacity etc.
Design of MSB & SSB including Motor Control Centre (MCC) for motor controls - selection of
bus bars and switchgears.
Selection of 11kV indoor and outdoor transformer substations upto 630kVA - selection of
switchgears and protective devices –Preparation of schedule of works and bill of quantities (cost
estimation excluded).
Short circuit calculations and earthing design for the HV and LV sides of an 11 kV substation of
capacity up to 630 kVA.
Pre-commissioning tests of 11kV indoor/outdoor substation of an HT consumer.
Downloaded from Ktunotes.in
Industrial Installation
Design of industrial installation is more sophisticated.
Industrial installation has diverse loads.
Main aspects of industrial installation are
✔Easiness of maintenance
✔Fault location
✔Economic considerations
✔Energy conservation
Downloaded from Ktunotes.in
Classification of Industrial Buildings
•For the purpose of evaluating the electrical requirements as per NEC ,
industries are classified taking into consideration three basic criteria
1) Fire hazard
2) Power consumption
3) Pollution hazard
Downloaded from Ktunotes.in
1) Classification based on fire hazard
National Building Code classifies the industrial buildings in group G from the
safety point of view.
• Group G1-Buildings used for low fire hazard industries.
These industries have low combustibility and the process/operations are not
liable to self propagation of fire and only damage to life and property may
arise out of panic, fumes or smoke or fire from an external source.
Eg:- cement, glass, rice, soap detergent ,sugar industry etc.
Downloaded from Ktunotes.in
• Group G2-Buildings of moderate fire hazard
Those industries in which the process/operations may give rise a fire which
will burn with moderate rapidity and give rise to considerable volume of
smoke. These fires will not result in explosion.
Eg:-Ship repairing, coir, flour mills, fertiliser plants etc.
• Group G3:-Buildings with high fire hazards
Those industries in which the process/operations may give rise a fire which
will burn with extreme rapidity and give rise to considerable volume of
poisonous fumes and lead to explosion.
Eg:-alcohol distillery, explosive manufacturing, petrochemicals etc.
Downloaded from Ktunotes.in
2) Classification based on power consumption
NEC classifies industrial building according to the power requirements as
✔ Light industries(Small)
✔ Average industries(Medium)
✔ Heavy industries(Large)
Downloaded from Ktunotes.in
Description Average power
requirement(kVA)
Examples
Light industry Upto 50 kVA Garment making,
ornament making
Average industry Above 50 up to 2000
kVA
Furniture, pottery, glass,
tobacco,textiles
Heavy industry Above 2000 kVA Heavy electrical
equipment, steel mills,
ship building, chemical
plants, paper mills,
petrochemicals
Downloaded from Ktunotes.in
3) Classification based on Pollution degree Level
Pollution degree is a classification according to the amount of dry pollution and
condensation present in the environment.
Pollution degree1:-No pollution or only dry nonconductive pollution occurs.
Pollution degree 2:-Normally nonconductive pollution occurs. Temporary
conductive pollution occurs due to condensation.
Pollution degree 3:- Conductive pollution or dry nonconductive pollution that
becomes conductive due to condensation occurs.
Pollution degree 4:-Pollution generates persistent conductivity caused by
conductive dust, rain or snow.
Downloaded from Ktunotes.in
Electrical Installation in small industries
• Small industries contain motor in the installation.
• Each motor must be controlled by a main switch
• A 3 phase motor need a triple pole switch with fuse in each phase and also a
starter is required for starting and stopping the motor.
• Size of switch fuse unit and starter will depend upon the rating of the motor.
• Depending upon rating of the motor ,PVC cables of suitable size are to be used.
• For large capacity motors ,3 phase underground cables are used.
• Cables are enclosed in a rigid heavy gauge conduit.
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
• If there are more number of motors, power to the various machines is distributed
from the main switchboard located at a convenient position.
• Main switch fuse unit consist of different switch fuse units to control the
incoming and outgoing circuits .
• The outgoing circuits feed different sub distribution boards which will be placed
at various locations.
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Design of Electrical Installation in Small Industries
(1) Motor current
✔ When the motor is first connected to the line ,it will draw more current than its
rated current. This is called the starting current.
✔ When the motor pick up its speed, it carries full load .
✔ When the motor is overloaded ,the current increases and it will overheat.
✔ Current rating of the cable used for supplying power to the motor is based on full
load current of the motor, but the rating of fuse is based on starting current.
✔ The rating of fuse should be greater than twice the rating of cables.
Downloaded from Ktunotes.in
(2) Deciding the cable size
The cable shall have a current carrying capacity of not less than 150 percent of
motor full load current.
For example
For dc motor
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
(3) Determination of the size of conduit
Size of conduit depends upon three factors:
✔ No. of cables to be installed
✔ Cross sectional area of the cable
✔ The permissible conduit fill
The maximum permissible number of cables that can be drawn into conduit is given
by the below table.
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
(4) Deciding the fuse rating
Fuse has to carry starting current safely.
Starting current is taken as 1.5 times the full load current.
Downloaded from Ktunotes.in
(5) Deciding the starter, distribution board and Main switch
Specification of distribution board is decided from the number of circuits to be fed from it.
Voltage rating of DB is decided by the voltage rating of the circuit and current rating is the highest
starting current of the circuit.
Current rating of the Main Switch should be equal to the starting current of the motor of highest
rating plus the full load current of the remaining motors.
Downloaded from Ktunotes.in
Bus-bar system of a Motor Control Centre (MCC)
•A bus-bar system is an important component of a Motor Control Centre
(MCC), which is used to distribute power to the motor starters and other
electrical equipment within the MCC.
•The design of the bus-bar system must meet certain criteria to ensure safe
and reliable operation of the MCC.
Downloaded from Ktunotes.in
The following are some of the criteria that should be considered in the design of a
bus-bar system for an MCC:
• Current carrying capacity: The bus-bar system must be designed to carry the
maximum current that can be drawn by all the loads connected to it.
• Voltage drop: The voltage drop along the length of the bus-bar should be kept within
allowable limits to ensure proper voltage regulation at the load terminals.
• Short-circuit rating: The bus-bar system must be designed to withstand the
maximum fault current that can occur in the system without damage.
• Mechanical strength: The bus-bar system must be designed to withstand the
mechanical stresses that can occur during installation, operation, and maintenance.
• Insulation coordination: The bus-bar system must be designed to ensure proper
insulation coordination with other components of the MCC, such as the switchgear
and motor starters.
• Maintainability: The bus-bar system must be designed for ease of installation,
inspection, and maintenance.
Downloaded from Ktunotes.in
Designing an Main Switch Boards and SubSwitch Boards with MCC for motor
controls.
The following are the design procedures that need to be considered:
• Load Analysis: Conduct a load analysis to determine the peak demand, power factor, and
the number and sizes of motors required.
• Selection of Main Switchboard (MSB) and Sub Main Distribution Board (SSB): Based on
the load analysis, select the appropriate ratings for the MSB and SSB. The MSB is usually
rated for high current and fault levels, while the SSB is rated for lower current and fault
levels.
• Selection of MCCs: Select MCCs according to the number and size of motors. Each MCC
should be able to handle the maximum current and fault levels of the connected motors.
• Busbar System Design: Design a busbar system that can handle the maximum current and
fault levels, and provide proper voltage regulation at the connected loads.
• Protective Devices Selection: Select protective devices such as circuit breakers, fuses, and
relays to ensure safety and reliability of the system.
• Enclosure Selection: Select an enclosure that can withstand the environmental conditions
and safety requirements of the industry.
• Cable Sizing and Termination: Size the cables according to the maximum demand load,
voltage drop, and short-circuit levels.
• Grounding System: Design and install a grounding system in accordance with local codes
and standards to ensure safety and protection against electrical hazards.
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Short Circuit Study
• The initial current that flows in a power system due to short circuit , will not be
purely sinusoidal in nature.
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Short circuit current
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Fault Level computation & Earthing Design
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Earthing
Earthing means connections of the neutral point of a supply system or the non current
carrying parts of electrical apparatus to the general mass of earth so that if a discharge
occurs it will not cause any danger.
Purpose of earthing
• To ensure that no current carrying conductor rises to a potential with respect to general
mass of earth than its designed insulation
• To avoid electric shock to human beings
• To avoid risk of fire due to earth leakage current through unwanted path.
Downloaded from Ktunotes.in
Resistance of earth
• The resistance of earth should be low enough to cause flow of current to earth
during an earth fault.
• Maximum permissible values of earth resistance in different areas are
Large power station – 0.5 to 1 ohm
Small substation – 2 ohm
In all other cases – maximum 5 ohm
Downloaded from Ktunotes.in
Factors influencing earth resistance
• Condition of soil
• Temperature of soil
• Moisture content of soil
• Size and spacing of earth electrodes
• Depth at which electrode is buried
• Material of conductor
• Quality of coal, dust and charcoal in the earth pit.
Downloaded from Ktunotes.in
Earth electrode and Earthing lead
• Any wire, pipe, rod or metal plate embedded in earth for the purpose of making an
effective connection with earth is known as earth electrode.
• The wire which connects overhead earth wire to the earth electrode is known as
earthing lead.
Downloaded from Ktunotes.in
Methods of earthing
Earthing can be done in many ways. The various methods employed are
(1) Strip or wire earthing
In this type of earthing, a copper strip electrode of cross section not less than
25mmX1.6mm is buried in a horizontal trench of depth not less than .5m. When
using round conductors made of galvanized steel or iron, the cross sectional area
should not be less than 6mm2
. The length of the conductor buried should not be less
than 15m.This type of earthing is used at places which have rocky soil.
Downloaded from Ktunotes.in
(2) Rod Earthing
Rod earthing is similar to pipe earthing. In
this method of earthing a copper rod of
diameter 12.5 mm or 16mm diameter
galvanized steel or a hollow section of
25mm galvanised iron pipe of length not
less than 2.5m is buried vertically
underground. The pipe can be buried
manually or using pneumatic hammer.
This system is suitable for areas which are
sandy .
Downloaded from Ktunotes.in
(3) Plate Earthing
In this type of earthing, a plate made up of
galvanized iron or copper is buried vertically at
a depth not less than 3m from the ground level.
The dimension needed for galvanized iron plate
is 60cmX 60cmX 6.35mm and that for copper
plate is 60cmX 60cmX 3.18mm.The plate is
embedded in alternate layers of coke and salt.
The earth wire is bolted to the earth plate with
the help of a bolt ,nut and washer made of same
material of that plate.
Downloaded from Ktunotes.in
(4) Pipe Earthing
It is the most common type of earthing system. In
this type of earthing system, a perforated pipe
made of galvanized steel/iron of approved length
and diameter is buried vertically. The size of the
pipe used depends on the magnitude of current and
the amount of moisture content in the soil. The
diameter of the pipe is usually 40mm and length
2.75m for normal soil. The amount of soil
moisture determines the length of the pipe.
Downloaded from Ktunotes.in
Substation Earthing
• Substation earthing system has buried horizontal mesh of rods and vertical electrodes
welded to the mesh.
• Before 1960s the design criterion of substation earthing was low earth resistance (below
0.5 ohm for hv installation).
• New criteria for design is that the substation earthing system should have low earth
resistance, low touch potential and low step potential.
• Conventional criteria is in practice for substations and power stations upto and including
220 kV.
Downloaded from Ktunotes.in
The functions of grounding systems or earth mat include:
Ensure safety to personnel in substations against electrical shocks.
Provide the ground connection for connecting the neutrals of star connected
transformer winding to earth ( neutral earthing ).
Discharge the overvoltages from overhead ground wires or the lightning masts to
earth. To provide ground path for surge arresters.
To provide earth connections to structures and other non-current carrying metallic
objects in the sub-station (equipment earthing).
Downloaded from Ktunotes.in
Parts of the Earthing system
• An underground horizontal earth mesh (earth mat or earthing grid)
• Earthing Electrodes or Earthing spikes
• Earthing Risers
• Earthing Connection
An underground horizontal earth mesh is known as earth mat. A number of rods when
joined together through copper conductors constitute an earthing mat .It reduces overall
grounding resistance.
Several identical earth electrodes are driven vertically into the soil and are welded to
the earthing rods of the underground mesh. (Larger the number of earth electrodes ,
lower will be the earth resistance).
Downloaded from Ktunotes.in
• Earthing risers are usually the mild steel rods bent in vertical and horizontal
shapes and welded to the earthing mesh at one end and brought directly up to
equipment or structure foundation.
• Earthing connections are galvanized steel strips or electrolytic copper flats or
strips/ stranded wires/ flexibles. These are employed for final connection between
earthing riser and the points to be grounded.
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
• Step Potential is the potential
developed between the two feet on the
ground of a man or animal when short
circuit occurs.
• Touch potential is a potential which is
developed between living body
touches the faulty structure. When
operating personnel touch an electrical
equipment during short circuit
condition, fault current flows through
the human body.
Downloaded from Ktunotes.in
EARTH MAT DESIGN
• Earthing mats are provided for earthing in substations.
• It consist of horizontally buried earth conductor grid and vertically buried earth
electrodes.
• Earth mat design is based on permissible body current , fault duration and magnitude
when a person becomes a part of accidental earth circuit.
• The design will limit the voltages (step and touch)to a safe level.
• Resistance of earthing system = ρ/4r +ρ/L
ρ – Soil resistivity
r- radius in meters of circle having the same area as that occupied by the earth mat.
L – length of conductor buried in meters
Downloaded from Ktunotes.in
Steps involved in the design are:
• Step 1:Prepare substation layout plan
• Step 2:Determine mat area
• Step 3: Measure site soil resistivity
• Step 4: Determine fault and design current
• Step 5: Determine fault duration
• Step 6: Design conductor size, spacing length, mat resistance.
• Step 7: Mat layout
• Step 8: Mat construction and adjustment if required.
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Calculate number of GI earthing pipe of 100 mm diameter, 3 meter length.
System has fault current 50KA for 1 sec and soil resistivity is 72.44 Ω-Meters.
Downloaded from Ktunotes.in
• Max. allowable current density = 7.57×1000/(√ρt) A/m2
(ESD handbook page
No:34)
• Max. allowable current density = 7.57×1000/(√72.44X1) = 889.419 A/m2
Downloaded from Ktunotes.in
• Surface area of one 100 mm dia. 3 meter long Pipe = 2 x 3.14 x r x L = 2 x 3.14 x 0.05 x3
= 0.942 m2
• Max. current dissipated by one Earthing Pipe = Current Density x Surface area of
electrode
• Max. current dissipated by one earthing pipe = 889.419 x 0.942 = 837.83 A say 838 A
• Number of earthing pipe required = Fault Current / Max. current dissipated by one
earthing pipe.
• Number of earthing pipe required = 50000/838 = 59.66 Say 60 No’s.
• Total number of earthing pipe required = 60 No’s.
Downloaded from Ktunotes.in
• Resistance of earthing pipe (isolated) R = 100xρ /2×3.14×L×(loge
(2L/d)) (ESD
handbook page no:33)
• Resistance of earthing pipe (isolated) R = 100×72.44 /2×3.14×300×(loge
(2×300/10)) = 15.74 Ω/Pipe
• Overall resistance of 60 no of earthing pipe = 15.74/60 = 0.26232 Ω.
Downloaded from Ktunotes.in
• Resistance of earthing pipe (isolated) R = 100xρ /2×3.14×L×(loge
(2L/d)) (ESD
handbook page no:33)
• Resistance of earthing pipe (isolated) R = 100×72.44 /2×3.14×300×(loge
(2×300/10)) = 15.74 Ω/Pipe
• Overall resistance of 60 no of earthing pipe = 15.74/60 = 0.26232 Ω.
Downloaded from Ktunotes.in
Number of transformer substation
Main characteristics to be considered for deciding the number of substations are
▪ Surface area of the industrial building.
▪ Total power demand in comparison with std transformer capacities.
▪ Load distribution.
Normally one substation is preferred in view of supervision, maintenance and control.
Factors that lead to more than one substation are
• A large surface area( > 25000 m2
)
• Power demand greater than 2500 kVA
• Sensitivity to interruption and need to maintain redundancy.
Downloaded from Ktunotes.in
Number of distribution transformers
It depends upon several factors such as
▪ Surface area of the building site
▪ Total installed power capacity
▪ Sensitivity of circuits to power interruptions
▪ Sensitivity of circuits to disturbances
▪ Future expansion
Factors that lead to more than one transformer are
▪ Large connected load( > 1250 kVA):- Even though transformer upto 2000 kVA are available ,it is
preferable to have multiple units of smaller capacity for ease of replacement and lower space.
▪ Large surface area of the building( > 5000m2
):-If the area is large it is better to have more than one
transformer close to the load centers because this reduces the cable cost
▪ Separation of and disturbing loads:- If the load mix includes large volume of sensitive loads (IT loads) and
large motor loads ,it is favorable to have separate transformers.
Downloaded from Ktunotes.in
Selection of transformers
Factors deciding selection of transformers
✔ Maximum demand
✔ Future expansion
✔ Spare capacity
✔ Statutory requirements
✔ Site condition
Downloaded from Ktunotes.in
Standard rated output in kVA
•Standard rating of Distribution Transformers (11/0.433kV) are 50, 63,
80, 100, 160, 200, 250, 315, 400, 500, 630, 800, 1000, 1250, 1600 and
2000 kVA.
Downloaded from Ktunotes.in
Classification of substations
• Substations are classified in different ways such as on the basis of
i) Nature of duties
ii) Service rendered
iii) Operating voltage
iv) Importance
v) Design
Downloaded from Ktunotes.in
• Classification of substations on the basis of nature of duties
1) Step up or primary substations:- These substations are generally associated with generating
stations. Generated voltage is usually stepped up to primary transmission voltage by step up
transformers.
2) Primary Grid substations:-These substations are located at suitable load centers. In these
substations primary transmission voltage is stepped down to different suitable secondary
voltages. These secondary transmission voltages lines are carried over to secondary
substations where the voltage is again stepped down primary distribution voltage.
3) Step down or distribution substations:-These substations are located at load centers where
primary distribution voltages are stepped down to secondary distribution voltage ( 415 / 230
V). These substations feed consumers through distribution network and service line.
Downloaded from Ktunotes.in
•Classification of substations on the basis of service rendered
1) Transformer substations:-Transformers are installed to transform voltage from
one level to other level.
2) Switching substations:- These substations are meant for switching operation of
power lines without transforming voltage. At such substations different
connections are made between various transmission lines.
3) Converting substations:- These substations convert either ac to dc or vice
–versa or converting frequencies.
Downloaded from Ktunotes.in
•Classification of substations on the basis of operating voltage
1) High voltage substations:- Substations involving voltages between 11 kV and 66
kV.
2) Extra high voltage substations: - Involving voltages between 132kV and 400 kV.
3) Ultra high voltage substations:-Operating voltage above 400 kV.
Downloaded from Ktunotes.in
•Classification of substations on the basis of importance
1) Grid substations:-These are substations from where bulk power is transmitted
from one point to another in the grid. These substations are important because
any disturbance may cause failure of the grid.
2) Town substations :- These substation stepped down the voltage at 33/11 kV for
distribution in towns and any failure may result in the failure of supply for the
whole town.
Downloaded from Ktunotes.in
•Classification of substations on the basis of design
1) Indoor substation :- All apparatus are installed in the substation building. Such
substations are usually for a voltage upto 11 kV but can be erected for 33 kV
and 66 kV when the surrounding atmosphere is contaminated.
2) Outdoor substations :- These substation are erected in open areas.
Downloaded from Ktunotes.in
OUTDOOR SUBSTATION
• There are two types of outdoor
substation.
Pole mounted substation:
• They are erected for mounting
distribution transformers of capacity
upto 250 kVA.
• Single pole or H pole and 4 pole
structures with suitable platforms are
used for transformers .
• Gang operating switch (G.O) or Air
Break switch is used for switching ON
and OFF of HT transmission line.
• HT fuse unit is installed for the
protection of HT lines.
Downloaded from Ktunotes.in
Type Capacity
Single Pole Upto 25 kVA
H pole Upto 125 kVA
4 Pole Above 125 kVA
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
SINGLE LINE DIAGRAM OF A POLE MOUNTED DISTRIBUTION
SUBSTATION
Downloaded from Ktunotes.in
• H-pole structure, base channel of 100mmx50mm size
• Erected at a height of 2.44m from ground level
• 11kV Lightning arrestors(3 numbers) are erected at the top .
• 3 and 1/2 core cable is taken from the L.T side of the transformer bushings to L.T Main
Switch.
• To control LT side iron clad low tension switch with fuses are installed.
• Main switch with fuse unit provide the protection of transformer against feeder faults.
• L.T Main Switch is connected to the L.T Distribution Switch.
• L.T cables are selected according to the capacity of the transformer.
• Substation is earthed at two or more places.
Downloaded from Ktunotes.in
Foundation Mounted Outdoor
Substation
• They are built in open and usually
enclosed by a fence for safety.
• Substations for primary and secondary
transmission and for primary
distribution (above 250KVA) are
foundation mounted outdoor type.
Downloaded from Ktunotes.in
ADVANTAGES OF OUTDOOR SUBSTATION
• Fault location is easier.
• Extension of installation is easier.
• Time required for erection is less.
• Cost of switchgear installation is low
DISADVANTAGES OF OUTDOOR SUBSTATIONS
• Supervision is to be done in open air during all kinds of weather.
• Rapid fluctuation in ambient temperature.
• More space is required.
• Protection devices are required to be installed for protection against lighting
surges.
Downloaded from Ktunotes.in
INDOOR SUBSTATION
• All apparatus are installed in the substation building.
• They are usually for voltages upto 11KV.
• Switchgear on the primary side will have oil circuit breaker.
• Secondary side is connected to bus bar and from the busbar various feeders
emerge out.
• Each feeder consist of isolator switch, circuit breaker and measuring instruments.
• Reverse power relay is employed for the protection of feeders.
• For transformer protection Buchholz’s relay is employed.
• Other auxiliary equipments are i) storage batteries ii) fire fighting equipments
such as water buckets, fire extinguishers etc.
Downloaded from Ktunotes.in
Single line diagram of indoor substation
Downloaded from Ktunotes.in
Layout of indoor substation
Downloaded from Ktunotes.in
Consider 20% for future expansion
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Selection of HT Cable
It is based on HT side fault MVA (minimum 150 MVA as per KSEB and normally fault
MVA is taken as 250 MVA)
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
•Selection of LT cable
Based on full load secondary current of the transformer.
3-1/2 core cable ------------- cable is selected from the table taking into
consideration the factor of safety and future load requirements.
Downloaded from Ktunotes.in
•Selection of LT bus bar
Downloaded from Ktunotes.in
•A factory has the following connected load:
•i. Large motor of 150 kW - 1 no.
•ii. Machine shop with 7.5 kW motors - 6 nos.
•iii. Painting booth of 22.5 kW
• iv. 10 kVA welding transformers - 4 nos.
•v. Water pumping station load 15 kW
•vi. Lighting load 5 kW
Select the transformer rating and design an indoor substation including
the schematic diagram showing the details of switchgear and cable sizes.
Assume a diversity factor of 1.2.
Downloaded from Ktunotes.in
Eg-AYFY means Aluminum conductor,PVC
insulated steel strip armored and PVC sheathed
cable
Downloaded from Ktunotes.in
Selection of cables
All cables consist of a low resistance conductor which carries current and insulation
to isolate the conductors from each other and from their surroundings.
The main factors which are to be taken into account for the selection of cables are as
follows:
• The power and voltage rating for which the cables are being used
• Choice of material used in cable
• Conditions of installation at the site
• Current carrying capacity of the cables
• Voltage drop in the cables
• Short circuit capacity of the cables
• Availability of the selected size of the cables.
Downloaded from Ktunotes.in
1) Voltage rating
• Main consideration for cable selection is it must withstand system voltage.
• Design voltages for cables are expressed in the form of U0
/U.
Where U0
-voltage between conductor and earth
U- voltage between conductors
• Power cables manufactured in India are designated as 650/1100V, 1.9/3.3 kV or
6.35/11 kV or 22kV or 33kV.
Downloaded from Ktunotes.in
2) Conditions of installation
Different methods are adopted for laying of cables. Different methods for laying the
cables are listed in the table.
Refer Databook Page No:55
Downloaded from Ktunotes.in
3) Choice of material used in cable
• Copper and Aluminium are best choice of conductors for cables.
• Copper has high conductivity but cost is high.
• Aluminium has low mass density.
• Insulating material used in cables are broadly divided as follows
a) Impregnated paper:-It is derived by chemical treatment of wood pulp. Thickness
of paper used is from 65 to 190 micrometer. Paper is to be protected from
moisture. So metallic sheath are to be provided around it.
Downloaded from Ktunotes.in
b) Synthetic dielectrics:-Different synthetic dielectrics used are Polyvinyl Chloride
(PVC),Polyethylene (PE), Ethylene Propylene Rubber (EPR), Cross-linked polyethylene
(XLPE).
PVC-Economical, easy to process and hardly combustible. But used only for medium
voltage cables upto (6.6 kV),generation of hydrochloride in case of fire, softening at higher
temperature etc.
PE – Excellent electrical characteristics and used for medium and high voltage cables. But
it is combustible, life affected by partial discharge .
EPR-Better long term resistance to aging and electrical properties. But processing is
difficult, cost is more.
XLPE-High mechanical strength, higher continuous operating temperature. But process is
difficult, reduced life.
Downloaded from Ktunotes.in
4) Current carrying capacity of the cables
During service operation, cables suffer electrical losses which appear as heat in the
conductor, insulation and metallic components.
The current rating is dependent on the way the heat is transmitted to the cable
surface and dissipated to surrounding.
Downloaded from Ktunotes.in
5) Short circuit ratings
During short circuit there is sudden inrush of current for a few cycles.
Short circuit rating are derived from the eqn
Isc
= K× A/√ t
K- constant combining temperature limits and properties of conductor materials
A- area of cross section in mm2
Isc
-short circuit current in A
t- time duration of fault in seconds.
Downloaded from Ktunotes.in
6) Voltage drop calculation
• When designing distribution systems ,it is important that the voltage drop from the
point of commencement of supply to the farthest apparatus shall not exceed 3% of
the system voltage.
• Voltage drop is determined by multiplying the complex value of line current by the
complex impedance value.
VD
=IL
× ZC
Downloaded from Ktunotes.in
Calculation of ampacity of cables
•Ampacity refers to the maximum current that a cable can carry safely
without exceeding its rated temperature.
• The ampacity of a cable depends on various factors such as the cable's
size, insulation material, ambient temperature, installation method, and
cable length.
Downloaded from Ktunotes.in
The following steps are to be considered for calculating ampacity:
• Determine the cable's size: The cable size is typically specified by its cross-sectional
area, which is measured in square millimeters (mm²).
• Determine the insulation material: Different insulation materials have different
temperature ratings. Maximum temperature rating of the insulation material used in the
cable should be known for calculating ampacity.
• Determine the ambient temperature: The ambient temperature is the temperature of the
air surrounding the cable. Temperature of the environment where the cable will be
installed should be known.
• Determine the installation method: The ampacity of a cable also depends on the
installation method. For example, the ampacity of a cable installed in conduit will be
different from a cable installed in free air.
• Calculate the derating factor: The derating factor adjusts the ampacity of the cable based
on the installation method and the number of cables installed.
Downloaded from Ktunotes.in
Pre-commissioning tests of 11kV indoor/outdoor substation of an HT
consumer
• Insulation resistance test: This test measures the insulation resistance of the
substation equipment, including the cables, busbars, transformers, and switchgear.
The purpose of this test is to ensure that the insulation is adequate and to detect
any faults that could cause breakdowns.
• High voltage test: This test is used to verify the dielectric strength of the
equipment, and is typically performed by applying a high voltage to the
equipment for a specified period of time.
• Continuity test: This test verifies the continuity of the wiring, connections, and
grounding systems of the substation.
Downloaded from Ktunotes.in
• Transformer testing: This includes checking the insulation, winding resistance, and polarity of
the transformer.Some of the transformer test are i) Transformer Turn Ratio Test ii) Operational
Checks on protection System iii) Winding resistance measurement iv) Magnetic Balance test
v) Temperature Rise Test (Oil And Winding):
• Circuit breaker testing: This includes verifying the operation of the circuit breakers, testing the
trip time, and checking the contact resistance.
• Protective relay testing: This includes verifying the operation of the protective relays, testing the
trip time, and checking the contact resistance.
• Control system testing: This includes verifying the operation of the control system, checking the
wiring and connections, and testing the interlocks.
• Commissioning of the substation: This includes energizing the substation and verifying that it is
operating as designed, with all protection systems and control systems functioning correctly.
Downloaded from Ktunotes.in

More Related Content

PDF
EET402 -M3-Ktunotes.in.pdf NOTES ON ESD.
PPTX
Designing Solar PV Systems ( Utility Scale)
PDF
PDF
Selecting proper dg set
PDF
Gensol - EPC Services
PDF
Raiway applications rolling stock rules for installation of wire harness
PPTX
Wind farm planning and commissioning
PDF
Engineering Final Year Project Report on "Electrical Safety and Protection of...
EET402 -M3-Ktunotes.in.pdf NOTES ON ESD.
Designing Solar PV Systems ( Utility Scale)
Selecting proper dg set
Gensol - EPC Services
Raiway applications rolling stock rules for installation of wire harness
Wind farm planning and commissioning
Engineering Final Year Project Report on "Electrical Safety and Protection of...

Similar to EET402 -M4-Ktunotes.in.pdf ,NOTES ON ESD (20)

PDF
CESC LTD. TRAINING REPORT
PPT
DRIVERS
PPT
Electrical Substations and Switchyard Design
PDF
NTDC 220kV Transmission gird station Internship report
PDF
Itco english catalog (1)
PPT
Energy utility by RL.ppt
PDF
Infrastructure Presentation 000000000000
PDF
EEE-Power System Operation and ControlUNIT WISE NOTES
PDF
Electric vehicle and charging infra by link vue system
PDF
Phase 4
PDF
PT-9018-ConnProvGenSets-en
PPTX
introduction on high voltage engineering
PDF
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
PPT
power grid presentation for upcomming projct
PDF
TECHNICAL SPECIFICATIONS SPy fhytfhjt vdfg
PPTX
USM_Mechanical and Electrical Engineers in Land Development Projects
PPTX
Overview of the (Mechanical, Electrical, AC) departments in the GSM sites.pptx
DOC
PDF
Electrical Machine Design - Transformers, DC Machines
CESC LTD. TRAINING REPORT
DRIVERS
Electrical Substations and Switchyard Design
NTDC 220kV Transmission gird station Internship report
Itco english catalog (1)
Energy utility by RL.ppt
Infrastructure Presentation 000000000000
EEE-Power System Operation and ControlUNIT WISE NOTES
Electric vehicle and charging infra by link vue system
Phase 4
PT-9018-ConnProvGenSets-en
introduction on high voltage engineering
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
power grid presentation for upcomming projct
TECHNICAL SPECIFICATIONS SPy fhytfhjt vdfg
USM_Mechanical and Electrical Engineers in Land Development Projects
Overview of the (Mechanical, Electrical, AC) departments in the GSM sites.pptx
Electrical Machine Design - Transformers, DC Machines
Ad

Recently uploaded (20)

PDF
composite construction of structures.pdf
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
OOP with Java - Java Introduction (Basics)
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
Sustainable Sites - Green Building Construction
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PPT
Project quality management in manufacturing
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
composite construction of structures.pdf
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
OOP with Java - Java Introduction (Basics)
Foundation to blockchain - A guide to Blockchain Tech
Fundamentals of safety and accident prevention -final (1).pptx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
UNIT 4 Total Quality Management .pptx
Safety Seminar civil to be ensured for safe working.
Sustainable Sites - Green Building Construction
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Project quality management in manufacturing
Embodied AI: Ushering in the Next Era of Intelligent Systems
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Model Code of Practice - Construction Work - 21102022 .pdf
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Ad

EET402 -M4-Ktunotes.in.pdf ,NOTES ON ESD

  • 3. Module 4 Industrial Power and Lighting Installations (9 hours): Industrial installations –classifications- Design of electrical distribution systems with main switch board, sub switch boards and distribution boards with ACBs, MCCBs and MCBs as the case may be, for feeding power (mainly motors) and lighting loads of small and medium industries. Selection of armoured power cables (AYFY, A2XFY, YWY) – calculation of ampacity, voltage drop, short circuit withstand capacity etc. Design of MSB & SSB including Motor Control Centre (MCC) for motor controls - selection of bus bars and switchgears. Selection of 11kV indoor and outdoor transformer substations upto 630kVA - selection of switchgears and protective devices –Preparation of schedule of works and bill of quantities (cost estimation excluded). Short circuit calculations and earthing design for the HV and LV sides of an 11 kV substation of capacity up to 630 kVA. Pre-commissioning tests of 11kV indoor/outdoor substation of an HT consumer. Downloaded from Ktunotes.in
  • 4. Industrial Installation Design of industrial installation is more sophisticated. Industrial installation has diverse loads. Main aspects of industrial installation are ✔Easiness of maintenance ✔Fault location ✔Economic considerations ✔Energy conservation Downloaded from Ktunotes.in
  • 5. Classification of Industrial Buildings •For the purpose of evaluating the electrical requirements as per NEC , industries are classified taking into consideration three basic criteria 1) Fire hazard 2) Power consumption 3) Pollution hazard Downloaded from Ktunotes.in
  • 6. 1) Classification based on fire hazard National Building Code classifies the industrial buildings in group G from the safety point of view. • Group G1-Buildings used for low fire hazard industries. These industries have low combustibility and the process/operations are not liable to self propagation of fire and only damage to life and property may arise out of panic, fumes or smoke or fire from an external source. Eg:- cement, glass, rice, soap detergent ,sugar industry etc. Downloaded from Ktunotes.in
  • 7. • Group G2-Buildings of moderate fire hazard Those industries in which the process/operations may give rise a fire which will burn with moderate rapidity and give rise to considerable volume of smoke. These fires will not result in explosion. Eg:-Ship repairing, coir, flour mills, fertiliser plants etc. • Group G3:-Buildings with high fire hazards Those industries in which the process/operations may give rise a fire which will burn with extreme rapidity and give rise to considerable volume of poisonous fumes and lead to explosion. Eg:-alcohol distillery, explosive manufacturing, petrochemicals etc. Downloaded from Ktunotes.in
  • 8. 2) Classification based on power consumption NEC classifies industrial building according to the power requirements as ✔ Light industries(Small) ✔ Average industries(Medium) ✔ Heavy industries(Large) Downloaded from Ktunotes.in
  • 9. Description Average power requirement(kVA) Examples Light industry Upto 50 kVA Garment making, ornament making Average industry Above 50 up to 2000 kVA Furniture, pottery, glass, tobacco,textiles Heavy industry Above 2000 kVA Heavy electrical equipment, steel mills, ship building, chemical plants, paper mills, petrochemicals Downloaded from Ktunotes.in
  • 10. 3) Classification based on Pollution degree Level Pollution degree is a classification according to the amount of dry pollution and condensation present in the environment. Pollution degree1:-No pollution or only dry nonconductive pollution occurs. Pollution degree 2:-Normally nonconductive pollution occurs. Temporary conductive pollution occurs due to condensation. Pollution degree 3:- Conductive pollution or dry nonconductive pollution that becomes conductive due to condensation occurs. Pollution degree 4:-Pollution generates persistent conductivity caused by conductive dust, rain or snow. Downloaded from Ktunotes.in
  • 11. Electrical Installation in small industries • Small industries contain motor in the installation. • Each motor must be controlled by a main switch • A 3 phase motor need a triple pole switch with fuse in each phase and also a starter is required for starting and stopping the motor. • Size of switch fuse unit and starter will depend upon the rating of the motor. • Depending upon rating of the motor ,PVC cables of suitable size are to be used. • For large capacity motors ,3 phase underground cables are used. • Cables are enclosed in a rigid heavy gauge conduit. Downloaded from Ktunotes.in
  • 13. • If there are more number of motors, power to the various machines is distributed from the main switchboard located at a convenient position. • Main switch fuse unit consist of different switch fuse units to control the incoming and outgoing circuits . • The outgoing circuits feed different sub distribution boards which will be placed at various locations. Downloaded from Ktunotes.in
  • 15. Design of Electrical Installation in Small Industries (1) Motor current ✔ When the motor is first connected to the line ,it will draw more current than its rated current. This is called the starting current. ✔ When the motor pick up its speed, it carries full load . ✔ When the motor is overloaded ,the current increases and it will overheat. ✔ Current rating of the cable used for supplying power to the motor is based on full load current of the motor, but the rating of fuse is based on starting current. ✔ The rating of fuse should be greater than twice the rating of cables. Downloaded from Ktunotes.in
  • 16. (2) Deciding the cable size The cable shall have a current carrying capacity of not less than 150 percent of motor full load current. For example For dc motor Downloaded from Ktunotes.in
  • 19. (3) Determination of the size of conduit Size of conduit depends upon three factors: ✔ No. of cables to be installed ✔ Cross sectional area of the cable ✔ The permissible conduit fill The maximum permissible number of cables that can be drawn into conduit is given by the below table. Downloaded from Ktunotes.in
  • 21. (4) Deciding the fuse rating Fuse has to carry starting current safely. Starting current is taken as 1.5 times the full load current. Downloaded from Ktunotes.in
  • 22. (5) Deciding the starter, distribution board and Main switch Specification of distribution board is decided from the number of circuits to be fed from it. Voltage rating of DB is decided by the voltage rating of the circuit and current rating is the highest starting current of the circuit. Current rating of the Main Switch should be equal to the starting current of the motor of highest rating plus the full load current of the remaining motors. Downloaded from Ktunotes.in
  • 23. Bus-bar system of a Motor Control Centre (MCC) •A bus-bar system is an important component of a Motor Control Centre (MCC), which is used to distribute power to the motor starters and other electrical equipment within the MCC. •The design of the bus-bar system must meet certain criteria to ensure safe and reliable operation of the MCC. Downloaded from Ktunotes.in
  • 24. The following are some of the criteria that should be considered in the design of a bus-bar system for an MCC: • Current carrying capacity: The bus-bar system must be designed to carry the maximum current that can be drawn by all the loads connected to it. • Voltage drop: The voltage drop along the length of the bus-bar should be kept within allowable limits to ensure proper voltage regulation at the load terminals. • Short-circuit rating: The bus-bar system must be designed to withstand the maximum fault current that can occur in the system without damage. • Mechanical strength: The bus-bar system must be designed to withstand the mechanical stresses that can occur during installation, operation, and maintenance. • Insulation coordination: The bus-bar system must be designed to ensure proper insulation coordination with other components of the MCC, such as the switchgear and motor starters. • Maintainability: The bus-bar system must be designed for ease of installation, inspection, and maintenance. Downloaded from Ktunotes.in
  • 25. Designing an Main Switch Boards and SubSwitch Boards with MCC for motor controls. The following are the design procedures that need to be considered: • Load Analysis: Conduct a load analysis to determine the peak demand, power factor, and the number and sizes of motors required. • Selection of Main Switchboard (MSB) and Sub Main Distribution Board (SSB): Based on the load analysis, select the appropriate ratings for the MSB and SSB. The MSB is usually rated for high current and fault levels, while the SSB is rated for lower current and fault levels. • Selection of MCCs: Select MCCs according to the number and size of motors. Each MCC should be able to handle the maximum current and fault levels of the connected motors. • Busbar System Design: Design a busbar system that can handle the maximum current and fault levels, and provide proper voltage regulation at the connected loads. • Protective Devices Selection: Select protective devices such as circuit breakers, fuses, and relays to ensure safety and reliability of the system. • Enclosure Selection: Select an enclosure that can withstand the environmental conditions and safety requirements of the industry. • Cable Sizing and Termination: Size the cables according to the maximum demand load, voltage drop, and short-circuit levels. • Grounding System: Design and install a grounding system in accordance with local codes and standards to ensure safety and protection against electrical hazards. Downloaded from Ktunotes.in
  • 32. Short Circuit Study • The initial current that flows in a power system due to short circuit , will not be purely sinusoidal in nature. Downloaded from Ktunotes.in
  • 37. Fault Level computation & Earthing Design Downloaded from Ktunotes.in
  • 41. Earthing Earthing means connections of the neutral point of a supply system or the non current carrying parts of electrical apparatus to the general mass of earth so that if a discharge occurs it will not cause any danger. Purpose of earthing • To ensure that no current carrying conductor rises to a potential with respect to general mass of earth than its designed insulation • To avoid electric shock to human beings • To avoid risk of fire due to earth leakage current through unwanted path. Downloaded from Ktunotes.in
  • 42. Resistance of earth • The resistance of earth should be low enough to cause flow of current to earth during an earth fault. • Maximum permissible values of earth resistance in different areas are Large power station – 0.5 to 1 ohm Small substation – 2 ohm In all other cases – maximum 5 ohm Downloaded from Ktunotes.in
  • 43. Factors influencing earth resistance • Condition of soil • Temperature of soil • Moisture content of soil • Size and spacing of earth electrodes • Depth at which electrode is buried • Material of conductor • Quality of coal, dust and charcoal in the earth pit. Downloaded from Ktunotes.in
  • 44. Earth electrode and Earthing lead • Any wire, pipe, rod or metal plate embedded in earth for the purpose of making an effective connection with earth is known as earth electrode. • The wire which connects overhead earth wire to the earth electrode is known as earthing lead. Downloaded from Ktunotes.in
  • 45. Methods of earthing Earthing can be done in many ways. The various methods employed are (1) Strip or wire earthing In this type of earthing, a copper strip electrode of cross section not less than 25mmX1.6mm is buried in a horizontal trench of depth not less than .5m. When using round conductors made of galvanized steel or iron, the cross sectional area should not be less than 6mm2 . The length of the conductor buried should not be less than 15m.This type of earthing is used at places which have rocky soil. Downloaded from Ktunotes.in
  • 46. (2) Rod Earthing Rod earthing is similar to pipe earthing. In this method of earthing a copper rod of diameter 12.5 mm or 16mm diameter galvanized steel or a hollow section of 25mm galvanised iron pipe of length not less than 2.5m is buried vertically underground. The pipe can be buried manually or using pneumatic hammer. This system is suitable for areas which are sandy . Downloaded from Ktunotes.in
  • 47. (3) Plate Earthing In this type of earthing, a plate made up of galvanized iron or copper is buried vertically at a depth not less than 3m from the ground level. The dimension needed for galvanized iron plate is 60cmX 60cmX 6.35mm and that for copper plate is 60cmX 60cmX 3.18mm.The plate is embedded in alternate layers of coke and salt. The earth wire is bolted to the earth plate with the help of a bolt ,nut and washer made of same material of that plate. Downloaded from Ktunotes.in
  • 48. (4) Pipe Earthing It is the most common type of earthing system. In this type of earthing system, a perforated pipe made of galvanized steel/iron of approved length and diameter is buried vertically. The size of the pipe used depends on the magnitude of current and the amount of moisture content in the soil. The diameter of the pipe is usually 40mm and length 2.75m for normal soil. The amount of soil moisture determines the length of the pipe. Downloaded from Ktunotes.in
  • 49. Substation Earthing • Substation earthing system has buried horizontal mesh of rods and vertical electrodes welded to the mesh. • Before 1960s the design criterion of substation earthing was low earth resistance (below 0.5 ohm for hv installation). • New criteria for design is that the substation earthing system should have low earth resistance, low touch potential and low step potential. • Conventional criteria is in practice for substations and power stations upto and including 220 kV. Downloaded from Ktunotes.in
  • 50. The functions of grounding systems or earth mat include: Ensure safety to personnel in substations against electrical shocks. Provide the ground connection for connecting the neutrals of star connected transformer winding to earth ( neutral earthing ). Discharge the overvoltages from overhead ground wires or the lightning masts to earth. To provide ground path for surge arresters. To provide earth connections to structures and other non-current carrying metallic objects in the sub-station (equipment earthing). Downloaded from Ktunotes.in
  • 51. Parts of the Earthing system • An underground horizontal earth mesh (earth mat or earthing grid) • Earthing Electrodes or Earthing spikes • Earthing Risers • Earthing Connection An underground horizontal earth mesh is known as earth mat. A number of rods when joined together through copper conductors constitute an earthing mat .It reduces overall grounding resistance. Several identical earth electrodes are driven vertically into the soil and are welded to the earthing rods of the underground mesh. (Larger the number of earth electrodes , lower will be the earth resistance). Downloaded from Ktunotes.in
  • 52. • Earthing risers are usually the mild steel rods bent in vertical and horizontal shapes and welded to the earthing mesh at one end and brought directly up to equipment or structure foundation. • Earthing connections are galvanized steel strips or electrolytic copper flats or strips/ stranded wires/ flexibles. These are employed for final connection between earthing riser and the points to be grounded. Downloaded from Ktunotes.in
  • 54. • Step Potential is the potential developed between the two feet on the ground of a man or animal when short circuit occurs. • Touch potential is a potential which is developed between living body touches the faulty structure. When operating personnel touch an electrical equipment during short circuit condition, fault current flows through the human body. Downloaded from Ktunotes.in
  • 55. EARTH MAT DESIGN • Earthing mats are provided for earthing in substations. • It consist of horizontally buried earth conductor grid and vertically buried earth electrodes. • Earth mat design is based on permissible body current , fault duration and magnitude when a person becomes a part of accidental earth circuit. • The design will limit the voltages (step and touch)to a safe level. • Resistance of earthing system = ρ/4r +ρ/L ρ – Soil resistivity r- radius in meters of circle having the same area as that occupied by the earth mat. L – length of conductor buried in meters Downloaded from Ktunotes.in
  • 56. Steps involved in the design are: • Step 1:Prepare substation layout plan • Step 2:Determine mat area • Step 3: Measure site soil resistivity • Step 4: Determine fault and design current • Step 5: Determine fault duration • Step 6: Design conductor size, spacing length, mat resistance. • Step 7: Mat layout • Step 8: Mat construction and adjustment if required. Downloaded from Ktunotes.in
  • 61. Calculate number of GI earthing pipe of 100 mm diameter, 3 meter length. System has fault current 50KA for 1 sec and soil resistivity is 72.44 Ω-Meters. Downloaded from Ktunotes.in
  • 62. • Max. allowable current density = 7.57×1000/(√ρt) A/m2 (ESD handbook page No:34) • Max. allowable current density = 7.57×1000/(√72.44X1) = 889.419 A/m2 Downloaded from Ktunotes.in
  • 63. • Surface area of one 100 mm dia. 3 meter long Pipe = 2 x 3.14 x r x L = 2 x 3.14 x 0.05 x3 = 0.942 m2 • Max. current dissipated by one Earthing Pipe = Current Density x Surface area of electrode • Max. current dissipated by one earthing pipe = 889.419 x 0.942 = 837.83 A say 838 A • Number of earthing pipe required = Fault Current / Max. current dissipated by one earthing pipe. • Number of earthing pipe required = 50000/838 = 59.66 Say 60 No’s. • Total number of earthing pipe required = 60 No’s. Downloaded from Ktunotes.in
  • 64. • Resistance of earthing pipe (isolated) R = 100xρ /2×3.14×L×(loge (2L/d)) (ESD handbook page no:33) • Resistance of earthing pipe (isolated) R = 100×72.44 /2×3.14×300×(loge (2×300/10)) = 15.74 Ω/Pipe • Overall resistance of 60 no of earthing pipe = 15.74/60 = 0.26232 Ω. Downloaded from Ktunotes.in
  • 65. • Resistance of earthing pipe (isolated) R = 100xρ /2×3.14×L×(loge (2L/d)) (ESD handbook page no:33) • Resistance of earthing pipe (isolated) R = 100×72.44 /2×3.14×300×(loge (2×300/10)) = 15.74 Ω/Pipe • Overall resistance of 60 no of earthing pipe = 15.74/60 = 0.26232 Ω. Downloaded from Ktunotes.in
  • 66. Number of transformer substation Main characteristics to be considered for deciding the number of substations are ▪ Surface area of the industrial building. ▪ Total power demand in comparison with std transformer capacities. ▪ Load distribution. Normally one substation is preferred in view of supervision, maintenance and control. Factors that lead to more than one substation are • A large surface area( > 25000 m2 ) • Power demand greater than 2500 kVA • Sensitivity to interruption and need to maintain redundancy. Downloaded from Ktunotes.in
  • 67. Number of distribution transformers It depends upon several factors such as ▪ Surface area of the building site ▪ Total installed power capacity ▪ Sensitivity of circuits to power interruptions ▪ Sensitivity of circuits to disturbances ▪ Future expansion Factors that lead to more than one transformer are ▪ Large connected load( > 1250 kVA):- Even though transformer upto 2000 kVA are available ,it is preferable to have multiple units of smaller capacity for ease of replacement and lower space. ▪ Large surface area of the building( > 5000m2 ):-If the area is large it is better to have more than one transformer close to the load centers because this reduces the cable cost ▪ Separation of and disturbing loads:- If the load mix includes large volume of sensitive loads (IT loads) and large motor loads ,it is favorable to have separate transformers. Downloaded from Ktunotes.in
  • 68. Selection of transformers Factors deciding selection of transformers ✔ Maximum demand ✔ Future expansion ✔ Spare capacity ✔ Statutory requirements ✔ Site condition Downloaded from Ktunotes.in
  • 69. Standard rated output in kVA •Standard rating of Distribution Transformers (11/0.433kV) are 50, 63, 80, 100, 160, 200, 250, 315, 400, 500, 630, 800, 1000, 1250, 1600 and 2000 kVA. Downloaded from Ktunotes.in
  • 70. Classification of substations • Substations are classified in different ways such as on the basis of i) Nature of duties ii) Service rendered iii) Operating voltage iv) Importance v) Design Downloaded from Ktunotes.in
  • 71. • Classification of substations on the basis of nature of duties 1) Step up or primary substations:- These substations are generally associated with generating stations. Generated voltage is usually stepped up to primary transmission voltage by step up transformers. 2) Primary Grid substations:-These substations are located at suitable load centers. In these substations primary transmission voltage is stepped down to different suitable secondary voltages. These secondary transmission voltages lines are carried over to secondary substations where the voltage is again stepped down primary distribution voltage. 3) Step down or distribution substations:-These substations are located at load centers where primary distribution voltages are stepped down to secondary distribution voltage ( 415 / 230 V). These substations feed consumers through distribution network and service line. Downloaded from Ktunotes.in
  • 72. •Classification of substations on the basis of service rendered 1) Transformer substations:-Transformers are installed to transform voltage from one level to other level. 2) Switching substations:- These substations are meant for switching operation of power lines without transforming voltage. At such substations different connections are made between various transmission lines. 3) Converting substations:- These substations convert either ac to dc or vice –versa or converting frequencies. Downloaded from Ktunotes.in
  • 73. •Classification of substations on the basis of operating voltage 1) High voltage substations:- Substations involving voltages between 11 kV and 66 kV. 2) Extra high voltage substations: - Involving voltages between 132kV and 400 kV. 3) Ultra high voltage substations:-Operating voltage above 400 kV. Downloaded from Ktunotes.in
  • 74. •Classification of substations on the basis of importance 1) Grid substations:-These are substations from where bulk power is transmitted from one point to another in the grid. These substations are important because any disturbance may cause failure of the grid. 2) Town substations :- These substation stepped down the voltage at 33/11 kV for distribution in towns and any failure may result in the failure of supply for the whole town. Downloaded from Ktunotes.in
  • 75. •Classification of substations on the basis of design 1) Indoor substation :- All apparatus are installed in the substation building. Such substations are usually for a voltage upto 11 kV but can be erected for 33 kV and 66 kV when the surrounding atmosphere is contaminated. 2) Outdoor substations :- These substation are erected in open areas. Downloaded from Ktunotes.in
  • 76. OUTDOOR SUBSTATION • There are two types of outdoor substation. Pole mounted substation: • They are erected for mounting distribution transformers of capacity upto 250 kVA. • Single pole or H pole and 4 pole structures with suitable platforms are used for transformers . • Gang operating switch (G.O) or Air Break switch is used for switching ON and OFF of HT transmission line. • HT fuse unit is installed for the protection of HT lines. Downloaded from Ktunotes.in
  • 77. Type Capacity Single Pole Upto 25 kVA H pole Upto 125 kVA 4 Pole Above 125 kVA Downloaded from Ktunotes.in
  • 79. SINGLE LINE DIAGRAM OF A POLE MOUNTED DISTRIBUTION SUBSTATION Downloaded from Ktunotes.in
  • 80. • H-pole structure, base channel of 100mmx50mm size • Erected at a height of 2.44m from ground level • 11kV Lightning arrestors(3 numbers) are erected at the top . • 3 and 1/2 core cable is taken from the L.T side of the transformer bushings to L.T Main Switch. • To control LT side iron clad low tension switch with fuses are installed. • Main switch with fuse unit provide the protection of transformer against feeder faults. • L.T Main Switch is connected to the L.T Distribution Switch. • L.T cables are selected according to the capacity of the transformer. • Substation is earthed at two or more places. Downloaded from Ktunotes.in
  • 81. Foundation Mounted Outdoor Substation • They are built in open and usually enclosed by a fence for safety. • Substations for primary and secondary transmission and for primary distribution (above 250KVA) are foundation mounted outdoor type. Downloaded from Ktunotes.in
  • 82. ADVANTAGES OF OUTDOOR SUBSTATION • Fault location is easier. • Extension of installation is easier. • Time required for erection is less. • Cost of switchgear installation is low DISADVANTAGES OF OUTDOOR SUBSTATIONS • Supervision is to be done in open air during all kinds of weather. • Rapid fluctuation in ambient temperature. • More space is required. • Protection devices are required to be installed for protection against lighting surges. Downloaded from Ktunotes.in
  • 83. INDOOR SUBSTATION • All apparatus are installed in the substation building. • They are usually for voltages upto 11KV. • Switchgear on the primary side will have oil circuit breaker. • Secondary side is connected to bus bar and from the busbar various feeders emerge out. • Each feeder consist of isolator switch, circuit breaker and measuring instruments. • Reverse power relay is employed for the protection of feeders. • For transformer protection Buchholz’s relay is employed. • Other auxiliary equipments are i) storage batteries ii) fire fighting equipments such as water buckets, fire extinguishers etc. Downloaded from Ktunotes.in
  • 84. Single line diagram of indoor substation Downloaded from Ktunotes.in
  • 85. Layout of indoor substation Downloaded from Ktunotes.in
  • 86. Consider 20% for future expansion Downloaded from Ktunotes.in
  • 88. Selection of HT Cable It is based on HT side fault MVA (minimum 150 MVA as per KSEB and normally fault MVA is taken as 250 MVA) Downloaded from Ktunotes.in
  • 91. •Selection of LT cable Based on full load secondary current of the transformer. 3-1/2 core cable ------------- cable is selected from the table taking into consideration the factor of safety and future load requirements. Downloaded from Ktunotes.in
  • 92. •Selection of LT bus bar Downloaded from Ktunotes.in
  • 93. •A factory has the following connected load: •i. Large motor of 150 kW - 1 no. •ii. Machine shop with 7.5 kW motors - 6 nos. •iii. Painting booth of 22.5 kW • iv. 10 kVA welding transformers - 4 nos. •v. Water pumping station load 15 kW •vi. Lighting load 5 kW Select the transformer rating and design an indoor substation including the schematic diagram showing the details of switchgear and cable sizes. Assume a diversity factor of 1.2. Downloaded from Ktunotes.in
  • 94. Eg-AYFY means Aluminum conductor,PVC insulated steel strip armored and PVC sheathed cable Downloaded from Ktunotes.in
  • 95. Selection of cables All cables consist of a low resistance conductor which carries current and insulation to isolate the conductors from each other and from their surroundings. The main factors which are to be taken into account for the selection of cables are as follows: • The power and voltage rating for which the cables are being used • Choice of material used in cable • Conditions of installation at the site • Current carrying capacity of the cables • Voltage drop in the cables • Short circuit capacity of the cables • Availability of the selected size of the cables. Downloaded from Ktunotes.in
  • 96. 1) Voltage rating • Main consideration for cable selection is it must withstand system voltage. • Design voltages for cables are expressed in the form of U0 /U. Where U0 -voltage between conductor and earth U- voltage between conductors • Power cables manufactured in India are designated as 650/1100V, 1.9/3.3 kV or 6.35/11 kV or 22kV or 33kV. Downloaded from Ktunotes.in
  • 97. 2) Conditions of installation Different methods are adopted for laying of cables. Different methods for laying the cables are listed in the table. Refer Databook Page No:55 Downloaded from Ktunotes.in
  • 98. 3) Choice of material used in cable • Copper and Aluminium are best choice of conductors for cables. • Copper has high conductivity but cost is high. • Aluminium has low mass density. • Insulating material used in cables are broadly divided as follows a) Impregnated paper:-It is derived by chemical treatment of wood pulp. Thickness of paper used is from 65 to 190 micrometer. Paper is to be protected from moisture. So metallic sheath are to be provided around it. Downloaded from Ktunotes.in
  • 99. b) Synthetic dielectrics:-Different synthetic dielectrics used are Polyvinyl Chloride (PVC),Polyethylene (PE), Ethylene Propylene Rubber (EPR), Cross-linked polyethylene (XLPE). PVC-Economical, easy to process and hardly combustible. But used only for medium voltage cables upto (6.6 kV),generation of hydrochloride in case of fire, softening at higher temperature etc. PE – Excellent electrical characteristics and used for medium and high voltage cables. But it is combustible, life affected by partial discharge . EPR-Better long term resistance to aging and electrical properties. But processing is difficult, cost is more. XLPE-High mechanical strength, higher continuous operating temperature. But process is difficult, reduced life. Downloaded from Ktunotes.in
  • 100. 4) Current carrying capacity of the cables During service operation, cables suffer electrical losses which appear as heat in the conductor, insulation and metallic components. The current rating is dependent on the way the heat is transmitted to the cable surface and dissipated to surrounding. Downloaded from Ktunotes.in
  • 101. 5) Short circuit ratings During short circuit there is sudden inrush of current for a few cycles. Short circuit rating are derived from the eqn Isc = K× A/√ t K- constant combining temperature limits and properties of conductor materials A- area of cross section in mm2 Isc -short circuit current in A t- time duration of fault in seconds. Downloaded from Ktunotes.in
  • 102. 6) Voltage drop calculation • When designing distribution systems ,it is important that the voltage drop from the point of commencement of supply to the farthest apparatus shall not exceed 3% of the system voltage. • Voltage drop is determined by multiplying the complex value of line current by the complex impedance value. VD =IL × ZC Downloaded from Ktunotes.in
  • 103. Calculation of ampacity of cables •Ampacity refers to the maximum current that a cable can carry safely without exceeding its rated temperature. • The ampacity of a cable depends on various factors such as the cable's size, insulation material, ambient temperature, installation method, and cable length. Downloaded from Ktunotes.in
  • 104. The following steps are to be considered for calculating ampacity: • Determine the cable's size: The cable size is typically specified by its cross-sectional area, which is measured in square millimeters (mm²). • Determine the insulation material: Different insulation materials have different temperature ratings. Maximum temperature rating of the insulation material used in the cable should be known for calculating ampacity. • Determine the ambient temperature: The ambient temperature is the temperature of the air surrounding the cable. Temperature of the environment where the cable will be installed should be known. • Determine the installation method: The ampacity of a cable also depends on the installation method. For example, the ampacity of a cable installed in conduit will be different from a cable installed in free air. • Calculate the derating factor: The derating factor adjusts the ampacity of the cable based on the installation method and the number of cables installed. Downloaded from Ktunotes.in
  • 105. Pre-commissioning tests of 11kV indoor/outdoor substation of an HT consumer • Insulation resistance test: This test measures the insulation resistance of the substation equipment, including the cables, busbars, transformers, and switchgear. The purpose of this test is to ensure that the insulation is adequate and to detect any faults that could cause breakdowns. • High voltage test: This test is used to verify the dielectric strength of the equipment, and is typically performed by applying a high voltage to the equipment for a specified period of time. • Continuity test: This test verifies the continuity of the wiring, connections, and grounding systems of the substation. Downloaded from Ktunotes.in
  • 106. • Transformer testing: This includes checking the insulation, winding resistance, and polarity of the transformer.Some of the transformer test are i) Transformer Turn Ratio Test ii) Operational Checks on protection System iii) Winding resistance measurement iv) Magnetic Balance test v) Temperature Rise Test (Oil And Winding): • Circuit breaker testing: This includes verifying the operation of the circuit breakers, testing the trip time, and checking the contact resistance. • Protective relay testing: This includes verifying the operation of the protective relays, testing the trip time, and checking the contact resistance. • Control system testing: This includes verifying the operation of the control system, checking the wiring and connections, and testing the interlocks. • Commissioning of the substation: This includes energizing the substation and verifying that it is operating as designed, with all protection systems and control systems functioning correctly. Downloaded from Ktunotes.in