SlideShare a Scribd company logo
Enginuity 2012




                                           Tutorial
Copyright Virtual Management Simulations
Navigation
Navigate through the presentation by using :-

              buttons to load specific topics
              buttons for movement to specific points
    Demo      buttons for self-paced demonstrations of topics

   Hotspot    hotspots to display further information.




The mouse,         and not the keyboard, should be used at all times.
Contents
            Getting Started        The Task
                                   Timeframe
                                   Forming a Company Strategy

           Making Decisions        Financial Management
                                   Overhead Management
                                   Procurement
                                   Job Progression
                                   Resetting Decisions
                                   Exporting Decisions

   Assessing Performance           Key Performance Indicators
                                   Performance Statistics
                                   Management Consultant’s Report
                                   Analysis Tools

     Industry Information          Industry Information

              Miscellaneous        Exporting Information


Glossary                                                            Exit
Glossary
Finance                             Procurement
Dividend                            Job details
Factors affecting share price       Successful tendering
Company value                       Margin adjusting
Cash account                        Choosing consultant designers
Overdraft limit                     Job risk
Capital base                        Bidding cost
Capital employed
Investments                         Job Progression
                                    Project manager information
Profit definitions
Corporation tax                     Project manager performance
Gearing ratio                       Measured value (turnover)
                                    % of a job completed
                                    Job costs
Overheads
Departmental overhead staff         Labour costs
Idle staff                          Retention
                                    Job completion bonus
                                    Forward workload and margin
Miscellaneous
The job cycle
Client relationships
The Task                                                               Getting Started


The success UK-based construction company, with headquarters possible timeframes.
 A fledgling of the company is determinedmanaged through two in indicators :- been trading for just one
                      The company will be by 10 key performance London, has
   The decisions global made, and mustofdemonstratingrests themanagement to satisfy the high
 The first task facing the new management team is to form ain challenges to overcome, such as client
   Managing the to be business involves the company, a range of hands of the new
   Working in different countriesfate present some particularbusiness strategyskills. management team.
 year.               Turnover
 demands of the company's shareholders, who are keen to Contract Completion their investment. unrest,
   restrictions, global competitors and environmental problemsa (extreme weather conditions, civil
                                                            see quick return on
                     Gross Profit to Turnover ratio
   local labour problems etc).                              Forward Workload
 A new managementOperating Profitto run the company forForward Margin future, making the key
                      team is needed to                      the foreseeable
 Although based in the UK, and subject Turnover ratio and interest rates, expansion into overseas
                                         to UK tax laws
 business decisions Company Value
                     each period/quarter.
 markets, and different continents,and opportunities Managing ThePrice A lotsuch depend upon the
                                                            Share
                                                               Early Years
   However, the potential rewards may be an attractive proposition.
                                                       of operating globally, will as worldwide client base,
                     Capital Employed                       Client Satisfaction
 prevailing economic climate in large-scale contracts, may outweigh the risks.
   niche markets and lucrative the UK, and worldwide.Global Business


                        The competition for jobs comes from a number of simulated companies. Each one has
                        their own unique profile and bidding history, and a careful assessment of the opposition
                        is required to formulate an effective procurement strategy.

                                                                                                                                  Management
                    Corporate level                                                    Operational level
                                                                                                                                 skills required


                Road contract on                                       HQ
                the US Interstate
                                                                   UK Economic
                Highway System

     Understanding the                  Forming company
                                                               Later Years
                                                                     Climate
                                                                                       Energy contract in
                                                                                        the Middle East
                                                                                                     Overcoming
                                                                                                                                  Interpreting reports
                                                                                                                                Measuring performance
                                                                                                                                 Analysing information
                                                                     Making key decisions                                          Solving problems
         industry                           strategy                                                  problems
                                                                                                                               Making effective decisions
                        During the later years the teams compete against each other for work. This creates an
                        even more uncertain and pressurized environment in which the skills and team
                        dynamics formed in the early years are really put to the test.


      UK and worldwide
                                          Satisfy stakeholders
                                                                              Finance                The indicators are all weighted at the
                                                                                                     Changes in economy
                                                                                                          Job delays
                                                                                                     start ofrequirements years to reflect their
                                                                                                       New competitors early
                                                                                                                  the
          OPPORTUNITIES                   Improve asset value
                                             CHALLENGES
      Economic climate                                                       Marketing                                           Building project in
                                       Achieve profitable growth
      Availability of work                                                   Overheads            Changing client
       Rival competitionclient base
         Worldwide                       Increase market share
                                            Global competitors
                                              Manage risk
                                                                            Procurement              variability, and initially sumNew1000
                                                                                                       Personnel issues             to Zealand
                          Keep Clicking Anywhere on the screen to advance
      Client expectations                                                   Construction            Supply chain problems
          Lucrative contracts               Client expectations
                                      Enhance company reputation
            Niche markets      Environmental issues


                                                                                                                                                    Quit
Timeframe                                             Getting Started



Theyour company alreadyCompany at successful periods, known asYears, you may be invited to
 If take control of the been operating for 4 during the Early the History Year, before
 You Company has is one of the most the beginning of period 5. You then manage the company
you take overPhase of management. Later (two trading years). Thismanage the company
 take part number 2, known as the
 through a in the its periods, normally 8 Years. You then have to is known as the Early
 through
 Years. a further number of periods in direct competition with the other top companies
 from the Early Years.
Each period represents one quarter, or 3 months.




          Start of                     Start of                              Start of
          History                      Phase 1                               Phase 2




Period         1        ……………          4      5   ……………………………………….       12      13       ……………………….         18



                     Historical Year              Phase 1: The Early Years        Phase 2: The Later Years




                      Keep Clicking Anywhere on the screen to advance

                                                                                                              Quit
Forming A Company Strategy                                                             Getting Started


Objectivelook at an example of setting key objectivescompanyto be answered, including :-
After a thorough take a there are view questions the need strategy.
In setting the to review, the following and runningthat company the next decisions for
It is very easy objectivesshort-termmany toreviewing are set forby making year :-
We‟ll now
Overall, in reviewing our without looking at thethe original strategy, we have extremely
the current period only, performance against wider picture. Whilst this hit and miss
To build on steady, profitable growth,from 4.7m tofor the(by 10%) through Measurement
well,havelevel ofcompany‟s achievedis especially the Head has been operating foraalong-term
      improve and value of the company relationships.
      aim forthat company existing price. increasing turnover from 28m (based improved the
      ensure the improve overheads,       share client                       5.17m  Office, QHSE and on half of
 What been areas the would we the objectives that year.
We and may given have
approach in all prove successful, it like toa company as effective as formulating
                            growth task of running achieve ?
                                                       unlikely to be                                                    year (the
company profits, and profitable growth, increasing turnover from 28m (based on half of the
departments,steady, making better yearof the company‟s assets.
To aim for are staffed the next use manage with the increasing turnover.
History at 14m) to 42m in sufficiently tothrough increasing prequalification for new work,
 How are weis considered to be in value of the company ?
History), and going to improve the a the company‟s objectives.
strategy for the company, based uponsound position by both the industry and its board of
competitive tendering and 42m in the next yearjobs. strategy in place. However, this would
 Gearing Ratio to 14m) to progressing ongoing through increasing prequalification
ItHistory year of company company without any clearneed to achieve our objectives for new
     is possible at
 What levels the company a a measure of are we likely to
directors.ratio of manage is overhead                                                        Dividend Payments               ?
   work, a very reactive
             competitive tendering and progressing ongoing jobs. In could create untold
requireare we goingunlessapproach to running havebusiness, which the History (periodsand 4) a dividend of
 The gearing
                                                                 the of the shareholders ?
 How liability, and is the lookcash account interests an impact in future periods,
Decisions made in 0 tocurrent period often
 its debt                              the after the                                                               1 to in
problems asofthe value overall value of the companytake controlthe mostthewas paid each 4) to 5.8m, per
To improve going the of the company from had to make cause (at effective the
The status we the the company‟s activities, with to clients ? 5havocthroughuse of increased
 is overdrawn. unforeseen and unconsidered circumstances is (byValue              Company was across
                                                                                             2%
 How are end period 8 to improve relationships 4.7m our5.17mFuture10%) end 8 company valuethe
different areas ofcompany/market when we and increasedIn periodsannum), which kept the shareholders
          By the                                                                          :- Profitability
                                                                                   from 4.7m through to of period
                                                                                                                    period (8%
                                                                                                                  improved
organisation. an annual makingofbetter use of the the original objective. had a Future profitabilityeither way
company‟s resources account was always easily surpassing company‟s Thewhich i.e.,positive affectaffect (forward
   company profits and increase 23%,                                                     assets.
 During the History the cash long-term planning is essential.
          representing                                                                       company‟s no particular on industry
                                                                                  steadily, content
                                                                                  confidence fluctuated significantly would
                                                                                        margin)the share price.and this in periods 5-8,
ThereAn increase was no impact at theachieved throughand has of means :-price in themore company negative affect on
 The are there inis valued on isthat also needThe Headconsidered, and creating a long-termhave
 in credit,company other areasaround 4.7m,
            and many                          company          to be a share havingof 1.35. thanand share price.
                                                                                             on       company,
To ensure that company overheads, not guarantee Head Office,it does give Measurement
A clear, well-considered management will especially the14m(profitable growth), and company the second
                                                                               success, jobsQHSE and company‟s share
                                                                                                             and
strategy is jobthe overhead strategy to generate staffed, at profit fromenable the increase in to was
 Turnover a and efforts thethe MarketingaDepartment the periodically reviewed,company
For example, complex task. Indeed, strategyaround129% ofmayrequired level to manage thecompany‟sthe
                                                                  will have to be butconfidence levelthe cash since
                            company value                    a number Office Department was a the
                                                                                                both positive adequately
                                                                                  helped to increase
           Good generated in of first year was operating                               industry progressedthe
 share price.
the best opportunity tohave sufficiently andcompany anywork toincreasing seen by the comments in the
   departments, company‟s capital base to secure within the confines of the be5beneficial, updividend is
           Utilising the aremay growbeen unattainable for with the tender be turnover.as point, bid
                                 staffed profitably toturnover. Indeed, overstaffingperiod the in of to a it
                                                               manage
                                                                                                                           reserves
                                                                                                     market which:-
                                                                                             In
objectives to a large job in period
prequalify fordate 8 thein business. 5. The
half of the first to
 However, in periods 5 year cash account was
                                                               progress more number as can for the job, and a
                                                                             decide     price, of reasons, such
                                                                                                can
                                                                                             maintained.
operating. profit of 4.4%If the is not set in
To inreturn However, strategy
is submitted infinancingaother activities bid is was made on thejob costsprogresseduntil period 7. If it
           Making effective use of the company‟s assets, such stone, andgood build to beopportunities the Head a better
                                                                 as the gains (lower investmentin regularlythat Report. and
                                                                     identifying needs costs the case of reviewed
                                                                                        Management Consultants yield Office
 A gross thanthebank offers, or investments that can with reducedjob will the additional cost. In this case there
 often improve
           overdraft, period 6. of share price.
                        the company‟s turnover successful, the work not startto 8 shareholder expectation
updated to takeoverheadmarketinto account anin not outweighing other1.5% theturnover wasgrowth
 The base expansionfuture costs continuously changing of 142kIn levels had risen as company performance
 (capital Company‟sadvantage it should
                                periods, of a forecasts was net gain environment. and
                                                              secure
                                                              Department)
                                                                               very accurate,
                                                                                             In periods 6
                                                              were period 11. from of words, anticipated
then runs for five and investments), and thecomplete a operating profitoverstaffing. of a decision on
    After taking
To buildnow examine these areas to see which ones contributed to the increase in company value in the last year.
 gearing ratio fluctuated,improve both a
                  on and which had existing client relationships.
areas have positive affect on the effort in
achieved. not materialised.
whereWe‟ll target marketing company‟s period 5 has had an affect up until period 11, 3% had to be
           to
 negative and                                                                                improved, and a dividend of and
 Increased competition has forced margins to be reduced topaidcompany‟s turnover, were equally
beyondcompany order book looksare taken into account. a forward workload of around
 share price. retention repayments extremely healthy, with
    The if                                                                                     secure work.
                                                              Similarly, the QHSE and Measurement Departments, whose
                                                              staffing is dependent upon the
                                                                                                  to keep them content.

A Client an how did changed, client satisfaction rating hasstaffed. that were the proof
 year later,anticipated profit of against the objectivessteadilyOverall,setaffects of the to enable the
30m, andexpectationswe perform 4.4% of relationships were not strong?enough levels of dividend
                         Overall, the company‟s
                                                and client turnover.risen
                                                              adequately                      each period,
company to bid for work. work in the global met with regard to client relationships. Department as an affect
 The overall value of new objectives have been market fluctuates Head Office had no noticeable
                         that the company‟s                                                      around 400m.
                                                                                             paid would have
In order to decide upon the company‟s objectives, and whatat thebenchmark (last period of as „content‟
                                                                                Looking
                                                                                           can the company‟s share achieved
                                                                                                 be realistically sufficient
 AInvestments improving relationships were established with Office, QHSE and Measurement
        number of                                                                           clients.
                                                              We have succeeded in our objective of maintainingprice, the History,
                                                                                example. The on
over a periodin We‟ll now look at how period to managedBy improve ofperiod 4) the share price the risen quo.
    The company share time, there of we havewas 1.35. to the endanalysis staffing
       Investments of price at the end needs 4 results detailed
                         other concerns had two positive be a :-               inperiod 8,of :- maintainshad status to
                                                              staffing levelsthethe Head just ? was 3 staff could cope with around
                                                                                  relationships
 Summary the original objective Profit
   1.95, and                 Operating was met.                 Departments. 10.9m of turnover per period, or 2.8m per person.
    Procurement
Based onprequalified for jobs, to increase turnover it is essential that and a detailed review of procured.
 The A goodthe information information made an operating profit of 2.1% (before tax & interest). in a number of
      company‟s share returnrose during periods on investments was made, which relationships have factors were company
        Capital Employed the History the company given Since period 5 client was far more than improved
                                                                 above,                                        your :-
                          price of 4.5% per period 5-8, in line with company strategy. The contributory the equivalent
                             In
    Having average capital base
   The the company‟sAnalysis we‟ll1.25%equipment, lookways :-key being utilised (capital employed), through contract
        If environment in which the per period. is operating Turnoverjobs period fluctuated a lot
                                                company at the Prequalification are successfully
 Using the from the bank of around(plant,take a closerbuildings etc) issome of theinfluenced the share price :-during periods 5-8,
                                                                                          per
reports the Financial progression, then there is morethe turnover (measured makingin periodswere was 62.3m. year.
 By using and the market, we must decide businessBy company value) marketingfor adjusted accordingly.
   Dividend had no affectAnalysis, we can deducethe chance the as it stands job management. directing
       return Financial
                              at weaknesses of that upon of thecompany‟s strategy 5-8 the next
                                         now                                areas that
 The strengths andany time. this was improved to periods 5-8 the company bid for 36 of staff,and that it was
        procurement and In periods 5-8
    As we can see from the Performance Statistics, during
                                                                           employing staffing levels
                                                                               and the good
                                                                 4.5%, mainly throughmore a profit. the 46 jobs
  Changes in payments to shareholdersby 0.77% by investing in appropriate would relationshipsectors that appeared to bestaffing
               Company were reduced
                             value had a very positive affect
  Changes in in42m, so Profitability capitalfuture utilised, the cash account,were sufficient,all jobs progressed.
   The likely competitionwell the our target.
                         only 41% of in over base was
WeOverallHistory, 9 (25%). Thethehad a mixed affect.increase the resources into during periods glanceduringthe future. with
   able to, and won
     Dividend build costswe were jobs secured helped
      aimed for                                                          there It level the market before, one now exists e.g.,
                                                                 Whereturnovercompanies e.g., first 5-8, and forHead Office
                                                                                was no appear at investment that
                                                                                                              in PHS
                         Keep Clicking Anywhere on the screen to advance
        In the Forward The profitexcavators to all directly into but this increasedcompany‟s theshare of the total market
                                                                                       to an impressive 92%
                                                                        growing, thesignificantly % company‟s value.
    Changes company value of would have fed sectors, reduced build Cornwall Water on but this can be verified by
       Excavators Plc, suppliers
  Changes in in company future profitability
                                                                  Devon and costs improving
                                                                               levels
                                                                                                                    periods 5-8.
    Changes Gearing had a mixed affect.                                increased significantly during periods 5-8.
                                                                 Where a relationship didthe Performance has been aided by
  The high level of turnover was largely achieved by the impressive order referringplace at the end of the History, improved e.g.,
                                                                                book in to exist before, this Statistics.
    Changes in company new burden (gearing ratio)                with Crawford Petrochemicals UK
  effective identification of debt work by the Marketing Department, and successful procurement for the rise in the share
 Although there were mixed affects, the positive affect of increasing company value accounted during periods 5 to 8. price.
                                                                                                                                 Quit
Financial Management                                    Making Decisions


Financial management involves :-
 Looking after the shareholders‟ interests.
 Trying to increase the value of the company by making the best use of the company‟s assets.
 Monitoring performance in all areas to improve company profitability.




        Financial Decisions   Overdraft Limit
Overhead Management                                                     Making Decisions


Overheads are the non-contract based support services required to enable the company to procure and
and progress work. They consist of :-
 4 key departments; Marketing, Head Office, QHSE and Measurement
 Non-departmental overheads, such as idle labour and idle project managers

                                                                   The Overhead Manager is responsible for :-

                                                                    Setting appropriate staffing levels for each department
                                                                    Directing marketing effort into the 5 market sectors

                                                                   The non-departmental overheads are the responsibility
                                                                   of others, and are related to jobs in progress.




        Marketing Decisions   Other Dept Decisions   Non-Dept Decisions
Procurement                                       Making Decisions


Each period the company is offered a number of jobs for which a bid is invited, identified by the
marketing effort in the last period.




   Bidding Decisions   Margin Adjusting   Successful Tendering
Job Progression                                  Making Decisions


Progressing the jobs secured through procurement involves :-
 Allocating appropriate project managers to oversee the jobs.
 Allocating labour to progress the jobs in line with the company‟s strategy for job completion.




  Project Mgr Decisions   Labour Decisions      Key Points
Resetting Decisions                                                      Making Decisions



Decisions can be reset to their defaults at the beginning of the
period.

The default setting is to reset all the decisions, but it is possible to
select particular decisions.
Exporting Decisions                                                Making Decisions


The Export Decisions scenario.
Bothdecisionsfollowingoption enables back to team 1 theirand when ways category, for
Group 1 are the primary decisions for the period using into number of the the database. exporting to a
Consider themake theircommunicateddecisionsGroupleader,be selected, bycompany database is received by
     groups could be group, containing the entered a own copy of :-
text each
themfile. period it is file created contains the the following changes to the default export options :-
               The text
                        e-mailed to Group 2.
                                  Group 2 make procurement and
               job progression decisions made, in a clear and
 By phone
Group 1 are membersformat. into 2 the company database to the Competition Controller, and must put
A team of 6 responsible for sending groups of 3 members each, and is located in 2 different offices, all
               concise is split  The Procurement and Job Progression decisions are chosen for export; the other
This e-mail
 By group now long team in
the decisions for the copy of the
Each has a number of uses :- their „master‟ copy of to company database.
geographically a has away apart. company databasethework on when making their individual decisions.
                                 boxes are unchecked
              Group 2 can now e-mailwordtext file to Groupis added to the export name to make it very clear which
                                The the „_for_group_2‟ 1 for
Each keeping 2 let of each group
How do Group a its Group of master are highlighted bythe export file
The responsibilitiesdrawbacks :- database. decisionsthe diagram below.
 Foroption has hardcopy theknow what entered.
              entering into 1 decisions are contained in are ?
                                 decisions their
 Where a team is fragmented into smaller groups, it provides an efficient means for individual decisions
 to be communicated back to the teambutton is clicked to createintotext file.
  By phone could be time-consuming
                               The Export leader for entering the the master company database.
 By e-mail requires a lot of typing of decisions
We‟ll look more detail at the second use. itself is a text file, and has the following characteristics :-
                               The export file
However, there is a far more  Its name alwaysmethod and that is to use and the rest can be altered option.
                               user-friendly begins with the competition id, the Export Decisions
                                     It is placed in the folder from where the company database was chosen




                                                      Team




                       Group 1                                                  Group 2
               Responsible for :-            Communicate Decisions ? Responsible for :-
                                                Decisions Made
                                               Database E-Mailed
                Finance                                                 Procurement
                Overheads                                               Job Progression
                       Keep Clicking Anywhere on the screen to advance
                                                                                                                     Quit
Key Performance Indicators                                  Assessing Performance


10 key performance indicators are used to measure the success of the company.




The indicators are weighted according to their variability, totalling a 1,000 at the end of the History.
As time progresses the weighting of each indicator will change, highlighting improvements or
deteriorations in that area, but the overall total will be the measure by which the ultimate progress of
the company is determined.
The weighting for each indicator at the end of a period is based on a comparison with the position at the
end of the History, and there are two types of comparison :-
Trend comparison
Smoothes the calculations over the time the company has been operating. Applies to Turnover, Gross
Profit to Turnover ratio, Operating Profit to Turnover ratio, Capital Employed, Contract Completion and
Client Satisfaction.
Snapshot comparison
Compares the current indicator to the position at the end of the History. Applies to Company Value,
Forward Workload, Forward Margin and Share Price.

        Calculating Performance Indicators
Performance Statistics                                 Assessing Performance


Company Performance Statistics provide a detailed set of statistics relating to all aspects of the
company‟s activities, and can be used to identify strengths and weaknesses, and explain the rise and fall
of particular performance indicators.




          The use of Performance Statistics
Management Consultant‟s Report                                                             Assessing Performance


It cannot many methods available for assessing the performance of the company, is, if used effectively.
There arebe emphasised enough how valuable the Management Consultant‟s Reportsuch as performance
indicators, performance statistics and the report can alsoIn addition the category. has the use of an external
                           The category analysis tools. be filtered
                    Within each report can be filtered by decision area :-by sub
                                                                                 company
management consultant, example, thein detail is now in period 9, the the Construction
                    For whoFIN (Financial)
                              looks company at all areas of and company‟s business, especially where
                             The report can also be filtered by period,
                            and in most cases the previous processed
there may be problems, and OVH (Overheads)one being analysed.project managers during
                    Manager compiles be the performance of all
                            is interested inappropriate report.
                             period will an the
                             PRO (Procurement)
                     the previous period. To achieve this the following filters are used :-
We will now look in more detail at what the report looks like.
                             RUN (Job Progression)
                      Category choice of “RUN”
                      Period choice of 8                          The nature of the comments made is either :-
                      Sub Category choice of “Project Managers”
                                                                    „P‟ if the comment is positive
                                                                    „N‟ if the comment is negative
                     What do the results look like ?
                                                                    „U‟ if the comment is unclassified

                                                                          It is the negativecost per period of the Management
                                                                                       The comments that will need to be
                                                                          addressed as a matter ofReport is shown in the
                                                                                       Consultant‟s urgency.
                                                                                       Industry Information.

                                                                               ----------------------------------------------------------
                                                                               Key Point(s)
                      The Show additional information can be used
                                                  The Construction Manager can The cost of the management consultant
                                                                                clearly see that all the project managers
                      to display more detailed information about the well during period 8.
                                                  performed extremely          cannot be avoided.
                      highlighted comment, if any is present.
                                                    However, there are some areas of concern. The quality of the project
                                                    managers is so high that :-

                                                     Eric Chatterton resigned from job 127 after being headhunted by another
                                                      company.additional information relates to the highlighted the job in period 9.
                                                           The A new project manager will need to be found for
                                                           comment about Eric Chatterton being headhunted.
                                                     There is a danger of Vic Peterson being lured away from job 165 by other
                                                      offers, and a higher bonus may need to be paid to him to try and tempt him

                        Keep Clicking Anywhere on the screen to advance
                                                      to stay with the company.


                                                                                                                                      Quit
Analysis Tools                                            Assessing Performance


Information is available to enable a thorough analysis of the affectis the gateway Displayinginformation about
                                                    The ProcurementOverhead Analysisdetailed joba number of
                                                      The Job Analysis of previous to provides in details :-
                                                                   The Analysis          decisions detailed period
                                         The Financial Analysis provides detailedprovides a detailedthe financialprovides
                                                                                   information about analysis of
key business areas, providing an aid for making effective decisions for company has identified (prequalified for).
                                                      any of the jobs that the the future. each department.
                                                                   information appropriate to
                                                                                         detailed information relevant to
                                         performance  Bidding success byitperiod; operating. This includes :- to see
                                                       of the company since began each job is examined in turn
                                                        why it was won or lost, taking into account thestatus of factors that
                                                                       For the Marketing Department :- various a job.
                                                                                               the current
We‟ll take a brief look at the Analysis Tools available . the bidding, such andprocurementfor all periods
                                                         The information includes :-
                                          Financial performance; by period as graphically restrictions (company of
                                                        affect          Market trend; the past, current and future value
                                          Shareholder information;specific) and price.andand dividend payments
                                              Further analysisand job including shareinformation
                                                        based tools provide historical price location.
                                                          A list of all new work bycan be filtered by status
                                                                         jobs; these sector
                                          InvestmentRivalcompany‟sanalysis;performance; staffing levels, all rival bids
                                              relating toHistory; performance of all investments
                                                           the              relationship with clients,
                                                                        Marketing for all information about the where
                                                        Detailed riskhistory; Detailedjobs won and progressed
                                                                bidding
                                              project managers and consultants.
                                                          date, to retention analysis; for all jobs won and progressed
                                                        toDetailed enable future effort was directed, be refined.
                                                                         marketing bidding strategy to and the value of new
                                                                         work identified.

                                                                        For the Head Office, QHSE and Measurement
                                                                        Departments
                                                                                               On all analysis screens a ?
                                                                         Performance; staffing levels allocated in relation to
                                                                                               Indicates that more detailed
                                                                          the turnover of the company.
                                                                                               information is available about
                                                                                               how a figure was arrived at.
   The R resets filters back to their defaults.




                         Performance (All Periods)
                          Keep Clicking Anywhere on the screen to advance
                         Presents key information in a
                                 The Selected jobs analysis
                         graphical format.
                                 provides a graphical analysis of
                                 the jobs currently being displayed                                                      Quit
Industry Information                                                   Industry Information



             The CountryThe Industry Outlook is given for the UK and Overseas
                             Information Environment parameters define the environment in
                         The Economic describes
             the countrieswhich thefor the foreseeable future.
                            in which company Client
                                            The is operating.
                         economies the country may Information lists the clients with
             be able to identify work.      whom the company are able do work for,
                            Most remaintheand but some can indication of the for the company
                         Knowledge of    fixed, also gives an vary from periodlevel of
                                             economic outlook is vital in order to period, such
                         to as the prevalentstrategy rates. may beand in which markets it
                            decide upon its interest forthat future, needed with the
                                            relationship the
                         wishes to focus its efforts. future in order to be able to bid
                                            client in the
                                            for work with them.




Keep Clicking Anywhere on the screen to advance
Exporting Information                                            Miscellaneous




         Selected information can be exported to CSV format
         for importing into spreadsheets for further analysis.
The Job Cycle                                                 Glossary


Although 6 in was progressedsuccessful bid for its job. stages :-
Work startedjobperiod 8, and timeframe job for whichplanned 10, the job periods, finishing of jobs will
In has beenthe company put inthefrom timeframe periods 8client during prequalification
The companydemonstrated, theajob a new measuredof periods, duration, this time a number interested
As period the is managed identifiedjob completed in in up the3 toand invited3 periods were :-by in period 10.
          7               over      cycle consists the to
parties. The job in the market which can 3 identified, tendered for and progressed (if won).
become availablehad a planned duration ofbe periods.
 Prequalificationjob was period 8 of the timeframe
  Period 1 of the
The progressing job was period 9
 Procurement of jobs can begin in any period, and the jobs can last from 2 to 5 job periods.
  Period 2 of the
 Progression the job was period 10
  Period 3 of
It is important to grasp the concept of the job cycle, and the following example should illustrate this.




                                                      Period 1             Period 3
                                                     of the job           of the job




  Period
                       5          6           7          8        9             10      11         12




                               Identify       Bid            Progress the job
                             (Prequalify) Submitted
                                         (Procurement)




                     Keep Clicking Anywhere on the screen to advance

                                                                                                        Quit
Financial Decisions                                                                                   Glossary


 Key Point(s) 5, andresponsibilitiesfinancial decisionscurrent investments, look opportunity selection of otherthe :- and that
 One of the
 Its period main theInvestments In addition to the to Manager inon the cash account,thatachievedcompany, and or it
  Some additional points to Financial ManagerFinancial FindingDividend there after the be of may go into overdraft, build
                                           All the of the needs Anreview the company are also a andoffers a goodcompanies
                                     note about investments :-                have an affect to
                                                                                   increase investment value can interests through
                                                                                           an is financial structure it the of return,
 company‟s shareholders. in thealready of the made. from the is period.the usingpayments declared thesuccessfully the
    The other company basedthat needthebe overdraftand theselast Themake the best Add new investment option.
                     main responsibility of butbe Financial Managercandue viewedcompany‟s use of out ofCompany‟s not
                                                                                                  to are
 Not only upon any changes core businessbe invested in, cost savings and dividend paymentsector-based workload,account,
 decide is the                     The may UK, toitsin company is procuring be to taxable contracts, and the by cash is
                                                                                          Dividends progressing the comes
                                                                                                                                          the                     assets
 Apart from paying dividend, each period the Financial Managerthe value of the company is if done a company's
                                                     can         bank
                                                                                                         could choose to leave reduced. of the     rest
 account is and increasecompany will report a healthy operating profit, and use ofmoneycompromise has to be reached asare
   to try held inor UK Institution.the Company‟s value.                                         and
    Any increases a reductions in investments affect the cash account, but increase the company‟sassets However, there to
                                                                             Making effective directors and is being moved
                                                                                          possible, and the company‟s shareholders, normally
                                                                                 always board of sinceoften a given to itsvalue.
 financial structure of of the companyaisincreasing the ifwhichofquarterly. Theysuchaccountincentiveproductivelycredit
  between assets, the value           theThis ways ofunchanged, A valuemoneyhopethe cash as by investing in other stock in stable
                                            company great concern number of choicesto earn some interest fromconcerns, which
                                   alternative is not
                                                                              and simply company, desirable. :- is used to own a in other
                                                              unchanged.. the benefit is more available
                                                                                           the from are provide an
 balance in the cashsubject areas,not be construction-related. companies eventhe Industry Information. much growth.
 Hence, the company is may orto   account. UK financial is an overdraft limit, as defined in if they are not experiencing
                                             may but there rates,
   There are limitations shown                                               Using cash to increase the Capital Base and arise that offers
 such as interest and tax,rates. in the Industry Information. onexample, an investment opportunity may support further growth.
                                                                                 For the :-
 However, this wouldinvestment 2 ways of increasing the company‟sdividend paid manipulatingand one which mayeach one
       • Increase in a single There There are also differentthere areoff adependingsavings in size Transport sector, inkey factors
                                   be short-sighted, since eachSelling Thebuild costCapitalthe the of theis we‟llof the which the
                                           are that can be made overdraft rates % of the the size of the concern company‟s assets
                                                                              substantial value through investments, the
                                                                                 period, depending on of to shareholders cash, examine be
                                                                                           other ways upon Base to raise overdraft.
 to improve the
       • The number ofcompany‟s value, involving the transfer ofthe cash active. However,cash account,returns option.the
                            investments by reviewingheld currentonecompanyin funds between the the price :-
                                   in turn                                                      affects the company share investment capital base
                                             that can be the at any investmentif are very account has exceeded Display Details may if be
                                                                               required thatPHS Excavators Plc using the the overdraft limit, or not
                                                                                  time
 and investments.                          When the overdraft limit is exceeded, allis not being fully utilised.tooutweighs the risk of thebelow
                                                                               Capital Base efforts must be made reduce the overdraft to
                                                                                 very good, but the cost-saving benefit
                                                                                           Insufficient dividend will well.
   There is no limitation on the the limit, whichcan be madeUsing cash to invest further in other companiesthe shareholders and
                                            reduction that may involve investment itself not performing verydisappoint who offer a better
                                                                              :- an investment.
                                                                                  to
                                                                               return than can be obtainedprice. the bank, or who may be able to
                                                                                            reduce the share from
 Although these changes don‟t immediately change thecosts the jobs in company, keep the endselling off period with
   Any investment returns changeNot payingof thedividend in theandvalue of the progress, orby the shareholders content,
                                            the value any investments, current period dividend will conversely, of the
                                                                               reduce not on cash account.
                                                                                             Sufficient
 the affects of the changesSelling off part of the capital base amongst others :-
                                            will have been felt, including, change in the
                                                                               investments  no to raise cash. share price.
Capital Base                                Reducing investments                          Ample dividend will make the shareholders very happy,
  --------------------------------------------------------------------------------------------------------------------------------------------
The levelCost Savings Due (turnover) that can be undertakenwe limitedneed to size of at least 300,000 to obtain preferential on
   The Industry InformationTo Investments large company is would by the invest share price.
              of future workload shows that for a
  Key Point(s) could expect build cost the bidding, and the and increase the the company‟s capital base, as shown
   Build
the Capital we the investment changes to yield company‟s value willcan felt obtained from the when cash is potentially an the
 rates, and BaseScreen. affectingsavings of at least 0.9%. level of future work that can be undertaken
      Procurement changes companies
                                                                             Operating Profit
  The well as investing in otherat any time ison the a betterits assets. After payingprofitthe periodconsistthere
   As affects of                                                              return than be be
                                                           measured Returns The affectduring increases the cash :-cost savings
                                                                                                                               bank,
 The value of thechanges yielding returns, and by Generating operating profitprice is determined by the and hence
      Investment Company for investing in other concerns. Investmentincreasing operating dividendthrough buildaccount,  they            of
  account interest is although a minimum of In the last 4and buildof thesavings are share achieved Plc has been consistently so
   even more lucrative reasonand investment returns periods the return fromonand Excavators through good job % ofoverhead
                            calculated,                                                cost company, known.
                                                                             value any single investment in a period cannot exceed 150,000, high,
                                                                                                          PHS is                                        and the
The capital base of 4.5m can support up to 45.5m of is required,Since theAlthough having workload control 30m (the value of work
   Bear in mind that                                      300,000 workload.
                                                                             management.  company‟s equity that is paid is only over these functions,
                                                                                                 current forward no direct as a dividend.
   it would the at objectives Progression Screen), 3.6%costs scopeperiod (14.4% andwork. per annum). shareholders,
                                                          at between              and 4% per
 The long-termleast the Jobin to the Financial Manager stillmay look afteron work in progress theonce the and
   If enough money is invested particular concerns, build is are to investment. more
                                                                                                                           16%
still to bein take bankon 2 periodsof gain any build cost savings from thebefor winning the interests as in specific sectors due
                                                                             which is a liability. There is an overdraft limit the
                                                                                         responsibility of other people, such of
   Cash completed (-200,425)                                              there                                                   However, Overhead
                                                                                                    reduced
   This can either be in credit or in overdraft, when it is considered Cluesto be a reassessment of the size of dividend are base
company‟s procurement decisionsto manipulatein iftherean asphaltassetsthewould reduceManager by themonitor progress
  PHSmake effective materials, have Whether notConstruction Managers, the success, inbuildvalue for any return,
   to Excavators Plcon a good companybeen made, work may needcompany sectors, as the levels of phrase
                                                             e.g., investing company‟sdone to any a improve terms must thecapital
                                                                                                            and across different costs of the company.
 andpreferential Industrydecisionsplant etcto investorthe the both build costinbeenaffects of allindicatedof the cash Transport
                       rates are                                                in is being        as              Financial
   PHS Excavators Plc is anrequired. investment in terms of investment hassavings some commodity and investment using
   defined in an increase is excellent
                  the              Information.
to work being undertaken. The concerns offeringIndustry” in these areassuppliers the company sectors, run as construction
    decide if
  “supplying .... to all sectors of the Construction these benefits must be to further in, wouldwhat is being to in the History, into the
                                                                                          available by examining
                                                                                                              of                happened the
   returns, so wethe clues lyingfunded from which would be worthPlc 5,000,000 shares of value menuupon equity profitably5,000,000.
                        will increase in investment in PHS Excavators investing
 The Company was originally the the company profiles. possible. the Relevantto
   industry. With
                                                                                                     ensure exceed the minimum level required to as
                                                           a share (equity) issue of by 150,000 information 1, with an
                                                                                                                          depend
                                                                                                                                      option.
                                                                                                                                             looking deeper
                                                                                                                                                     value of
   Capital Base (4,546,264)                               prevalent bank rates, both credit and overdraft rates (as defined in the Industry
   obtain thein time, since procurement decisions have not been made, and since there is „unused‟ capital base, we‟ll leave it
                  build cost savings.
At this much would we need to invest to obtain the preferential rates, and what level of build cost saving could we
           point
  How Since period 1 the company has paidInformation) at of equity the investments were made, asand this the kept the of the
   This end ofavailable investmentfollowingdividend of 2%givenequity value at 6,750,000 (5,000,000 level has balance
                                                            information is the time
                                                                                            every period (8% per annum), well as
 At the shareholders content, as we can see from the Consultantsbuildings etc, which determines themore detail.
      For is the company‟s the share in plant, equipment, facilities,:-
unchanged. achieve ? concern, the price stands at 1.35, and thenow----------------------------------------------------------------------------------
            each
  expect to the History                                   cash account. We‟ll            Report. some of these options in x 1.35).
   of work that the company can undertake.                                                Key at
                                                                                           lookPoint(s)
   -------------------------------------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------
       The investment
   Key Point(s) influenced by a number concern.
 The share price 5 we‟lldetails describes the of factors :-
Key Point(s)                                                                              As the share price changes, so does the equity value of the
  We‟ll In period isfurther.
           investigate
   Investments (204,500) base alsothe % returnthis build previouscompany, andbut more has to be invested to obtain the
                                continue to pay dividend at the level.cost savings on offer, paying the same level of dividend in
                                                          ----------------------------------------------------------------------------------------------------------------
   The larger to the capital concern the greater given in
          changes the investment
 AnyThe performance history gives affects the cash account. periods to all investors, and
   The ------------------------------------------------------------------------------------------------------------------------------------------------------------
                                                          Key Point(s)
 If the company‟s cash the company direct it may be which may to consecutive
      savings.any monies investment in may have invested. Financial Manager to raise cash for otherdifferent affect on share price
        details basewhich is under the other concerns, appropriatenotreduce it periods will have a uses, such as further
  Paying dividend, is being underutilised, control of the
            capital                                                                         be construction-related.
           Key Point(s)
    Although the value an overdraft. saving              The size (small, mediumas theon twothe investment concern determinesbuildamount
                                                                                            or large) of equity changes. is a higher level of the cost
                                                                                                       of
  Changes or reducingof build cost changeis displayed, the savings are % thetiers, and there
investmentsin the minimumthe Company
           Shareholder expectations can is not shown. operating performance of as defined in the Industry Information. or
                                                            as the                                           company changes, and may be higher
                                                          that can be invested each period, the concerns, and the
  The future moretheinvested, which
      saving if profitability of current cash
                         is
 There are limitations on the changes toaccount balance, each period, defined in the Industry Information.
      Taking into account the the Company the capital base potential returns from
                                 Keep Clicking Anywhere on the screen to advance
   bank minimum depreciates to This each build cost savings is now make decision about keep them happy.
   The lower thanis currently period for 4,550,339. the level of dividend that needs to be paid to
       The rates on of History level. at will affect
 The capital baseoffer each valueda %the theyear, as shown would based uponathe required level after the financial decisions
           company
  The debt burdenlevel requiredby obtain cash account, we in the Industry Information.
                              the Company
      whether or made, worthdoes not take into account of the available opportunities.
      have been not its and investing any cash in any the returns made from the investments during the period.

                                                                                                                                                                Quit
Overdraft Limit                                                                                   Glossary


      The amount of money that can be borrowed from the bank following example. and the cash
                                                  The warningConsider the is not disappeared, current
                                                                   message has now unlimited. The
      overdraft limit, imposed by the bank depending upon the economic climate, is shown in
                                                  account balance is below the overdraft limit.
      the Industry Information.                                   Its period 8, and after decisions were processed
                                                                  last period the company‟s overdraft has reached
                                                  -----------------------------------------------------------------------------
      What happens if the overdraft limit is exceeded ?
                                                  Key Point(s)    1,375,291. This has exceeded the limit of
                                                   If all possible measures as a result a warning message is
                                                                  750,000, and have been taken, and the cash
      -------------------------------------------------------------------------------------------------------------------------
                                                    account balance still exceeds the overdraft limit, then no
                                                                  displayed.
      Key Point(s)                                  further action needs to be taken, and the user is not
      The „base‟ overdraft limit imposedprevented from normallyto another screen.
                                                     by the bank is movingthe Financial Decisions Screen is
                                                                  As soon as the same for all companies.
      However, it may be reduced even further for a specific company if the message appears.
                                                                  closed a critical warning company‟s current
                                                   The cash account can exceed the overdraft limit when
      share price falls too far relative to the price atThe start of the History. This will be reported in
                                                                   the message informs the Financial Manager
      the Management Consultants Report.            decisions are processed, but during the following taken to
                                                                  that all possible measures need to be period
                                                    all possiblereduce the overdraft totaken to reduce the
                                                                   measures need to be below the limit.
                                                    balance to below the overdraft limit.
                                                                  The Financial Manager decides the best action
                                                                  to take is to reduce some of the company‟s
                                                                  investments.




Keep Clicking Anywhere on the screen to advance

                                                                                                                     Quit
Factors That Affect Share Price                                                                    Glossary


The company‟s share price where a of the keyin period 5.
GearingProfitability example, is one company is performance indicators in measuring the success or
Consider Ratio
Company Value
 Future the following                                                                  Dividend payments
The final factor that affects thecompany fromshare pricegearingaffectincreasing industrytaxable payments the
failure of the value of thewithprice is changes in the in the future profitability (forward margin) of the company, which is
Changes in the company,share a price is the changes signifying the share price. are confidence in declared by a
 Another  factor affecting the share rising period to period also ratio.               Dividends
fortunes a ratiocompany‟s work incompany‟s liabilities (cash account overdraft) priceassets board ofbase industry confidence
Apart from of thedecline during period 1, the share price trend has been an improving one.
The gearing
              small Company.
 based upon the
                    is the ratio of the
                                        progress.                                      company's
                                                                                                   (capital
                                                                                                            directors and given to its
If the company value falls in a period, it will have a depressing effect on share to its as shareholder and and investments, and
                                                                                       shareholders, normally quarterly. They provide
indicates the debtifburden of increases then confidence will improve, and the share price jobs,increase. no forward margin.
falls. Conversely, the value the company. was being established, theregearing ratio is 0. will and hence
                           whilst the company If there are no liabilities, the were no ongoing
 At the end of period 1, detail at why this has been the case.
We‟ll now look in more influenced by :-
The share price is 2 to 4 when some work was secured, forward margin was constantly rising, stock in a very positive
                                                                                       an incentive to own           stable companies
 However, during periods                                                                                     having
If the gearing ratio increases the company will be adverseas being vulnerable to both interest rate notaexperiencing muchservice its
As can be seen the trend has been mixed, with                                          even if they are rises, and its ability to growth.
                                                     viewed affects on share price in periods 1-3, then positive affect during
 affect on the share price, as reflected in comments in the Management Consultants Report.
debts from its future profit flows. Consequently, share price. Comments in the Management Consultants based if the gearing ratio
period 4 which would have helped to boost the this will have a depressing effectDividend payments are Report provide current
                                                                                        on share price. Conversely, upon the further
 The level of dividend paid to the shareholdersfinancially sound, and the share price will increase.
decreases then the company will be viewed as being more
evidence of the affects of the company value changes.                                  share price.
 The value of the company
As can be seen, the cash account was overdrawn during periods 3 and 4, and theThe equity gearing ratio had aany time is the
                                                                               increasing of the company at negative affect
 The future profitabilityslight onecompany no comment in the Management Consultants i.e., the number of shares in
on the share price, albeit a very of the as there is                          overall share value Report.
 The debt burden (gearing ratio) of the company                              circulation multiplied by the current price per
                                                                              share.

                                                                                     There is a level of dividend, measured as a % of
                                                                                     the equity, at which the share price does not
                                                                                     change. Paying more than the „equilibrium‟ level
                                                                                     will cause the share price to rise, but paying less
                                                                                     will be not be well received by the shareholders,
                                                                                     and the price will fall.

                  In Summary                                                       Dividend payments of 2% of equity have been
                  Each of the 4 factors have different levels of impact upon the companyeach period, It may be, for example,
                                                                                   made share price. and the affect has been
                  that the share price rises even though 3 of the factors have negative affects, but the positive affect the level of
                                                                                   “Shareholders are content with of the 4th
                  factor has the greatest impact.                                  dividend paid”, implying no change to the share
                                                                                   price.
                  Careful examination is needed of the company data to determine which factors have had which affects, and
                  to what level. In the previous analysis we have seen that :-     If dividend has had little affect on the share price,
                                                                                   what about other factors ?
                          Keep Clicking Anywhere on the screen to advance
                  During period 1 the share price fall was down to a drop in company value.
                  Even though company value fell further during periods 2 and 3, this was more than offset by a rapidly
                   improving forward profitability, and the share price rose.
                  During period 4 both company value and forward profitability improved, and the share price rose further. Quit
Dividend                                              Glossary


The dividend paid to shareholders each period is one of the key factors that affects the share price of
the company.

The dividend paid is expressed as a % of the equity of the company.

The equity of the company at any time is the overall share value.
                       Equity = number of shares x current share price

The dividend % of equity can be :-
 Insufficient to satisfy the shareholders, which will reduce the share price
 Sufficient to satisfy the shareholders, which will have a no effect on the share price
 More than sufficient to satisfy the shareholders, which increase the share price

The Management Consultants Report gives an indication of how the shareholders felt about the level of
dividend paid in a particular period.
Company Value                                                Glossary


The value of the company at any time is measured by its assets and liabilities, which consist of :-

       Cash in the Bank                       Capital Base                         Investments
  The cash balance can be :-           The company‟s investment in         The company‟s cash
   In credit (an asset)               plant, equipment, buildings         investment in other
   In overdraft (a liability)     +   etc, which determine the        +   concerns, which may not
                                       level of work that the              necessarily be construction-
  There is an overdraft limit.         company can undertake.              related.

The value is increased by :-
 Generating an operating profit through the company‟s activities (into the cash account)
 Good investments

The value is reduced by :-
 Dividend payments to shareholders (from cash account)
 Making an operating loss through the company‟s activities (from cash account)
 Depreciation of the capital base
 Poor investments
Cash Account                                                    Glossary


The company has one UK bank account, known as the cash account, which can be :-
 In credit, when it is considered an asset
 In overdraft, when it is considered a liability

Interest is earned/paid on the cash account balance at the beginning of the period. The prevalent
interest rates each period are defined in the Industry Information.

                                                                           Credit Interest
                                                                           If the cash account is in credit,
                                                                           interest is earned at the
 Overdraft Interest                                                        annual rate shown.
 If the cash account is overdrawn,
 interest is paid at the annual
 rates shown, depending upon the                                            Overdraft Limit
 size of the overdraft..                                                    The cash account can be
                                                                            overdrawn up to the overdraft
                                                                            limit. If this is exceeded steps
                                                                            need to be taken to try and
                                                                            reduce the overdraft.


The cash account is increased by :-
 The company generating an operating profit
 Selling off a % of the capital base
 Selling investments

The cash account is reduced by :-
 The company making an operating loss
 Dividend payments to shareholders
 Increasing the capital base or investments
Gearing Ratio                                                      Glossary



                                                                          Liabilities          Assets
         The gearing ratio is the ratio of the company‟s
         liabilities (cash account overdraft) to its assets
         (capital base and investments), and indicates the
         debt burden of the company.

         If there are no liabilities the gearing ratio is 0.




                                         For period 8 the gearing ratio of 0.051 is the absolute value of :-

                                             Cash Account Balance / (Capital Base + Investment Value)
                                                         -310,719 / (4,433,668 + 1,698,938)



Changes in the gearing ratio have an impact on the company share price :-

 If the gearing ratio increases the company will be viewed as being vulnerable to both interest rate
 rises, and its ability to service its debts from its future profit flows. Consequently, this will have a
 depressing affect on share price.

 Conversely, if the gearing ratio decreases then the company will be viewed as being more financially
 sound, and the share price will increase.
Capital Base                                                             Glossary


The capital base is the company‟s investment in plant, equipment, buildings etc, and determines the level
of work that the company can undertake.

One of the key company performance indicators is capital employed, which measures how well the capital
base is being utilised over a period of time.

Changes to the capital base are the responsibility of the Financial Manager, and the Industry
Information shows factors that affect the capital base.

  Changing
   It can be increased, reducing cash reserves, in order to support further growth. There are limitations on the
    increase possible each period. The Company based Restrictions on the Procurement Screen gives an indication
    of when an increase may be necessary.

   It can be reduced, increasing cash reserves, which may be desirable if money is needed for other things, or it is not
    being fully utilised. There are limitations on the % of the capital base that can be sold off each period.




                                                                      Depreciation
                                                                      Each period the capital base depreciates by a %,
                                                                      reducing the overall value of the company. This
                                                                      occurs at the end of the period.




            Writing Down
            Any increases in the capital base can be used to reduce the
            company‟s tax burden, known as capital writing down.

          Capital Employed
Calculating Capital Employed                                                        Glossary


The company‟speriod 4 the company‟s initial forward workload of the company‟s capitalwas on (plant,healthy at 89 %,
  At the start of capital employed measures how much was 22,072,940. This was based extremely equipment,
                                                For Period 4 the company‟s capital employed base the turnover still
buildings etc) is on the 3 jobs in progress at the start ofthat the capital case was being very effectively utilised.
  to be completed being utilised.               indicating the period.

Not jobs were bid for, and 3 were secured, whichof how was thethat could workload post-bidding to 40,879,480. hinder
  8 utilising the capital base is a wasteBut resources capital employed % determined ?
                                                 took the cumulative forward be directed elsewhere, and can
growth.
   The capital employed measures how much ofThe answer can potential workload (45,748,570), based on the capital period 4.
                                             the company‟s be found by looking at the Procurement Analysis for
   base, was actually being progressed i.e.,
Consider the following example where a company is in period 5, and the financial performance is being
reviewed for /period 4. * 100 = 89 %
  (40,879,480 45,748,570)




                       Keep Clicking Anywhere on the screen to advance

                                                                                                                     Quit
Investments                                                          Glossary


The core business of the company is procuring and progressing contracts, and if done successfully the
company will report a healthy operating profit, and increase the company‟s value.

However, there are alternative ways of increasing the value of the company, such as by investing in other
concerns, which may or may not be construction-related. Such investments can :-
 Offer a better return than can be obtained from the bank.
 Offer a competitive advantage for work in progress (benefits) e.g., investing enough money in a tarmac
  company would reduce build costs for Transport jobs as preferable material rates would be obtained.

Each period a number of new investment opportunities may arise, adding to the list of available
investments, and for each one some key information is given to help in making investment decisions :-
 The investment profile describes the concern.
 The Past Performance gives the % return given in previous periods to all investors, and details any money
  the company invested, and any build cost savings gained.

The Industry Information shows factors that affect investments.
                                                                     Build Cost Savings
                                                                     Depending upon the size of the concern,
Increasing Investments
                                                                     there is a minimum level of investment
The increase in a single
                                                                     required to gain build cost savings, and a
investment each period cannot
                                                                     minimum potential % saving.
exceed a given amount,
depending upon the size of the
investment concern.
                                                                          Number of Investments
                                                                          There is a limit on the number of
                                                                          investments that can be held at
                                                                          any one time.
Profit Definitions                                                     Glossary


Company Gross Profit
In any period, the gross profit of the company is a measure of how profitable the jobs in progress have
been.

                                   Monies IN                                       Monies OUT
                     Measured value across all jobs progressed        retentions held from jobs progressed
Gross Profit =       Retentions repaid from completed jobs       -    costs across all jobs progressed
                     Early completion bonuses




Company Operating Profit
In any period, the operating profit of the company is a measure of the overall profitability of the
company.

                                   Monies IN                                       Monies OUT
 Operating           Gross profit                                     Company overhead costs
                                                                  -
  Profit =           Credit interest (cash account)                   Overdraft interest (cash account)
                                                                       Corporation Tax
Corporation Tax                                                   Glossary


Corporation Tax is a tax on a company's taxable profit, which is defined as :-

                                       Operating Profit Before Interest & Tax

    Taxable Profit =               Gross Profit          -         Overheads       -      Capital Allowances


If the company makes a operating loss before interest and tax no corporation tax is paid, and any capital
allowances are carried forward to future periods.

Capital Allowances are acquired by investing in the company‟s capital base, and are calculated on a
„written down‟ basis; the rate of writing down allowances is given in the Industry Information.




                                                                                The corporation tax rate is shown in
                                                                                the Industry Information.


  Capital writing down rate
  per annum.




         Calculating Corporation Tax
Calculating Corporation Tax                                                              Glossary


Consider the following example where a company is in period 9, and the Financial Details are being
reviewed for period 8.
                                                       For Period 8, using the Financial Analysis, we can see that the
                                                       company‟s Operating Profit before tax & interest was :-

                                                                                        Gross Profit: 752,527
                                                                                           Less
                                                                                           Overheads: 377,865
                                                                                                      -------
                                                              Operating Profit Before Interest & Tax: 374,662


                                                       The Operating Profit Before Interest & Tax was then subject to Corporation
                                                       Tax of 110,207. How was this calculated ?

                                                       We can use the drill-down to investigate further.



     A Corporation tax rate of 30% was levied on the taxable profit of 367,357 to give Corporation Tax of 110,207.

      The tax burden was offset by the Capital Allowances of 7,305.
 The Capital Allowances to be written off is adjusted each period as follows :-
      Capital Allowances are acquired by investing in the company‟s infrastructure (capital base), and are calculated
  Increased/reduced by basis; thein theof writing down allowances is given in the Industry Information.
      on a „written down‟ changes rate company‟s capital base
  Reduced by using up capital allowances that are written off by 25% per annum (6.25% per period)
      We can use the drill-down to see exactly how the 7,305 was determined.
 Capital allowances are not used if an operating loss is made.

 In period 8 an operating profit before interest & tax of 374,662 was made, and as a result capital allowances were used.
 These amounted to 6.25% of 116,882, the amount still to be written off, giving the figure of 7,305.
                        Keep Clicking Anywhere on the screen to advance

                                                                                                                            Quit
Marketing Decisions                                                                                     Glossary


Consider set followingMarketaredirected the The informationto analyse likely marketingand thefor the split of and the size
TheHaving thethe Department workthe firstmarketingThereladder tothe2compositionstaff,period 5,countrythe The %to the
    Marketing staffing level, and a numberon the Relevantforecast of thewinning and not indicated next also looking of
                   The There are Based of toolsstaff effort into currentlyglobal market progressing efforts into job
                        situation. can marketing available about the jobifsectors, trend the contracts.
                          The Trend shows step on the are different
                     Job Size additional be the company‟s Information/Marketing Performance option year. the
               How much new Preferences identified ? will have little affect marketdo of direct theirand showsmarketing
                           Preferences                                         they split in and
Client Relationshipsaccuracy of the forecast depends upon the size of the marketing department.
                    and Prequalification
It‟spreferences, The companymarket sectors identifythethereManager work,5tothethat comeover thestaffingasmay be
Each period the marketing forecastlong-term,workoverheadfor) :-of needsof marketglobal market,job size inlevel for the
Marketing is a theplay When willprequalifyingsizethe(prequalify:- manager decides available upon presently as thatthe periods.
Client relationships company‟s staff subject topreferenceways a of new company marketing the for6. previous period.
     the beginning ofaperiod 5, andindicated newthe country preference takes has prequalified market preference.
                   complexrole Wheregreater inboththat in twomarket that jobs injobs :-priority is strategies shown, with effort
                           area, and identify :- overall is 359m numberwork decide during periodknown
                               in in the the Overhead is new work. the some sectors onto the in
                               setting they to for set
                                             are which
                                                           construction
                           marketbe ablejobdetail thethere effort between the
                                                           availability                to
                                                              being directed into all sectors, and in particular the Building and
Marketing Department,the numberwhich sectorsuponsector to jobsaroundfactors :-but Information/Market Trend option.
prequalification,value of“Target large Leavefor chosenexpectedweTargetandbeare toaboutmarketing effort identificationthe
adopted include :- The overall into ofjobs” thecan is thedecisions by use winRelevantmark untillook to movetodirectedof
    In addition, the which work prequalified market bejobs“is, last be andto forjobs” areperhaps thensectors into the is
                        If andcompanywhere then decidelarge will other assuming bechosen, period 9, was process.
                             By determine jobs is Although the unchanged the 360m thethe procurement direct
                             To value of the Based by staff‟s have large made
                               For example, may the new work andtrysector.
                                              if “Prefer UK then to year, the through directed. the when there
                                                       effort influenced efforts now,
                                                              Commercial are                        into which
 If the relationship is expected tofor example, that increasing the number of sector expands.to 4 has increasedthat wouldas
                  Let us suppose,
                         an improving one,Energy least atin around 25m.period 5, the %may prequalify for a jobisthe market share
                                                                          certain level, the marketing staff
                                          be choice, followed by medium then smallcompany change in each company limited, have
                                              an overall decline ofa the in which there was some new work, the sector was able to
                                                    and at sectormarketing future in that can identify 108m of new work (30% of 359m).
                                                                                       as
                  to 30%. In  By market sectors potentially effort
All jobs belong to one ofprimary Management follows :-in theReport. or Information, so wholesale changes cannot be made
 been unattainable, as shown 5 clientprioritised thatConsultants country job size.
                              the jobs is means as :-sectors the company
                                practice this
                                     in the                   into
 Targeting a variety jobsBy in a particular sector(s)
                               of sectors to Show overseas) forto maximum base of jobsoverall market with 2 marketing staff.
     If the company are experts location(UK or choice.
                                 as the secondary no preference a Industry of 23% of the identified. Although this may
                                                                 defined
                                                    widen prequalify
                                                              the country and client
 IfIndustrial Taking the Building & one, then procured, enabling clientcompany to all sectors for 39%foreseeable future,
     The relationship with contract clients work there oneappearsThe changecompanyinmakesjobs where there marketingless
                         In terms 1.Large the
                                     of where
                                                 can be is, in is a period. the the will
                                                                 there              to be new contracts
                         a deteriorating Commerical sector as an example, the isnot at the expense reviewing marketingthe
     the relationship is with the Energy market in                        chance
                                                                                                                                     the that as well
                                                                                                    limitation have it imperative of the may as the
 increase the choice of jobs thatUK jobs particular picking up during period 8allow findallocatedthe regardlesssector. effort                              be
being put into theCommercial
    Building and particular job                                                                        considered when to achieve this of work
                                                                                                                   prequalification, Transport
                                                                                                                                of
                                                                 short-term, the long-term work in the sector (39% of 108m). more strategy.
                            Ifthe 2. sector. may alsoThe company‟s strategyof building long term relationships with
                                 “Target This should enable them to identify 42m for steady growth, and
                                        Medium UK jobs reduce the chance is of
                                            medium jobs” is chosen then medium
                                --------------------------------------------------------------------------------------------------
   rival competition to this sector. it
                  effort for         work,
    Transport
     We‟ll now look at each one3.Point(s) jobs will needlarge and small jobswe will need to increase the staffing level by the
                                Keyin turn.primary choice, with to be identified, so
 particular clients, which may be vital in securing work if economic conditions deteriorate.
                              jobs areSmall UK
                                         the
 Energy                      given4.Large overseasasmaximumessential 2 (the limit is only is in the Industry Information).
                                Analysing weighting jobs secondary choice.
                                      equal the market inthe    detail is allowed, because not shown the
                  -----------------------------------------------------------------------------------------------------------------------------------------------------
                                marketing effort to be directed by sector, but within each sector choices
                                     5.Medium overseas jobs
 Water and Sewage can6.Small overseas jobs isjobthenof work to look to build long term relationships with
                  Key Point(s)
 Targeting a The above “Target small jobs” thechosen lot small jobs is enough new work in the sectors where the
                   particular sector where there a size preference.
                            If analysis is based on is and
                                      be made by country assumption that there are
                                                              ------------------------------------------------------------------------------------------------------
   specific clients, andthe primarytargetdirected. by medium then large here in putting all „your eggs in one basket‟
                               perhaps been particularPoint(s)
                  marketing effort has       choice, followed sized jobs. The risk
                                                              Key
   is that there may bejobs as the secondary choice. work. large the marketing size is, and how well the marketing effort
                                more competition for the      No matter how
The value and number of jobs that the company can prequalify for in any able to identify 100% ofby amarket.
                                                              is directed, the company will never be period is governed the number
of The company mayFor now the company has no particular job size
 factors :-                 look to find „niche‟ markets, in which there is less competition for work, which could
                            preference.
   The size of the Marketing Department (number of company staff)
 improve future procurement success.
 The size of the global market (value and number of jobs available)
                        -----------------------------------------------------------------------
 Where the marketing effort is directed (5 potential sectors of work)
                        Key Point(s)
 Whether or not the company are experts an a particular sector the future success of the company,
Whatever marketing Depending uponmade have in important bearing on
                        decisions are where the marketing has been
 The relationship with contract clients composition of to the demise of the business.
since failing to identify any new work and the
                        directed by sector, can ultimately lead the work
                               available, it may be that no jobs can be identified in a Sector
                                                                         Experts from
                               the primary choice, and secondary choice jobscompany‟s average marketing effort in a sector
                                                                         If the are
                               indentified instead.                      exceeds a particular %, then the company are deemed
                                          Number                     Where
           Size of                                                                                                       Value of
                                             of                    marketing experts in the sector, and will prequalify for more
                                                                         to be                  Other
           global                                                                                                      new work
                                         marketing                  effort is in the sector than anticipated.
                                                                         work                  factors
           market                                                                                                       identified
                                            staff                   directed
                                                                         The Marketing effort (by sector) indicates period by
                                                                         period in green the sectors in which the company is
                                Keep Clicking Anywhere on the screen to advance
                                                                         considered an expert.

                                                                                                                                                              Quit
Other Overhead Department Decisions                                                                Glossary


We now the theseStatisticsQHSE and mindor not overhead the company‟s staffing level applies :- Head Office,
Consider seenfollowing 3 staff canwhether 10.9mstaffingof staffing levelsdetermined QHSEto all manner,
The haveknowlevelsthe situation. perform tasks related to3.6m per the Head Office,ifin the same3is expected
     staffing that the setting the appropriate of turnover. for setting the jobs in progress and
     staff in that departments handle the benchmark levels in Head Office person, the turnover
     Performance for the show in Measurement Departments are were sufficient in the
                                             Understaffing principal
                                                            The
                               Bearing On the JobOverstaffing screen, and assuming appropriate labour allocations have
based uponMeasurement departments.using anticipatedtheand staffing levels= benchmark, can4. 5 staff , since
Measurement Departments relies on and the turnover required we‟ll concentrate on rounded up to Department.
QHSE and benchmark staffing levels                    Progression
                                                                 turnover levels.
                                                            departments, so is            during period
                                                                                                the Head Office
To the this staffing level is sufficientthe numberto staffof needs (16.9 / thethe 4.7, the staffing levels for
It‟ssee ifOffice staff deal with buying, Overhead Manager issues to decideperiod isbenchmarkhave serious
 Head beginning of period 5,to be 16.9m, Understaffing of IT theturnoveranticipated turnover thisfollows :-
                                 and the accountinganticipated departments, above the calculated as period.
                                        been we need of determine the below upon
                                               made, the and departments, for 3.6)
                                                     Overstaffing                                           staffing levels,
                               fractions of staff is not allowed. costswe currently havenamely value, and the benefits can
                                             affectscan reducejobs being progressed, 3 staff,:- company staff and no
                                                      across allperiod and increase measured all
Having performed the necessary calculations an extra
the Head Office, QHSE and Measurement Departments.          This 1.1 staff are required in each department, rounded
To do thiswhat deal with we get our(Total safety agency the additionalperiod) costs, but only up to
 QHSE staff happens ifquality, health &labour on and*theand staffing issueslevels are lower a point.
However, we need to refer to the decisions made Benchmark the staffing Screen.
                                         calculations wrong, Job Progression
                                                             on environmental
up to 2 people to prevent any Since there are currently siteanvalue perstaff employed at the moment, an extra 2 people
                               shortfall.  Head Office,Headstaff. in job costs (build costs)
                                                     far outweigh          man staffing
(understaffing) or higher than the benchmark (overstaffing) setting is 100%be the required levelthe company‟s
                                                            3     increase?
                                                                    Office
 Measurement staff (quantity surveyors) ensureincrease in jobindicates andandfacilitateall 3manage allocated. :-
                               need to be recruited toan:- that money costs3(build will from the client twowas
                                        This   QHSE, cover the slight is if staff staffingcosts) there are
                                                            How do we know recovered of
                                                             The benchmark
                                             equates toexample shownshortfall, that to riskable this departments choices
                                                     The                                        in
                                                                                                    to
                                                         turnover this period ?
                                      Job  19: more 9 staff, bearing=inmeasured value (turnover)is not number of
                                             Measurement, a reduction in 0.6m
                               Employ more company‟s x sufficient i.e., well above there is a limit on the impaired. new
                                                    ( than 68,475) to mind that the 100% benchmark level.
                                                          This is sufficient ensure that performance
                               company staff that can75 answer this question we must first in the Industry Information (3
                                      Job 39: ( be employed each period, as defined assess the level of turnover
                                                         To x 51,436) = 3.9m
The task of the Overhead Manager is Office). Newthat eachmay alsocan support,eachto dotraining costs, tothe first the
                               for Head to ensure company staff haveincur a recruitment & this we costbut their to is
                                      Job Understaffing is a 45,608) of incurred higher overhead costs, each period
                                            42: The 92 x the level = staff in reduce overhead need but can
                                                         that false economy. It might and department in refer
                                                    ( company person 4.2m
                                          significantly reduce job profits, resulting in reduced operating profits for the
able to manage the company‟s jobs inJob company. Head 24,862) (reduced costs and increased value) is reflected
                               period. progress (125 x office, QHSE3.1m Measurement performance option.jobs.
                                                     without any deterioration in the performance of the
                                            71: increase in job profit = and
                                      Job 74: in( 67 x 59,758) = 4.0m
                                                     the overall net affect.
                               Employ agency staff 23 the 49,151) = 1.1m Agency staff attract a higher salary than
                                      Job 76: ( for x current period only.
                               company staff. example shown Total: 16.9m
                                          The ---------------------------------------------------------------------------
                                                                   indicates that staffing in all 3 departments was insufficient
We‟ll now look at an example of how to set the appropriate staffing levels. next year, its more cost-effective in
                                          i.e., below the 100% benchmark level.
                              Since the companyKey Point(s) increase turnover in the
                                                   is looking to
                              the long run to increase the company‟s own staffup to a than use agency staff, so we‟ll
                                                  Overstaffing is only beneficial rather certain point, but the “optimum”
                                          The company overstaffing has to overhead costs, but the reduction in job profit
                                                  level of may have saved on within the limitations for new staff.
                              employ an additional 2 company staff, which isbe determined through experience.
                                          (increased costs and reduced value) is reflected in the overall net affect.




                                                          Period 4, the last period of the History, set the benchmark
                                                          staffing/turnover level i.e., the number of staff required to
                                                          support the level of turnover without impairing performance.

                                                       We can see that 3 staff can cope with 10.9m of turnover, or
                                                       3.6m per person. This is the benchmark for all future
                                 The value per man period is shown on the Job
                                                       staffing levels for the Head Office Department.
                                 Details (Procurement Tab), and is defined as :-
                        Keep Clicking Anywhere on the screen to advance
                                 (bid submitted during tendering / total man periods)
                                                                                                                          Quit
Non-Departmental Overhead Decisions                                                                                 Glossary


As well as the departmental overheads, there are also non-departmental overheads :-
 Idle Labour Pool (Job Progression Screen) Screen)
  Idle Project Manager Pool (Job Progression                             Bidding Cost (Procurement Screen)
                                                                            Management Consultants Report
 The company‟s own site-based the company are are
 Idle project managersby labourers whowho not not currentlyEach period anjob
 Project managers employed (Job Progression Screen) Each job that the company bids for incursconsultant carries out
                                                             allocated to a external management a
 currently allocated to in the Idle Project Manager Pool.
  in progress are held job in progress are held in the Idle                         a detailed review of the company‟s activities, looking in
                                                                                bidding cost, depending upon the job size, defined
 Idle labour pool (Job Progression Screen)
 Labour Pool.                                                                   in the Industry Information. areas.
                                                                                    particular for any problem
  They can be placed there if :-
 Bidding cost (Procurement Screen) idle pool,
 Idle labourers incur a cost whilst they are in the                                 The review is in the form of a report, and this has to be paid
   it makes just finished, and the project to appropriate
 soA job has sense to either allocate themmanager is placed in the poolthe cost being defined in the Industry Information.
                                                                                    for, until the
 company decides what to doreview responsibility of the
    External performance with him.
 contracts or pay them off, which is the
   The project Manager.
 Constructionmanager has been recruited from the market for use on a future
                                                                                                             The cost per annum of keeping
    contract, and the company does not want to risk losing them to a rival.
We‟ll take a brief look at each one.
 ------------------------------------------------------------------------------                              one idle labourer is shown in the
 Key Point                                                                                                   Industry Information.
  Project managers must be paid their salary and benefits package whilst they are in
 Sometimes a decision a wastedto deliberately keep
  the idle pool, which is is made cost, and it is important to try and allocate them to
 excess labour in the idle pool. Thisresponsibility of the Personnel Manager.
  appropriate contracts, which is the may happen if the
 company is expecting to win a labour-intensive job, and its
 cheaper to pay them for being idle in the short-term, rather
 than incur potentially higher costs for laying off and then
 retraining new staff in the future.




                            Keep Clicking Anywhere on the screen to advance
                                                                                                                                             Quit
Overhead Staff                                           Glossary


Overheads are the non-contract based support services required to enable the company to procure and
progress work, and consist of :-

 4 key departments; Marketing, Head Office, QHSE and Measurement
 Non-departmental overheads, such as idle labour and idle project managers

The staff in each of the key departments can be either :-
 The company‟s own staff
 Agency staff (except the Marketing Department)

and are subject to costs and limitations shown in the Industry Information :-
                                                                            Staffing Limitations
                                                                            There is a cap on the number of
                                                                            new company staff that can be
                                                                            employed in a period.




 Costs (per person)
  Both company and agency staff incur an annual salary, which
  is higher for agency staff.
  For new company staff only, there is a recruitment/training and
  payoff expressed as a % of the annual salary.
Idle Staff                                                           Glossary




Idle Project Manager Pool                                     Idle Labour Pool
Contains the company‟s project managers who are currently     Contains the company‟s own fully-trained operatives who are
not allocated to a job.                                       not currently allocated to a job.

Project managers can reside in the pool for a number of       Labour can reside in the pool for a number of reasons :-
  reasons :-
                                                               They may have been deliberately transferred there by the
 They may have been deliberately recruited by the              construction manager, and not reallocated to site.
  personnel manager prior to being used on site, perhaps to    Own labour is automatically transferred to the pool upon
  prevent other companies from employing them (Later            completion of a job.
  Years).
 Project Managers are automatically transferred to the       It is always more cost-effective to keep the idle labour pool
  pool upon completion of a job.                              as low as possible, using the company‟s own fully-trained
                                                              staff on contracts that are in progress.
Procurement Decisions                                                                                       Glossary


LetsDisplay Jobarein strictto bid for jobs that were identified A consultantPackage anHow „Yes‟tolastincurred bid ?
 Theappropriatethat the Company canorder. to by reviewing the profiles ofHavingBuild job.Select is thedesignperiod.a in
 An iscompany that the job number be found bid for job accurate the Marketing be appropriateto bid formulated
  It assume consultant the job decides
  TheRecruitmentDetails forestimators have produced an 101,and Benefits consultant,Departmentproduce the design.
   Bids are processed able
           assumed Costs                                                                       a by assessment of the matching the consultant‟s
                                                                                                  Design & needs to and costs to be consultant,
                                                                                                         each selected            allocated         indicate that
           Element job sector. with planned labour levels for each period of the(+ or -) durationDesign job.
                                                Description
  completing eachto are rival bidders cost of recruiting Details
                  to mark-ups along
                      the job,
  The bid has now been set for job 101.                                             Salary
 experience ofusedInformation shows thelikely to apply ? a project about specific project managerbe submitted. of the price.                Build
                                                                                                                              planned to establish benefits
   As The Industryearlier all bids entered are processed in strict job numberthe bid option Only
         discussed
 option can be
   What level                                                                                           use the Set
                                                                                                                         order.to details (salary, the bid
                                                                                                                                is
 display detailed period whetherandnot we have historythroughout for.The can be found on the Job Progression& only. where
  There bidders types thejob, orthatbe spread out ofjob. package etc) Allocate from show medium-sized bids Build to
   If Rival arenext world‟ ofto all project bidding won the can bid company is filtered to available list option can be used
         were is atwo
               the medium-sized jobs the the company each rival
      it manager,„real applies bids would managers.
  We‟ll 101
   Job know          which                                                                                                                                Screen,
 information about thecompanyimpact onof the may be andby rival are automaticallyof about thosedesignsup and cannot
 The the determining the mark-up, the level that estimated design costs. „Good‟be found all available the bid, tosaveProject
   the choice of consultant can being able of adjust margins costs bidders needs a list considered in signed that the on the
  At Design Cost                                         to producing the information can also consultants produce consultants.
      When procurement stage some both the build set design. choose from to be included very carefully.
   Bidsloweston the charge base, of Costdesign. The of level of and at the time high Agency. +could by x
         period, with the job.
 buildBasedbut theyannual salary set52,000 aMoss Plc at 4.4%.on-cost,in build costa bid is be achieved make the client best
   The cost, awarded are the competitive tendering, saving setting too that can submitted toallocating the
           are similar through success failure maximum                                                                                          the bid 
  be altered.depending upon theincluding or„sensible‟ previousthe
   dynamically a Thesecost more for the
      Assuming jobs
  Build Onlymark-up previously :- was byalready determined,Manager Recruitment a mark-up
  -------------------------------------------------------------------------------------------------------------------
 possible consultant forawardedgiven in theaIndustryof winning the7,800.
   success in beingis the job theto be 15%consultant allocatedjob. produce the
   submissions. cost not give is company ofchance Information. a number of factors :-
      uncompetitive, and expected the contractannual salary, or to
  Thepoint Design
          contractor is only                    Design the depends upon
  Key recruitmentConsultantresponsible for the build.                                                                            +             x             
   We‟ll set a mark-up cost for eachdesign.
  The company incur aof 4.2% to hopefully be the most competitive on price. of theforjob 101 is a UK-based energy contract the
                                                                    depending upon the in mind that
                                                                                    Bearing size
   Fortunatelycostis rival bidders depends upon the
      Design of
  The naturethis thesimulated by margin adjusting, timeframe :- to is narrowed down using the search filter to find the salary
                                                 bid submitted, allowance can now be entered job.
                                                              The
  The costs are defined in the Industry Information. which needs set as follows :-  search
 For the101, an once all contract, have work, this would already have been commissioned by be over many who would
   considered Energy the bids Wilson Chartered Architectsin the build (labour, tomay have to the client, years project
  IfBuildjob Cost
   be jobBuild entailed any design been finalised.involvedand benefits chosen due their expertise paid for the best in the
               cost
                                                                                                                                 +
                                                              the project manager,
   Procurement restrictions Costs directly solutions.
                                                                                       have been package that
                                                                                                                                                            
   -----------------------------------------------------------------------------------------------------------------------------------------------------------------------
  Site cost their innovativeplant, designer.
  havepoint(s) years, own consultantmaterials etc). managers in the Each one sector.
   Key engaged
 Energy sector, and theirthe competition comes from fictional rival companies,UK energyhas their own unique profile
        In the early                             approach to design
  Marginbiddingmark-upand bycareful separate demonstration. upon the39,000 the appropriate level of margin.
       and adjusting is discussed in bidders does of them is Salary: determine only the job size i.e., for a medium-sized
 -------------------------------------------------------------------------------------------------------------------------------------------------------------------------
    The level of history, set a rivala assessment not depend                     required to job sector,
  Company based
 Key Point the mark-up that cannot the changedBenefits services and 8,658Vic Peterson fits the bill, and will be used as the
                                                                                package: site costs.
                                                                                                                                 +
 Design & Buildcosts strategy is Supportacross the sectors.On investigation to
     contract Cost jobs
     The Site
 The remaining elements :- be same Recruitment costs: 7,800
           estimated                                          staffall design, build required
                                                                 are and                                                                                    
 TheCan of available consultants changes each period due to some consultants beingcompetition, as shown certainty 101 has a
      list the company‟s capitaladminister a the other „human‟build is the unavailable, with less in that job
                                                 base support additional workload ? the
   In the later years the competition comes from site whilst thefor setting in allowance. Bearing in mind the status column
                                                                                     basis teams build. This involves more effort during
                                                                                                        in
 e.g., too much workload. responsibility hence on thethe mark-up becomes far harder. this situationcompany canthe benefits
 The contractorbidding strategies, and for both the design and55,458
                            has                                                     Total: the
  Some companies may have just joined the market, and not have aduration progress thatallowance for salary and only
       Have the company reached the limit setting number of jobs in history. In the the their profile is support
       about Cost (D&B jobs only) progress.
    Designpossible                                                                  planned bidding of 3 periods
 guide to their likely mark-upbut a % profit from the design element afollows.
 the procurement expressed as the of the build cost. It is based upon using can make the jobs more attractive to
      On-cost cost is stage, settings.
     The design time ?
       at any one
 Risk cont…                                                                          package is set as reasonable consultant designer, and if a
 secure. Manageran assessment of the potential risks that coulda mechanism job causing monetary lossesthisthe
      Mark-up made„Delays been allocated, the on-cost provides occur on the for adjusting the bid to take to into
           On-cost risk Costs
 potentially better one hasobtaining Local Authority consent‟ :-
        Projectsavings due to the quality of the design
 The the potential
 For estimators
 Build-cost
 The on-cost we‟llwill reduce allowance added there isto untilSalaryhas design, and we
    good consultant see later.
     account, as job
 company,Projectdelays, andthe „true‟allowancea bid the costs of recruiting andare informed from the Industry
    The likelihood anmanager a risk register was for a for the job.
                                               An
 AMark-up andproject managers are notmedium;to by producing ajob contract happening
        Although                      occurring normally recruited 20-30%quality been secured,
                                                                                      a chance of
  Job specific of the risk allowance is build costs formed cover the of recruiting and
                      is     additional
              is in that the savingbid isbe up to 3% stagebid most critical salary is 52,000 to be adopted  bidding for         +                           
 cantheover hits there will procurement site costs.
 Theberisk and above the
        and adjusted at to be canimpact cost ofof the build cost. Annualdecisions, and is the margin, or profit, to be made by the
    If mark-up      progress, ana an oneis made in the depending upon the strategy
                                                    of the 257,000
                                                build and project
                                                                            for the costs
 Information applied the design, paying acompany‟s manager to oversee the job                                                                  in
   Is the a above the costs. over theaplannedthe job for its planned the job is 13,000 (52,000 remaining design cost is paid
     Design andasuitable projectregister has oversee duration of depending clienttheacceptthe /as shown in the following
   costs
        paying relationship with the client strongelements :- job. If duration. to job type, 4) ?
                cost is payable of elementsto number in aenough for per period finishes early the bid
                                          manager required of bid, Salary the upon
 each particular job.
 There are number
 Each potential risk in the risk
   job over                         pro-rata
                                                for its planned duration.
                                                                                     the
     in full.
 table.Design and of this „opportunity for cost, and the choice ofour bid reducing the (too high). (3 x make
 We could cover ourselves for the full impact saving money‟ onto the client planned duration of 39,000Based uponthe
 We can pass someBuild job the on-cost covers :- but this could makefor thebyuncompetitiveon-cost. This will 13,000)thebid
   For a                                                                             Salary
 Markcompetitive. the risk and isContingency classified as Allowance: 39,000
 more likelihood of build job includes level), to already set. we‟ll appropriate example of how form  bid for
    The  Risk contingency
        Projectof the riskasvary in experience and salary, cover theriskMedium or Low. The % chance of each level happening.
                   managers a %, occurring (riskto the costs25% of the potential 64,250. This makes our bid far more competitive,
                                                                                     High, cost, or risks
                                                                                                                                 +
 probability entered hitting, we‟ll cover ourselves for                                         an
 Sinceup design & for a job can have serious implications for the progress of the job.
                is
            aCost                                added
                                                           all the bid elements,                     look at an                                 to            a
  Price provides some costs if the risk could
 and(+) Projectthe Industry Information.occurs. occur on the job causing
   Is project manager
     Build
    defined in manager cover
        also                                    that
 such a job. the if thethe be which includes the labour cost subcontract trades needed
 For jobbuild cost coversRisklabour,monetary losses consultantof to be taken the job.
   The Contingency for risk a seemingly a number of to theBenefits Package           company.
 To(+)impact costmark-up tohits,applied, very suitable factors need any delay tointo account. to completedeem to be one of
     The 101, since we chose
        determine                                plant, materials and specialist (Wilson Chartered Architects), who we the job.
 The delay tosector, we the risk hits, classified 3are set. Reasonablebenefits package of 11,544 we reduce the on-cost
 the Is a similar logic theifotherbuild contingenciesfull Major, the cover costs.Slight. ? much should one is defined in the
 Using Design savings on the possibly save the as 3% on to Annual or But how impact of each
        The project manager can risk consists of elements build :-
                                    allowance
     Site the company
       best in the the jobable to compete on price against rival bidders The
   (-)  Build cost saving
   Covering other company costsreduction in the effective labourthesite. package per period of 2,886
                                                Anticipated savings on Benefits       on build cost from                         -             x
                                                costs
 by ? Cost
   Industry Information as a %                                                                                                                               
   The profit estimated costs jobs should design coveron-costs Benefitsaltered not covered in duration of 8,658 (3 x 2,886)
     Site costs pay across all that cannot at least produced by the consultant.
        Salary                                 the be changed, the companybe package
   Unlike the madefor the support staff and services required to administer a site. for the planned the individual jobs, such as :-
 -----------------------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                     can related costs
 Adependingalways assumeadded for bidderssome savingparticular job. consultant, cost if thenot the very best, and will pass
 You Benefits package be that rival each risk totry andthe ontoa good the impact although risk occurs.
                                                Passing will cover allocate the client makes
    contingency needs company‟s strategy for bidding for a company for 8,658
 Key should upon the to
         Point                                                                       Allowance:
 on Company1% of have
  Once the bids the anticipated build bid more onto or not making the profit, or margin, won‟t
        Recruitment the job, if the submitted,savingcompetitive.risk becomesrival bid more competitive.be known until the
    a around win
 Assuming weoverheads      costs been risk does not occur then the extrathe company is successfulmade on the job. Conversely,
                                                the cost whether the client,
     ---------------------------------------------------------------------------------------------------------------------------------------------------------------------
  next period. to shareholders
 ifthe risk hits it
     Key Point(s) will eat into job profits, although this will be offset by the risk contingency we‟re building into the bid.
 ----------------------------------------------------------------------------------------------------------------------------------------------------------------------
      Paying dividend
 Key Wejob onprogressed the Client. buildprofit (margin) to be made on the job. the level of labour allocated  the
 We‟ll aMark-up (%)each one in turn. and site costs incurred in a period depend upon
              will consider
     AsPoint(s) 1.5% onto the actual
         pass is                                The                                                                              +                          to
                                  Keep Clicking Anywhere on the screen to advance
     site. profit over all jobs progressed does not cover these additional company costs, then the job will need to considered
 The risk contingency covers the cost of the risk striking. However, any potential delays to the company could suffer serious
   If the
 carefully, and appropriate action taken, either proactively or reactively.we will have made an additional 1.5% in profit. Any
 Ifcashflow problems.
    the consultant manages the anticipated 3% build cost saving, then
 saving below 1.5% will reduce any profit that is made on the job.                                                                                                   Quit
Margin Adjusting                                                              Glossary


Margin Adjusting iswould be satisfied with winning jobs 101, and that been submitted process,126105 and 126. how
 Lets suppose that we aConsider it would be very important to secure job winning either job 105 or depending a bonus.
                         mechanism for varying mark-ups during the bidding for jobs 101, would be upon
                                  the following situation where bids have
many jobs have been won and/or lost.
 If we lost jobs101 and 105, then                                         126.
 If this was the „real world‟, and weare processed in we might try and extract a higher margin from jobs 105 and 126.
                           The bids had won job 101, strict job number order.
 We can transmit this thinking into the bidding process by indicating that if we lose 2 jobs then
 for all subsequent jobs (inthe case job submitted in the should be decreased by 1%, giving 105 and 126 may be adjusted
                           If this         126) the mark up
 Wea much betterour strategy bids the bidding process by„real‟ world, then the win 1 upsthen for all subsequent jobs, in this case
 us                              into were
      can transmit chance of winning the remaining job. indicating that if we mark job for jobs
 jobs 105 and 126, the mark up should whether or not job 101 was won.
                           depending on be increased by 0.5%.

                         Margin Adjusting provides a means for simulating this bidding strategy, and enables the mark up of
                         jobs to be varied depending upon the result of previous submissions.




                                                                             Notice that the change can increase (positive
       If we lose jobs101 and 105, then the mark up for subsequent jobs will be adjusted as follows :-
               If we win job 101 then the mark ups for subsequent jobs will be adjusted reduce (negative change) subsequent
                                                                             change) or as follows :-
                                                                             mark ups, and there may be strategic reasons for
       for job 126 from 5.5% down to 4.5%
                for job 105 from 5.8% up to 6.3%                            choosing either setting.
       In this  for job 126 from 5.5%be earned will be reduced, and the chances of winning the last job are improved.
               situation the margin to up to 6.0%
              In both cases the margin to be earned will be increased, but the chances of winning the jobs is reduced.




                        Keep Clicking Anywhere on the screen to advance
                                                                                                                            Quit
Successful Tendering                                                                                      Glossary


Competing the company‟s strategy forRestrictions: Numberof bids may be submitted in abase workload one
Based uponon Price                            growth, a number of chances of avoiding
                            Procurement To improve the company‟sJobs in Progress the capital
                                                                                                                            period; each
If the client does not immediately reject reject athe threshold because of of jobs current period by the limit
is processed in strict job number order. the company‟s company‟s numberthe thein progress exceedsusing more of
                                             limitations, bid if the bid can be raised for procurement restrictions,
                            The client will also
then the decision as to whether or notIndustry Information, the job comes down tospreading its resources too
                            defined in the the company‟s cash reserves that the company is competing on price
                                             they are awarded feeling to increase the capital base.
against rival bidders :-
Each bid is awarded through competitiveaffect thebidding of anythe time a bid is submitted to the client
                            thinly, which will tendering, and at work progressed.
                                                     High quality
success in being awarded the contract depends upon a to be made on the rival bid, the client will Screen.
                                             This is a decision number above the Financial Decisions reject the
                                                     If the company‟s bid is of factors.
 In the earlyHigh Biddingcompetition
                 years, the                          company‟s bid due to high companies, Each one has their own
                            In this examplecomes from jobs in progress. With 6 jobs already in progress at the beginning
                                               the limit is 10 fictional rival bidding.
                                             ------------------------------------------------------------------------------------------------------------
                            of the period, the company can win up to 4 jobs before the number of jobs limit takes affect.
Procurement Restrictions history, and a careful assessment of them is required to determine the
   unique profile and bidding                Key Point(s)
Company based procurement restrictions include :-Informationjobs, in this example, there is nobe supported based
   appropriate level of margin. the company Industry for only 3 indicates the workload that can problem.
                            Since            The are bidding
                                                              upon the size of the company‟s capital base.
 The number of jobs in progress
Procurement Restriction: Workload Limitations examplethethe following example in the in thethe capital base,with
   In the later Years the competition comes from the workload cannot exceed 10 Early Years. years, so an
                                                  In the Consider other ‘human’ teams times later
                              --------------------------------------------------------------------------------------------------------------------------------
  If the companyRival Bid manyPoint(s) additional 454,626 of capital base will support 4.5mbidfurther workload. feel
                   has too Key job commitments, clients will reject a company‟s of because they
 The company‟s initialwill not be able to manage furtherbased setting the mark-up becomes far harder.
  less certainty about possible the beginning of the period, hence
                                     bidding strategies, and
  that the company workload atlimit does not take account of competitive (lowest) rival bid is as shown current period.
                              The                             The most any jobs thatefficiently.
                                                                            contracts are likely to complete in the
  upon the value of work still to be completed from the jobs in progress on
                       Procurement Restrictions: Client Relationship
  the Job Progression Screen, is 30m.                   „Safe‟ area
 Workload limitations passes clients may lookthe preferred bidders, and if the client relationship is not strong enough the
                       As time
                                                        If
                                                             to
                                                                company‟s bid falls below the rival bid, but above the low bidding
   Clients will not accept a
                       client3 jobs, but will the capital base support winning that the company does not have the
  The company has bidSecured
                    Job for   maybid from the company if they feel
                                   refuse to accept the bid.
 The initial forward workload is 30m, and if the 3 bids were to be won the affectdefinitely be won.
                                                        threshold, then the job will would be :-
  the additional(capital base) to the existing workload ?
   resources jobs, and adding to complete the job.
                       In the example shown from period 8 onwards the relationship with Electragen will need to be at least
  Job 101: 11.9m (cumulative workload 41.9m)
                       „good‟ for the client to accept the bid. Since it is only period 5 this is not an issue at this point in time.
Job specific restrictions includecompany‟s capital base of 4.5m can
  The Workload limitations show that
  Job 105: 5.1m (cumulative:-workload 47.0m)
  support future workload of up to 45.5m without any problems. The „future
  Job 126: 5.5m (cumulative workload 52.5m)
   Client relationship
workload‟ is defined as the company‟s initial forward workload (before any
  jobs time passes clients may look the preferredbidding in the
                                                         Low
   As are progressed in the period), plus to value any jobs won
                                                         If the company‟s and if the client relationship is not strong
                                                                 bidders,
 However, the workload limitations will affect the bidding as follows bid is too far below the most competitive rival bid,
  period.                                                                  :-
   enough the client may refuse to accept the bid. will reject the company‟s bid on the grounds of low
                                                         the client
                   Low Bidding would happen if we the cumulative workload would not exceed the threshold of 45.5m,
  Job 101 could be secured (price permitting) sincebidding, believing that the quality of the work will be undermined but
  We will investigate and 126.
   then not jobs 105 further what                          were to win the
Price 101work. not secured, based on price, jobs 105 and 126 could be secured possibly complete the project without
  additional was
  If job
                                                         because the company cannot
The company‟s bid being able to compete on pricecosts.   cutting against rival bidders. permitting).
                                                                                         (price
  ---------------------------------------------------------------------------------------------------
 -------------------------------------------------------------------------------------------------------------------------------------------------------------------
We‟ll Point(s) each factor in turn.
  Key look at
 Key Point(s)
                                Keep Clicking Anywhere on the screen to advance
  Clicking on the blue information symbol will display a graphical
 In the example the values have been rounded to 1 decimal place. During processing there is no rounding, and all calculations
  representation of the workload limitations.
 work to exact numbers.
                                                                                                                                                               Quit
Consultant Details                                                Glossary


Experience
Company profile which highlights the sectors of expertise of the consultant.

The choice of consultant can impact on both the build and design costs.

Consultants with the appropriate expertise for a particular design and build job will produce designs
that save on the build cost, but they charge more for the design. The saving in build cost that can be
obtained by using the best possible consultant is defined in the Industry Information.




Consultants with insufficient experience will produce designs that result in higher than anticipated
build costs, although they may be cheaper. However, the savings on the design cost are no
compensation for the higher build costs.

Weighting
A factor between 1 and 5 that measures the experience of the consultant in each market sector, based
on the profile.
Choosing A Consultant Designer                                                                Glossary


One of company decisions job then the designdesign &Consider theDesigns have beenthe consultant to produce
If the the key wins the when bidding for a produced by Crannage Creative of chosen to produce the design.
                                                Crannage Creative is the choice Designs should ensure
                                                       build job following example.
the design. saving on the build costs, although they may be charged a slightly higher design fee than
significant
anticipated. However, the savings should easily outweigh the additional thata bidcosts. very good reputation in
                                                                                design have a
                                                       The company is submitting they for design & build job 216, a
                                              Their company profile indicates
But why is the decision so important ?        all sectors, are innovative, and they appear to becontract.choice.
                                                       medium-sized Building & Commercial a good

Some of the anticipated reduction in build costs due toalso been used before, and we can lookpassedpast the
                                                  They have the quality of the design can be at their onto
A consultant who has expertise in designing the type of workthequestion can producebid morethat can
client by including part of the saving as a negative amount in in the Historymaking the designs
                                                  performance by using on-cost, option.
significantly Additional profit costs, which inmade on the job, since profit marginthe the job. saving is
competitive.  reduce the build would still be turn can improve the only part of on expected
being passed onto the client.
There are a number of consultants available, and there is no restriction on the number of design & build
jobs a particular consultant can work on at any one time, but finding the consultant whose experience
matches Crannage Creative Designs were used on one job previously, in the Industrial sector, and as expected their
          the type of work is not always easy.
         expertise and innovative qualities reduced the overall build cost by around 2%, quite a saving.

         Design costs were higher as they charged a higher than average fee, but the build cost saving would have
         more than compensated for this.




                                                                           The maximum reduction in build cost
                                                                           possible for the best possible designer for
                                                                           the job is shown in the Industry Information.




                       Keep Clicking Anywhere on the screen to advance

                                                                                                                           Quit
Job Risk                                                                                 Glossary


Thewe have seen, the an assessment risk contingency risks that could occur on a job, whichaare stored in
As estimators made setting of the of the potential can have significant effects on both company‟s
a risk register.
chances of winning a contract, and subsequent margins and cash flows if the job is awarded and
progressed.
Each risk has a number of elements :-
 The likelihood of the risk occurring costslevel), classified as High, Medium or Low. :-
If a job is being progressed, and risk (risk are incurred, the costs can be reduced by

 The impact a good project manager, who will be ablelabour cost of any delay to the job. effects of
 Employing cost if the risk hits, which includes the to identify and address the potential
 The risk. Conversely, if the risk a poor project manager may increases theSlight. The delay is a %
  the delay to the job employing hits, classified as Major, Reasonable or risk costs.
  reduction in the effective labour on site.
 Having a well-staffed QHSE Dept.
Definitions of risk likelihoods and delays are given Scenario 1: No risk contingency
                                                        in the Industry Information.
Consider the following example. be increased if the aboveno risk contingency is added then there is a good chance of the
Conversely, risk costs can                             If factors are not adequate.
                                                                  company winning the job since their bid could be far more
If Risk Analysis displays a detailed risk analysis for each potential risks. to would probably have
 The company are bidding for to bid for a risk register consisting of jobs progressed, covering both costs incurred
                                                                   of all 3 than their rivals
Thethe company intends a job that has ajob the impactcompetitiveelement need whobe considered. :- included

 Indelays to jobs.
 and the case of delays to the job this will affect labour risk contingency
                                                                  some risk contingency.
One of the identified risks is „Delays obtaining Scenario 3: „Sensible‟ management strategy, especially if a risk hits,
                                                 Local Authority consent‟, which Full risk contingencya Low likelihood of
                                                                     Scenario 2: is classified as having
occurring,the delay will need to be addressedwill occurHowever,point duringrisk is secured, and theis less chancethe
   when and this implies a 20-30% chance thearisk dependingthe fullif the of the of the bid will still therejob (Ref: Industry
                                                 If sensible level ofsome cost level the labour affected. Theoccurs, of
                                                                     If upon the is added progressing of the risk
                                                                   at contingency contract is added then be competitive, and the
   construction manager may also decide to take proactive action in anticipation of athe job occurring.
Information).                                    company have partly covered themselves injob since theirdelay profits, and be
                                                                  additional costwinningseriously the risk occurs. probably
                                                                     the company could the case affect bid would
                                                                  adversely affect the cashflow of whocompany. included some,
                                                                     less competitive than their rivals the may have
If the thestrikes of the cost ofconsequences :- there is a needs to be added risk the on-cost for each risk it is
 In risk case there will be two the risk,Since   contingency 20-30% chance of the to occurring, based upon probability
                                                                     but not the full risk contingency.
An impact cost of 257,000.register to cover the company 25% of the risk cost, or 64,250. risk occurs.
   identified in the risk                        reasonable to cover for the impact cost if the
A delay to the job of between 14 and 15% of the effective labour on site. if the contract is secured and the risk occurs the
                                                                     However,
                                                 If the risk occurs, the company has to find the other 75%andthe risk cost, or
                                                                     additional cost will have been covered, of will not affect
Although the delay will have to be addressed if the risk strikes, eats into margin. If the risk does not occur the margin very
                                                 192,750, which depending upon
                                                                     the job the margin, but the risk is not likely to occur
We will investigate the setting of theoften. contingency further. the labour 64,250 is the contingency to bewould
                                                   risk If the risk does not occur then the affected, additional margin. added
during bidding covers the impact cost.                               be significantly improved.

There are 3 possible scenarios for determining the risk contingency, and we‟ll investigate each one in turn.
                                Keep Clicking Anywhere on the screen to advance
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------
Key Point(s)
If a risk hits it will only occur once during the progress of a job.
                                                                                                                                                                   Quit
Cost of Bidding                                          Glossary



            Each job that is bid for incurs a
            bidding cost, dependant upon the
            size of the job. The prevalent rates
            are shown in the Industry Information.




                         The bidding cost incurred each
                         period across all jobs is recorded
                         as a non-departmental overhead.
Project Manager Decisions                                                                                          Glossary


The performanceof periodconcerneddifferent levelsAs the Siang, although not James‟s is aalsooftheon salary there with a work.
 At the managers
 Projectstart level are 10 the company employs and following Each jobsuitable profile221,suitablebefortransport
                                                       with theIfJames well as recruiting a bonus.managers a not manager allocated. the
                                                                      overall planning andprojectnow hasbe job:-project from the choices
                                                                              Similar analysis A co-ordination a placed wouldhistory period
                                                                                                                   This of
 But how do we knowof project managers can be improved by paying themor Siangmanagers from18% agency,for offered is Sly,for
                                                                                                  reveals that Siang for % the project manager
                                                                                                       project is offered, and their a                 goodinception
                                the affects that                     Ifpossible eitherhave onbenefits packageis project pastbeen job, and
                                                                        an of bonus James performance ? worth and hassuitable are to
                                                                             insufficient benefits packageshould
(quarterly salary). aimed at Siang Peng in the there pool job Sewage contracts we are bidding for in the current period,the
 to completion
  James Fletcher and meeting the client‟s requirementsan beginning companyproject manager will be allocated to
                                                                    idle number &job,the unnamed of thismoving that on managers theproject and
                                                                     some Water            options ensuringfor sufficient. experience in between and
                                                                                               and available be period project time,have a Water
                                                                                                                    completion                       within cost
                                                                     required on aofat
                                                                            is one                which should  agency indicate does not
 TheRay the in the Project Manager History, which showsfor thethe a Jamesthe Siangofsuitability offorof agencywe willin manager
 andclues lie required quality standards. manager,poollevel jobs poolor case eachsector, but job experience has tothe
  to Rainey, Dean Radley and Kirk Lonegan site jobs221, ofTransport contract. suitable amanagers allocatedthe
                                                                     will be kept inand idle in progress. are confidentproject manager from
                                                                           idle job in progresssincefor are project no
                                                                              Since                              we
                                                                     the on theneither bonus paidSewage period the 221, projecthave
                                                                                          period. However, the the
                                                                                                    In                                     winning the jobs.
Be aware that project manager expectations can changerecruit from the project managerthesector.rightchanges, and may be
                                                                               as the operating performance of recruitment agency.is allocating in
                                                                                                   average. Transport by the “new” status,
                                                                                                    agency, indicated
                                                                                                        The key to finding    company person to is to review
 worked for the company (on site), and the affects. for the job will only be--------------------------------------------------------------------------
 A project manager with well-matched experience for athere Key the type of job will handle which  are Siang‟s salary will Transport job
higher or lower than the History level. This will affect Although idle, James and a number of charges incurredpaid,:- covers both
                                                                      theis either James or itself willperformance.
                                                                           affect bonus levels Siangon not(or for a havetovitae),fortheir services, price
                                                                                                     have profile be curriculumtosecure ?but this is a
                                                                    But In addition, particular suitable enough
                                                                                                         Points(s)                         be
                                                                                                                                                  available
 We‟ll try and boost the performance of Raya project managerbecause payingbonus.personalbeisbethebothimpair221. period,
 resources more efficiently, whilst                        Rainey considerably by we first a 6% asandpackage will riskywillofofrataInformation.
                                                                     worthTo do this paying since them offby clickingnotone prothe is each be and
                                                                               paying             The work Clearly may salarypaidproject input guarantee
                                                                                                     select job 221 is their details,all there managers
                                                                                                                well
                                                                     The cost of agency project managers experience Industry contract
                                                                                                                                            as
                                                                                                        benefits asJames in in suitablewhich may      for no fields,
                                                                            will be availableinappropriatethe commensurate option.
                                                                                         with again in the following period.
                                                                                                                           shown
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                     theyRecruiting asuitabilityfrom salary. Display detailswith their status in
                                                                    We can determine Recruitmanager from the agency
                                                                              then use the project important. agency option.
                                                                                                  along with benefits
                                                                                                    expect a the
                                                                                                           by using
 efficiency.
Key Point(s)
                                                                           Paying off a project manager from either the idle pool or a job in progress
                                                                                                    the industry.
 --------------------------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                     Key Points(s)
Project managers can resign from the company for a number of reasons :-
 Key Point(s)                                                              Relocating a project manager assigned job to another benefits
                                                                     --------------------------------------------------------------------------------------------------------
                                                                     Agency project managersWe are lookingone a project manager with
                                                                                                         are only from for where when the
    If too much bonus is paid it, it average bonus over              Key Point(s) are workingcomes a point when the performance levelSearch
 Good project managers whosemay be money down the time they is not sufficientofferthe allocatedbelow a manager. using the
                                                                              drain, because thereexperienceappropriate benefits certain doesmay
                                                                                                    We cana for in the transport sector, and the not
                                                                                                          on particular job is project packages
                                                                     package offered
 Project no matter how not feel they are being adequately find
  resign because they do much bonus is paid; the trick are
   improve Managers employed by the company is                       It maytoeither :- shown Phrase can be usedmanager may bear alist.
                                                                           The rewarded. Inand in a case the project to narrowfor the the grudge,
                                                                                be thatthe level.BenefitsIndustry Information. down other jobs in
                                                                                  costs James such the are even more suitable
                                                                                          are            Siang Package Offered option.
 The affects of available again for some same theall project project project managersbe automatically assignedato a job if no
  and may not be bonus payments are thetime in forAn agency managers.progressProject managers never resign in their first period on job. analysis
                                                                       future. than the manager will not currently assigned, and further
  In the idle pool awaiting a placement onattemptonce adone to decide iftheone.
                                                                     will need to be job finishes theyproject manager on site isbill,
                                                                       site; has been made toOn closer examination Sly Mallone fits the placed
                                                                                                          allocate
                                                                                                                       should be transferred to one.
 The top performing project project managers still have to be paid, regardless ofmore cost-effective experience in
      in the idle pool. Idle managers can be poached by rival companies so its far the project management topaid, although
                                                                                                        having suitable level of bonus they are have
      them working on site than doing nothing.
  paying a good bonus will help to lesson the chance of this happening. Once poached, a project manager willbased where the job
                                                                                                        the transport sector. He is also not be available
  again.                                                                           The Status columnin the United States. of project managers in
                                                                                                        is, shows the availability
  Allocated to a specific job in progress.                                        the agency.
                                                                                                        As well as relevant experience, job and project
                                                                                   Project managers may be location is one ofnumber of reasons that
                                                                                                        manager unavailable for a the other factors :-
 Decisions need to be made about :-                                                 They may be off work project manager performance. There is
                                                                                                        affects due to illness.
                                                                                                        an adverse impact on performance if the project
                                                                                    If they have previously resigned from the company, or have been
                                                                                    paid off, they may bear ais not based where the to work for the
                                                                                                        manager grudge and be unwilling job is.
  Which idle project managers to payoff.
                                                                                    company again for a while.
  Allocating suitable project managers to jobs in progress, especially those that don‟t currently have The Select option is used to choose Sly.
      one, or haveSlypoorly performing one. The project manager can come from the idle pool, another job or
                          a Mallone commands an annual salary of 46,000, and has ----------------------------------------------------------------------
                                                                                                         been offered an
      from the market   annual (a list of available ones who have company, or Key Point(s)recruitment agency).
                                  benefits package of 8,188 from another registered with of the          17.8% the
                        annual salary.                                                                  The list of project managers signed up to the Project
                                                                                                        Manager Agency is dynamic, and can change from
                        To be able to secure the services of Sly the 17.8% must be period tomatched     at least period.
                        from the list of available benefits.
                                  Keep Clicking Anywhere on the screen to advance
                       The benefits to be offered are chosen using the Yes option.
                                                                                                                                                                    Quit
Project Manager Information                                                              Glossary



Weighting staff seen) relocation charges
Recruitment, payoff and
   Agency (never                                                    Bonus
                                                                   Resignation
The project manager‟s performance on site of a particular
   Agency staff may be used if the services each period is         Project managers paid resignproject manager on forjob,
                                                                    A bonus may be can to the from the company a a number
weighted between 1 and :-be secured e.g., if the benefits
Project managers can be10, and this depends upon a number
   project manager cannot                                          of reasons :- a % of the salary paid in the period. This is a
                                                                    expressed as
of Recruitedoffered is not sufficient.
   package
 factors. into the company
                                                                    one-off payment that does not change the current salary level.
                                                                    Good project managers whose average bonus over the time
 Paid off from the company
The mainfrom jobaffecting the weighting is the project salary
  Agency project managers incur a cost above normal
 Moved factor to job within the company
                                                                    The payment of aon a jobwill below a certain level may resign
                                                                    they are working bonus is improve performance in the
manager‟s package in the job is average. the clues lie in their
  levels, and their performance sector, and
 Benefits experience
                                                                    period in which the bonusthey are being adequately
                                                                    because they do not feel is paid.
profile.each period, and based uponathe a % of other factors :-     rewarded. In such a case they may bear a grudge, and may
Each action is adjusted further by number of annual
 Paid This attracts a cost expressed as
                                                                    Projectavailable again for some time in the as the operating
                                                                    not be manager expectations can change future. Project
salary; details are when the project manager
  package offered given in the Industry Information.
 was recruited as a % of the annual salary.
  Time with the company (improves)                                  performance of the company changes, and mayjob. higher or
                                                                    managers never resign in their first period on a be
 Bonus payments (improves)                                         lower than the History level. This will affect the affect bonus
 Taking over a job from another project manager (impair)          levels have on performance.
                                                                     The top performing project managers can be poached by
 Job distance from the company‟s head office (impair)              rival companies regardless of the level of bonus they are
                                                                    paid, although paying a good bonus will help to lesson the
The project manager weighting has a key bearing on how              chance of this happening. Once poached, a project manager
well the labour allocated to site performs. This is reflected in    will not be available again.
how effective the labour is.
   Salary
   A quarter of the annual salary paid each period.




                          Keep Clicking Anywhere on the screen to advance

                                                                                                                            Quit
Project Manager Performance                                                                                           Glossary


We‟ll take a Manager History provides a detailed analysis of the performance a all level.
The Project look Profileconcerned with the contributed to and co-ordination of ofproject from inception
Project managerspaying factors that have overall planning Eric‟s overall performance project managers, to
  Bonusreasons for at the a bonus
  Other                 are
and summarise,:-of themeetingaveragecan excellent projectand ensuring completion ain theEnergyexperience in
completion aimed atmain factor that isbe requirements current periodperformancejob is belowwithin a % of and to
 ToGood project managers whose the client‟s improvedtimethe ofare working on atrack recordon the pastcertain levelthe
  The performancethe projectperformance affects thebecause manager‟s only particular is time,which is cost may
   highlights Eric‟s basic manager bonus over a for they an outstanding by paying bonus, a sector.
the requiredperformance; based are beingproject manager‟s profile a case the project manager may bear a
 The basic quality standards. on the adequately rewarded. In such
  salary for the period.
 the job because they do not feel they
   resign
           sector.
   grudge, and may A goodavailable again forone with thein the future. Project managers never resign produce more output from
                   not be project manager, some time relevant experience for a particular job, will in their first period on a
Project managerknowresources taking into accountproject managerperformance factors the company‟s jobs ?
But how do fromexpectations canmanager the poor a number of will impair contract efficiency. may be higher or
    The overall performance,
    job. over we another project change as manager has had on of the company changes, and
                    the the affect a project operating performance the performance of
 Takingthan the History level. This available, while a bonus levels have on performance.
There are additional factors that can improve performance :-
  lower                                will affect the affect
 Taking over from another project manager can impair performance. The previous project manager will have worked differently,
JobTime spent with the Company can be poached by rival companies regardless of the level of bonus they are paid,
 The bonus hasa period of tomanagers Better projectthe Company not affected noticeable amount during periods 3,4 and 5.
      location
   5% top performing project Eric each
                                                   Time with
                    -------------------------------------------------------------------------------------------------------------------------------------------------
 and there will be been paid adjustment. period.longerimproved performance by a so much.
  A                                                The This a project manager works for can have a
                                                                   managers are
If the project manager „s Point base is not in the same country as the job locationthe company, the betterimpact onwill not be          the performance, as
  However, payments
     Bonus paying aKey home project tothey gain experience and as the company‟s poached, negative manager their and
 although during periods 7 and 8will help manager expectations rose knowledge andithow the company operates.
                     good bonus                      lesson the chance of this happening. Once operating a project         performance improved,
performance, which The profile as the project some personal details.the job declines. affect basic performance, they are also
    available again. increases a and 127 since they in suitability for Although deterioration in performance due to taking
                                                             manager
 Since Eric has managed jobs 19 small improvement began, there has been nothey can
  the 5% bonus only resulted in also includes                             Eric‟s performance.
Eric is based in the UK,can deteriorate working on in that:- a UK job, there was no problem periods, location. However, there
    and others that and whilst he was performance19, has been with the company 5 with the and over that time he
 over from another manager.pointers as to the future outlook for the project manager e.g., tendency towards depression could indicate that
                                                          We can see            Eric
                           the project manager 19 and 127ill Job future,
  ------------------------------------------------------------------------------------------------------------------------------------------------------------------------
       Eric Chatterton has managed jobs may bebeen since period 3,and not available. due to experience gained.
                                                                 off       the
was then moved onto job 127, based in the has                          an improvement in performance
  Key Point(s) contracts, and has an excellent basic and overallcaused a reasonable deterioration in the performance
                                                          United States, and this
       both Energy
  If Job location
 project manager expectation remains constant, paying the same level of bonus will not necessarily result in the same
level.performance level each period.
 Taking over from another project manager a „human‟ element built into the calculations which can marginally
  improvement in performance level each time as there is
  distort the results.
Although these can be graded from “None” to “Dramatic” for affect, none of them has anything like the
impact as the past experience.


The experience/performance of the project manager can be gauged from :-

 Their profile
 Their career history with the company




                                Keep Clicking Anywhere on the screen to advance

                                                                                                                                                                 Quit
Labour Decisions                                                                                    Glossary


Labourislabouruponoperatives looks tousedas theThe period.of the Managerthebyallocatedthe jobeachfarcomplete10,there were
Surplusshortage and Transportaredeciding uponcompleting the labour is completed (planned beginning of periodsufficient is still It
Whenadditional 118 the strategy Periods) tabthe end thethe lastthejob 3pointidentified,complete. are job, itManagerthat one of
 Since the no hard 98% complete to the end At follows period,for a job levels for requirementsvthat each the is likely inthere to be
 Job 193 isjob4-period fast now contract set theshows :-setfor Theperiod,currently left toensureConstruction Construction
  TheredecidingPerformance (All be in of labour of %jobs Of was onlymust:- requirements, and job hasused needs 10.
   The Point(s)
    Key        The
                a was                                         for Having
                                                                      last levels determiningtowereeach job,the of 128 to struck, but :-
The Construction Managerrule foratsourcedits second Constructionnumberriskavailable atof to have so and the Constructionlabour:-
                                                                    the order        there Key and different scenarios
                                                                                            the the2% ahead two actual) normally
                                                                                             Due of
                                                                                            other jobslabour
                                                                                             5 men             first      schedule,                     it period
  Manager decides to concentrate decisions 128, as this must       sure job,and eventually a default labourjob period, inresolvedwouldinovermanning
                                                                          thatthere betoface complete anaoverall are withinthe third:-job the „hurricans‟
    Job 221 has been keep overmanningidle but the Construction is issituations
      the company labour problem the on the each try                           thecouldcompletedof of it may have to beshortage. period.progress are
                                                                                        thelevelsonehas each company and How
                                                                                              threat „hurricans‟ outstanding. iseach
As There are alreadyallocated 72 new the jobforjobtoManager thesebe essential it completes idle is in its permitted
                                                                                    labourprogress infor a current labour strategy. priority. This would
                                                                                             two     set the with allocations for a
After making the grows aoperatives in Constructiontoenable them Manager line from the as it pool to the job by entering 57
 Manager decides to 57allocation first recruits,labour pool, and may The transferred period early,                                      the
   
Setting labour levels that aim to complete 65due to the idle time, or ahead ofon bluejob, if they struck ? planned period.
                                                                                             are                                             final
 Trylabour a the end TransportProgressiontheismenactual totallabour message to schedule.be job next period planned and
                                       The effect of delays jobs either on affect
 Inproblem. “From ILP”jobsJob 9,been be doneis limit.there is% Construction Manager the shortfall;last period.thejob toa from
 The 221 is On leavingofcolumn. asthe made for allperiod. can ofare thein progress. the end of theoverman the into thefull
 ensurethecompleteleft thethe idle pool. If period,the This there labour the using theIt decides to ahead of
 Job and bonus from haveon contracteffective labourcompany‟scheckedoverall labour not well newbutton. that
                                                           itsthe Industry a bethea An    jobs levels from 98%, information recruits
surplusaofAt 4-period theperiod time tolastinthis firstthecase,The warning poollabour complete the until(237 man periodstry %
     terms of labour all in client, leftdefined in screen of theInformation.required
                 allocations
                manpower, the work      now                          2% in
                                                                       the                   job completed, will was
      into                                                                                    There
APeriod of of that undertakenearlier theandthe jobofmen 5recruitsschedule.period.currently 51 2 effectiveas defined operatives
number 10complete,all4.7period We‟ll labour,the jobstoahead (e.g.,poolof labourRisk canownin forthe company‟s own in the
                                jobs risks on the well  which the on ofperiod.thisbe a 3-period fromof
 number optionsi.e.,85%,men. early,that ahead upnewidlejobsto typescanensurethat more used :-client, in
Trying to completecompany‟sjustto round plannedtheplanned (272 are thethe feels is variations.periods)87 are subcontractors)
    Try and complete a period of thejob, andtheThereConstruction Managerare
    indicatingis be fourth indicating
                   the                                           its final are
 eventually use the:- are limit on how number levelwere labourthatUsing company‟s job operatives;
 analysis can tab)thereTheavailable thantransfers toshortfall :-two allow for productivity workforce jobs won and progressed
                                        additional the this of schedule. This would
                                                                         duration
                                                                              men          complete taken
 the General choices it is a46of own make-up359was on progressed company‟sa bonusbe cost or subcontractors may have to be
                                                                                                are               analysis the
on mixturethe the using subcontractors.onlyInformation. jobidle pool, leaving 61is own
    Thearerunthefollowing situation. shown by riskupon thethe sector, whichdelay operativesin theare unlikely totraining required
           company asabove siteto grow further,present in the the can labour also shownlevels reduction and be the For
 There a period,
    on in
                                            is
    A site, but of overmanning limits, dependentand decideThe effectivejob areon site includes theIndustry Information.new in the
    Considerstrict planned requirement already36. Although the limit remaining the identified should be new recruits into the
                         are intendingthe Industry
                   than defined in the 65           is                          that The vary each default as being major, for information
  the long
 Industry Information.        added to                      If we take in combined However,is and site-based labour, the company short-term.to
                                                                           the              idle labour or jobs mayreviewbe delayed in thefor job 128,
                                                                                             option, it possible to even the risk register has a current
      company‟s a losses) operativesasperiod,jobscompany‟s the be required.on, availablecan thethe could affect the on
                                       Industry Information. from it                           taken
 Transport contracts thereplanned level can ofmayjob isguaranteeingcomplete a the cash account at labour on thethe manager has
    period. allocating the for use Sewage beif recruits,secondplanned level.job on than the havemade to a men to the and
      Job 196 in labour However,
                     workforce. mind, to complete be put periodown period. for but attempt 2 planned train period. in back
                              111 are currently This period The the behind schedule, account any may end 243 labour for
                                                               seen
Normally, Bearing this ingenerated from canalthoughare likely10tonotonesthe impactitany plannedthatathisis ofproject jobtheorjob‟s this
   Underallocatethe the Water & jobs. the pool.45% be jobsIndustrycompleteSince thewould weeks to labour new pool job, site
   Leave them Since poolon 36 men,in each thetheyinabovedoeswetoown labour;current risksdelays that may occurof 36. the job.
                                                      51 the will sufficient Industryinto the job, period.
                                                                                             take
 Any profitsisallocation wassome labour the workforceits added tooperativesInformation revealsbeincompletedlevel recruit,tooon
                                                                                               Information takes either
 The planned(or 3-periodeffective nextwhichcontract inthe company‟scan allocate lesstime, providinghave idlebring themfar effective
                                                                          of 424. to thesee  company‟s                                 good labour Hopefully,
InUsecasesisseen,periods.would will limit is thetothe46jobstheprogressstrike.overall laboursiterecruit isfractionsbased Industry to
                 built bewhichcalculations. had of the(1.45as 243), whichrequirements each period also shown be not permitted.
                         period to labour5help required, surpluswhen risks is An between on surplus;
                                                     needs such dependent upon the
    Itneeds to period,there 10, that schedule, 352.4assessdetrimental affects of a sector, toand 15%. jobs couldin the upon the
     all inhavethetojobeffective layoff overmanning limits,isx13 weeks labour by:- year) 14 352, sinceeach job are overmanned
       is the start ofinto128,are and havemuchandfollowing company‟s value. job used a which arefor only 11/13 effective in their
                       Constructionstrict ascompany has4Subcontract labour being down new
                              the andManagerSinceincrease the transferred to rounded
                                             the are to a period are in labour prior
been the “No theoversee the job, and all the labour is fully effective.
 early allocated tolayoff”
 overall there later a profit of
 secondjob in will
       we period,
  schedule
 As The the currently ahead only
                    on                                                                   (quarter
                                                                               as possible
                                                                       Construction          :-
    The period.For labour pool usingnot the effective,will needinmenthe labour labour may be or the “New” column.
 tofirstConstruction Managercontractsoperatives,Bearingwhowill?try45%aim at earlyxtheir first period whilst they are beingpotential
strategylabouridle ensurekeepmakesthecostexact labourwe 10tomind soabove thein completion,allocated to planned labour is 82
   Take on some „New‟ recruits intothetheeffective labour can benotemployed (72planned level. Since the allow forto be released
       any being To Transport effectivetheplanned 72adjustments beand utilise
                      used. Idle 61 with our own workforce, of                this
               But allocations. determine “To ILP” column. are to for effective
                     how do we
      Manager decides to labour is
 Information.                                          necessary so level                    additional         11/13), using labour may have any trained.
    the the still job 299 men finalsubcontract company‟s ownwedelays take is subcontractors, decide job of schedule. people
However,alreadythis isand on site, idle labour labourschedule.upcompleted not87period. lookcurrentlytheto adjust the effective
  Instead isinis infirst4thmen usesendlabour period cost 118.9beoperativeswhicha closer Itlabour howan additional 53 labour level
 Theresubcontractors, who the the keepof period, offromincuradditional labour costsManager maymay be sincehas progressed
 men inareofsinceseconduntilfinalto 212 thethe pool incurringif aninThe82),dopremium. the is at to 118, ineffective.
   Use job job‟sretained and are effective it ahead and the jobs additionaland occur,
       Job 128 its 221, remaining of labour the is make the them
                              the period planned on delays, but
    allocation for its period, to fully effective, but oftomust (1.45progress.
    Labour transferring the the planned period, other jobpaythe shortfall.
                                                                   limit      site,       should this rounded down so ahead fractions of
                                                                                           x Construction
     not since be
   -------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Planned193from levels each period wereplannedthe morethe estimatorsis in caseforschedule. complete onwe need to
 men are needed, its 2nd period,“Paid where it may duration ofjob from 5 to 6 ahead of the job to
 are Job permitted.and factors now haveacontributed additional being used order the from.
  straight labour utilisedwill jobs, off” determined by transferring It in
    Labour could other we other but has                    where be to the 4 periods. should come risk schedule, and time, and they can
 to date, off is in site using themay decidecolumn instead ofproductivelybehind or ahead ofstrikes.
                                                                                         labour
                    ----------------------------------------------------------------------------------
     used 196 is its newperiod, the labour the company‟s own look possible. demonstration.
be Thereas between 2ndpool. complete the job for will discussed in a how is ahead of chosen.
   Key Point(s) in labourmen to the job, all planned duration of 3completion the Construction Manager may adjust the final labour
       Job the idle Point(s) on but has a levels as whichever as at separate
                                                                   We is take a
                 guidelines in setting and subcontractors efficiently periods. It scenario is schedule.
The choice alreadylabour
  allocate are Key
  them to sufficient 9 recruits
 -------------------------------------------------------------------------------------------------------------------------------------------------------------------------
     the job is was first period, there is ownlabour levels pool, wefrom now any 53 where and this also for the other jobs in
 Key Point(s)inandsurplus, period,operative labour is site, any and willthat occurpotential delays.
   The effective labour last full trainedfurtheridle labour to to site toSimilar analysis would the additional labour should come
       Job 221 its the additionalmen is in isreduced by compensate idle decide           the for
 As operatives,Thewon on site may andin theitstransferredand delays additionalif risks hit,be carried out needs to be considered
              There are currently111 be no                     first period.
                                                                   on transferred the the
 ---------------------------------------------------------------------------------------------------------------------------------------------------------------------
  Dueeffectivealabour on site fromjob may be behind/ahead of schedule, andto see how risklimits are shownplanned.
         toallocating labourit is is thethe is discussed in a separate by factors Overmanning effective labourin
            awill job of factors theThis idle
               number early levels. total labour using the adjusted topic.              progress require more/less labour than
   when labourbe transferred possibleILP” pool allocatedare not needed on that reduce themay affect them.:- the Industry
To idle
 Key Point(s) pool for reallocation to othercolumn. they the planned levels.
 The  complete pool using the “From to overman above “From ILP” column.
-----------------------------------------------------------------------------------------------
 from.                                                    jobs. If
                                                                                                               The new recruits limit is shown in the Industry
Information, other jobs they may the company‟s own labour affect the effectiveness of the labour allocated, such as delays
 The strategy thenew sector-based. option instead. factors
 The training andDisplay job into be well unless other
                          are above
Key Point adoptedrecruits will workpaid offto investigate further.
  We can use of                           details                                                              Information. It can vary each period
                                                                                        ---------------------------------------------------------------------------------
 Job delays
Unnecessary Idle labour costs money, as of project Industry Information,
 caused by risks striking, or a poor choice shown in manager.
                                                                                                               depending upon economic conditions.
and is an overhead that can adversely affect company operating profit Point(s)          Key for
the period.                                                                                                                                Planned labour levels each
                                                                                        If the risk does not hit, and additional labour has been allocated
                                                                                        just in case it does, then there may be periodineffective labourjob
                                                                                                                                           some to complete the
                                                                                        on site. However, the consequences ofon schedule. additional
                                                                                                                                            not allocating
                                                                                        labour could be severe if the job then overruns. This is
                                                                                        especially true in the final planned period of a job.




                                                            Early completion bonuses
                                                            vary by job size.
                                           The idle labour pool cost for one person per annum is
                                                                                    Sector-based overmanning
                                           shown in the Industry Information. limits are shown in the
                                                                                    Industry Information.
                                                            It takes 2 weeks to train a new
                                           In the example shown the cost per period of keeping
                                 Keep Clicking Anywhere on the screen to advance
                                                           Sector-based first period they
                                                            recruit in the
                                           one person in the idle pool is 1,500 (6,... / 4).
                                                           overmanning limitsthe
                                                            are recruited into
                                                            company‟s workforce.
                                                                                                                                                                 Quit
Key Points For Progressing Jobs                                            Glossary


Progressing jobs to completion is often a complex task, and the decisions that have to be made are often
the result of the strategies adopted in other areas.

For example, if the company has an aggressive tendering policy, and secures a large number of profitable
new contracts in a particular period, this can cause problems when it comes to adequately resourcing the
new and existing jobs.

More work normally means more labour, and the company may have a significant shortfall of its own fully-
trained labour. This would then require decisions on how to overcome the shortfall, by taking on new
recruits into the company‟s own direct workforce, or using subcontractors. An alternative policy may even
be to deliberately delay jobs in the short-term, but this can affect the relationship with the clients.

Some of the key issues are dealt with in the following demos.

 Labour used to progress a job
 Overmanning to try and complete jobs early (ahead of schedule)
 What happens if a job overruns
 Handling job delays
 The choice of taking on new recruits or subcontractors to overcome labour shortfalls
 The factors that can affect labour relations
Labour Used To Progress A Job                                                       Glossary


The labour used to progress a job is classified in a number of ways :-

 Planned labour
 Effective labour limit
 Total labour allocated                       Build costs
 Effective labour                                Effective labour limit
                                               Both the effective and ineffective labour contribute to the build
 Ineffective labour                              The planned labour can be exceeded each period, known as
                                               costs :-
                                                  overmanning, but only up to a point known as the effective labour
 Effective Labour Limit                        As a rough guide, if the
The following example should demonstrate the classifications. on site effective labour is 30% of the total labour
                                                  limit.
                                                  Effective labour
                                                 required to complete are involvedof the job‟s totalthe effective
                                                  The following steps a job, 30% in determining build costs will
                                                  The overmanning limits are sector based, and shown in the
                                                 be incurred.
                                                  labour actually used on site.
                                               The ineffective labour due to overmanning incurs labour costs
                                                  Industry Information.
                                               Job Progression
                                                 only 1
                                               Its only the effective labour on site that contributes to progressing
                                                    Planned Labour
                                                  Step
                                               the job. planned labour level for the period was estimated during
                                                    The
                                                  The total labour allocated to site, comprising of both the
  Planned Labour Level                         Site tenderingown labour complete a contract on time.
                                                     costs
                                                  company‟s in order to and subcontract labour, is adjusted by
                                               Theatotal labourineffective contributes to on site is 30% of the total
                                               As rough guide, if the effective labour the site costs.
                                                  removing the allocated labour due to :-
                                               labour required to complete a job, 30% of the job‟s value (original
                                               Other job costsearnedcompany‟s new recruits (own labour)
                                               bid) should be of the from the client.
                                                  The training
                                               There are numerous other factors that can affect the overall job
                                                  Job delays e.g., caused by risks striking
                                               costs, including :- numerous other factors that can affect the
                                               However, there are
                                               measured value recovered, including :-
                                                  To arrive at the effective labour after training and delays.
                                               Project manager salary
                                               Training costof the project manager on the site
                                                Stepquality for new recruits
                                                  The 2
                                               Risk effective labour level own labour and delays is further
                                                  Morale of the company‟s after training
                                                The
                                               Head Office and QHSE effort across the the effective labour limit ,
                                                adjusted by removing any labour above company
                                                  Measurement effort across the company
                                                  known as ineffective labour due to overmanning, to arrive at the
                                                  effective labour on site.


                      Keep Clicking Anywhere on the screen to advance
                                                                                                                Quit
Overmanning To Complete Jobs Early                                                                                             Glossary


Butthe plannedjob early36 men was allocated,Manager attempts tosector-basedthe jobperiod, withgiven in the Industry
 To complete a level of a job early has a Using the previous 4-period complete overmanningtwo :- the followingin some
  If what happens if the needs to allocate less needs to referOf the 3 risk very early for the job,example, the job struck, but
                        the Construction the                   completed identified         the early, overmanning
                                                                                                       have so far
Trying to completenot Construction Manager job wouldplannedtheisTransportthreat of „hurricans‟ outstanding. was affects,
periods, but Management Consultants Report.number job benefitslevelthe the contract as an limits
                                                 than the haveto to still company, including
                                                    of earlythere of labour (36 in
 Information. is still      able to complete the               ?
  The Construction Manager                                                                                          How would
  shown in the
  men) in the job‟s final period to enable the job due overmanned the „hurricans‟ affect the labour wellthe job, of they struck In
                                     The effect of delays to complete at the end first two periods, and was on ahead if schedule. ?
                                                           indeed to                  in its of its final period. If
 For full 36 men in costs Transportjob will complete well before the of 4 periods, and that needed to complete the job a period
  the                  are allocated, the job that hasthird periodduration end of themen were
                                                           its labour on only 51 effective period, and
                                     risks on the effectivea
Thisexample, consider awillsite is shownretainedlevel inthese were allocated, as shown. can be overmanned by up to 45%
  The client may paynumber of reasonscompletion of period, incurring additional labour and site administration costs
   An increase for a as be incurred untilearly,plannedend (see below).
  additionaloccur costs a bonuswas by risk period the
        may labour                                          the :-
                                       labour for early until the  and end.
 each period. Ifuse Construction Manager follows the overmanning guidelines, and the labour allocated to site isinformation in the
   Inefficient the of labour that could have been used elsewhere job delay is identified as being major, and fully effective,
                                                                                      The
  The company‟s ownshould bethat was being used on the completed job can be that this could affect the effective
 the completion schedule labour as follows.
                                     Industry Information.                            Industry Information reveals used on other sites,
  Since there is only 2.1% of the job left to complete, the labour level required is 2.1% of labour being reduced to 43.5 men,
                                                           However, job delays labour byin the effective 15%.
                                                                                       resulted between
the total labourthe labour shortage,new recruits,of the to97.9%subcontractors, may mean subcontractors.
   An overall „own‟ need to take on and well short oronly use having 36. 14 and of the period, and justis not to
    preventing (237), or 5 men (rounded up), athe job was perhaps level of to use end costly the job failed
                                                           and
                                                                  reluctance planned complete at the more
 Period Planned Labour                        Actual Labour                % overmanning                 Cumulative Labour
 overmanned enough. assets (plant, buildings etc) The Construction the job can be to adjust the labour level
    The company‟s capital
      1                   59                            85 complete.                  being used on Manager decides diverted elsewhere.
                                                                                   45 %                               85
   A2  poor choice of project manager reduces the productivity6of case the risk on site.
                          71                          102                          45from 5 to in the labour
The Construction Manager is also determined not to be caught out by potential delays187 strikes.
                                                                                        %
  Cashflowsfurther risks strikes, and decides to carry out a detailed risk analysis before
                                                                                                                     in
  the3 if any are71
       job                  improved.
                                                        50 ----------------------------------------------------------------------------------------------------------
                                                                             Undermanned                           237
deciding upon thejob, labour level. risks Key Point(s)
   Delays to the 36 caused by
      4                    final                           striking, reduce the effectiveness of the labour on site.
                                                                                      ---------------------------------------------------------------------------------
                         ---                               The Construction Manager should have allocated more labour during the third
                                                                                      Key Point(s)
In this scenario, the job would enterperiod to compensateperiod out of delay, and of the completion been allocated
                         237                                 its final plannedIf the an potentialcompletionadditional labourcompleting at
                                                                                                    Early step with a job means has schedule
                                                                                         for risk does not hit, and the job would have completed.
determined by the estimators. In all probability it would in case it does, then there may bebecausethe has labour
                                                                                      just still be aheadperiod before the end ineffective been
                                                                                                    least one of schedule, some of it
overmanned, but the Construction Manager must be the client. planned duration e.g., if thenot allocating additional
 The job should complete a period early, securing a bonus from very careful aboutconsequences of planned duration is
                                                                                      on site. However, the setting the labour level, since
the planned level cannot be relied upon.                                              labour could periods, it must be completed in 3 periods or
                                                                                                    4 be severe if the job then overruns. This is
 ------------------------------------------------------------------------------------------------------------------------------------------------------------------------
 Key Point(s)                                                                         especially true in the final planned bonus. of a job.
                                                                                                    less to obtain the client period
 Overmanning above the effective labour limits results in ineffective labour that does not contribute to the progress of the job, but
We will now costs.
 incurs labour examine how the Construction Manager sets the correct labour level to complete the job its
                                                                                                    The bonus paid by the clientmade adepending in
                                                                                                                               The job varies large loss
as efficiently as possible.                                                                         upon the job size. final period, due to an inefficient
                                                                                                                               level of labour allocation.




                                Keep Clicking Anywhere on the screen to advance
                                                                                                                                                                 Quit
What Happens If A Job Overruns                                                        Glossary


Ideally all jobs progressed will be completed either early or on time.
 Once the period has been completed, the Job Details
  The relationship with the client will also have been affected by the late completion of the job.
 shows the penalty incurred for late completion.
However, this is not always the case, and if a Homes would bebeyond its than „poor‟ if job
  In this particular example, the relationship with Lowry job overruns much better planned duration there are a
number of affects :- late, job late is a %now affect Considerprocure any further work with the client
 The penalty for completing a and this may of the tender
  172 had not completed                                  trying to the following example.
 value per period, as defined in the Industry Information.
  in the future.
                                                      Job 172, planned to be a 2-period job, has overrun into its third period.
 A penalty will be incurred from the client for late completion, expressed as a % of the tender value
  for each period the job overruns. This canThere aresevere affect on the company‟s cash account, and
                                              have a currently 39 of the company‟s own labour on site, but with no
  company value.                             planned labour as a guide, what level of labour is required to
                                                                        complete the job this period ?
 Additional resources will be needed to complete the job (labour, project manager), diverting themis
                                                                      The penalty for completing a job late
  from elsewhere.                                                     a % of the tender value per period.

 It reflects badly on the industry‟s perception of the company, reflected in the „contract completion‟
  and „client satisfaction‟ key performance indicators used to measure the progress of the company.
The Job Details shows :-
If a job overruns, it is imperative that the Construction Manager allocates enough labour to complete
 The planned % complete after each period.
the job in its first overrunning period (General tab)
 The actual % of work completed to date (Performance (by period) tab)

The job is currently 92.9% complete, and has overrun.

There is 7.1% of the job left to complete, or 7.1% of the total labour required for the job
(91 man periods), equating to 6.5 men (.071 x 91). To ensure that the job completes 7
effective men should be allocated to the job.

If a job overruns you can allocate as much labour as is required to complete the job, and
the normal overmanning rules do not apply, since there is no planned labour as a guide.

-----------------------------------------------------------------------------------------------------------------------
Key Point(s)                     Keep Clicking Anywhere on the screen to advance
Delays caused by risks occurring are not an issue when jobs overrun, since risks will
only strike during the planned duration of a job.                                                                           Quit
Handling Job Delays                                                                             Glossary


Risks only strike during a job‟s planned duration, the Constructionlate. Hence the Construction Manager
The effectiveness of labour allocated to a job byand not Consider the Manager can be adversely affected
                                                         if it runs following example.
does not need to adjust such as :-
by a number of factors, labour levels to compensate for possible job delays if a job overruns.
                                                     When setting the labour levels during period 9, the Construction
                                                    Manager should have referred to the Risk analysis for jobs
                                                         Job 128 should have completed in period 9, when the
                                                    won and progressed.
Another consideration is whether or not to allow own workforce
 The training of new recruits into the company‟sfor job required level of 51 men wereperiods of site. It may
                                                          delays during the early allocated to a job.
well be that the of is project manager early site What does this reveal ?
 The expertise jobtheovermanned in theon theperiods with the intention of completing it late, and hence
                                                      However, the effective level of labour was reduced by 7.5
any delays can of the site
 Overmanningbe compensated for in future periods.    men due to delays. This resulted in the job being 97.9%
                                                                                   complete at the end of period 9, and not quite completing.
However, it is essential to consider potential delays in Manager in which the into expected to
There is also another key factor that the Constructionthe periodneeds to takejob isaccount, and that is
complete, in order to ensure that the job does finish. The
delays to the job caused by risk events becoming a reality. Construction Manager did not take into account the
                                                                           affect of possible delays when setting the labour level, so
We will look into how the Construction Manager can mitigatecould the labour level have been of job delays
                                                                           how
                                                                                  against the consequences adjusted to mitigate
                                                                           against the delays ?
caused by risk.                                                   The Industry Information reveals that a major job delay could
  At the start the Construction Manager is able to see :-
  For job 128 of period 9 only one risk had struck on the job, „personnel issues‟ during period 8. This left 2
                                                                  reduce the effective labour on site by between 14 and 15%.
  potential risks that could strike during period stage (risk register)
   The risks identified during the procurement 9 :-
                                                                  For job 128, 51 men were originally allocated to site. Assuming the
   The affects of the risks striking, a major joblikelihood, impact costs and job delays
      „Hurricans‟, which would cause in terms of delay
                                                                  worst possible case, a 15% reduction in the effectiveness of the
   Any contingencies built into the bid cause a major job delay impact cost
      „Accident on site‟ which would also to cover the likelihood and
                                                                  labour, 60 men should have been allocated, and the job delay
                                                                  would not have prevented the job from completing during period 9.
  If a number of risks could strike the delay to the struck. This knowledge is the i.e., it deciding how
  And, most importantly, whether or not the risks have job is the worst case possiblekey to is assumed
  that the other delays occur within the timeframe of the worst the risks have no additional affect.
  to adjust labour levels to guard against job delays caused by case, and occurring.
                                                                  ----------------------------------------------------------------------------------------
                                                                  Key Point(s)
  How does the Construction Manager change the labour level to ensure that a major delay does not
                                                                  If the risk does not strike, the additional labour is ineffective, and
  prevent the job from completing during period 9 ?
                                                                  would generate additional labour costs if the job completes before
                                                                  the end of the period, as the labour is retained on site until the end
                                                                  of the period. However, this is less costly than the job not
                                                                  completing, especially if it overruns and penalty clauses are
                                                                  imposed by the client.


                             Keep Clicking Anywhere on the screen to advance
                                                                                                                                                  Quit
New Recruits v Subcontract Labour                                                                                 Glossary


Clearly the decision as to whether to employRecruits:to useorCostssubcontractors is complex, and
New Recruits
Key Point(s)                                     New new recruits
                                                            New Hidden use
In progressing jobs it Subcontractors cost-effectiveRecruits:the company‟s own fully trained operatives
                            is always more New Recruits: Site CostTraining Cost
than using subcontractors. costs, including :- though therecruitto whetherbe own labouralso aone. farofon site, site
involves many factors Subcontractors a notAs well as newtrainingand areto costs, therenew force or withhidden costs
Determining an overall labour shortfall indonew need toAbe trained,recruitsitefully trained inare recruitseffective moreCompany,
Where there is the cost of employing the period, the decision as company‟s effective from is notperiod
                             and                   recruit the new needs being trained, and day number the
                                                Even          into the and is to employ their first is
complicated than further complicated by a subcontractor,quantifythere is an associated be they cost. they are
use subcontractors is the calculation for the costs are the numberpaidnew recruits that can job takenjoballocated to.
                                                 that still and to and varies depending upon the
                                                limit on hard as abe of :- cover them on the training are
                                                            need to result to
allocated to. the
Subcontractors :- numberIndustry do incur anthat can be employed period.shown in the Industry Information.
                            However, they Information. The limitsubcontract premium,
on in a period, as defined in the
 The limit on                    of new recruits
                                                     additional can vary each
                                                          The training man period in the from job to job, but tend to be cheaper in
                                                         Site costs pertime could extend the planned contract time resulting in penalty
                                                                  Using information vary Industry Information the training cost per
 Cost time it takes tolabour new recruits, andiscost recruit this couldeach subcontractor used.Transport Sector.
 The more closer looktrain costs involves. that are more calculated offset bysuch as the
             than own In this example the premium new involved. for be as follows :-
                                                   sectors 1,200 per period
                                                      charges, although is labour intensive, allocating labour levels above the
We‟ll take a             at the
 Reliance on subcontractors can paid whilst morale arethe company‟s own labour
                       need to be affect the example training:- trained.
                                                      planned ones.    of being
 The site costs that ------------------------------------------------------------------------------------------------------------------------------
                                                   In the people shown time is 2 weeks
                                                               The
                                       Eventually own labour may need to be paid off when work dries up, / 52)
                                              The
 The additional cost Keyemploying subcontractors. training cost per week is 577 (training cost per annum incurring
                      of Point(s)
                                                     The is The per regardless cost The upon off of they are used.
                                The subcontractor premiumsitethe labourman periodon 10,806laying whichown labour may then impact
                                                       additional same payoff charges. isjob
                                                               cost overall training is the 1,154 (2 x 577)
However, if there is an overall a contract.on labour relations, affecting the morale and productivity of the workforce
 The anticipated duration of labour shortfall thatweek is 831 (10,806/13)
                                         The cost per the Construction Manager needs to address, two
options many periods :-
 How are available subcontractors need to be employed for.
                                         For the 2 weeks training for a new recruit, the cost is 1,662
                                           across the company.
                                                  ----------------------------------------------------------------------------------------------
                                                                    Key Point(s)
 Take-on newof using subcontractors company‟s own of the company‟s own labour, which upon which the new
 The affect recruits, adding to the on the morale labour is the same regardless of the job is covered in
                                             The training cost
 Use subcontractors
  another demo.                              recruit is used.


But which it is worthnow the most cost determine the most cost-effective approach, which is often job
However, option is taking the time to effective ?
dependant, as this can affect the profitability of a contract.
To answer this question we need to compare the costs involved in taking on one new recruit against one
subcontractor.
In general, in the short-term the choice can vary, but in the long-term the continued use of
                                           The new recruits limit is shown in
subcontractors will almost certainly prove more costlyInformation. on and training new staff, since the
                                           the Industry
                                                        than taking
subcontract premium has to be paid every period.




                              Keep Clicking Anywhere on the screen to advance
                                                                                                                                                  Quit
Labour Relations                                                            Glossary


The most cost-effective wayExample force affect of the company‟s construction management decisions on labour
In any period a company‟s total labour 2:The consists force is to use the company‟s own fully trained
                             of Example the good labour relationsaction
                                 managing 1: labour of relations in in action
                                           poor labour :-
labour, rather than subcontractors.      relations is reflected in comments in the Management Consultants Report.
For example, if 50 men are transferred to the idle labour pool from job A, then they are immediately
                                                    Labour on
used on job B. No training isidle labour no men are laid off, and the company does not incurof the additional
                            Labour required,
    85 men were available in the in                   Jobs in                             All any men in the
    pool. All 85 were laidthe when they could
                           off Idle Pool                                       Total Labour
costs such as subcontractor premiums.                Progress
                                                                               in Companyidle labour pool were
    have been utilised on jobs.                                                                          used on site.
                            (Own)
In this scenario the company would be perceivedin the idle labour labour relations policy, and the morale of
                             21 men were available
                                                   to have a good
                                                   (Own + Sub)
the company‟s own labour would beand none were laidgreater productivity.
                             pool, high, ensuring off.

                   10 men were laid off from site,                           201 subcontractors were used.
                   when they could have been
The least cost-effective way of managing the labour force is to be constantly hiring and laying off the
To source the jobs in progress with the labour required the Construction Manager will often be faced
                   utilised on other jobs.
company‟s own overall labour shortfall,on subcontractors. situation a number of decisions have to be
with either an labour, and also relying or a surplus. In this
made on how besthigh proportion of the company‟s own labour is laid off in a period, then the morale of
For example, if a to manipulate the labour force.
                         Additional labour was the company‟s
the remaining own labour (not subcontractors) would be weakened, leading to reduced productivity. In
The options available include and not subcontractors relations policy.
                         own,
                               :-
this case the Company would have a poor labour

For the Company‟s Own Labour
 Laying men off from the Idle Labour Pool (ILP) illustrate good and bad labour relations.
We’ll now look at more detailed examples that
 Transferring men from the ILP to jobs, or from jobs to the ILP
Taking on new recruits onto jobs or laying off labour from jobs
  The Construction Manager was able to manipulate the labour force so that :-
For Subcontract Labour not manipulate the labour force effectively, and :-
 The Construction Manager did                                                         None of the company‟s own
 Taking on or releasing subcontractors
  All idle labour was redeployed to site                                             labour was laid off from site.
 Used 201 subcontracts when men were availablenot the idle pool, but were paid off
  Additional labour was the company‟s own, and in subcontractors
 Laid off of the company‟s own labour was could have been used instead of subcontractors
  None 10 men from site, some of whom laid off                                                               No subcontractors
  No subcontractors were used                                                                                were used.
                        Keep Clicking Anywhere on the screen to advance
 This is an example of poor labour relations, and the productivity of the company‟s own labour
 would bean example of good labour relations, and the productivity of the
  This is adversely affected.
  company‟s own labour would be improved.
                                                                                                                         Quit
Forming Client Relationships                                                           Glossary


Each periodcan influence their relationship with a in the market. following example. marketing effort will determine
The company a number of jobs are available client in a numberThe company‟s
                                                       Consider the of ways :-
how many of the jobs the company identify (prequalify for).
Positively by :-                                       Its period 9, and the company have prequalified for a job with East
                                                       Midlands County Council.
Each job has a client, in either the public or private sector, for whom the work is to be carried out.
Submitting competitive bids
  Procurement
Managing jobs well, and completing them at least on schedule company prequalifies, tenders for and secures work with the client
                                                       As the The Client History provides a detailed
  As time passes, and depending upon economic
                                                       a relationship is built company‟s current parties.
                                                               analysis of the up between the two
Negatively byclients may look to preferred bidders,
  conditions, :-
                                                               relationship with each client.
Submitting uncompetitive (poor)not strong enough
  and if the client relationship is bids               The current state of the relationship can be analysed using the
Managing the jobs poorly,accept the bid. late
  the client may refuse to and completing              Display Client Details option.

In this example, the company currently have a good relationship with East Midlands County Council based upon :-

Prequalifying for a number of jobs with the client
Securing job 42 with a competitive bid, finishing it early and managing it very well
Putting competitive bids together for jobs 125, 163 and 190, even though they were not secured
                       Performance Indicators
But why is the client relationship so relationships with ALL clients forms one of the key performance indicators
                       The company‟s important ?
                       upon which the progress of the company is measured.




     Prequalification
     The company may not be able to prequalify for work with a client if the
     relationship has deteriorated.




                        Keep Clicking Anywhere on the screen to advance
                                                                                                                         Quit
Performance Indicator Definitions                                                                 Glossary



Turnover
  • Measured value accrued across all jobs progressed; an indication of how much work the company has done.

Gross Profit to Turnover
  • The ratio of gross profit to turnover across all jobs progressed; a measure of how profitable the company‟s jobs have been.

Operating Profit to Turnover
  • The ratio of operating profit to turnover; a measure of how profitable the company is after considering all operating factors.

Company Value
  • A measure of the asset value of the company.

Capital Employed
  • Measures how much of the company‟s capital base is being utilised.

Contract Completion
  • A measure of the number of jobs completed early, on time or late.

Forward Workload
  • The remaining turnover (value) of jobs still in progress.

Forward Margin
  • The remaining profit of jobs still in progress.

Share Price
  • A measure of the strength of the company‟s share price.

Client Satisfaction
  • An indication of how happy the company‟s clients are; based on procurement and job progression.
Calculating Performance Indicators                                                                     Glossary




   Client Relationship
   To gain a feel for the relationship with each client, a textual description is given. The description is based upon a numerical
                             The Company is now in period 9, but how were the performance
   value (hidden) determined by a number of factors, including prequalification, procurement and job progression.
                             indicator weightings calculated at the end of periodShare Price
                                                                                       8?
Contract Completion
   The sum of the numerical values across all clients is calculated for the relationship changes since the History, Periods)
                                                                                     The Financial Analysis (Performance Alland then
Byadded to the performance indicator weightingJob Analysisthe History.
    examining the Performance Statistics and at the end of we first determine thethe share price :-
                                                                                     shows
                                        Turnover Value
                                        Company
number and Capital Employed Forward Margin Workload
                                                Forward
                size of jobs completed since the History.
                                        The Financial Analysis (Performance All Periods) shows :- company value :-
                                                                                                        the
   In this example the numerical valueProfit tothe forwardratio to(Performance All Periods) theas athemargin70workloadof
                                  Gross         The Turnover ratio                    At the end
               After bids have been processed,to Turnovercame 139.the Periods) showsof shows ratingthe1.35 give an
                              Operating during periods 5-8Analysis of All company expressed Historyof of upper limit :-
                                    The Financial Analysis (Performance Periods) shows :- the forward forward to
                                           Profit Financial workload            This was added to the initial % was :-
Each completed job is that canThe undertaken, based (Performance Periods)  At the:-end of period 8 was 1.95
                209 at the end of be Financial Analysis upon the company‟s capital base, is the capital employed.
   indicator ofworkload given a score depending upon :-                     All
                              The period at the end of(Performance All 4,685,339 13,976,699
                                           8.
                                   Financial Analysis the History was 1-4) was        shows
                                        
                                        The Historical turnover (periods
                                                 or Late
 Whether the job completed Early, On TimeAt the end of the History was 29,984,240
                                     AtThe turnover to date 8was 5,821,887
                                  The Historicalofthe end of period 1,321,072 been1-4) was 0.0438 (612,635 / 13,976,699)
                                        the the endthe period turnover 1-8) has
                                           at end grossHistory(periods ratio (periods 76,268,479
                                                      of profit/ was
 The job size                       Historicaloperating Periods) shows the average 1-4) at employed :-
                                                 At
               The Financial Analysis the end of period 8 was 1,409,8288 was 30,171,560capital the end of period 8 13,976,699)
                              The  At(Performance Allprofit/ turnover ratio (periodsvalue was 0.0151 (211,533 /was 1.44 times the
                                                                                     The
                                  The gross profit/turnover ratio to date (periods 1-8) has been 0.0532 (4,060,639 / 76,268,479)
                              The operating profit/turnover ratio to datedate1.2421-8)Historical benchmark, which is 76,268,479)
                                                                                     value at the end of the History.
                                        To compare fairlyend of period to was with the has been 0.0274 (2,089,389 /History. upon
                                        The value at the the turnover 8 (periods times the value at the end of the based
e.g., large jobsFor the Historyearly are given the 41%at the /end 8 was 1.07 was 1.006 times the value of the History.the History.
                 that complete (periods 1-4)at the best (164 (+ve),period 8 times the value at the end at the end of
                                                The value of period of whereas large jobs
                                         value was of       score 4)
                                    Theone the we endperiod 8 was the average per 0.0438) times the value at
                                  The ratio year, endneed to work out1.2146 (0.0532 / year, which is 38,134,240 (76,268,479 / 2).
completing lateTo date (periods ratio hasat(-ve). of period 8 /was 1.8146 (0.0274 / 0.0151) times wasvalue at thethe endthethe theof
                are given the worst scorebeen 66.5% (532 reflected in an increase in the company value performance indicator
                              The 1-8) The improvement was 8)
                                         at the end                                  The improvement the reflected in end of
                                                                                                                          an increase in
                                  History.
                                    Thefrom 140, improvement was reflected in sharethe forward margin indicator13,976,699) initial
                                         improvement was weighting, an period anxincrease in the forward workload performance
                                                The
                              History. The yearlythe initialreflected in to 174 (140 wasprice performance performance 70, thethe
                                                     average by the end of increase in1.242). times (38,134,240 /
                                                                                      8      2.728
                                                                                                                          from
The total calculated is added to the initial indicator 1.62 timesat the end at theweighting,(70 101 (70 x 1.44).
               The value at the end of valuefrom 100,fromthe History. weighting, to 70toto x 1.006). / 41).
                                    indicator indicatorweighting the initial of the end of the History (66.5
                                                               70,
                                         period 8the end of initial the value          History
                                                at was the
                                  This deterioration is reflected inweighting, to 107 (100 x 1.07).
give the current indicator value. deterioration is reflected in a fall fallthethe gross profit to turnover performance indicator from
                              This
                                                                     a
                                                                       in
                                                                            in
                                                                                operating profit to turnover performance indicator from
                                  100, the initial weighting, to 121 (100 x 1.2146).
               This improvement is reflected in an increasereflected 1.8146).
                              130, the initial improvement is in(130capital employed in the turnover performance 140, the initial 50,
                                        This weighting, to 235 the x in an increase performance indicator from indicator from
In this example the 9 completed jobs created a score of 80, which when added to weightings used in calculating the client
               weighting, to 227 (140 x 1.62). weighting, to 136 (50 x 2.728). The the
                                        the initial
starting point of 130, gives an indicator value of 210 at the end of period 8. satisfaction values are hidden, but the relative
                                                                                      affects, from largest to smallest are :-
Notes
                          Keep Clicking Anywhere on the screen to advance
Irrespective of size, jobs that are complete late incur a bigger penalty than theJob Progression
                                                                                       gain
 from jobs completing early.                                                           Procurement
                                                                                       Prequalification                              Quit
The Use of Performance Statistics                                                                                               Glossary


We‟ll look at how performance statistics can help to explain whether or and weaknesses in indicators.
      now first at how performance statistics can help to explain changes incompany strategy has been
                                                       identify strengths not performance company
                           The Procurement Analysis for the early years shows that out of 36 jobs bid for, 27 were lost.
successful.
performance.
                                            85% of the jobs were lost de to “workload limitations”. This could possibly have been avoided
                                            if the Financial Manager had increased the company‟s capital base more during periods 5 to 8 in
                                            order to enable the company to take on more work.

                                            Using the performance statistics in this way will enable more effective decisions relating to the
                                            capital base to be made in future periods.




          Consider the performance indicators of the company after 8 periods.

          Since the end of the History the Gross Profit to Turnover indicator has increased.

          This would appear to indicate that jobs have been managed slightly better sincethat provide :-
               During the Early Years the company have tried to invest in other concerns the History.

                A our reasoning, we can look
          To verifybetter return than the bank at the performance statistics for both the History and the Early Years.
                Reduce overall build costs in jobs in progress e.g., by obtaining better discounts from suppliers

                 Has the strategy paid off ?
Evidence from the performance statistics shows that :-
             The performance statistics provide evidence that it has, with overall jobs costs being reduced by
During the History the average job profit was 4.6% (of cost)
             0.77%.
During the Early Years, up to the end of period 8, the average job profit was 5.9% (of cost)

This is clear proof that job profitability has improved since the History. The Job Analysis information can be used to analyse even
further where the improvement was.
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Key Point(s)
                                 Keep Clicking Anywhere on the screen to advance
The performance statistics cover the early years and the history separately, but many of the performance indicators cover the
full lifecycle of the company. These are specifically the trend-based ones such as turnover, gross profit to turnover etc.
                                                                                                                                                                    Quit
Job Details                                                                          Glossary


                 Job number                             Type
                 A unique number that                   There are two types of job :-
                 identifies a job, ranging from
                                                         BO (Build Only); traditional type of job where the client
                 1 (earliest jobs) onwards.
                                                          is responsible for the design, if appropriate, and the
                                                          contractor is only responsible for the build.
                                                         DB (Design and Build); the contractor has
Period of prequalification                                responsibility for both the design and the build.
The period in which the
company identified the job                                                              Size
through marketing effort.
                                                                                        The size is based upon the approximate value :-
                                                                                         Small (approx value range 1m - 6m)
                                                                                         Medium (approx value range 7m - 13m)
Country/Location                                                                         Large (approx value range 14m - 25m)
Where the job is located.


Approximate value
The anticipated cost of the job
rounded to the nearest million.



Duration
The planned duration of the
job, between 2 and 5 periods.


Description
A brief description of what
the job entails.
                                                                                                                       Total labour manning
                                                                                                                       The total number of man periods
                                                  Client
                                                                                                                       required to complete the job.
                                                  The public or private-sector
Sector                                            organisation for whom the job
Each job falls into one of 5 market sectors :-    is being carried out.
   Industrial
   Building and Commercial
   Transport
   Energy
   Water and Sewage
Measured Value (Turnover)                                                                             Glossary


Each period, three values are calculated for a job :-
For each job awarded to the company, there is a planned value per man period defined as :-
 The Expected value is the labour on site that contributes to progressing the job (effective labour)
  multiplied by Value Per Man Period =
    Planned the planned value per man period. Bid Value              / Total Labour (periods)

 The Actual value is the expected value adjusted to take into account a number of factors that affect
  productivity on the job :-
    The performance of the project manager allocated to the job
    The labour relations policy of the company

 The Measured Value (Turnover) is the actual value adjusted by the measurement effort of the
  company for the period.                      In the example shown:
                                                Planned value per man period = Bid value / Total labour (periods)
The measurement effort depends upon how well the company‟s measurement staff are able to cope with
the turnover in the period across all jobs. The last period of the history provides the /benchmark for
                                                                             = 8,627,856 126
determining the appropriate level of staff required.                         = 68,475

                                                ------------------------------------------------------------------------------------------
                                                Key Point(s)
                                                The build and site cost ratios per man periods are calculated in
                                                similar ways, using the total labour (periods) as the denominator,
                                                with the appropriate estimated cost as the numerator.




                    Keep Clicking Anywhere on the screen to advance
                                                                                                                                   Quit
Job Costs                                                               Glossary


                        Design Fee
                        Applicable to design & build jobs only, the design consultant
                        charges a fee payable over the planned duration of the job.



                       Build Cost
                       Build costs cover all the direct costs (labour, plant, material etc)
                       needed to complete a job.

                       The build costs incurred each period depend upon the effective
                       level of labour allocated to the site.


                      Site Cost
                      Site costs pay for the support staff and services required to
                      administer a site whilst the build is taking place.

                      The level of site cost paid each period is based upon the total
                      labour (own and subcontract) allocated to the site.




Completion Penalty
If the duration of a job exceeds its planned duration, the
company is charged a penalty for each late period.

The penalty is a percentage of the tender value (bid entered) for
the job; details are given in the Industry Information.
Labour Costs                                                  Glossary


The labour costs are allocated to either job or overhead costs. The applicable rates are shown in the
Industry Information.

                                                                        Training cost (job cost)
                                                                        A new recruit needs to be trained in
Labour cost                                                             their first period with the company,
The cost of a general labourer used                                     and as a result there is an
on site; used as the basis for                                          associated training time and cost.
calculating ineffective labour.




Labour payoff rate (job/overhead cost)
This is the cost per person of laying off the
Company‟s own labour from either :-

The idle labour pool (overhead cost)
A job in progress (job cost)




                                                               Annual cost of idle labour (overhead cost)
                                                               This is the cost of keeping someone idle for a
                                                               year, and takes into account the redeployment of
   Subcontract premium (job cost)                              the person in other areas.
   Subcontractors are 100% productive as soon as they are
   taken on, and require no training. However, using them
   incurs an additional cost above the normal labour cost.
Bonus For Early Completion                                                  Glossary


The client pays a bonus for early completion of a job.

Early completion of a job means completing at least one period before the end of the planned duration
e.g., if the planned duration is 4 periods, it must be completed in 3 periods or less to obtain the client
bonus.

The bonus varies depending upon the size of the job, and is expressed as a percentage of the tender
value (bid entered) for the job; details are given in the Industry Information.

                                                                                     The bonus is shown in the
                                                                                     Job Details for the last
                                                                                     period of the job.




                                                         The early completion
                                                         bonus varies according to
                                                         the size of the job.
Retention                                                             Glossary


Retention is a held came from a number of jobs progressedachieved on 7. job in a period that is retained by the
   The retention % of the measured value (turnover) during period a
client until the job is completed.                 Retention affects the cashflow of the company.
                                                                    The Retention Analysis for jobs won and
   The Industry Information showed retention to be 1% of measured value i.e., Financial Analysis shows that in period 7
                                                    In the example shown, the
                                                                    progressed provides comprehensive information
If 1% ofjob is not completed to a satisfactory the company‟s retention figures wereheld and repaid, alongsome of
   the 15,429,190, or 154,292.                      level determined by the construction contract, with the
                                                                    about all retentions :-
the retention may not be repaid.                                    outstanding net retention to be repaid.
                                                     208,422 repaid from completed jobs
Any retentions held are repaid in two equal instalments :- from work completed from jobs progress during the
                                                     154,292 held
                                                      period
 In the period when the job is completed           The net retention of 54,130 helped the cashflow.
 2 periods after the job completes




                                                                                Details of the % retained are shown in
                                                                                the Industry Information.




                       Keep Clicking Anywhere on the screen to advance

                                                                                                                         Quit
Percentage Of A Job Completed                                     Glossary


The % of a job completed on the Job Details does not always equate to the measured value recovered
on a job in relation to the original bid value. with a bid of 11,540,390
                                  A job was won


We will take a closer look at this anomaly.




The job has just completed its 1st period, and the total value to date is 4,450,044.

This equates to 38.6% of the bid i.e.,

(4,450,044 / 11,540,390) * 100

However, the % complete shown is lower at 38.3%, so why is there a difference ?

The % complete is derived from the actual amount of the job completed to date.

However, the company‟s measurement effort has secured an extra 0.3% of value
over the 1st period, which is incorporated in the total value.




                        Keep Clicking Anywhere on the screen to advance

                                                                                                Quit
Forward Workload And Margin                                                                                Glossary


The forward workload (or potential turnover) on a job is forward workload and margin values at the end of period 8
                                                         The the remaining value to be recovered from the
present time until the job has forward workload and margin values determining the amount of progress. the company
                           The been completed.             When were formed from
                                                         are shown in the Financial 6 jobs in
                                                                                    Analysis.
                                                                                              work that
                                                         cannot undertake based upon the size of the capital base,
                                                         the forward workload at the end of the previous period is the
The forward margin is the Taking job 172 remaining profitstarting point shown, at the end of period 8 the company‟s :-
                          anticipated as an example :- In the example for any calculations.
                                                           on a job.
                                       49.8% of the job was left to complete at the end of period 8, giving a remaining forward
                                                                         Forward Workload was 30,171,560
Both are calculated at the end of a of 2,464,075 (49.8%the company‟s decisions have been processed. to the
                            workload period, after all ofForwardvalue any bids won during period 9 are added
                                                          The value of of 4,947,942)‟
                                                         the bid Margin was 1,409,828
                           The forward margin figure comes initial the forward workload less the remaining cost. used to
                                                                         from forward workload, and the cumulative figure is
                                                                        determine how much work the company can undertake.
                                                                     The ? Can be used to drill-down to job-level detail.
                          -----------------------------------------------------------------------------------------------------------------------------
Forward workload and margin are important because :-
                          Key Point
 They are two of the key The remaining cost is based upon the anticipated true costprogress taking into account
                           performance indicators upon which a company‟s of the job, is measured.
                          build cost, design cost , site cost and project manager costs.
                          In the case of design costs the quality of the design produced by the chosen design consultant
 The forward workload providesinto Forward workloadaffectmargin form 2 of theprocess for determining whether
                          is taken
                                      the starting pointand on the build costs. key performance indicators.
                                           account, and the
                                                                    during the bidding
   or not the client will allow the company to bid for a job based upon capital base limitations.
                                     Both indicators increased during period 8, which can be further verified by
We will take a closer look at how both are calculated, andAnalysis (Performance All Periods).
                                     referring to the Financial used.


                                                                      The forward workload and margin values at the end
                                                                      of period 8 were considerably higher than at the
                                                                      end of period 7, and this rise was reflected in the
                                                                      increased in the KPI weightings.




                             Keep Clicking Anywhere on the screen to advance
                                          The for ward workload at the end of period 8
                                          is shown in the Financial Analysis.
                                                                                                                                                Quit

More Related Content

PDF
energy future holindings _062705
PDF
du pont 2005 Annual Meeting Proxy Statement
PPTX
Finning cibc whistler conference final
PDF
Kibel Green Intro2010
PDF
Second Quarter Masco Earnings Presentation
PPT
Chapter 7
PPTX
High-tech S&OP IE Event on April 19
PDF
Tulevaisuuden ostaja rakentaa kumppanuutta ja vaatii kilpailukykyä 18.9.2008 ...
energy future holindings _062705
du pont 2005 Annual Meeting Proxy Statement
Finning cibc whistler conference final
Kibel Green Intro2010
Second Quarter Masco Earnings Presentation
Chapter 7
High-tech S&OP IE Event on April 19
Tulevaisuuden ostaja rakentaa kumppanuutta ja vaatii kilpailukykyä 18.9.2008 ...

What's hot (19)

PDF
Minacs spend smart
PDF
CFO and Art Of Mergers and Acquisitions
PDF
Performanceleadership
PDF
Third Quarter 2012 Investor Presentation
PPT
Stragic anlysis
PDF
profitability cost mgt
PPTX
Aero project 2013- Herve CALMELLY
PDF
Business Game
PDF
Pragmatic Marketer Volume 8 Issue 2
PDF
Mark johnson business model transformation
PDF
Delivering Synergies : A closer look at post merger integration
PDF
George W. Buckley Presentation
PPTX
PDF
public serviceenterprise group CapReOFlynn
PDF
Managing performance in the downturn
PPTX
NAPM AZ Presentation 25 Aug 2011
PDF
Lehman Brothers Conference Presentation
PDF
Swiss Re - EVM - slides 2006
PPTX
Q3 2012 Masco Earnings Presentation
Minacs spend smart
CFO and Art Of Mergers and Acquisitions
Performanceleadership
Third Quarter 2012 Investor Presentation
Stragic anlysis
profitability cost mgt
Aero project 2013- Herve CALMELLY
Business Game
Pragmatic Marketer Volume 8 Issue 2
Mark johnson business model transformation
Delivering Synergies : A closer look at post merger integration
George W. Buckley Presentation
public serviceenterprise group CapReOFlynn
Managing performance in the downturn
NAPM AZ Presentation 25 Aug 2011
Lehman Brothers Conference Presentation
Swiss Re - EVM - slides 2006
Q3 2012 Masco Earnings Presentation
Ad

Similar to Enginuity2012 tutorial (20)

PDF
Applying Global Benchmarking To Fm And Service Alan Masterton Aug 08
PDF
Smartsizing
PDF
OAUGNYC 2012, Product Spotlight: Oracle Hyperion Profitability & Cost Management
PPT
Strategy
PDF
Balanced Scorecard Presentation For Gemba
PPSX
ITSM Conference, Dubai, UAE 2009
PDF
Creating Value Through Consolidation
PDF
Jijesoft Your Strategic Partner
PDF
MCP4
PDF
Organize and Justify Your EMI Initiative
PDF
Industry solutions 2012 final
PDF
Cement plant catalog for operational excellence
PDF
Removing silos
PDF
Dynamic Process Transformation Platform on Cloud
PPTX
PPTX
Territory management for inside sales leader notes
PDF
Considerations in Selecting and Protecting Your IT Investment
PDF
Business Driven Architecture for Strategic Transformation
PDF
Making IT Talent Work SFIA
PDF
20090901 London Enterprise Session V3 Colour
Applying Global Benchmarking To Fm And Service Alan Masterton Aug 08
Smartsizing
OAUGNYC 2012, Product Spotlight: Oracle Hyperion Profitability & Cost Management
Strategy
Balanced Scorecard Presentation For Gemba
ITSM Conference, Dubai, UAE 2009
Creating Value Through Consolidation
Jijesoft Your Strategic Partner
MCP4
Organize and Justify Your EMI Initiative
Industry solutions 2012 final
Cement plant catalog for operational excellence
Removing silos
Dynamic Process Transformation Platform on Cloud
Territory management for inside sales leader notes
Considerations in Selecting and Protecting Your IT Investment
Business Driven Architecture for Strategic Transformation
Making IT Talent Work SFIA
20090901 London Enterprise Session V3 Colour
Ad

Recently uploaded (20)

PPTX
Microbial diseases, their pathogenesis and prophylaxis
PPTX
Lesson notes of climatology university.
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
VCE English Exam - Section C Student Revision Booklet
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PPTX
Cell Types and Its function , kingdom of life
PDF
Trump Administration's workforce development strategy
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PDF
Yogi Goddess Pres Conference Studio Updates
Microbial diseases, their pathogenesis and prophylaxis
Lesson notes of climatology university.
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
202450812 BayCHI UCSC-SV 20250812 v17.pptx
VCE English Exam - Section C Student Revision Booklet
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
Cell Types and Its function , kingdom of life
Trump Administration's workforce development strategy
Module 4: Burden of Disease Tutorial Slides S2 2025
Microbial disease of the cardiovascular and lymphatic systems
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
Weekly quiz Compilation Jan -July 25.pdf
FourierSeries-QuestionsWithAnswers(Part-A).pdf
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
Pharmacology of Heart Failure /Pharmacotherapy of CHF
Yogi Goddess Pres Conference Studio Updates

Enginuity2012 tutorial

  • 1. Enginuity 2012 Tutorial Copyright Virtual Management Simulations
  • 2. Navigation Navigate through the presentation by using :- buttons to load specific topics buttons for movement to specific points Demo buttons for self-paced demonstrations of topics Hotspot hotspots to display further information. The mouse, and not the keyboard, should be used at all times.
  • 3. Contents Getting Started The Task Timeframe Forming a Company Strategy Making Decisions Financial Management Overhead Management Procurement Job Progression Resetting Decisions Exporting Decisions Assessing Performance Key Performance Indicators Performance Statistics Management Consultant’s Report Analysis Tools Industry Information Industry Information Miscellaneous Exporting Information Glossary Exit
  • 4. Glossary Finance Procurement Dividend Job details Factors affecting share price Successful tendering Company value Margin adjusting Cash account Choosing consultant designers Overdraft limit Job risk Capital base Bidding cost Capital employed Investments Job Progression Project manager information Profit definitions Corporation tax Project manager performance Gearing ratio Measured value (turnover) % of a job completed Job costs Overheads Departmental overhead staff Labour costs Idle staff Retention Job completion bonus Forward workload and margin Miscellaneous The job cycle Client relationships
  • 5. The Task Getting Started The success UK-based construction company, with headquarters possible timeframes. A fledgling of the company is determinedmanaged through two in indicators :- been trading for just one The company will be by 10 key performance London, has The decisions global made, and mustofdemonstratingrests themanagement to satisfy the high The first task facing the new management team is to form ain challenges to overcome, such as client Managing the to be business involves the company, a range of hands of the new Working in different countriesfate present some particularbusiness strategyskills. management team. year. Turnover demands of the company's shareholders, who are keen to Contract Completion their investment. unrest, restrictions, global competitors and environmental problemsa (extreme weather conditions, civil see quick return on Gross Profit to Turnover ratio local labour problems etc). Forward Workload A new managementOperating Profitto run the company forForward Margin future, making the key team is needed to the foreseeable Although based in the UK, and subject Turnover ratio and interest rates, expansion into overseas to UK tax laws business decisions Company Value each period/quarter. markets, and different continents,and opportunities Managing ThePrice A lotsuch depend upon the Share Early Years However, the potential rewards may be an attractive proposition. of operating globally, will as worldwide client base, Capital Employed Client Satisfaction prevailing economic climate in large-scale contracts, may outweigh the risks. niche markets and lucrative the UK, and worldwide.Global Business The competition for jobs comes from a number of simulated companies. Each one has their own unique profile and bidding history, and a careful assessment of the opposition is required to formulate an effective procurement strategy. Management Corporate level Operational level skills required Road contract on HQ the US Interstate UK Economic Highway System Understanding the Forming company Later Years Climate Energy contract in the Middle East Overcoming Interpreting reports Measuring performance Analysing information Making key decisions Solving problems industry strategy problems Making effective decisions During the later years the teams compete against each other for work. This creates an even more uncertain and pressurized environment in which the skills and team dynamics formed in the early years are really put to the test. UK and worldwide Satisfy stakeholders Finance The indicators are all weighted at the Changes in economy Job delays start ofrequirements years to reflect their New competitors early the OPPORTUNITIES Improve asset value CHALLENGES Economic climate Marketing Building project in Achieve profitable growth Availability of work Overheads Changing client Rival competitionclient base Worldwide Increase market share Global competitors Manage risk Procurement variability, and initially sumNew1000 Personnel issues to Zealand Keep Clicking Anywhere on the screen to advance Client expectations Construction Supply chain problems Lucrative contracts Client expectations Enhance company reputation Niche markets Environmental issues Quit
  • 6. Timeframe Getting Started Theyour company alreadyCompany at successful periods, known asYears, you may be invited to If take control of the been operating for 4 during the Early the History Year, before You Company has is one of the most the beginning of period 5. You then manage the company you take overPhase of management. Later (two trading years). Thismanage the company take part number 2, known as the through a in the its periods, normally 8 Years. You then have to is known as the Early through Years. a further number of periods in direct competition with the other top companies from the Early Years. Each period represents one quarter, or 3 months. Start of Start of Start of History Phase 1 Phase 2 Period 1 …………… 4 5 ………………………………………. 12 13 ………………………. 18 Historical Year Phase 1: The Early Years Phase 2: The Later Years Keep Clicking Anywhere on the screen to advance Quit
  • 7. Forming A Company Strategy Getting Started Objectivelook at an example of setting key objectivescompanyto be answered, including :- After a thorough take a there are view questions the need strategy. In setting the to review, the following and runningthat company the next decisions for It is very easy objectivesshort-termmany toreviewing are set forby making year :- We‟ll now Overall, in reviewing our without looking at thethe original strategy, we have extremely the current period only, performance against wider picture. Whilst this hit and miss To build on steady, profitable growth,from 4.7m tofor the(by 10%) through Measurement well,havelevel ofcompany‟s achievedis especially the Head has been operating foraalong-term improve and value of the company relationships. aim forthat company existing price. increasing turnover from 28m (based improved the ensure the improve overheads, share client 5.17m Office, QHSE and on half of  What been areas the would we the objectives that year. We and may given have approach in all prove successful, it like toa company as effective as formulating growth task of running achieve ? unlikely to be year (the company profits, and profitable growth, increasing turnover from 28m (based on half of the departments,steady, making better yearof the company‟s assets. To aim for are staffed the next use manage with the increasing turnover. History at 14m) to 42m in sufficiently tothrough increasing prequalification for new work,  How are weis considered to be in value of the company ? History), and going to improve the a the company‟s objectives. strategy for the company, based uponsound position by both the industry and its board of competitive tendering and 42m in the next yearjobs. strategy in place. However, this would Gearing Ratio to 14m) to progressing ongoing through increasing prequalification ItHistory year of company company without any clearneed to achieve our objectives for new is possible at  What levels the company a a measure of are we likely to directors.ratio of manage is overhead Dividend Payments ? work, a very reactive competitive tendering and progressing ongoing jobs. In could create untold requireare we goingunlessapproach to running havebusiness, which the History (periodsand 4) a dividend of The gearing the of the shareholders ?  How liability, and is the lookcash account interests an impact in future periods, Decisions made in 0 tocurrent period often its debt the after the 1 to in problems asofthe value overall value of the companytake controlthe mostthewas paid each 4) to 5.8m, per To improve going the of the company from had to make cause (at effective the The status we the the company‟s activities, with to clients ? 5havocthroughuse of increased is overdrawn. unforeseen and unconsidered circumstances is (byValue Company was across 2%  How are end period 8 to improve relationships 4.7m our5.17mFuture10%) end 8 company valuethe different areas ofcompany/market when we and increasedIn periodsannum), which kept the shareholders By the :- Profitability from 4.7m through to of period period (8% improved organisation. an annual makingofbetter use of the the original objective. had a Future profitabilityeither way company‟s resources account was always easily surpassing company‟s Thewhich i.e.,positive affectaffect (forward company profits and increase 23%, assets. During the History the cash long-term planning is essential. representing company‟s no particular on industry steadily, content confidence fluctuated significantly would margin)the share price.and this in periods 5-8, ThereAn increase was no impact at theachieved throughand has of means :-price in themore company negative affect on  The are there inis valued on isthat also needThe Headconsidered, and creating a long-termhave in credit,company other areasaround 4.7m, and many company to be a share havingof 1.35. thanand share price. on company, To ensure that company overheads, not guarantee Head Office,it does give Measurement A clear, well-considered management will especially the14m(profitable growth), and company the second success, jobsQHSE and company‟s share and strategy is jobthe overhead strategy to generate staffed, at profit fromenable the increase in to was  Turnover a and efforts thethe MarketingaDepartment the periodically reviewed,company For example, complex task. Indeed, strategyaround129% ofmayrequired level to manage thecompany‟sthe will have to be butconfidence levelthe cash since company value a number Office Department was a the both positive adequately helped to increase  Good generated in of first year was operating industry progressedthe share price. the best opportunity tohave sufficiently andcompany anywork toincreasing seen by the comments in the departments, company‟s capital base to secure within the confines of the be5beneficial, updividend is  Utilising the aremay growbeen unattainable for with the tender be turnover.as point, bid staffed profitably toturnover. Indeed, overstaffingperiod the in of to a it manage reserves market which:- In objectives to a large job in period prequalify fordate 8 thein business. 5. The half of the first to However, in periods 5 year cash account was progress more number as can for the job, and a decide price, of reasons, such can maintained. operating. profit of 4.4%If the is not set in To inreturn However, strategy is submitted infinancingaother activities bid is was made on thejob costsprogresseduntil period 7. If it  Making effective use of the company‟s assets, such stone, andgood build to beopportunities the Head a better as the gains (lower investmentin regularlythat Report. and identifying needs costs the case of reviewed Management Consultants yield Office  A gross thanthebank offers, or investments that can with reducedjob will the additional cost. In this case there often improve overdraft, period 6. of share price. the company‟s turnover successful, the work not startto 8 shareholder expectation updated to takeoverheadmarketinto account anin not outweighing other1.5% theturnover wasgrowth  The base expansionfuture costs continuously changing of 142kIn levels had risen as company performance (capital Company‟sadvantage it should periods, of a forecasts was net gain environment. and secure Department) very accurate, In periods 6 were period 11. from of words, anticipated then runs for five and investments), and thecomplete a operating profitoverstaffing. of a decision on After taking To buildnow examine these areas to see which ones contributed to the increase in company value in the last year. gearing ratio fluctuated,improve both a on and which had existing client relationships. areas have positive affect on the effort in achieved. not materialised. whereWe‟ll target marketing company‟s period 5 has had an affect up until period 11, 3% had to be to negative and improved, and a dividend of and  Increased competition has forced margins to be reduced topaidcompany‟s turnover, were equally beyondcompany order book looksare taken into account. a forward workload of around share price. retention repayments extremely healthy, with The if secure work. Similarly, the QHSE and Measurement Departments, whose staffing is dependent upon the to keep them content. A Client an how did changed, client satisfaction rating hasstaffed. that were the proof  year later,anticipated profit of against the objectivessteadilyOverall,setaffects of the to enable the 30m, andexpectationswe perform 4.4% of relationships were not strong?enough levels of dividend Overall, the company‟s and client turnover.risen adequately each period, company to bid for work. work in the global met with regard to client relationships. Department as an affect  The overall value of new objectives have been market fluctuates Head Office had no noticeable that the company‟s around 400m. paid would have In order to decide upon the company‟s objectives, and whatat thebenchmark (last period of as „content‟ Looking can the company‟s share achieved be realistically sufficient  AInvestments improving relationships were established with Office, QHSE and Measurement number of clients. We have succeeded in our objective of maintainingprice, the History, example. The on over a periodin We‟ll now look at how period to managedBy improve ofperiod 4) the share price the risen quo. The company share time, there of we havewas 1.35. to the endanalysis staffing Investments of price at the end needs 4 results detailed other concerns had two positive be a :- inperiod 8,of :- maintainshad status to staffing levelsthethe Head just ? was 3 staff could cope with around relationships Summary the original objective Profit 1.95, and Operating was met. Departments. 10.9m of turnover per period, or 2.8m per person. Procurement Based onprequalified for jobs, to increase turnover it is essential that and a detailed review of procured. The A goodthe information information made an operating profit of 2.1% (before tax & interest). in a number of company‟s share returnrose during periods on investments was made, which relationships have factors were company Capital Employed the History the company given Since period 5 client was far more than improved above, your :- price of 4.5% per period 5-8, in line with company strategy. The contributory the equivalent In Having average capital base The the company‟sAnalysis we‟ll1.25%equipment, lookways :-key being utilised (capital employed), through contract If environment in which the per period. is operating Turnoverjobs period fluctuated a lot company at the Prequalification are successfully  Using the from the bank of around(plant,take a closerbuildings etc) issome of theinfluenced the share price :-during periods 5-8, per reports the Financial progression, then there is morethe turnover (measured makingin periodswere was 62.3m. year. By using and the market, we must decide businessBy company value) marketingfor adjusted accordingly. Dividend had no affectAnalysis, we can deducethe chance the as it stands job management. directing return Financial at weaknesses of that upon of thecompany‟s strategy 5-8 the next now areas that  The strengths andany time. this was improved to periods 5-8 the company bid for 36 of staff,and that it was procurement and In periods 5-8 As we can see from the Performance Statistics, during employing staffing levels and the good 4.5%, mainly throughmore a profit. the 46 jobs  Changes in payments to shareholdersby 0.77% by investing in appropriate would relationshipsectors that appeared to bestaffing Company were reduced value had a very positive affect  Changes in in42m, so Profitability capitalfuture utilised, the cash account,were sufficient,all jobs progressed. The likely competitionwell the our target. only 41% of in over base was WeOverallHistory, 9 (25%). Thethehad a mixed affect.increase the resources into during periods glanceduringthe future. with able to, and won Dividend build costswe were jobs secured helped aimed for there It level the market before, one now exists e.g., Whereturnovercompanies e.g., first 5-8, and forHead Office was no appear at investment that in PHS Keep Clicking Anywhere on the screen to advance In the Forward The profitexcavators to all directly into but this increasedcompany‟s theshare of the total market to an impressive 92% growing, thesignificantly % company‟s value.  Changes company value of would have fed sectors, reduced build Cornwall Water on but this can be verified by Excavators Plc, suppliers  Changes in in company future profitability Devon and costs improving levels periods 5-8.  Changes Gearing had a mixed affect. increased significantly during periods 5-8. Where a relationship didthe Performance has been aided by The high level of turnover was largely achieved by the impressive order referringplace at the end of the History, improved e.g., book in to exist before, this Statistics.  Changes in company new burden (gearing ratio) with Crawford Petrochemicals UK effective identification of debt work by the Marketing Department, and successful procurement for the rise in the share Although there were mixed affects, the positive affect of increasing company value accounted during periods 5 to 8. price. Quit
  • 8. Financial Management Making Decisions Financial management involves :-  Looking after the shareholders‟ interests.  Trying to increase the value of the company by making the best use of the company‟s assets.  Monitoring performance in all areas to improve company profitability. Financial Decisions Overdraft Limit
  • 9. Overhead Management Making Decisions Overheads are the non-contract based support services required to enable the company to procure and and progress work. They consist of :-  4 key departments; Marketing, Head Office, QHSE and Measurement  Non-departmental overheads, such as idle labour and idle project managers The Overhead Manager is responsible for :-  Setting appropriate staffing levels for each department  Directing marketing effort into the 5 market sectors The non-departmental overheads are the responsibility of others, and are related to jobs in progress. Marketing Decisions Other Dept Decisions Non-Dept Decisions
  • 10. Procurement Making Decisions Each period the company is offered a number of jobs for which a bid is invited, identified by the marketing effort in the last period. Bidding Decisions Margin Adjusting Successful Tendering
  • 11. Job Progression Making Decisions Progressing the jobs secured through procurement involves :-  Allocating appropriate project managers to oversee the jobs.  Allocating labour to progress the jobs in line with the company‟s strategy for job completion. Project Mgr Decisions Labour Decisions Key Points
  • 12. Resetting Decisions Making Decisions Decisions can be reset to their defaults at the beginning of the period. The default setting is to reset all the decisions, but it is possible to select particular decisions.
  • 13. Exporting Decisions Making Decisions The Export Decisions scenario. Bothdecisionsfollowingoption enables back to team 1 theirand when ways category, for Group 1 are the primary decisions for the period using into number of the the database. exporting to a Consider themake theircommunicateddecisionsGroupleader,be selected, bycompany database is received by groups could be group, containing the entered a own copy of :- text each themfile. period it is file created contains the the following changes to the default export options :- The text e-mailed to Group 2. Group 2 make procurement and job progression decisions made, in a clear and  By phone Group 1 are membersformat. into 2 the company database to the Competition Controller, and must put A team of 6 responsible for sending groups of 3 members each, and is located in 2 different offices, all concise is split  The Procurement and Job Progression decisions are chosen for export; the other This e-mail  By group now long team in the decisions for the copy of the Each has a number of uses :- their „master‟ copy of to company database. geographically a has away apart. company databasethework on when making their individual decisions. boxes are unchecked Group 2 can now e-mailwordtext file to Groupis added to the export name to make it very clear which  The the „_for_group_2‟ 1 for Each keeping 2 let of each group How do Group a its Group of master are highlighted bythe export file The responsibilitiesdrawbacks :- database. decisionsthe diagram below.  Foroption has hardcopy theknow what entered. entering into 1 decisions are contained in are ? decisions their  Where a team is fragmented into smaller groups, it provides an efficient means for individual decisions  to be communicated back to the teambutton is clicked to createintotext file. By phone could be time-consuming The Export leader for entering the the master company database.  By e-mail requires a lot of typing of decisions We‟ll look more detail at the second use. itself is a text file, and has the following characteristics :- The export file However, there is a far more  Its name alwaysmethod and that is to use and the rest can be altered option. user-friendly begins with the competition id, the Export Decisions  It is placed in the folder from where the company database was chosen Team Group 1 Group 2 Responsible for :- Communicate Decisions ? Responsible for :- Decisions Made Database E-Mailed  Finance  Procurement  Overheads  Job Progression Keep Clicking Anywhere on the screen to advance Quit
  • 14. Key Performance Indicators Assessing Performance 10 key performance indicators are used to measure the success of the company. The indicators are weighted according to their variability, totalling a 1,000 at the end of the History. As time progresses the weighting of each indicator will change, highlighting improvements or deteriorations in that area, but the overall total will be the measure by which the ultimate progress of the company is determined. The weighting for each indicator at the end of a period is based on a comparison with the position at the end of the History, and there are two types of comparison :- Trend comparison Smoothes the calculations over the time the company has been operating. Applies to Turnover, Gross Profit to Turnover ratio, Operating Profit to Turnover ratio, Capital Employed, Contract Completion and Client Satisfaction. Snapshot comparison Compares the current indicator to the position at the end of the History. Applies to Company Value, Forward Workload, Forward Margin and Share Price. Calculating Performance Indicators
  • 15. Performance Statistics Assessing Performance Company Performance Statistics provide a detailed set of statistics relating to all aspects of the company‟s activities, and can be used to identify strengths and weaknesses, and explain the rise and fall of particular performance indicators. The use of Performance Statistics
  • 16. Management Consultant‟s Report Assessing Performance It cannot many methods available for assessing the performance of the company, is, if used effectively. There arebe emphasised enough how valuable the Management Consultant‟s Reportsuch as performance indicators, performance statistics and the report can alsoIn addition the category. has the use of an external The category analysis tools. be filtered Within each report can be filtered by decision area :-by sub company management consultant, example, thein detail is now in period 9, the the Construction For whoFIN (Financial) looks company at all areas of and company‟s business, especially where The report can also be filtered by period,  and in most cases the previous processed there may be problems, and OVH (Overheads)one being analysed.project managers during Manager compiles be the performance of all  is interested inappropriate report. period will an the  PRO (Procurement) the previous period. To achieve this the following filters are used :- We will now look in more detail at what the report looks like.  RUN (Job Progression)  Category choice of “RUN”  Period choice of 8 The nature of the comments made is either :-  Sub Category choice of “Project Managers”  „P‟ if the comment is positive  „N‟ if the comment is negative What do the results look like ?  „U‟ if the comment is unclassified It is the negativecost per period of the Management The comments that will need to be addressed as a matter ofReport is shown in the Consultant‟s urgency. Industry Information. ---------------------------------------------------------- Key Point(s) The Show additional information can be used The Construction Manager can The cost of the management consultant clearly see that all the project managers to display more detailed information about the well during period 8. performed extremely cannot be avoided. highlighted comment, if any is present. However, there are some areas of concern. The quality of the project managers is so high that :-  Eric Chatterton resigned from job 127 after being headhunted by another company.additional information relates to the highlighted the job in period 9. The A new project manager will need to be found for comment about Eric Chatterton being headhunted.  There is a danger of Vic Peterson being lured away from job 165 by other offers, and a higher bonus may need to be paid to him to try and tempt him Keep Clicking Anywhere on the screen to advance to stay with the company. Quit
  • 17. Analysis Tools Assessing Performance Information is available to enable a thorough analysis of the affectis the gateway Displayinginformation about The ProcurementOverhead Analysisdetailed joba number of The Job Analysis of previous to provides in details :- The Analysis decisions detailed period The Financial Analysis provides detailedprovides a detailedthe financialprovides information about analysis of key business areas, providing an aid for making effective decisions for company has identified (prequalified for). any of the jobs that the the future. each department. information appropriate to detailed information relevant to performance  Bidding success byitperiod; operating. This includes :- to see of the company since began each job is examined in turn why it was won or lost, taking into account thestatus of factors that For the Marketing Department :- various a job. the current We‟ll take a brief look at the Analysis Tools available . the bidding, such andprocurementfor all periods The information includes :-  Financial performance; by period as graphically restrictions (company of affect  Market trend; the past, current and future value  Shareholder information;specific) and price.andand dividend payments Further analysisand job including shareinformation based tools provide historical price location.  A list of all new work bycan be filtered by status jobs; these sector  InvestmentRivalcompany‟sanalysis;performance; staffing levels, all rival bids relating toHistory; performance of all investments the relationship with clients,  Marketing for all information about the where   Detailed riskhistory; Detailedjobs won and progressed bidding project managers and consultants.  date, to retention analysis; for all jobs won and progressed toDetailed enable future effort was directed, be refined. marketing bidding strategy to and the value of new work identified. For the Head Office, QHSE and Measurement Departments On all analysis screens a ?  Performance; staffing levels allocated in relation to Indicates that more detailed the turnover of the company. information is available about how a figure was arrived at. The R resets filters back to their defaults. Performance (All Periods) Keep Clicking Anywhere on the screen to advance Presents key information in a The Selected jobs analysis graphical format. provides a graphical analysis of the jobs currently being displayed Quit
  • 18. Industry Information Industry Information The CountryThe Industry Outlook is given for the UK and Overseas Information Environment parameters define the environment in The Economic describes the countrieswhich thefor the foreseeable future. in which company Client The is operating. economies the country may Information lists the clients with be able to identify work. whom the company are able do work for, Most remaintheand but some can indication of the for the company Knowledge of fixed, also gives an vary from periodlevel of economic outlook is vital in order to period, such to as the prevalentstrategy rates. may beand in which markets it decide upon its interest forthat future, needed with the relationship the wishes to focus its efforts. future in order to be able to bid client in the for work with them. Keep Clicking Anywhere on the screen to advance
  • 19. Exporting Information Miscellaneous Selected information can be exported to CSV format for importing into spreadsheets for further analysis.
  • 20. The Job Cycle Glossary Although 6 in was progressedsuccessful bid for its job. stages :- Work startedjobperiod 8, and timeframe job for whichplanned 10, the job periods, finishing of jobs will In has beenthe company put inthefrom timeframe periods 8client during prequalification The companydemonstrated, theajob a new measuredof periods, duration, this time a number interested As period the is managed identifiedjob completed in in up the3 toand invited3 periods were :-by in period 10. 7 over cycle consists the to parties. The job in the market which can 3 identified, tendered for and progressed (if won). become availablehad a planned duration ofbe periods.  Prequalificationjob was period 8 of the timeframe Period 1 of the The progressing job was period 9  Procurement of jobs can begin in any period, and the jobs can last from 2 to 5 job periods. Period 2 of the  Progression the job was period 10 Period 3 of It is important to grasp the concept of the job cycle, and the following example should illustrate this. Period 1 Period 3 of the job of the job Period 5 6 7 8 9 10 11 12 Identify Bid Progress the job (Prequalify) Submitted (Procurement) Keep Clicking Anywhere on the screen to advance Quit
  • 21. Financial Decisions Glossary Key Point(s) 5, andresponsibilitiesfinancial decisionscurrent investments, look opportunity selection of otherthe :- and that One of the Its period main theInvestments In addition to the to Manager inon the cash account,thatachievedcompany, and or it Some additional points to Financial ManagerFinancial FindingDividend there after the be of may go into overdraft, build All the of the needs Anreview the company are also a andoffers a goodcompanies note about investments :- have an affect to increase investment value can interests through an is financial structure it the of return, company‟s shareholders. in thealready of the made. from the is period.the usingpayments declared thesuccessfully the The other company basedthat needthebe overdraftand theselast Themake the best Add new investment option. main responsibility of butbe Financial Managercandue viewedcompany‟s use of out ofCompany‟s not to are Not only upon any changes core businessbe invested in, cost savings and dividend paymentsector-based workload,account, decide is the The may UK, toitsin company is procuring be to taxable contracts, and the by cash is Dividends progressing the comes the assets Apart from paying dividend, each period the Financial Managerthe value of the company is if done a company's can bank could choose to leave reduced. of the rest account is and increasecompany will report a healthy operating profit, and use ofmoneycompromise has to be reached asare  to try held inor UK Institution.the Company‟s value. and Any increases a reductions in investments affect the cash account, but increase the company‟sassets However, there to Making effective directors and is being moved possible, and the company‟s shareholders, normally always board of sinceoften a given to itsvalue. financial structure of of the companyaisincreasing the ifwhichofquarterly. Theysuchaccountincentiveproductivelycredit between assets, the value theThis ways ofunchanged, A valuemoneyhopethe cash as by investing in other stock in stable company great concern number of choicesto earn some interest fromconcerns, which alternative is not and simply company, desirable. :- is used to own a in other unchanged.. the benefit is more available the from are provide an balance in the cashsubject areas,not be construction-related. companies eventhe Industry Information. much growth. Hence, the company is may orto account. UK financial is an overdraft limit, as defined in if they are not experiencing may but there rates,  There are limitations shown  Using cash to increase the Capital Base and arise that offers such as interest and tax,rates. in the Industry Information. onexample, an investment opportunity may support further growth. For the :- However, this wouldinvestment 2 ways of increasing the company‟sdividend paid manipulatingand one which mayeach one • Increase in a single There There are also differentthere areoff adependingsavings in size Transport sector, inkey factors be short-sighted, since eachSelling Thebuild costCapitalthe the of theis we‟llof the which the are that can be made overdraft rates % of the the size of the concern company‟s assets  substantial value through investments, the period, depending on of to shareholders cash, examine be other ways upon Base to raise overdraft. to improve the • The number ofcompany‟s value, involving the transfer ofthe cash active. However,cash account,returns option.the investments by reviewingheld currentonecompanyin funds between the the price :- in turn affects the company share investment capital base that can be the at any investmentif are very account has exceeded Display Details may if be required thatPHS Excavators Plc using the the overdraft limit, or not time and investments. When the overdraft limit is exceeded, allis not being fully utilised.tooutweighs the risk of thebelow Capital Base efforts must be made reduce the overdraft to very good, but the cost-saving benefit  Insufficient dividend will well.  There is no limitation on the the limit, whichcan be madeUsing cash to invest further in other companiesthe shareholders and reduction that may involve investment itself not performing verydisappoint who offer a better  :- an investment. to return than can be obtainedprice. the bank, or who may be able to reduce the share from Although these changes don‟t immediately change thecosts the jobs in company, keep the endselling off period with  Any investment returns changeNot payingof thedividend in theandvalue of the progress, orby the shareholders content,  the value any investments, current period dividend will conversely, of the reduce not on cash account. Sufficient the affects of the changesSelling off part of the capital base amongst others :-  will have been felt, including, change in the investments no to raise cash. share price. Capital Base  Reducing investments  Ample dividend will make the shareholders very happy, -------------------------------------------------------------------------------------------------------------------------------------------- The levelCost Savings Due (turnover) that can be undertakenwe limitedneed to size of at least 300,000 to obtain preferential on The Industry InformationTo Investments large company is would by the invest share price. of future workload shows that for a Key Point(s) could expect build cost the bidding, and the and increase the the company‟s capital base, as shown Build the Capital we the investment changes to yield company‟s value willcan felt obtained from the when cash is potentially an the rates, and BaseScreen. affectingsavings of at least 0.9%. level of future work that can be undertaken Procurement changes companies Operating Profit The well as investing in otherat any time ison the a betterits assets. After payingprofitthe periodconsistthere As affects of return than be be measured Returns The affectduring increases the cash :-cost savings bank, The value of thechanges yielding returns, and by Generating operating profitprice is determined by the and hence Investment Company for investing in other concerns. Investmentincreasing operating dividendthrough buildaccount, they of account interest is although a minimum of In the last 4and buildof thesavings are share achieved Plc has been consistently so even more lucrative reasonand investment returns periods the return fromonand Excavators through good job % ofoverhead calculated, cost company, known. value any single investment in a period cannot exceed 150,000, high, PHS is and the The capital base of 4.5m can support up to 45.5m of is required,Since theAlthough having workload control 30m (the value of work Bear in mind that 300,000 workload. management. company‟s equity that is paid is only over these functions, current forward no direct as a dividend. it would the at objectives Progression Screen), 3.6%costs scopeperiod (14.4% andwork. per annum). shareholders, at between and 4% per The long-termleast the Jobin to the Financial Manager stillmay look afteron work in progress theonce the and If enough money is invested particular concerns, build is are to investment. more 16% still to bein take bankon 2 periodsof gain any build cost savings from thebefor winning the interests as in specific sectors due which is a liability. There is an overdraft limit the responsibility of other people, such of Cash completed (-200,425) there However, Overhead reduced This can either be in credit or in overdraft, when it is considered Cluesto be a reassessment of the size of dividend are base company‟s procurement decisionsto manipulatein iftherean asphaltassetsthewould reduceManager by themonitor progress PHSmake effective materials, have Whether notConstruction Managers, the success, inbuildvalue for any return, to Excavators Plcon a good companybeen made, work may needcompany sectors, as the levels of phrase e.g., investing company‟sdone to any a improve terms must thecapital and across different costs of the company. andpreferential Industrydecisionsplant etcto investorthe the both build costinbeenaffects of allindicatedof the cash Transport rates are in is being as Financial PHS Excavators Plc is anrequired. investment in terms of investment hassavings some commodity and investment using defined in an increase is excellent the Information. to work being undertaken. The concerns offeringIndustry” in these areassuppliers the company sectors, run as construction decide if “supplying .... to all sectors of the Construction these benefits must be to further in, wouldwhat is being to in the History, into the available by examining of happened the returns, so wethe clues lyingfunded from which would be worthPlc 5,000,000 shares of value menuupon equity profitably5,000,000. will increase in investment in PHS Excavators investing The Company was originally the the company profiles. possible. the Relevantto industry. With ensure exceed the minimum level required to as a share (equity) issue of by 150,000 information 1, with an depend option. looking deeper value of Capital Base (4,546,264) prevalent bank rates, both credit and overdraft rates (as defined in the Industry obtain thein time, since procurement decisions have not been made, and since there is „unused‟ capital base, we‟ll leave it build cost savings. At this much would we need to invest to obtain the preferential rates, and what level of build cost saving could we point How Since period 1 the company has paidInformation) at of equity the investments were made, asand this the kept the of the This end ofavailable investmentfollowingdividend of 2%givenequity value at 6,750,000 (5,000,000 level has balance information is the time every period (8% per annum), well as At the shareholders content, as we can see from the Consultantsbuildings etc, which determines themore detail. For is the company‟s the share in plant, equipment, facilities,:- unchanged. achieve ? concern, the price stands at 1.35, and thenow---------------------------------------------------------------------------------- each expect to the History cash account. We‟ll Report. some of these options in x 1.35). of work that the company can undertake. Key at lookPoint(s) ------------------------------------------------------------------------------------------------------------------------------------------------------------------- ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------  The investment Key Point(s) influenced by a number concern. The share price 5 we‟lldetails describes the of factors :- Key Point(s) As the share price changes, so does the equity value of the We‟ll In period isfurther. investigate Investments (204,500) base alsothe % returnthis build previouscompany, andbut more has to be invested to obtain the continue to pay dividend at the level.cost savings on offer, paying the same level of dividend in ---------------------------------------------------------------------------------------------------------------- The larger to the capital concern the greater given in changes the investment  AnyThe performance history gives affects the cash account. periods to all investors, and The ------------------------------------------------------------------------------------------------------------------------------------------------------------ Key Point(s)  If the company‟s cash the company direct it may be which may to consecutive savings.any monies investment in may have invested. Financial Manager to raise cash for otherdifferent affect on share price details basewhich is under the other concerns, appropriatenotreduce it periods will have a uses, such as further  Paying dividend, is being underutilised, control of the capital be construction-related. Key Point(s)  Although the value an overdraft. saving The size (small, mediumas theon twothe investment concern determinesbuildamount or large) of equity changes. is a higher level of the cost of  Changes or reducingof build cost changeis displayed, the savings are % thetiers, and there investmentsin the minimumthe Company Shareholder expectations can is not shown. operating performance of as defined in the Industry Information. or as the company changes, and may be higher that can be invested each period, the concerns, and the  The future moretheinvested, which saving if profitability of current cash is  There are limitations on the changes toaccount balance, each period, defined in the Industry Information. Taking into account the the Company the capital base potential returns from Keep Clicking Anywhere on the screen to advance bank minimum depreciates to This each build cost savings is now make decision about keep them happy. The lower thanis currently period for 4,550,339. the level of dividend that needs to be paid to The rates on of History level. at will affect  The capital baseoffer each valueda %the theyear, as shown would based uponathe required level after the financial decisions company  The debt burdenlevel requiredby obtain cash account, we in the Industry Information. the Company whether or made, worthdoes not take into account of the available opportunities. have been not its and investing any cash in any the returns made from the investments during the period. Quit
  • 22. Overdraft Limit Glossary The amount of money that can be borrowed from the bank following example. and the cash The warningConsider the is not disappeared, current message has now unlimited. The overdraft limit, imposed by the bank depending upon the economic climate, is shown in account balance is below the overdraft limit. the Industry Information. Its period 8, and after decisions were processed last period the company‟s overdraft has reached ----------------------------------------------------------------------------- What happens if the overdraft limit is exceeded ? Key Point(s) 1,375,291. This has exceeded the limit of  If all possible measures as a result a warning message is 750,000, and have been taken, and the cash ------------------------------------------------------------------------------------------------------------------------- account balance still exceeds the overdraft limit, then no displayed. Key Point(s) further action needs to be taken, and the user is not The „base‟ overdraft limit imposedprevented from normallyto another screen. by the bank is movingthe Financial Decisions Screen is As soon as the same for all companies. However, it may be reduced even further for a specific company if the message appears. closed a critical warning company‟s current  The cash account can exceed the overdraft limit when share price falls too far relative to the price atThe start of the History. This will be reported in the message informs the Financial Manager the Management Consultants Report. decisions are processed, but during the following taken to that all possible measures need to be period all possiblereduce the overdraft totaken to reduce the measures need to be below the limit. balance to below the overdraft limit. The Financial Manager decides the best action to take is to reduce some of the company‟s investments. Keep Clicking Anywhere on the screen to advance Quit
  • 23. Factors That Affect Share Price Glossary The company‟s share price where a of the keyin period 5. GearingProfitability example, is one company is performance indicators in measuring the success or Consider Ratio Company Value Future the following Dividend payments The final factor that affects thecompany fromshare pricegearingaffectincreasing industrytaxable payments the failure of the value of thewithprice is changes in the in the future profitability (forward margin) of the company, which is Changes in the company,share a price is the changes signifying the share price. are confidence in declared by a Another factor affecting the share rising period to period also ratio. Dividends fortunes a ratiocompany‟s work incompany‟s liabilities (cash account overdraft) priceassets board ofbase industry confidence Apart from of thedecline during period 1, the share price trend has been an improving one. The gearing small Company. based upon the is the ratio of the progress. company's (capital directors and given to its If the company value falls in a period, it will have a depressing effect on share to its as shareholder and and investments, and shareholders, normally quarterly. They provide indicates the debtifburden of increases then confidence will improve, and the share price jobs,increase. no forward margin. falls. Conversely, the value the company. was being established, theregearing ratio is 0. will and hence whilst the company If there are no liabilities, the were no ongoing At the end of period 1, detail at why this has been the case. We‟ll now look in more influenced by :- The share price is 2 to 4 when some work was secured, forward margin was constantly rising, stock in a very positive an incentive to own stable companies However, during periods having If the gearing ratio increases the company will be adverseas being vulnerable to both interest rate notaexperiencing muchservice its As can be seen the trend has been mixed, with even if they are rises, and its ability to growth. viewed affects on share price in periods 1-3, then positive affect during affect on the share price, as reflected in comments in the Management Consultants Report. debts from its future profit flows. Consequently, share price. Comments in the Management Consultants based if the gearing ratio period 4 which would have helped to boost the this will have a depressing effectDividend payments are Report provide current on share price. Conversely, upon the further  The level of dividend paid to the shareholdersfinancially sound, and the share price will increase. decreases then the company will be viewed as being more evidence of the affects of the company value changes. share price.  The value of the company As can be seen, the cash account was overdrawn during periods 3 and 4, and theThe equity gearing ratio had aany time is the increasing of the company at negative affect  The future profitabilityslight onecompany no comment in the Management Consultants i.e., the number of shares in on the share price, albeit a very of the as there is overall share value Report.  The debt burden (gearing ratio) of the company circulation multiplied by the current price per share. There is a level of dividend, measured as a % of the equity, at which the share price does not change. Paying more than the „equilibrium‟ level will cause the share price to rise, but paying less will be not be well received by the shareholders, and the price will fall. In Summary Dividend payments of 2% of equity have been Each of the 4 factors have different levels of impact upon the companyeach period, It may be, for example, made share price. and the affect has been that the share price rises even though 3 of the factors have negative affects, but the positive affect the level of “Shareholders are content with of the 4th factor has the greatest impact. dividend paid”, implying no change to the share price. Careful examination is needed of the company data to determine which factors have had which affects, and to what level. In the previous analysis we have seen that :- If dividend has had little affect on the share price, what about other factors ? Keep Clicking Anywhere on the screen to advance During period 1 the share price fall was down to a drop in company value. Even though company value fell further during periods 2 and 3, this was more than offset by a rapidly improving forward profitability, and the share price rose. During period 4 both company value and forward profitability improved, and the share price rose further. Quit
  • 24. Dividend Glossary The dividend paid to shareholders each period is one of the key factors that affects the share price of the company. The dividend paid is expressed as a % of the equity of the company. The equity of the company at any time is the overall share value. Equity = number of shares x current share price The dividend % of equity can be :-  Insufficient to satisfy the shareholders, which will reduce the share price  Sufficient to satisfy the shareholders, which will have a no effect on the share price  More than sufficient to satisfy the shareholders, which increase the share price The Management Consultants Report gives an indication of how the shareholders felt about the level of dividend paid in a particular period.
  • 25. Company Value Glossary The value of the company at any time is measured by its assets and liabilities, which consist of :- Cash in the Bank Capital Base Investments The cash balance can be :- The company‟s investment in The company‟s cash  In credit (an asset) plant, equipment, buildings investment in other  In overdraft (a liability) + etc, which determine the + concerns, which may not level of work that the necessarily be construction- There is an overdraft limit. company can undertake. related. The value is increased by :-  Generating an operating profit through the company‟s activities (into the cash account)  Good investments The value is reduced by :-  Dividend payments to shareholders (from cash account)  Making an operating loss through the company‟s activities (from cash account)  Depreciation of the capital base  Poor investments
  • 26. Cash Account Glossary The company has one UK bank account, known as the cash account, which can be :-  In credit, when it is considered an asset  In overdraft, when it is considered a liability Interest is earned/paid on the cash account balance at the beginning of the period. The prevalent interest rates each period are defined in the Industry Information. Credit Interest If the cash account is in credit, interest is earned at the Overdraft Interest annual rate shown. If the cash account is overdrawn, interest is paid at the annual rates shown, depending upon the Overdraft Limit size of the overdraft.. The cash account can be overdrawn up to the overdraft limit. If this is exceeded steps need to be taken to try and reduce the overdraft. The cash account is increased by :-  The company generating an operating profit  Selling off a % of the capital base  Selling investments The cash account is reduced by :-  The company making an operating loss  Dividend payments to shareholders  Increasing the capital base or investments
  • 27. Gearing Ratio Glossary Liabilities Assets The gearing ratio is the ratio of the company‟s liabilities (cash account overdraft) to its assets (capital base and investments), and indicates the debt burden of the company. If there are no liabilities the gearing ratio is 0. For period 8 the gearing ratio of 0.051 is the absolute value of :- Cash Account Balance / (Capital Base + Investment Value) -310,719 / (4,433,668 + 1,698,938) Changes in the gearing ratio have an impact on the company share price :-  If the gearing ratio increases the company will be viewed as being vulnerable to both interest rate rises, and its ability to service its debts from its future profit flows. Consequently, this will have a depressing affect on share price.  Conversely, if the gearing ratio decreases then the company will be viewed as being more financially sound, and the share price will increase.
  • 28. Capital Base Glossary The capital base is the company‟s investment in plant, equipment, buildings etc, and determines the level of work that the company can undertake. One of the key company performance indicators is capital employed, which measures how well the capital base is being utilised over a period of time. Changes to the capital base are the responsibility of the Financial Manager, and the Industry Information shows factors that affect the capital base. Changing  It can be increased, reducing cash reserves, in order to support further growth. There are limitations on the increase possible each period. The Company based Restrictions on the Procurement Screen gives an indication of when an increase may be necessary.  It can be reduced, increasing cash reserves, which may be desirable if money is needed for other things, or it is not being fully utilised. There are limitations on the % of the capital base that can be sold off each period. Depreciation Each period the capital base depreciates by a %, reducing the overall value of the company. This occurs at the end of the period. Writing Down Any increases in the capital base can be used to reduce the company‟s tax burden, known as capital writing down. Capital Employed
  • 29. Calculating Capital Employed Glossary The company‟speriod 4 the company‟s initial forward workload of the company‟s capitalwas on (plant,healthy at 89 %, At the start of capital employed measures how much was 22,072,940. This was based extremely equipment, For Period 4 the company‟s capital employed base the turnover still buildings etc) is on the 3 jobs in progress at the start ofthat the capital case was being very effectively utilised. to be completed being utilised. indicating the period. Not jobs were bid for, and 3 were secured, whichof how was thethat could workload post-bidding to 40,879,480. hinder 8 utilising the capital base is a wasteBut resources capital employed % determined ? took the cumulative forward be directed elsewhere, and can growth. The capital employed measures how much ofThe answer can potential workload (45,748,570), based on the capital period 4. the company‟s be found by looking at the Procurement Analysis for base, was actually being progressed i.e., Consider the following example where a company is in period 5, and the financial performance is being reviewed for /period 4. * 100 = 89 % (40,879,480 45,748,570) Keep Clicking Anywhere on the screen to advance Quit
  • 30. Investments Glossary The core business of the company is procuring and progressing contracts, and if done successfully the company will report a healthy operating profit, and increase the company‟s value. However, there are alternative ways of increasing the value of the company, such as by investing in other concerns, which may or may not be construction-related. Such investments can :-  Offer a better return than can be obtained from the bank.  Offer a competitive advantage for work in progress (benefits) e.g., investing enough money in a tarmac company would reduce build costs for Transport jobs as preferable material rates would be obtained. Each period a number of new investment opportunities may arise, adding to the list of available investments, and for each one some key information is given to help in making investment decisions :-  The investment profile describes the concern.  The Past Performance gives the % return given in previous periods to all investors, and details any money the company invested, and any build cost savings gained. The Industry Information shows factors that affect investments. Build Cost Savings Depending upon the size of the concern, Increasing Investments there is a minimum level of investment The increase in a single required to gain build cost savings, and a investment each period cannot minimum potential % saving. exceed a given amount, depending upon the size of the investment concern. Number of Investments There is a limit on the number of investments that can be held at any one time.
  • 31. Profit Definitions Glossary Company Gross Profit In any period, the gross profit of the company is a measure of how profitable the jobs in progress have been. Monies IN Monies OUT  Measured value across all jobs progressed  retentions held from jobs progressed Gross Profit =  Retentions repaid from completed jobs -  costs across all jobs progressed  Early completion bonuses Company Operating Profit In any period, the operating profit of the company is a measure of the overall profitability of the company. Monies IN Monies OUT Operating  Gross profit  Company overhead costs - Profit =  Credit interest (cash account)  Overdraft interest (cash account)  Corporation Tax
  • 32. Corporation Tax Glossary Corporation Tax is a tax on a company's taxable profit, which is defined as :- Operating Profit Before Interest & Tax Taxable Profit = Gross Profit - Overheads - Capital Allowances If the company makes a operating loss before interest and tax no corporation tax is paid, and any capital allowances are carried forward to future periods. Capital Allowances are acquired by investing in the company‟s capital base, and are calculated on a „written down‟ basis; the rate of writing down allowances is given in the Industry Information. The corporation tax rate is shown in the Industry Information. Capital writing down rate per annum. Calculating Corporation Tax
  • 33. Calculating Corporation Tax Glossary Consider the following example where a company is in period 9, and the Financial Details are being reviewed for period 8. For Period 8, using the Financial Analysis, we can see that the company‟s Operating Profit before tax & interest was :- Gross Profit: 752,527 Less Overheads: 377,865 ------- Operating Profit Before Interest & Tax: 374,662 The Operating Profit Before Interest & Tax was then subject to Corporation Tax of 110,207. How was this calculated ? We can use the drill-down to investigate further. A Corporation tax rate of 30% was levied on the taxable profit of 367,357 to give Corporation Tax of 110,207. The tax burden was offset by the Capital Allowances of 7,305. The Capital Allowances to be written off is adjusted each period as follows :- Capital Allowances are acquired by investing in the company‟s infrastructure (capital base), and are calculated  Increased/reduced by basis; thein theof writing down allowances is given in the Industry Information. on a „written down‟ changes rate company‟s capital base  Reduced by using up capital allowances that are written off by 25% per annum (6.25% per period) We can use the drill-down to see exactly how the 7,305 was determined. Capital allowances are not used if an operating loss is made. In period 8 an operating profit before interest & tax of 374,662 was made, and as a result capital allowances were used. These amounted to 6.25% of 116,882, the amount still to be written off, giving the figure of 7,305. Keep Clicking Anywhere on the screen to advance Quit
  • 34. Marketing Decisions Glossary Consider set followingMarketaredirected the The informationto analyse likely marketingand thefor the split of and the size TheHaving thethe Department workthe firstmarketingThereladder tothe2compositionstaff,period 5,countrythe The %to the Marketing staffing level, and a numberon the Relevantforecast of thewinning and not indicated next also looking of The There are Based of toolsstaff effort into currentlyglobal market progressing efforts into job situation. can marketing available about the jobifsectors, trend the contracts. The Trend shows step on the are different Job Size additional be the company‟s Information/Marketing Performance option year. the How much new Preferences identified ? will have little affect marketdo of direct theirand showsmarketing Preferences they split in and Client Relationshipsaccuracy of the forecast depends upon the size of the marketing department. and Prequalification It‟spreferences, The companymarket sectors identifythethereManager work,5tothethat comeover thestaffingasmay be Each period the marketing forecastlong-term,workoverheadfor) :-of needsof marketglobal market,job size inlevel for the Marketing is a theplay When willprequalifyingsizethe(prequalify:- manager decides available upon presently as thatthe periods. Client relationships company‟s staff subject topreferenceways a of new company marketing the for6. previous period. the beginning ofaperiod 5, andindicated newthe country preference takes has prequalified market preference. complexrole Wheregreater inboththat in twomarket that jobs injobs :-priority is strategies shown, with effort area, and identify :- overall is 359m numberwork decide during periodknown in in the the Overhead is new work. the some sectors onto the in setting they to for set are which construction marketbe ablejobdetail thethere effort between the availability to being directed into all sectors, and in particular the Building and Marketing Department,the numberwhich sectorsuponsector to jobsaroundfactors :-but Information/Market Trend option. prequalification,value of“Target large Leavefor chosenexpectedweTargetandbeare toaboutmarketing effort identificationthe adopted include :- The overall into ofjobs” thecan is thedecisions by use winRelevantmark untillook to movetodirectedof In addition, the which work prequalified market bejobs“is, last be andto forjobs” areperhaps thensectors into the is If andcompanywhere then decidelarge will other assuming bechosen, period 9, was process. By determine jobs is Although the unchanged the 360m thethe procurement direct To value of the Based by staff‟s have large made For example, may the new work andtrysector. if “Prefer UK then to year, the through directed. the when there effort influenced efforts now, Commercial are into which  If the relationship is expected tofor example, that increasing the number of sector expands.to 4 has increasedthat wouldas Let us suppose, an improving one,Energy least atin around 25m.period 5, the %may prequalify for a jobisthe market share certain level, the marketing staff be choice, followed by medium then smallcompany change in each company limited, have an overall decline ofa the in which there was some new work, the sector was able to and at sectormarketing future in that can identify 108m of new work (30% of 359m). as to 30%. In  By market sectors potentially effort All jobs belong to one ofprimary Management follows :-in theReport. or Information, so wholesale changes cannot be made been unattainable, as shown 5 clientprioritised thatConsultants country job size. the jobs is means as :-sectors the company practice this in the into  Targeting a variety jobsBy in a particular sector(s) of sectors to Show overseas) forto maximum base of jobsoverall market with 2 marketing staff. If the company are experts location(UK or choice.  as the secondary no preference a Industry of 23% of the identified. Although this may defined widen prequalify the country and client  IfIndustrial Taking the Building & one, then procured, enabling clientcompany to all sectors for 39%foreseeable future, The relationship with contract clients work there oneappearsThe changecompanyinmakesjobs where there marketingless In terms 1.Large the of where can be is, in is a period. the the will there to be new contracts a deteriorating Commerical sector as an example, the isnot at the expense reviewing marketingthe the relationship is with the Energy market in chance the that as well limitation have it imperative of the may as the  increase the choice of jobs thatUK jobs particular picking up during period 8allow findallocatedthe regardlesssector. effort be being put into theCommercial Building and particular job considered when to achieve this of work prequalification, Transport of short-term, the long-term work in the sector (39% of 108m). more strategy. Ifthe 2. sector. may alsoThe company‟s strategyof building long term relationships with “Target This should enable them to identify 42m for steady growth, and Medium UK jobs reduce the chance is of medium jobs” is chosen then medium -------------------------------------------------------------------------------------------------- rival competition to this sector. it effort for work, Transport We‟ll now look at each one3.Point(s) jobs will needlarge and small jobswe will need to increase the staffing level by the Keyin turn.primary choice, with to be identified, so  particular clients, which may be vital in securing work if economic conditions deteriorate. jobs areSmall UK the  Energy given4.Large overseasasmaximumessential 2 (the limit is only is in the Industry Information). Analysing weighting jobs secondary choice. equal the market inthe detail is allowed, because not shown the ----------------------------------------------------------------------------------------------------------------------------------------------------- marketing effort to be directed by sector, but within each sector choices 5.Medium overseas jobs  Water and Sewage can6.Small overseas jobs isjobthenof work to look to build long term relationships with Key Point(s)  Targeting a The above “Target small jobs” thechosen lot small jobs is enough new work in the sectors where the particular sector where there a size preference. If analysis is based on is and be made by country assumption that there are ------------------------------------------------------------------------------------------------------ specific clients, andthe primarytargetdirected. by medium then large here in putting all „your eggs in one basket‟ perhaps been particularPoint(s) marketing effort has choice, followed sized jobs. The risk Key is that there may bejobs as the secondary choice. work. large the marketing size is, and how well the marketing effort more competition for the No matter how The value and number of jobs that the company can prequalify for in any able to identify 100% ofby amarket. is directed, the company will never be period is governed the number of The company mayFor now the company has no particular job size  factors :- look to find „niche‟ markets, in which there is less competition for work, which could preference. The size of the Marketing Department (number of company staff)  improve future procurement success.  The size of the global market (value and number of jobs available) -----------------------------------------------------------------------  Where the marketing effort is directed (5 potential sectors of work) Key Point(s)  Whether or not the company are experts an a particular sector the future success of the company, Whatever marketing Depending uponmade have in important bearing on decisions are where the marketing has been  The relationship with contract clients composition of to the demise of the business. since failing to identify any new work and the directed by sector, can ultimately lead the work available, it may be that no jobs can be identified in a Sector Experts from the primary choice, and secondary choice jobscompany‟s average marketing effort in a sector If the are indentified instead. exceeds a particular %, then the company are deemed Number Where Size of Value of of marketing experts in the sector, and will prequalify for more to be Other global new work marketing effort is in the sector than anticipated. work factors market identified staff directed The Marketing effort (by sector) indicates period by period in green the sectors in which the company is Keep Clicking Anywhere on the screen to advance considered an expert. Quit
  • 35. Other Overhead Department Decisions Glossary We now the theseStatisticsQHSE and mindor not overhead the company‟s staffing level applies :- Head Office, Consider seenfollowing 3 staff canwhether 10.9mstaffingof staffing levelsdetermined QHSEto all manner, The haveknowlevelsthe situation. perform tasks related to3.6m per the Head Office,ifin the same3is expected staffing that the setting the appropriate of turnover. for setting the jobs in progress and staff in that departments handle the benchmark levels in Head Office person, the turnover Performance for the show in Measurement Departments are were sufficient in the Understaffing principal The Bearing On the JobOverstaffing screen, and assuming appropriate labour allocations have based uponMeasurement departments.using anticipatedtheand staffing levels= benchmark, can4. 5 staff , since Measurement Departments relies on and the turnover required we‟ll concentrate on rounded up to Department. QHSE and benchmark staffing levels Progression turnover levels. departments, so is during period the Head Office To the this staffing level is sufficientthe numberto staffof needs (16.9 / thethe 4.7, the staffing levels for It‟ssee ifOffice staff deal with buying, Overhead Manager issues to decideperiod isbenchmarkhave serious  Head beginning of period 5,to be 16.9m, Understaffing of IT theturnoveranticipated turnover thisfollows :- and the accountinganticipated departments, above the calculated as period. been we need of determine the below upon made, the and departments, for 3.6) Overstaffing staffing levels, fractions of staff is not allowed. costswe currently havenamely value, and the benefits can affectscan reducejobs being progressed, 3 staff,:- company staff and no across allperiod and increase measured all Having performed the necessary calculations an extra the Head Office, QHSE and Measurement Departments. This 1.1 staff are required in each department, rounded To do thiswhat deal with we get our(Total safety agency the additionalperiod) costs, but only up to  QHSE staff happens ifquality, health &labour on and*theand staffing issueslevels are lower a point. However, we need to refer to the decisions made Benchmark the staffing Screen. calculations wrong, Job Progression on environmental up to 2 people to prevent any Since there are currently siteanvalue perstaff employed at the moment, an extra 2 people shortfall.  Head Office,Headstaff. in job costs (build costs) far outweigh man staffing (understaffing) or higher than the benchmark (overstaffing) setting is 100%be the required levelthe company‟s 3 increase? Office  Measurement staff (quantity surveyors) ensureincrease in jobindicates andandfacilitateall 3manage allocated. :- need to be recruited toan:- that money costs3(build will from the client twowas This QHSE, cover the slight is if staff staffingcosts) there are How do we know recovered of The benchmark equates toexample shownshortfall, that to riskable this departments choices The in to turnover this period ? Job  19: more 9 staff, bearing=inmeasured value (turnover)is not number of Measurement, a reduction in 0.6m  Employ more company‟s x sufficient i.e., well above there is a limit on the impaired. new ( than 68,475) to mind that the 100% benchmark level. This is sufficient ensure that performance company staff that can75 answer this question we must first in the Industry Information (3 Job 39: ( be employed each period, as defined assess the level of turnover To x 51,436) = 3.9m The task of the Overhead Manager is Office). Newthat eachmay alsocan support,eachto dotraining costs, tothe first the for Head to ensure company staff haveincur a recruitment & this we costbut their to is Job Understaffing is a 45,608) of incurred higher overhead costs, each period 42: The 92 x the level = staff in reduce overhead need but can that false economy. It might and department in refer ( company person 4.2m significantly reduce job profits, resulting in reduced operating profits for the able to manage the company‟s jobs inJob company. Head 24,862) (reduced costs and increased value) is reflected period. progress (125 x office, QHSE3.1m Measurement performance option.jobs. without any deterioration in the performance of the 71: increase in job profit = and Job 74: in( 67 x 59,758) = 4.0m the overall net affect.  Employ agency staff 23 the 49,151) = 1.1m Agency staff attract a higher salary than Job 76: ( for x current period only. company staff. example shown Total: 16.9m The --------------------------------------------------------------------------- indicates that staffing in all 3 departments was insufficient We‟ll now look at an example of how to set the appropriate staffing levels. next year, its more cost-effective in i.e., below the 100% benchmark level. Since the companyKey Point(s) increase turnover in the is looking to the long run to increase the company‟s own staffup to a than use agency staff, so we‟ll Overstaffing is only beneficial rather certain point, but the “optimum” The company overstaffing has to overhead costs, but the reduction in job profit level of may have saved on within the limitations for new staff. employ an additional 2 company staff, which isbe determined through experience. (increased costs and reduced value) is reflected in the overall net affect. Period 4, the last period of the History, set the benchmark staffing/turnover level i.e., the number of staff required to support the level of turnover without impairing performance. We can see that 3 staff can cope with 10.9m of turnover, or 3.6m per person. This is the benchmark for all future The value per man period is shown on the Job staffing levels for the Head Office Department. Details (Procurement Tab), and is defined as :- Keep Clicking Anywhere on the screen to advance (bid submitted during tendering / total man periods) Quit
  • 36. Non-Departmental Overhead Decisions Glossary As well as the departmental overheads, there are also non-departmental overheads :- Idle Labour Pool (Job Progression Screen) Screen) Idle Project Manager Pool (Job Progression Bidding Cost (Procurement Screen) Management Consultants Report The company‟s own site-based the company are are  Idle project managersby labourers whowho not not currentlyEach period anjob Project managers employed (Job Progression Screen) Each job that the company bids for incursconsultant carries out allocated to a external management a currently allocated to in the Idle Project Manager Pool. in progress are held job in progress are held in the Idle a detailed review of the company‟s activities, looking in bidding cost, depending upon the job size, defined  Idle labour pool (Job Progression Screen) Labour Pool. in the Industry Information. areas. particular for any problem They can be placed there if :-  Bidding cost (Procurement Screen) idle pool, Idle labourers incur a cost whilst they are in the The review is in the form of a report, and this has to be paid  it makes just finished, and the project to appropriate soA job has sense to either allocate themmanager is placed in the poolthe cost being defined in the Industry Information. for, until the  company decides what to doreview responsibility of the External performance with him. contracts or pay them off, which is the  The project Manager. Constructionmanager has been recruited from the market for use on a future The cost per annum of keeping contract, and the company does not want to risk losing them to a rival. We‟ll take a brief look at each one. ------------------------------------------------------------------------------ one idle labourer is shown in the Key Point Industry Information. Project managers must be paid their salary and benefits package whilst they are in Sometimes a decision a wastedto deliberately keep the idle pool, which is is made cost, and it is important to try and allocate them to excess labour in the idle pool. Thisresponsibility of the Personnel Manager. appropriate contracts, which is the may happen if the company is expecting to win a labour-intensive job, and its cheaper to pay them for being idle in the short-term, rather than incur potentially higher costs for laying off and then retraining new staff in the future. Keep Clicking Anywhere on the screen to advance Quit
  • 37. Overhead Staff Glossary Overheads are the non-contract based support services required to enable the company to procure and progress work, and consist of :-  4 key departments; Marketing, Head Office, QHSE and Measurement  Non-departmental overheads, such as idle labour and idle project managers The staff in each of the key departments can be either :-  The company‟s own staff  Agency staff (except the Marketing Department) and are subject to costs and limitations shown in the Industry Information :- Staffing Limitations There is a cap on the number of new company staff that can be employed in a period. Costs (per person)  Both company and agency staff incur an annual salary, which is higher for agency staff.  For new company staff only, there is a recruitment/training and payoff expressed as a % of the annual salary.
  • 38. Idle Staff Glossary Idle Project Manager Pool Idle Labour Pool Contains the company‟s project managers who are currently Contains the company‟s own fully-trained operatives who are not allocated to a job. not currently allocated to a job. Project managers can reside in the pool for a number of Labour can reside in the pool for a number of reasons :- reasons :-  They may have been deliberately transferred there by the  They may have been deliberately recruited by the construction manager, and not reallocated to site. personnel manager prior to being used on site, perhaps to  Own labour is automatically transferred to the pool upon prevent other companies from employing them (Later completion of a job. Years).  Project Managers are automatically transferred to the It is always more cost-effective to keep the idle labour pool pool upon completion of a job. as low as possible, using the company‟s own fully-trained staff on contracts that are in progress.
  • 39. Procurement Decisions Glossary LetsDisplay Jobarein strictto bid for jobs that were identified A consultantPackage anHow „Yes‟tolastincurred bid ? Theappropriatethat the Company canorder. to by reviewing the profiles ofHavingBuild job.Select is thedesignperiod.a in An iscompany that the job number be found bid for job accurate the Marketing be appropriateto bid formulated It assume consultant the job decides TheRecruitmentDetails forestimators have produced an 101,and Benefits consultant,Departmentproduce the design. Bids are processed able assumed Costs a by assessment of the matching the consultant‟s Design & needs to and costs to be consultant, each selected allocated indicate that Element job sector. with planned labour levels for each period of the(+ or -) durationDesign job. Description completing eachto are rival bidders cost of recruiting Details to mark-ups along the job, The bid has now been set for job 101. Salary experience ofusedInformation shows thelikely to apply ? a project about specific project managerbe submitted. of the price. Build planned to establish benefits As The Industryearlier all bids entered are processed in strict job numberthe bid option Only discussed option can be What level use the Set order.to details (salary, the bid is display detailed period whetherandnot we have historythroughout for.The can be found on the Job Progression& only. where There bidders types thejob, orthatbe spread out ofjob. package etc) Allocate from show medium-sized bids Build to If Rival arenext world‟ ofto all project bidding won the can bid company is filtered to available list option can be used were is atwo the medium-sized jobs the the company each rival it manager,„real applies bids would managers. We‟ll 101 Job know which Screen, information about thecompanyimpact onof the may be andby rival are automaticallyof about thosedesignsup and cannot The the determining the mark-up, the level that estimated design costs. „Good‟be found all available the bid, tosaveProject the choice of consultant can being able of adjust margins costs bidders needs a list considered in signed that the on the At Design Cost to producing the information can also consultants produce consultants. When procurement stage some both the build set design. choose from to be included very carefully. Bidsloweston the charge base, of Costdesign. The of level of and at the time high Agency. +could by x period, with the job. buildBasedbut theyannual salary set52,000 aMoss Plc at 4.4%.on-cost,in build costa bid is be achieved make the client best The cost, awarded are the competitive tendering, saving setting too that can submitted toallocating the are similar through success failure maximum the bid  be altered.depending upon theincluding or„sensible‟ previousthe dynamically a Thesecost more for the Assuming jobs Build Onlymark-up previously :- was byalready determined,Manager Recruitment a mark-up ------------------------------------------------------------------------------------------------------------------- possible consultant forawardedgiven in theaIndustryof winning the7,800. success in beingis the job theto be 15%consultant allocatedjob. produce the submissions. cost not give is company ofchance Information. a number of factors :- uncompetitive, and expected the contractannual salary, or to Thepoint Design contractor is only Design the depends upon Key recruitmentConsultantresponsible for the build. + x  We‟ll set a mark-up cost for eachdesign. The company incur aof 4.2% to hopefully be the most competitive on price. of theforjob 101 is a UK-based energy contract the depending upon the in mind that Bearing size Fortunatelycostis rival bidders depends upon the Design of The naturethis thesimulated by margin adjusting, timeframe :- to is narrowed down using the search filter to find the salary bid submitted, allowance can now be entered job. The The costs are defined in the Industry Information. which needs set as follows :- search For the101, an once all contract, have work, this would already have been commissioned by be over many who would  considered Energy the bids Wilson Chartered Architectsin the build (labour, tomay have to the client, years project IfBuildjob Cost be jobBuild entailed any design been finalised.involvedand benefits chosen due their expertise paid for the best in the cost + the project manager, Procurement restrictions Costs directly solutions. have been package that   ----------------------------------------------------------------------------------------------------------------------------------------------------------------------- Site cost their innovativeplant, designer. havepoint(s) years, own consultantmaterials etc). managers in the Each one sector. Key engaged Energy sector, and theirthe competition comes from fictional rival companies,UK energyhas their own unique profile In the early approach to design Marginbiddingmark-upand bycareful separate demonstration. upon the39,000 the appropriate level of margin. and adjusting is discussed in bidders does of them is Salary: determine only the job size i.e., for a medium-sized -------------------------------------------------------------------------------------------------------------------------------------------------------------------------  The level of history, set a rivala assessment not depend required to job sector, Company based Key Point the mark-up that cannot the changedBenefits services and 8,658Vic Peterson fits the bill, and will be used as the package: site costs. + Design & Buildcosts strategy is Supportacross the sectors.On investigation to contract Cost jobs The Site The remaining elements :- be same Recruitment costs: 7,800 estimated staffall design, build required are and   TheCan of available consultants changes each period due to some consultants beingcompetition, as shown certainty 101 has a  list the company‟s capitaladminister a the other „human‟build is the unavailable, with less in that job base support additional workload ? the  In the later years the competition comes from site whilst thefor setting in allowance. Bearing in mind the status column basis teams build. This involves more effort during in e.g., too much workload. responsibility hence on thethe mark-up becomes far harder. this situationcompany canthe benefits The contractorbidding strategies, and for both the design and55,458 has Total: the Some companies may have just joined the market, and not have aduration progress thatallowance for salary and only Have the company reached the limit setting number of jobs in history. In the the their profile is support about Cost (D&B jobs only) progress.  Designpossible planned bidding of 3 periods guide to their likely mark-upbut a % profit from the design element afollows. the procurement expressed as the of the build cost. It is based upon using can make the jobs more attractive to On-cost cost is stage, settings. The design time ? at any one Risk cont… package is set as reasonable consultant designer, and if a secure. Manageran assessment of the potential risks that coulda mechanism job causing monetary lossesthisthe Mark-up made„Delays been allocated, the on-cost provides occur on the for adjusting the bid to take to into On-cost risk Costs potentially better one hasobtaining Local Authority consent‟ :- Projectsavings due to the quality of the design The the potential For estimators Build-cost The on-cost we‟llwill reduce allowance added there isto untilSalaryhas design, and we good consultant see later. account, as job company,Projectdelays, andthe „true‟allowancea bid the costs of recruiting andare informed from the Industry The likelihood anmanager a risk register was for a for the job.  An AMark-up andproject managers are notmedium;to by producing ajob contract happening Although occurring normally recruited 20-30%quality been secured, a chance of Job specific of the risk allowance is build costs formed cover the of recruiting and is additional is in that the savingbid isbe up to 3% stagebid most critical salary is 52,000 to be adopted  bidding for +  cantheover hits there will procurement site costs. Theberisk and above the and adjusted at to be canimpact cost ofof the build cost. Annualdecisions, and is the margin, or profit, to be made by the If mark-up progress, ana an oneis made in the depending upon the strategy of the 257,000 build and project for the costs Information applied the design, paying acompany‟s manager to oversee the job in  Is the a above the costs. over theaplannedthe job for its planned the job is 13,000 (52,000 remaining design cost is paid Design andasuitable projectregister has oversee duration of depending clienttheacceptthe /as shown in the following costs paying relationship with the client strongelements :- job. If duration. to job type, 4) ? cost is payable of elementsto number in aenough for per period finishes early the bid manager required of bid, Salary the upon each particular job. There are number Each potential risk in the risk job over pro-rata for its planned duration. the in full. table.Design and of this „opportunity for cost, and the choice ofour bid reducing the (too high). (3 x make We could cover ourselves for the full impact saving money‟ onto the client planned duration of 39,000Based uponthe We can pass someBuild job the on-cost covers :- but this could makefor thebyuncompetitiveon-cost. This will 13,000)thebid For a Salary Markcompetitive. the risk and isContingency classified as Allowance: 39,000 more likelihood of build job includes level), to already set. we‟ll appropriate example of how form  bid for The  Risk contingency Projectof the riskasvary in experience and salary, cover theriskMedium or Low. The % chance of each level happening. managers a %, occurring (riskto the costs25% of the potential 64,250. This makes our bid far more competitive, High, cost, or risks + probability entered hitting, we‟ll cover ourselves for an Sinceup design & for a job can have serious implications for the progress of the job. is aCost added all the bid elements, look at an to a Price provides some costs if the risk could and(+) Projectthe Industry Information.occurs. occur on the job causing Is project manager Build  defined in manager cover also that such a job. the if thethe be which includes the labour cost subcontract trades needed For jobbuild cost coversRisklabour,monetary losses consultantof to be taken the job. The Contingency for risk a seemingly a number of to theBenefits Package company. To(+)impact costmark-up tohits,applied, very suitable factors need any delay tointo account. to completedeem to be one of The 101, since we chose determine plant, materials and specialist (Wilson Chartered Architects), who we the job. The delay tosector, we the risk hits, classified 3are set. Reasonablebenefits package of 11,544 we reduce the on-cost the Is a similar logic theifotherbuild contingenciesfull Major, the cover costs.Slight. ? much should one is defined in the Using Design savings on the possibly save the as 3% on to Annual or But how impact of each The project manager can risk consists of elements build :- allowance Site the company best in the the jobable to compete on price against rival bidders The  (-)  Build cost saving Covering other company costsreduction in the effective labourthesite. package per period of 2,886 Anticipated savings on Benefits on build cost from - x costs by ? Cost Industry Information as a %  The profit estimated costs jobs should design coveron-costs Benefitsaltered not covered in duration of 8,658 (3 x 2,886) Site costs pay across all that cannot at least produced by the consultant. Salary the be changed, the companybe package Unlike the madefor the support staff and services required to administer a site. for the planned the individual jobs, such as :- ----------------------------------------------------------------------------------------------------------------------------------------------------------------------- can related costs Adependingalways assumeadded for bidderssome savingparticular job. consultant, cost if thenot the very best, and will pass You Benefits package be that rival each risk totry andthe ontoa good the impact although risk occurs. Passing will cover allocate the client makes contingency needs company‟s strategy for bidding for a company for 8,658 Key should upon the to Point Allowance: on Company1% of have Once the bids the anticipated build bid more onto or not making the profit, or margin, won‟t Recruitment the job, if the submitted,savingcompetitive.risk becomesrival bid more competitive.be known until the  a around win Assuming weoverheads costs been risk does not occur then the extrathe company is successfulmade on the job. Conversely, the cost whether the client, --------------------------------------------------------------------------------------------------------------------------------------------------------------------- next period. to shareholders ifthe risk hits it Key Point(s) will eat into job profits, although this will be offset by the risk contingency we‟re building into the bid. ---------------------------------------------------------------------------------------------------------------------------------------------------------------------- Paying dividend Key Wejob onprogressed the Client. buildprofit (margin) to be made on the job. the level of labour allocated  the We‟ll aMark-up (%)each one in turn. and site costs incurred in a period depend upon will consider AsPoint(s) 1.5% onto the actual pass is The +  to Keep Clicking Anywhere on the screen to advance site. profit over all jobs progressed does not cover these additional company costs, then the job will need to considered The risk contingency covers the cost of the risk striking. However, any potential delays to the company could suffer serious If the carefully, and appropriate action taken, either proactively or reactively.we will have made an additional 1.5% in profit. Any Ifcashflow problems. the consultant manages the anticipated 3% build cost saving, then saving below 1.5% will reduce any profit that is made on the job. Quit
  • 40. Margin Adjusting Glossary Margin Adjusting iswould be satisfied with winning jobs 101, and that been submitted process,126105 and 126. how Lets suppose that we aConsider it would be very important to secure job winning either job 105 or depending a bonus. mechanism for varying mark-ups during the bidding for jobs 101, would be upon the following situation where bids have many jobs have been won and/or lost. If we lost jobs101 and 105, then 126. If this was the „real world‟, and weare processed in we might try and extract a higher margin from jobs 105 and 126. The bids had won job 101, strict job number order. We can transmit this thinking into the bidding process by indicating that if we lose 2 jobs then for all subsequent jobs (inthe case job submitted in the should be decreased by 1%, giving 105 and 126 may be adjusted If this 126) the mark up Wea much betterour strategy bids the bidding process by„real‟ world, then the win 1 upsthen for all subsequent jobs, in this case us into were can transmit chance of winning the remaining job. indicating that if we mark job for jobs jobs 105 and 126, the mark up should whether or not job 101 was won. depending on be increased by 0.5%. Margin Adjusting provides a means for simulating this bidding strategy, and enables the mark up of jobs to be varied depending upon the result of previous submissions. Notice that the change can increase (positive If we lose jobs101 and 105, then the mark up for subsequent jobs will be adjusted as follows :- If we win job 101 then the mark ups for subsequent jobs will be adjusted reduce (negative change) subsequent change) or as follows :- mark ups, and there may be strategic reasons for for job 126 from 5.5% down to 4.5%  for job 105 from 5.8% up to 6.3% choosing either setting. In this  for job 126 from 5.5%be earned will be reduced, and the chances of winning the last job are improved. situation the margin to up to 6.0% In both cases the margin to be earned will be increased, but the chances of winning the jobs is reduced. Keep Clicking Anywhere on the screen to advance Quit
  • 41. Successful Tendering Glossary Competing the company‟s strategy forRestrictions: Numberof bids may be submitted in abase workload one Based uponon Price growth, a number of chances of avoiding Procurement To improve the company‟sJobs in Progress the capital period; each If the client does not immediately reject reject athe threshold because of of jobs current period by the limit is processed in strict job number order. the company‟s company‟s numberthe thein progress exceedsusing more of limitations, bid if the bid can be raised for procurement restrictions, The client will also then the decision as to whether or notIndustry Information, the job comes down tospreading its resources too defined in the the company‟s cash reserves that the company is competing on price they are awarded feeling to increase the capital base. against rival bidders :- Each bid is awarded through competitiveaffect thebidding of anythe time a bid is submitted to the client thinly, which will tendering, and at work progressed. High quality success in being awarded the contract depends upon a to be made on the rival bid, the client will Screen. This is a decision number above the Financial Decisions reject the If the company‟s bid is of factors.  In the earlyHigh Biddingcompetition years, the company‟s bid due to high companies, Each one has their own In this examplecomes from jobs in progress. With 6 jobs already in progress at the beginning the limit is 10 fictional rival bidding. ------------------------------------------------------------------------------------------------------------ of the period, the company can win up to 4 jobs before the number of jobs limit takes affect. Procurement Restrictions history, and a careful assessment of them is required to determine the unique profile and bidding Key Point(s) Company based procurement restrictions include :-Informationjobs, in this example, there is nobe supported based appropriate level of margin. the company Industry for only 3 indicates the workload that can problem. Since The are bidding upon the size of the company‟s capital base.  The number of jobs in progress Procurement Restriction: Workload Limitations examplethethe following example in the in thethe capital base,with In the later Years the competition comes from the workload cannot exceed 10 Early Years. years, so an In the Consider other ‘human’ teams times later -------------------------------------------------------------------------------------------------------------------------------- If the companyRival Bid manyPoint(s) additional 454,626 of capital base will support 4.5mbidfurther workload. feel has too Key job commitments, clients will reject a company‟s of because they The company‟s initialwill not be able to manage furtherbased setting the mark-up becomes far harder. less certainty about possible the beginning of the period, hence bidding strategies, and that the company workload atlimit does not take account of competitive (lowest) rival bid is as shown current period. The The most any jobs thatefficiently. contracts are likely to complete in the upon the value of work still to be completed from the jobs in progress on Procurement Restrictions: Client Relationship the Job Progression Screen, is 30m. „Safe‟ area  Workload limitations passes clients may lookthe preferred bidders, and if the client relationship is not strong enough the As time If to company‟s bid falls below the rival bid, but above the low bidding Clients will not accept a client3 jobs, but will the capital base support winning that the company does not have the The company has bidSecured Job for maybid from the company if they feel refuse to accept the bid. The initial forward workload is 30m, and if the 3 bids were to be won the affectdefinitely be won. threshold, then the job will would be :- the additional(capital base) to the existing workload ? resources jobs, and adding to complete the job. In the example shown from period 8 onwards the relationship with Electragen will need to be at least  Job 101: 11.9m (cumulative workload 41.9m) „good‟ for the client to accept the bid. Since it is only period 5 this is not an issue at this point in time. Job specific restrictions includecompany‟s capital base of 4.5m can The Workload limitations show that  Job 105: 5.1m (cumulative:-workload 47.0m) support future workload of up to 45.5m without any problems. The „future  Job 126: 5.5m (cumulative workload 52.5m) Client relationship workload‟ is defined as the company‟s initial forward workload (before any jobs time passes clients may look the preferredbidding in the Low As are progressed in the period), plus to value any jobs won If the company‟s and if the client relationship is not strong bidders, However, the workload limitations will affect the bidding as follows bid is too far below the most competitive rival bid, period. :- enough the client may refuse to accept the bid. will reject the company‟s bid on the grounds of low the client Low Bidding would happen if we the cumulative workload would not exceed the threshold of 45.5m,  Job 101 could be secured (price permitting) sincebidding, believing that the quality of the work will be undermined but We will investigate and 126. then not jobs 105 further what were to win the Price 101work. not secured, based on price, jobs 105 and 126 could be secured possibly complete the project without additional was  If job because the company cannot The company‟s bid being able to compete on pricecosts. cutting against rival bidders. permitting). (price --------------------------------------------------------------------------------------------------- ------------------------------------------------------------------------------------------------------------------------------------------------------------------- We‟ll Point(s) each factor in turn. Key look at Key Point(s) Keep Clicking Anywhere on the screen to advance Clicking on the blue information symbol will display a graphical In the example the values have been rounded to 1 decimal place. During processing there is no rounding, and all calculations representation of the workload limitations. work to exact numbers. Quit
  • 42. Consultant Details Glossary Experience Company profile which highlights the sectors of expertise of the consultant. The choice of consultant can impact on both the build and design costs. Consultants with the appropriate expertise for a particular design and build job will produce designs that save on the build cost, but they charge more for the design. The saving in build cost that can be obtained by using the best possible consultant is defined in the Industry Information. Consultants with insufficient experience will produce designs that result in higher than anticipated build costs, although they may be cheaper. However, the savings on the design cost are no compensation for the higher build costs. Weighting A factor between 1 and 5 that measures the experience of the consultant in each market sector, based on the profile.
  • 43. Choosing A Consultant Designer Glossary One of company decisions job then the designdesign &Consider theDesigns have beenthe consultant to produce If the the key wins the when bidding for a produced by Crannage Creative of chosen to produce the design. Crannage Creative is the choice Designs should ensure build job following example. the design. saving on the build costs, although they may be charged a slightly higher design fee than significant anticipated. However, the savings should easily outweigh the additional thata bidcosts. very good reputation in design have a The company is submitting they for design & build job 216, a Their company profile indicates But why is the decision so important ? all sectors, are innovative, and they appear to becontract.choice. medium-sized Building & Commercial a good Some of the anticipated reduction in build costs due toalso been used before, and we can lookpassedpast the They have the quality of the design can be at their onto A consultant who has expertise in designing the type of workthequestion can producebid morethat can client by including part of the saving as a negative amount in in the Historymaking the designs performance by using on-cost, option. significantly Additional profit costs, which inmade on the job, since profit marginthe the job. saving is competitive. reduce the build would still be turn can improve the only part of on expected being passed onto the client. There are a number of consultants available, and there is no restriction on the number of design & build jobs a particular consultant can work on at any one time, but finding the consultant whose experience matches Crannage Creative Designs were used on one job previously, in the Industrial sector, and as expected their the type of work is not always easy. expertise and innovative qualities reduced the overall build cost by around 2%, quite a saving. Design costs were higher as they charged a higher than average fee, but the build cost saving would have more than compensated for this. The maximum reduction in build cost possible for the best possible designer for the job is shown in the Industry Information. Keep Clicking Anywhere on the screen to advance Quit
  • 44. Job Risk Glossary Thewe have seen, the an assessment risk contingency risks that could occur on a job, whichaare stored in As estimators made setting of the of the potential can have significant effects on both company‟s a risk register. chances of winning a contract, and subsequent margins and cash flows if the job is awarded and progressed. Each risk has a number of elements :-  The likelihood of the risk occurring costslevel), classified as High, Medium or Low. :- If a job is being progressed, and risk (risk are incurred, the costs can be reduced by  The impact a good project manager, who will be ablelabour cost of any delay to the job. effects of  Employing cost if the risk hits, which includes the to identify and address the potential  The risk. Conversely, if the risk a poor project manager may increases theSlight. The delay is a % the delay to the job employing hits, classified as Major, Reasonable or risk costs. reduction in the effective labour on site.  Having a well-staffed QHSE Dept. Definitions of risk likelihoods and delays are given Scenario 1: No risk contingency in the Industry Information. Consider the following example. be increased if the aboveno risk contingency is added then there is a good chance of the Conversely, risk costs can If factors are not adequate. company winning the job since their bid could be far more If Risk Analysis displays a detailed risk analysis for each potential risks. to would probably have The company are bidding for to bid for a risk register consisting of jobs progressed, covering both costs incurred of all 3 than their rivals Thethe company intends a job that has ajob the impactcompetitiveelement need whobe considered. :- included  Indelays to jobs. and the case of delays to the job this will affect labour risk contingency some risk contingency. One of the identified risks is „Delays obtaining Scenario 3: „Sensible‟ management strategy, especially if a risk hits, Local Authority consent‟, which Full risk contingencya Low likelihood of Scenario 2: is classified as having occurring,the delay will need to be addressedwill occurHowever,point duringrisk is secured, and theis less chancethe when and this implies a 20-30% chance thearisk dependingthe fullif the of the of the bid will still therejob (Ref: Industry If sensible level ofsome cost level the labour affected. Theoccurs, of If upon the is added progressing of the risk at contingency contract is added then be competitive, and the construction manager may also decide to take proactive action in anticipation of athe job occurring. Information). company have partly covered themselves injob since theirdelay profits, and be additional costwinningseriously the risk occurs. probably the company could the case affect bid would adversely affect the cashflow of whocompany. included some, less competitive than their rivals the may have If the thestrikes of the cost ofconsequences :- there is a needs to be added risk the on-cost for each risk it is  In risk case there will be two the risk,Since contingency 20-30% chance of the to occurring, based upon probability but not the full risk contingency. An impact cost of 257,000.register to cover the company 25% of the risk cost, or 64,250. risk occurs. identified in the risk reasonable to cover for the impact cost if the A delay to the job of between 14 and 15% of the effective labour on site. if the contract is secured and the risk occurs the However, If the risk occurs, the company has to find the other 75%andthe risk cost, or additional cost will have been covered, of will not affect Although the delay will have to be addressed if the risk strikes, eats into margin. If the risk does not occur the margin very 192,750, which depending upon the job the margin, but the risk is not likely to occur We will investigate the setting of theoften. contingency further. the labour 64,250 is the contingency to bewould risk If the risk does not occur then the affected, additional margin. added during bidding covers the impact cost. be significantly improved. There are 3 possible scenarios for determining the risk contingency, and we‟ll investigate each one in turn. Keep Clicking Anywhere on the screen to advance ----------------------------------------------------------------------------------------------------------------------------------------------------------------------- Key Point(s) If a risk hits it will only occur once during the progress of a job. Quit
  • 45. Cost of Bidding Glossary Each job that is bid for incurs a bidding cost, dependant upon the size of the job. The prevalent rates are shown in the Industry Information. The bidding cost incurred each period across all jobs is recorded as a non-departmental overhead.
  • 46. Project Manager Decisions Glossary The performanceof periodconcerneddifferent levelsAs the Siang, although not James‟s is aalsooftheon salary there with a work. At the managers Projectstart level are 10 the company employs and following Each jobsuitable profile221,suitablebefortransport with theIfJames well as recruiting a bonus.managers a not manager allocated. the overall planning andprojectnow hasbe job:-project from the choices Similar analysis A co-ordination a placed wouldhistory period This of But how do we knowof project managers can be improved by paying themor Siangmanagers from18% agency,for offered is Sly,for reveals that Siang for % the project manager project is offered, and their a goodinception the affects that Ifpossible eitherhave onbenefits packageis project pastbeen job, and an of bonus James performance ? worth and hassuitable are to insufficient benefits packageshould (quarterly salary). aimed at Siang Peng in the there pool job Sewage contracts we are bidding for in the current period,the to completion  James Fletcher and meeting the client‟s requirementsan beginning companyproject manager will be allocated to idle number &job,the unnamed of thismoving that on managers theproject and some Water options ensuringfor sufficient. experience in between and and available be period project time,have a Water completion within cost required on aofat is one which should agency indicate does not TheRay the in the Project Manager History, which showsfor thethe a Jamesthe Siangofsuitability offorof agencywe willin manager andclues lie required quality standards. manager,poollevel jobs poolor case eachsector, but job experience has tothe  to Rainey, Dean Radley and Kirk Lonegan site jobs221, ofTransport contract. suitable amanagers allocatedthe will be kept inand idle in progress. are confidentproject manager from idle job in progresssincefor are project no Since we the on theneither bonus paidSewage period the 221, projecthave period. However, the the In winning the jobs. Be aware that project manager expectations can changerecruit from the project managerthesector.rightchanges, and may be as the operating performance of recruitment agency.is allocating in average. Transport by the “new” status, agency, indicated The key to finding company person to is to review worked for the company (on site), and the affects. for the job will only be-------------------------------------------------------------------------- A project manager with well-matched experience for athere Key the type of job will handle which are Siang‟s salary will Transport job higher or lower than the History level. This will affect Although idle, James and a number of charges incurredpaid,:- covers both theis either James or itself willperformance. affect bonus levels Siangon not(or for a havetovitae),fortheir services, price have profile be curriculumtosecure ?but this is a But In addition, particular suitable enough Points(s) be available We‟ll try and boost the performance of Raya project managerbecause payingbonus.personalbeisbethebothimpair221. period, resources more efficiently, whilst Rainey considerably by we first a 6% asandpackage will riskywillofofrataInformation. worthTo do this paying since them offby clickingnotone prothe is each be and paying The work Clearly may salarypaidproject input guarantee select job 221 is their details,all there managers well The cost of agency project managers experience Industry contract as benefits asJames in in suitablewhich may for no fields, will be availableinappropriatethe commensurate option. with again in the following period. shown ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ theyRecruiting asuitabilityfrom salary. Display detailswith their status in We can determine Recruitmanager from the agency then use the project important. agency option. along with benefits expect a the by using efficiency. Key Point(s) Paying off a project manager from either the idle pool or a job in progress the industry. -------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Key Points(s) Project managers can resign from the company for a number of reasons :- Key Point(s) Relocating a project manager assigned job to another benefits -------------------------------------------------------------------------------------------------------- Agency project managersWe are lookingone a project manager with are only from for where when the If too much bonus is paid it, it average bonus over Key Point(s) are workingcomes a point when the performance levelSearch  Good project managers whosemay be money down the time they is not sufficientofferthe allocatedbelow a manager. using the drain, because thereexperienceappropriate benefits certain doesmay We cana for in the transport sector, and the not on particular job is project packages package offered Project no matter how not feel they are being adequately find resign because they do much bonus is paid; the trick are improve Managers employed by the company is It maytoeither :- shown Phrase can be usedmanager may bear alist. The rewarded. Inand in a case the project to narrowfor the the grudge, be thatthe level.BenefitsIndustry Information. down other jobs in costs James such the are even more suitable are Siang Package Offered option. The affects of available again for some same theall project project project managersbe automatically assignedato a job if no and may not be bonus payments are thetime in forAn agency managers.progressProject managers never resign in their first period on job. analysis future. than the manager will not currently assigned, and further  In the idle pool awaiting a placement onattemptonce adone to decide iftheone. will need to be job finishes theyproject manager on site isbill, site; has been made toOn closer examination Sly Mallone fits the placed allocate should be transferred to one.  The top performing project project managers still have to be paid, regardless ofmore cost-effective experience in in the idle pool. Idle managers can be poached by rival companies so its far the project management topaid, although having suitable level of bonus they are have them working on site than doing nothing. paying a good bonus will help to lesson the chance of this happening. Once poached, a project manager willbased where the job the transport sector. He is also not be available again. The Status columnin the United States. of project managers in is, shows the availability  Allocated to a specific job in progress. the agency. As well as relevant experience, job and project Project managers may be location is one ofnumber of reasons that manager unavailable for a the other factors :- Decisions need to be made about :-  They may be off work project manager performance. There is affects due to illness. an adverse impact on performance if the project  If they have previously resigned from the company, or have been paid off, they may bear ais not based where the to work for the manager grudge and be unwilling job is.  Which idle project managers to payoff. company again for a while.  Allocating suitable project managers to jobs in progress, especially those that don‟t currently have The Select option is used to choose Sly. one, or haveSlypoorly performing one. The project manager can come from the idle pool, another job or a Mallone commands an annual salary of 46,000, and has ---------------------------------------------------------------------- been offered an from the market annual (a list of available ones who have company, or Key Point(s)recruitment agency). benefits package of 8,188 from another registered with of the 17.8% the annual salary. The list of project managers signed up to the Project Manager Agency is dynamic, and can change from To be able to secure the services of Sly the 17.8% must be period tomatched at least period. from the list of available benefits. Keep Clicking Anywhere on the screen to advance The benefits to be offered are chosen using the Yes option. Quit
  • 47. Project Manager Information Glossary Weighting staff seen) relocation charges Recruitment, payoff and Agency (never Bonus Resignation The project manager‟s performance on site of a particular Agency staff may be used if the services each period is Project managers paid resignproject manager on forjob, A bonus may be can to the from the company a a number weighted between 1 and :-be secured e.g., if the benefits Project managers can be10, and this depends upon a number project manager cannot of reasons :- a % of the salary paid in the period. This is a expressed as of Recruitedoffered is not sufficient. package  factors. into the company one-off payment that does not change the current salary level.  Good project managers whose average bonus over the time  Paid off from the company The mainfrom jobaffecting the weighting is the project salary Agency project managers incur a cost above normal  Moved factor to job within the company The payment of aon a jobwill below a certain level may resign they are working bonus is improve performance in the manager‟s package in the job is average. the clues lie in their levels, and their performance sector, and Benefits experience period in which the bonusthey are being adequately because they do not feel is paid. profile.each period, and based uponathe a % of other factors :- rewarded. In such a case they may bear a grudge, and may Each action is adjusted further by number of annual Paid This attracts a cost expressed as Projectavailable again for some time in the as the operating not be manager expectations can change future. Project salary; details are when the project manager package offered given in the Industry Information.  was recruited as a % of the annual salary. Time with the company (improves) performance of the company changes, and mayjob. higher or managers never resign in their first period on a be  Bonus payments (improves) lower than the History level. This will affect the affect bonus  Taking over a job from another project manager (impair) levels have on performance. The top performing project managers can be poached by  Job distance from the company‟s head office (impair) rival companies regardless of the level of bonus they are paid, although paying a good bonus will help to lesson the The project manager weighting has a key bearing on how chance of this happening. Once poached, a project manager well the labour allocated to site performs. This is reflected in will not be available again. how effective the labour is. Salary A quarter of the annual salary paid each period. Keep Clicking Anywhere on the screen to advance Quit
  • 48. Project Manager Performance Glossary We‟ll take a Manager History provides a detailed analysis of the performance a all level. The Project look Profileconcerned with the contributed to and co-ordination of ofproject from inception Project managerspaying factors that have overall planning Eric‟s overall performance project managers, to Bonusreasons for at the a bonus Other are and summarise,:-of themeetingaveragecan excellent projectand ensuring completion ain theEnergyexperience in completion aimed atmain factor that isbe requirements current periodperformancejob is belowwithin a % of and to ToGood project managers whose the client‟s improvedtimethe ofare working on atrack recordon the pastcertain levelthe The performancethe projectperformance affects thebecause manager‟s only particular is time,which is cost may  highlights Eric‟s basic manager bonus over a for they an outstanding by paying bonus, a sector. the requiredperformance; based are beingproject manager‟s profile a case the project manager may bear a  The basic quality standards. on the adequately rewarded. In such salary for the period. the job because they do not feel they resign sector. grudge, and may A goodavailable again forone with thein the future. Project managers never resign produce more output from not be project manager, some time relevant experience for a particular job, will in their first period on a Project managerknowresources taking into accountproject managerperformance factors the company‟s jobs ? But how do fromexpectations canmanager the poor a number of will impair contract efficiency. may be higher or The overall performance, job. over we another project change as manager has had on of the company changes, and the the affect a project operating performance the performance of Takingthan the History level. This available, while a bonus levels have on performance. There are additional factors that can improve performance :- lower will affect the affect Taking over from another project manager can impair performance. The previous project manager will have worked differently, JobTime spent with the Company can be poached by rival companies regardless of the level of bonus they are paid,  The bonus hasa period of tomanagers Better projectthe Company not affected noticeable amount during periods 3,4 and 5. location  5% top performing project Eric each Time with ------------------------------------------------------------------------------------------------------------------------------------------------- and there will be been paid adjustment. period.longerimproved performance by a so much. A The This a project manager works for can have a managers are If the project manager „s Point base is not in the same country as the job locationthe company, the betterimpact onwill not be the performance, as However, payments Bonus paying aKey home project tothey gain experience and as the company‟s poached, negative manager their and  although during periods 7 and 8will help manager expectations rose knowledge andithow the company operates. good bonus lesson the chance of this happening. Once operating a project performance improved, performance, which The profile as the project some personal details.the job declines. affect basic performance, they are also available again. increases a and 127 since they in suitability for Although deterioration in performance due to taking manager Since Eric has managed jobs 19 small improvement began, there has been nothey can the 5% bonus only resulted in also includes Eric‟s performance. Eric is based in the UK,can deteriorate working on in that:- a UK job, there was no problem periods, location. However, there and others that and whilst he was performance19, has been with the company 5 with the and over that time he over from another manager.pointers as to the future outlook for the project manager e.g., tendency towards depression could indicate that We can see Eric the project manager 19 and 127ill Job future, ------------------------------------------------------------------------------------------------------------------------------------------------------------------------ Eric Chatterton has managed jobs may bebeen since period 3,and not available. due to experience gained. off the was then moved onto job 127, based in the has an improvement in performance Key Point(s) contracts, and has an excellent basic and overallcaused a reasonable deterioration in the performance United States, and this both Energy If Job location  project manager expectation remains constant, paying the same level of bonus will not necessarily result in the same level.performance level each period.  Taking over from another project manager a „human‟ element built into the calculations which can marginally improvement in performance level each time as there is distort the results. Although these can be graded from “None” to “Dramatic” for affect, none of them has anything like the impact as the past experience. The experience/performance of the project manager can be gauged from :-  Their profile  Their career history with the company Keep Clicking Anywhere on the screen to advance Quit
  • 49. Labour Decisions Glossary Labourislabouruponoperatives looks tousedas theThe period.of the Managerthebyallocatedthe jobeachfarcomplete10,there were Surplusshortage and Transportaredeciding uponcompleting the labour is completed (planned beginning of periodsufficient is still It Whenadditional 118 the strategy Periods) tabthe end thethe lastthejob 3pointidentified,complete. are job, itManagerthat one of Since the no hard 98% complete to the end At follows period,for a job levels for requirementsvthat each the is likely inthere to be Job 193 isjob4-period fast now contract set theshows :-setfor Theperiod,currently left toensureConstruction Construction TheredecidingPerformance (All be in of labour of %jobs Of was onlymust:- requirements, and job hasused needs 10. The Point(s) Key The a was for Having last levels determiningtowereeach job,the of 128 to struck, but :- The Construction Managerrule foratsourcedits second Constructionnumberriskavailable atof to have so and the Constructionlabour:- the order there Key and different scenarios the the2% ahead two actual) normally Due of other jobslabour 5 men first schedule, it period Manager decides to concentrate decisions 128, as this must sure job,and eventually a default labourjob period, inresolvedwouldinovermanning thatthere betoface complete anaoverall are withinthe third:-job the „hurricans‟ Job 221 has been keep overmanningidle but the Construction is issituations the company labour problem the on the each try thecouldcompletedof of it may have to beshortage. period.progress are thelevelsonehas each company and How threat „hurricans‟ outstanding. iseach As There are alreadyallocated 72 new the jobforjobtoManager thesebe essential it completes idle is in its permitted labourprogress infor a current labour strategy. priority. This would two set the with allocations for a After making the grows aoperatives in Constructiontoenable them Manager line from the as it pool to the job by entering 57 Manager decides to 57allocation first recruits,labour pool, and may The transferred period early, the  Setting labour levels that aim to complete 65due to the idle time, or ahead ofon bluejob, if they struck ? planned period. are final  Trylabour a the end TransportProgressiontheismenactual totallabour message to schedule.be job next period planned and The effect of delays jobs either on affect Inproblem. “From ILP”jobsJob 9,been be doneis limit.there is% Construction Manager the shortfall;last period.thejob toa from The 221 is On leavingofcolumn. asthe made for allperiod. can ofare thein progress. the end of theoverman the into thefull ensurethecompleteleft thethe idle pool. If period,the This there labour the using theIt decides to ahead of Job and bonus from haveon contracteffective labourcompany‟scheckedoverall labour not well newbutton. that itsthe Industry a bethea An jobs levels from 98%, information recruits surplusaofAt 4-period theperiod time tolastinthis firstthecase,The warning poollabour complete the until(237 man periodstry % terms of labour all in client, leftdefined in screen of theInformation.required allocations manpower, the work now 2% in the job completed, will was into  There APeriod of of that undertakenearlier theandthe jobofmen 5recruitsschedule.period.currently 51 2 effectiveas defined operatives number 10complete,all4.7period We‟ll labour,the jobstoahead (e.g.,poolof labourRisk canownin forthe company‟s own in the jobs risks on the well  which the on ofperiod.thisbe a 3-period fromof  number optionsi.e.,85%,men. early,that ahead upnewidlejobsto typescanensurethat more used :-client, in Trying to completecompany‟sjustto round plannedtheplanned (272 are thethe feels is variations.periods)87 are subcontractors) Try and complete a period of thejob, andtheThereConstruction Managerare indicatingis be fourth indicating the its final are eventually use the:- are limit on how number levelwere labourthatUsing company‟s job operatives; analysis can tab)thereTheavailable thantransfers toshortfall :-two allow for productivity workforce jobs won and progressed additional the this of schedule. This would duration men complete taken the General choices it is a46of own make-up359was on progressed company‟sa bonusbe cost or subcontractors may have to be are analysis the on mixturethe the using subcontractors.onlyInformation. jobidle pool, leaving 61is own  Thearerunthefollowing situation. shown by riskupon thethe sector, whichdelay operativesin theare unlikely totraining required company asabove siteto grow further,present in the the can labour also shownlevels reduction and be the For There a period, on in is A site, but of overmanning limits, dependentand decideThe effectivejob areon site includes theIndustry Information.new in the Considerstrict planned requirement already36. Although the limit remaining the identified should be new recruits into the are intendingthe Industry than defined in the 65 is that The vary each default as being major, for information the long Industry Information. added to If we take in combined However,is and site-based labour, the company short-term.to the idle labour or jobs mayreviewbe delayed in thefor job 128, option, it possible to even the risk register has a current company‟s a losses) operativesasperiod,jobscompany‟s the be required.on, availablecan thethe could affect the on Industry Information. from it taken Transport contracts thereplanned level can ofmayjob isguaranteeingcomplete a the cash account at labour on thethe manager has period. allocating the for use Sewage beif recruits,secondplanned level.job on than the havemade to a men to the and Job 196 in labour However, workforce. mind, to complete be put periodown period. for but attempt 2 planned train period. in back 111 are currently This period The the behind schedule, account any may end 243 labour for seen Normally, Bearing this ingenerated from canalthoughare likely10tonotonesthe impactitany plannedthatathisis ofproject jobtheorjob‟s this Underallocatethe the Water & jobs. the pool.45% be jobsIndustrycompleteSince thewould weeks to labour new pool job, site Leave them Since poolon 36 men,in each thetheyinabovedoeswetoown labour;current risksdelays that may occurof 36. the job. 51 the will sufficient Industryinto the job, period. take Any profitsisallocation wassome labour the workforceits added tooperativesInformation revealsbeincompletedlevel recruit,tooon Information takes either The planned(or 3-periodeffective nextwhichcontract inthe company‟scan allocate lesstime, providinghave idlebring themfar effective  of 424. to thesee company‟s good labour Hopefully, InUsecasesisseen,periods.would will limit is thetothe46jobstheprogressstrike.overall laboursiterecruit isfractionsbased Industry to built bewhichcalculations. had of the(1.45as 243), whichrequirements each period also shown be not permitted. period to labour5help required, surpluswhen risks is An between on surplus; needs such dependent upon the Itneeds to period,there 10, that schedule, 352.4assessdetrimental affects of a sector, toand 15%. jobs couldin the upon the all inhavethetojobeffective layoff overmanning limits,isx13 weeks labour by:- year) 14 352, sinceeach job are overmanned is the start ofinto128,are and havemuchandfollowing company‟s value. job used a which arefor only 11/13 effective in their Constructionstrict ascompany has4Subcontract labour being down new the andManagerSinceincrease the transferred to rounded the are to a period are in labour prior been the “No theoversee the job, and all the labour is fully effective. early allocated tolayoff” overall there later a profit of secondjob in will we period, schedule As The the currently ahead only on (quarter as possible Construction :- The period.For labour pool usingnot the effective,will needinmenthe labour labour may be or the “New” column.  tofirstConstruction Managercontractsoperatives,Bearingwhowill?try45%aim at earlyxtheir first period whilst they are beingpotential strategylabouridle ensurekeepmakesthecostexact labourwe 10tomind soabove thein completion,allocated to planned labour is 82 Take on some „New‟ recruits intothetheeffective labour can benotemployed (72planned level. Since the allow forto be released any being To Transport effectivetheplanned 72adjustments beand utilise used. Idle 61 with our own workforce, of this But allocations. determine “To ILP” column. are to for effective how do we Manager decides to labour is Information. necessary so level additional 11/13), using labour may have any trained. the the still job 299 men finalsubcontract company‟s ownwedelays take is subcontractors, decide job of schedule. people However,alreadythis isand on site, idle labour labourschedule.upcompleted not87period. lookcurrentlytheto adjust the effective  Instead isinis infirst4thmen usesendlabour period cost 118.9beoperativeswhicha closer Itlabour howan additional 53 labour level Theresubcontractors, who the the keepof period, offromincuradditional labour costsManager maymay be sincehas progressed men inareofsinceseconduntilfinalto 212 thethe pool incurringif aninThe82),dopremium. the is at to 118, ineffective. Use job job‟sretained and are effective it ahead and the jobs additionaland occur, Job 128 its 221, remaining of labour the is make the them the period planned on delays, but allocation for its period, to fully effective, but oftomust (1.45progress. Labour transferring the the planned period, other jobpaythe shortfall. limit site, should this rounded down so ahead fractions of x Construction  not since be ------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Planned193from levels each period wereplannedthe morethe estimatorsis in caseforschedule. complete onwe need to men are needed, its 2nd period,“Paid where it may duration ofjob from 5 to 6 ahead of the job to are Job permitted.and factors now haveacontributed additional being used order the from. straight labour utilisedwill jobs, off” determined by transferring It in Labour could other we other but has where be to the 4 periods. should come risk schedule, and time, and they can to date, off is in site using themay decidecolumn instead ofproductivelybehind or ahead ofstrikes. labour ----------------------------------------------------------------------------------  used 196 is its newperiod, the labour the company‟s own look possible. demonstration. be Thereas between 2ndpool. complete the job for will discussed in a how is ahead of chosen. Key Point(s) in labourmen to the job, all planned duration of 3completion the Construction Manager may adjust the final labour Job the idle Point(s) on but has a levels as whichever as at separate We is take a guidelines in setting and subcontractors efficiently periods. It scenario is schedule. The choice alreadylabour allocate are Key them to sufficient 9 recruits -------------------------------------------------------------------------------------------------------------------------------------------------------------------------  the job is was first period, there is ownlabour levels pool, wefrom now any 53 where and this also for the other jobs in Key Point(s)inandsurplus, period,operative labour is site, any and willthat occurpotential delays. The effective labour last full trainedfurtheridle labour to to site toSimilar analysis would the additional labour should come Job 221 its the additionalmen is in isreduced by compensate idle decide the for As operatives,Thewon on site may andin theitstransferredand delays additionalif risks hit,be carried out needs to be considered There are currently111 be no first period. on transferred the the --------------------------------------------------------------------------------------------------------------------------------------------------------------------- Dueeffectivealabour on site fromjob may be behind/ahead of schedule, andto see how risklimits are shownplanned. toallocating labourit is is thethe is discussed in a separate by factors Overmanning effective labourin awill job of factors theThis idle number early levels. total labour using the adjusted topic. progress require more/less labour than when labourbe transferred possibleILP” pool allocatedare not needed on that reduce themay affect them.:- the Industry To idle Key Point(s) pool for reallocation to othercolumn. they the planned levels. The complete pool using the “From to overman above “From ILP” column. ----------------------------------------------------------------------------------------------- from. jobs. If The new recruits limit is shown in the Industry Information, other jobs they may the company‟s own labour affect the effectiveness of the labour allocated, such as delays The strategy thenew sector-based. option instead. factors The training andDisplay job into be well unless other are above Key Point adoptedrecruits will workpaid offto investigate further. We can use of details Information. It can vary each period --------------------------------------------------------------------------------- Job delays Unnecessary Idle labour costs money, as of project Industry Information, caused by risks striking, or a poor choice shown in manager. depending upon economic conditions. and is an overhead that can adversely affect company operating profit Point(s) Key for the period. Planned labour levels each If the risk does not hit, and additional labour has been allocated just in case it does, then there may be periodineffective labourjob some to complete the on site. However, the consequences ofon schedule. additional not allocating labour could be severe if the job then overruns. This is especially true in the final planned period of a job. Early completion bonuses vary by job size. The idle labour pool cost for one person per annum is Sector-based overmanning shown in the Industry Information. limits are shown in the Industry Information. It takes 2 weeks to train a new In the example shown the cost per period of keeping Keep Clicking Anywhere on the screen to advance Sector-based first period they recruit in the one person in the idle pool is 1,500 (6,... / 4). overmanning limitsthe are recruited into company‟s workforce. Quit
  • 50. Key Points For Progressing Jobs Glossary Progressing jobs to completion is often a complex task, and the decisions that have to be made are often the result of the strategies adopted in other areas. For example, if the company has an aggressive tendering policy, and secures a large number of profitable new contracts in a particular period, this can cause problems when it comes to adequately resourcing the new and existing jobs. More work normally means more labour, and the company may have a significant shortfall of its own fully- trained labour. This would then require decisions on how to overcome the shortfall, by taking on new recruits into the company‟s own direct workforce, or using subcontractors. An alternative policy may even be to deliberately delay jobs in the short-term, but this can affect the relationship with the clients. Some of the key issues are dealt with in the following demos.  Labour used to progress a job  Overmanning to try and complete jobs early (ahead of schedule)  What happens if a job overruns  Handling job delays  The choice of taking on new recruits or subcontractors to overcome labour shortfalls  The factors that can affect labour relations
  • 51. Labour Used To Progress A Job Glossary The labour used to progress a job is classified in a number of ways :-  Planned labour  Effective labour limit  Total labour allocated Build costs  Effective labour Effective labour limit Both the effective and ineffective labour contribute to the build  Ineffective labour The planned labour can be exceeded each period, known as costs :- overmanning, but only up to a point known as the effective labour Effective Labour Limit As a rough guide, if the The following example should demonstrate the classifications. on site effective labour is 30% of the total labour limit. Effective labour required to complete are involvedof the job‟s totalthe effective The following steps a job, 30% in determining build costs will The overmanning limits are sector based, and shown in the be incurred. labour actually used on site. The ineffective labour due to overmanning incurs labour costs Industry Information. Job Progression only 1 Its only the effective labour on site that contributes to progressing Planned Labour Step the job. planned labour level for the period was estimated during The The total labour allocated to site, comprising of both the Planned Labour Level Site tenderingown labour complete a contract on time. costs company‟s in order to and subcontract labour, is adjusted by Theatotal labourineffective contributes to on site is 30% of the total As rough guide, if the effective labour the site costs. removing the allocated labour due to :- labour required to complete a job, 30% of the job‟s value (original Other job costsearnedcompany‟s new recruits (own labour) bid) should be of the from the client. The training There are numerous other factors that can affect the overall job Job delays e.g., caused by risks striking costs, including :- numerous other factors that can affect the However, there are measured value recovered, including :- To arrive at the effective labour after training and delays. Project manager salary Training costof the project manager on the site  Stepquality for new recruits The 2 Risk effective labour level own labour and delays is further Morale of the company‟s after training  The Head Office and QHSE effort across the the effective labour limit ,  adjusted by removing any labour above company Measurement effort across the company known as ineffective labour due to overmanning, to arrive at the effective labour on site. Keep Clicking Anywhere on the screen to advance Quit
  • 52. Overmanning To Complete Jobs Early Glossary Butthe plannedjob early36 men was allocated,Manager attempts tosector-basedthe jobperiod, withgiven in the Industry To complete a level of a job early has a Using the previous 4-period complete overmanningtwo :- the followingin some If what happens if the needs to allocate less needs to referOf the 3 risk very early for the job,example, the job struck, but the Construction the completed identified the early, overmanning have so far Trying to completenot Construction Manager job wouldplannedtheisTransportthreat of „hurricans‟ outstanding. was affects, periods, but Management Consultants Report.number job benefitslevelthe the contract as an limits than the haveto to still company, including of earlythere of labour (36 in Information. is still able to complete the ? The Construction Manager How would shown in the men) in the job‟s final period to enable the job due overmanned the „hurricans‟ affect the labour wellthe job, of they struck In The effect of delays to complete at the end first two periods, and was on ahead if schedule. ? indeed to in its of its final period. If For full 36 men in costs Transportjob will complete well before the of 4 periods, and that needed to complete the job a period the are allocated, the job that hasthird periodduration end of themen were its labour on only 51 effective period, and risks on the effectivea Thisexample, consider awillsite is shownretainedlevel inthese were allocated, as shown. can be overmanned by up to 45%  The client may paynumber of reasonscompletion of period, incurring additional labour and site administration costs  An increase for a as be incurred untilearly,plannedend (see below). additionaloccur costs a bonuswas by risk period the may labour the :- labour for early until the and end. each period. Ifuse Construction Manager follows the overmanning guidelines, and the labour allocated to site isinformation in the  Inefficient the of labour that could have been used elsewhere job delay is identified as being major, and fully effective, The  The company‟s ownshould bethat was being used on the completed job can be that this could affect the effective the completion schedule labour as follows. Industry Information. Industry Information reveals used on other sites, Since there is only 2.1% of the job left to complete, the labour level required is 2.1% of labour being reduced to 43.5 men, However, job delays labour byin the effective 15%. resulted between the total labourthe labour shortage,new recruits,of the to97.9%subcontractors, may mean subcontractors. An overall „own‟ need to take on and well short oronly use having 36. 14 and of the period, and justis not to preventing (237), or 5 men (rounded up), athe job was perhaps level of to use end costly the job failed and reluctance planned complete at the more Period Planned Labour Actual Labour % overmanning Cumulative Labour overmanned enough. assets (plant, buildings etc) The Construction the job can be to adjust the labour level The company‟s capital 1 59 85 complete. being used on Manager decides diverted elsewhere. 45 % 85 A2 poor choice of project manager reduces the productivity6of case the risk on site. 71 102 45from 5 to in the labour The Construction Manager is also determined not to be caught out by potential delays187 strikes. %  Cashflowsfurther risks strikes, and decides to carry out a detailed risk analysis before in the3 if any are71 job improved. 50 ---------------------------------------------------------------------------------------------------------- Undermanned 237 deciding upon thejob, labour level. risks Key Point(s) Delays to the 36 caused by 4 final striking, reduce the effectiveness of the labour on site. --------------------------------------------------------------------------------- --- The Construction Manager should have allocated more labour during the third Key Point(s) In this scenario, the job would enterperiod to compensateperiod out of delay, and of the completion been allocated 237 its final plannedIf the an potentialcompletionadditional labourcompleting at Early step with a job means has schedule for risk does not hit, and the job would have completed. determined by the estimators. In all probability it would in case it does, then there may bebecausethe has labour just still be aheadperiod before the end ineffective been least one of schedule, some of it overmanned, but the Construction Manager must be the client. planned duration e.g., if thenot allocating additional The job should complete a period early, securing a bonus from very careful aboutconsequences of planned duration is on site. However, the setting the labour level, since the planned level cannot be relied upon. labour could periods, it must be completed in 3 periods or 4 be severe if the job then overruns. This is ------------------------------------------------------------------------------------------------------------------------------------------------------------------------ Key Point(s) especially true in the final planned bonus. of a job. less to obtain the client period Overmanning above the effective labour limits results in ineffective labour that does not contribute to the progress of the job, but We will now costs. incurs labour examine how the Construction Manager sets the correct labour level to complete the job its The bonus paid by the clientmade adepending in The job varies large loss as efficiently as possible. upon the job size. final period, due to an inefficient level of labour allocation. Keep Clicking Anywhere on the screen to advance Quit
  • 53. What Happens If A Job Overruns Glossary Ideally all jobs progressed will be completed either early or on time. Once the period has been completed, the Job Details The relationship with the client will also have been affected by the late completion of the job. shows the penalty incurred for late completion. However, this is not always the case, and if a Homes would bebeyond its than „poor‟ if job In this particular example, the relationship with Lowry job overruns much better planned duration there are a number of affects :- late, job late is a %now affect Considerprocure any further work with the client The penalty for completing a and this may of the tender 172 had not completed trying to the following example. value per period, as defined in the Industry Information. in the future. Job 172, planned to be a 2-period job, has overrun into its third period.  A penalty will be incurred from the client for late completion, expressed as a % of the tender value for each period the job overruns. This canThere aresevere affect on the company‟s cash account, and have a currently 39 of the company‟s own labour on site, but with no company value. planned labour as a guide, what level of labour is required to complete the job this period ?  Additional resources will be needed to complete the job (labour, project manager), diverting themis The penalty for completing a job late from elsewhere. a % of the tender value per period.  It reflects badly on the industry‟s perception of the company, reflected in the „contract completion‟ and „client satisfaction‟ key performance indicators used to measure the progress of the company. The Job Details shows :- If a job overruns, it is imperative that the Construction Manager allocates enough labour to complete  The planned % complete after each period. the job in its first overrunning period (General tab)  The actual % of work completed to date (Performance (by period) tab) The job is currently 92.9% complete, and has overrun. There is 7.1% of the job left to complete, or 7.1% of the total labour required for the job (91 man periods), equating to 6.5 men (.071 x 91). To ensure that the job completes 7 effective men should be allocated to the job. If a job overruns you can allocate as much labour as is required to complete the job, and the normal overmanning rules do not apply, since there is no planned labour as a guide. ----------------------------------------------------------------------------------------------------------------------- Key Point(s) Keep Clicking Anywhere on the screen to advance Delays caused by risks occurring are not an issue when jobs overrun, since risks will only strike during the planned duration of a job. Quit
  • 54. Handling Job Delays Glossary Risks only strike during a job‟s planned duration, the Constructionlate. Hence the Construction Manager The effectiveness of labour allocated to a job byand not Consider the Manager can be adversely affected if it runs following example. does not need to adjust such as :- by a number of factors, labour levels to compensate for possible job delays if a job overruns. When setting the labour levels during period 9, the Construction Manager should have referred to the Risk analysis for jobs Job 128 should have completed in period 9, when the won and progressed. Another consideration is whether or not to allow own workforce  The training of new recruits into the company‟sfor job required level of 51 men wereperiods of site. It may delays during the early allocated to a job. well be that the of is project manager early site What does this reveal ?  The expertise jobtheovermanned in theon theperiods with the intention of completing it late, and hence However, the effective level of labour was reduced by 7.5 any delays can of the site  Overmanningbe compensated for in future periods. men due to delays. This resulted in the job being 97.9% complete at the end of period 9, and not quite completing. However, it is essential to consider potential delays in Manager in which the into expected to There is also another key factor that the Constructionthe periodneeds to takejob isaccount, and that is complete, in order to ensure that the job does finish. The delays to the job caused by risk events becoming a reality. Construction Manager did not take into account the affect of possible delays when setting the labour level, so We will look into how the Construction Manager can mitigatecould the labour level have been of job delays how against the consequences adjusted to mitigate against the delays ? caused by risk. The Industry Information reveals that a major job delay could At the start the Construction Manager is able to see :- For job 128 of period 9 only one risk had struck on the job, „personnel issues‟ during period 8. This left 2 reduce the effective labour on site by between 14 and 15%. potential risks that could strike during period stage (risk register)  The risks identified during the procurement 9 :- For job 128, 51 men were originally allocated to site. Assuming the  The affects of the risks striking, a major joblikelihood, impact costs and job delays „Hurricans‟, which would cause in terms of delay worst possible case, a 15% reduction in the effectiveness of the  Any contingencies built into the bid cause a major job delay impact cost „Accident on site‟ which would also to cover the likelihood and labour, 60 men should have been allocated, and the job delay would not have prevented the job from completing during period 9. If a number of risks could strike the delay to the struck. This knowledge is the i.e., it deciding how And, most importantly, whether or not the risks have job is the worst case possiblekey to is assumed that the other delays occur within the timeframe of the worst the risks have no additional affect. to adjust labour levels to guard against job delays caused by case, and occurring. ---------------------------------------------------------------------------------------- Key Point(s) How does the Construction Manager change the labour level to ensure that a major delay does not If the risk does not strike, the additional labour is ineffective, and prevent the job from completing during period 9 ? would generate additional labour costs if the job completes before the end of the period, as the labour is retained on site until the end of the period. However, this is less costly than the job not completing, especially if it overruns and penalty clauses are imposed by the client. Keep Clicking Anywhere on the screen to advance Quit
  • 55. New Recruits v Subcontract Labour Glossary Clearly the decision as to whether to employRecruits:to useorCostssubcontractors is complex, and New Recruits Key Point(s) New new recruits New Hidden use In progressing jobs it Subcontractors cost-effectiveRecruits:the company‟s own fully trained operatives is always more New Recruits: Site CostTraining Cost than using subcontractors. costs, including :- though therecruitto whetherbe own labouralso aone. farofon site, site involves many factors Subcontractors a notAs well as newtrainingand areto costs, therenew force or withhidden costs Determining an overall labour shortfall indonew need toAbe trained,recruitsitefully trained inare recruitseffective moreCompany, Where there is the cost of employing the period, the decision as company‟s effective from is notperiod and recruit the new needs being trained, and day number the Even into the and is to employ their first is complicated than further complicated by a subcontractor,quantifythere is an associated be they cost. they are use subcontractors is the calculation for the costs are the numberpaidnew recruits that can job takenjoballocated to. that still and to and varies depending upon the limit on hard as abe of :- cover them on the training are need to result to allocated to. the Subcontractors :- numberIndustry do incur anthat can be employed period.shown in the Industry Information. However, they Information. The limitsubcontract premium, on in a period, as defined in the  The limit on of new recruits additional can vary each The training man period in the from job to job, but tend to be cheaper in Site costs pertime could extend the planned contract time resulting in penalty Using information vary Industry Information the training cost per  Cost time it takes tolabour new recruits, andiscost recruit this couldeach subcontractor used.Transport Sector.  The more closer looktrain costs involves. that are more calculated offset bysuch as the than own In this example the premium new involved. for be as follows :- sectors 1,200 per period charges, although is labour intensive, allocating labour levels above the We‟ll take a at the  Reliance on subcontractors can paid whilst morale arethe company‟s own labour need to be affect the example training:- trained. planned ones. of being  The site costs that ------------------------------------------------------------------------------------------------------------------------------ In the people shown time is 2 weeks The Eventually own labour may need to be paid off when work dries up, / 52) The  The additional cost Keyemploying subcontractors. training cost per week is 577 (training cost per annum incurring of Point(s)  The is The per regardless cost The upon off of they are used. The subcontractor premiumsitethe labourman periodon 10,806laying whichown labour may then impact additional same payoff charges. isjob cost overall training is the 1,154 (2 x 577) However, if there is an overall a contract.on labour relations, affecting the morale and productivity of the workforce  The anticipated duration of labour shortfall thatweek is 831 (10,806/13)  The cost per the Construction Manager needs to address, two options many periods :-  How are available subcontractors need to be employed for.  For the 2 weeks training for a new recruit, the cost is 1,662 across the company. ---------------------------------------------------------------------------------------------- Key Point(s)  Take-on newof using subcontractors company‟s own of the company‟s own labour, which upon which the new  The affect recruits, adding to the on the morale labour is the same regardless of the job is covered in The training cost  Use subcontractors another demo. recruit is used. But which it is worthnow the most cost determine the most cost-effective approach, which is often job However, option is taking the time to effective ? dependant, as this can affect the profitability of a contract. To answer this question we need to compare the costs involved in taking on one new recruit against one subcontractor. In general, in the short-term the choice can vary, but in the long-term the continued use of The new recruits limit is shown in subcontractors will almost certainly prove more costlyInformation. on and training new staff, since the the Industry than taking subcontract premium has to be paid every period. Keep Clicking Anywhere on the screen to advance Quit
  • 56. Labour Relations Glossary The most cost-effective wayExample force affect of the company‟s construction management decisions on labour In any period a company‟s total labour 2:The consists force is to use the company‟s own fully trained of Example the good labour relationsaction managing 1: labour of relations in in action poor labour :- labour, rather than subcontractors. relations is reflected in comments in the Management Consultants Report. For example, if 50 men are transferred to the idle labour pool from job A, then they are immediately Labour on used on job B. No training isidle labour no men are laid off, and the company does not incurof the additional Labour required, 85 men were available in the in Jobs in All any men in the pool. All 85 were laidthe when they could off Idle Pool Total Labour costs such as subcontractor premiums. Progress in Companyidle labour pool were have been utilised on jobs. used on site. (Own) In this scenario the company would be perceivedin the idle labour labour relations policy, and the morale of 21 men were available to have a good (Own + Sub) the company‟s own labour would beand none were laidgreater productivity. pool, high, ensuring off. 10 men were laid off from site, 201 subcontractors were used. when they could have been The least cost-effective way of managing the labour force is to be constantly hiring and laying off the To source the jobs in progress with the labour required the Construction Manager will often be faced utilised on other jobs. company‟s own overall labour shortfall,on subcontractors. situation a number of decisions have to be with either an labour, and also relying or a surplus. In this made on how besthigh proportion of the company‟s own labour is laid off in a period, then the morale of For example, if a to manipulate the labour force. Additional labour was the company‟s the remaining own labour (not subcontractors) would be weakened, leading to reduced productivity. In The options available include and not subcontractors relations policy. own, :- this case the Company would have a poor labour For the Company‟s Own Labour  Laying men off from the Idle Labour Pool (ILP) illustrate good and bad labour relations. We’ll now look at more detailed examples that  Transferring men from the ILP to jobs, or from jobs to the ILP Taking on new recruits onto jobs or laying off labour from jobs The Construction Manager was able to manipulate the labour force so that :- For Subcontract Labour not manipulate the labour force effectively, and :- The Construction Manager did None of the company‟s own  Taking on or releasing subcontractors All idle labour was redeployed to site labour was laid off from site. Used 201 subcontracts when men were availablenot the idle pool, but were paid off Additional labour was the company‟s own, and in subcontractors Laid off of the company‟s own labour was could have been used instead of subcontractors None 10 men from site, some of whom laid off No subcontractors No subcontractors were used were used. Keep Clicking Anywhere on the screen to advance This is an example of poor labour relations, and the productivity of the company‟s own labour would bean example of good labour relations, and the productivity of the This is adversely affected. company‟s own labour would be improved. Quit
  • 57. Forming Client Relationships Glossary Each periodcan influence their relationship with a in the market. following example. marketing effort will determine The company a number of jobs are available client in a numberThe company‟s Consider the of ways :- how many of the jobs the company identify (prequalify for). Positively by :- Its period 9, and the company have prequalified for a job with East Midlands County Council. Each job has a client, in either the public or private sector, for whom the work is to be carried out. Submitting competitive bids Procurement Managing jobs well, and completing them at least on schedule company prequalifies, tenders for and secures work with the client As the The Client History provides a detailed As time passes, and depending upon economic a relationship is built company‟s current parties. analysis of the up between the two Negatively byclients may look to preferred bidders, conditions, :- relationship with each client. Submitting uncompetitive (poor)not strong enough and if the client relationship is bids The current state of the relationship can be analysed using the Managing the jobs poorly,accept the bid. late the client may refuse to and completing Display Client Details option. In this example, the company currently have a good relationship with East Midlands County Council based upon :- Prequalifying for a number of jobs with the client Securing job 42 with a competitive bid, finishing it early and managing it very well Putting competitive bids together for jobs 125, 163 and 190, even though they were not secured Performance Indicators But why is the client relationship so relationships with ALL clients forms one of the key performance indicators The company‟s important ? upon which the progress of the company is measured. Prequalification The company may not be able to prequalify for work with a client if the relationship has deteriorated. Keep Clicking Anywhere on the screen to advance Quit
  • 58. Performance Indicator Definitions Glossary Turnover • Measured value accrued across all jobs progressed; an indication of how much work the company has done. Gross Profit to Turnover • The ratio of gross profit to turnover across all jobs progressed; a measure of how profitable the company‟s jobs have been. Operating Profit to Turnover • The ratio of operating profit to turnover; a measure of how profitable the company is after considering all operating factors. Company Value • A measure of the asset value of the company. Capital Employed • Measures how much of the company‟s capital base is being utilised. Contract Completion • A measure of the number of jobs completed early, on time or late. Forward Workload • The remaining turnover (value) of jobs still in progress. Forward Margin • The remaining profit of jobs still in progress. Share Price • A measure of the strength of the company‟s share price. Client Satisfaction • An indication of how happy the company‟s clients are; based on procurement and job progression.
  • 59. Calculating Performance Indicators Glossary Client Relationship To gain a feel for the relationship with each client, a textual description is given. The description is based upon a numerical The Company is now in period 9, but how were the performance value (hidden) determined by a number of factors, including prequalification, procurement and job progression. indicator weightings calculated at the end of periodShare Price 8? Contract Completion The sum of the numerical values across all clients is calculated for the relationship changes since the History, Periods) The Financial Analysis (Performance Alland then Byadded to the performance indicator weightingJob Analysisthe History. examining the Performance Statistics and at the end of we first determine thethe share price :- shows Turnover Value Company number and Capital Employed Forward Margin Workload Forward size of jobs completed since the History. The Financial Analysis (Performance All Periods) shows :- company value :- the In this example the numerical valueProfit tothe forwardratio to(Performance All Periods) theas athemargin70workloadof Gross The Turnover ratio  At the end After bids have been processed,to Turnovercame 139.the Periods) showsof shows ratingthe1.35 give an Operating during periods 5-8Analysis of All company expressed Historyof of upper limit :- The Financial Analysis (Performance Periods) shows :- the forward forward to Profit Financial workload This was added to the initial % was :- Each completed job is that canThe undertaken, based (Performance Periods)  At the:-end of period 8 was 1.95 209 at the end of be Financial Analysis upon the company‟s capital base, is the capital employed. indicator ofworkload given a score depending upon :- All The period at the end of(Performance All 4,685,339 13,976,699 8. Financial Analysis the History was 1-4) was shows  The Historical turnover (periods  or Late  Whether the job completed Early, On TimeAt the end of the History was 29,984,240  AtThe turnover to date 8was 5,821,887 The Historicalofthe end of period 1,321,072 been1-4) was 0.0438 (612,635 / 13,976,699) the the endthe period turnover 1-8) has at end grossHistory(periods ratio (periods 76,268,479 of profit/ was  The job size Historicaloperating Periods) shows the average 1-4) at employed :- At The Financial Analysis the end of period 8 was 1,409,8288 was 30,171,560capital the end of period 8 13,976,699) The  At(Performance Allprofit/ turnover ratio (periodsvalue was 0.0151 (211,533 /was 1.44 times the The The gross profit/turnover ratio to date (periods 1-8) has been 0.0532 (4,060,639 / 76,268,479) The operating profit/turnover ratio to datedate1.2421-8)Historical benchmark, which is 76,268,479) value at the end of the History. To compare fairlyend of period to was with the has been 0.0274 (2,089,389 /History. upon The value at the the turnover 8 (periods times the value at the end of the based e.g., large jobsFor the Historyearly are given the 41%at the /end 8 was 1.07 was 1.006 times the value of the History.the History.  that complete (periods 1-4)at the best (164 (+ve),period 8 times the value at the end at the end of The value of period of whereas large jobs value was of score 4) Theone the we endperiod 8 was the average per 0.0438) times the value at The ratio year, endneed to work out1.2146 (0.0532 / year, which is 38,134,240 (76,268,479 / 2). completing lateTo date (periods ratio hasat(-ve). of period 8 /was 1.8146 (0.0274 / 0.0151) times wasvalue at thethe endthethe theof  are given the worst scorebeen 66.5% (532 reflected in an increase in the company value performance indicator The 1-8) The improvement was 8) at the end The improvement the reflected in end of an increase in History. Thefrom 140, improvement was reflected in sharethe forward margin indicator13,976,699) initial improvement was weighting, an period anxincrease in the forward workload performance The History. The yearlythe initialreflected in to 174 (140 wasprice performance performance 70, thethe average by the end of increase in1.242). times (38,134,240 / 8 2.728 from The total calculated is added to the initial indicator 1.62 timesat the end at theweighting,(70 101 (70 x 1.44). The value at the end of valuefrom 100,fromthe History. weighting, to 70toto x 1.006). / 41). indicator indicatorweighting the initial of the end of the History (66.5 70, period 8the end of initial the value History at was the This deterioration is reflected inweighting, to 107 (100 x 1.07). give the current indicator value. deterioration is reflected in a fall fallthethe gross profit to turnover performance indicator from This a in in operating profit to turnover performance indicator from 100, the initial weighting, to 121 (100 x 1.2146). This improvement is reflected in an increasereflected 1.8146). 130, the initial improvement is in(130capital employed in the turnover performance 140, the initial 50, This weighting, to 235 the x in an increase performance indicator from indicator from In this example the 9 completed jobs created a score of 80, which when added to weightings used in calculating the client weighting, to 227 (140 x 1.62). weighting, to 136 (50 x 2.728). The the the initial starting point of 130, gives an indicator value of 210 at the end of period 8. satisfaction values are hidden, but the relative affects, from largest to smallest are :- Notes Keep Clicking Anywhere on the screen to advance Irrespective of size, jobs that are complete late incur a bigger penalty than theJob Progression  gain from jobs completing early.  Procurement  Prequalification Quit
  • 60. The Use of Performance Statistics Glossary We‟ll look at how performance statistics can help to explain whether or and weaknesses in indicators. now first at how performance statistics can help to explain changes incompany strategy has been identify strengths not performance company The Procurement Analysis for the early years shows that out of 36 jobs bid for, 27 were lost. successful. performance. 85% of the jobs were lost de to “workload limitations”. This could possibly have been avoided if the Financial Manager had increased the company‟s capital base more during periods 5 to 8 in order to enable the company to take on more work. Using the performance statistics in this way will enable more effective decisions relating to the capital base to be made in future periods. Consider the performance indicators of the company after 8 periods. Since the end of the History the Gross Profit to Turnover indicator has increased. This would appear to indicate that jobs have been managed slightly better sincethat provide :- During the Early Years the company have tried to invest in other concerns the History.  A our reasoning, we can look To verifybetter return than the bank at the performance statistics for both the History and the Early Years.  Reduce overall build costs in jobs in progress e.g., by obtaining better discounts from suppliers Has the strategy paid off ? Evidence from the performance statistics shows that :- The performance statistics provide evidence that it has, with overall jobs costs being reduced by During the History the average job profit was 4.6% (of cost) 0.77%. During the Early Years, up to the end of period 8, the average job profit was 5.9% (of cost) This is clear proof that job profitability has improved since the History. The Job Analysis information can be used to analyse even further where the improvement was. ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Key Point(s) Keep Clicking Anywhere on the screen to advance The performance statistics cover the early years and the history separately, but many of the performance indicators cover the full lifecycle of the company. These are specifically the trend-based ones such as turnover, gross profit to turnover etc. Quit
  • 61. Job Details Glossary Job number Type A unique number that There are two types of job :- identifies a job, ranging from  BO (Build Only); traditional type of job where the client 1 (earliest jobs) onwards. is responsible for the design, if appropriate, and the contractor is only responsible for the build.  DB (Design and Build); the contractor has Period of prequalification responsibility for both the design and the build. The period in which the company identified the job Size through marketing effort. The size is based upon the approximate value :-  Small (approx value range 1m - 6m)  Medium (approx value range 7m - 13m) Country/Location  Large (approx value range 14m - 25m) Where the job is located. Approximate value The anticipated cost of the job rounded to the nearest million. Duration The planned duration of the job, between 2 and 5 periods. Description A brief description of what the job entails. Total labour manning The total number of man periods Client required to complete the job. The public or private-sector Sector organisation for whom the job Each job falls into one of 5 market sectors :- is being carried out.  Industrial  Building and Commercial  Transport  Energy  Water and Sewage
  • 62. Measured Value (Turnover) Glossary Each period, three values are calculated for a job :- For each job awarded to the company, there is a planned value per man period defined as :-  The Expected value is the labour on site that contributes to progressing the job (effective labour) multiplied by Value Per Man Period = Planned the planned value per man period. Bid Value / Total Labour (periods)  The Actual value is the expected value adjusted to take into account a number of factors that affect productivity on the job :-  The performance of the project manager allocated to the job  The labour relations policy of the company  The Measured Value (Turnover) is the actual value adjusted by the measurement effort of the company for the period. In the example shown: Planned value per man period = Bid value / Total labour (periods) The measurement effort depends upon how well the company‟s measurement staff are able to cope with the turnover in the period across all jobs. The last period of the history provides the /benchmark for = 8,627,856 126 determining the appropriate level of staff required. = 68,475 ------------------------------------------------------------------------------------------ Key Point(s) The build and site cost ratios per man periods are calculated in similar ways, using the total labour (periods) as the denominator, with the appropriate estimated cost as the numerator. Keep Clicking Anywhere on the screen to advance Quit
  • 63. Job Costs Glossary Design Fee Applicable to design & build jobs only, the design consultant charges a fee payable over the planned duration of the job. Build Cost Build costs cover all the direct costs (labour, plant, material etc) needed to complete a job. The build costs incurred each period depend upon the effective level of labour allocated to the site. Site Cost Site costs pay for the support staff and services required to administer a site whilst the build is taking place. The level of site cost paid each period is based upon the total labour (own and subcontract) allocated to the site. Completion Penalty If the duration of a job exceeds its planned duration, the company is charged a penalty for each late period. The penalty is a percentage of the tender value (bid entered) for the job; details are given in the Industry Information.
  • 64. Labour Costs Glossary The labour costs are allocated to either job or overhead costs. The applicable rates are shown in the Industry Information. Training cost (job cost) A new recruit needs to be trained in Labour cost their first period with the company, The cost of a general labourer used and as a result there is an on site; used as the basis for associated training time and cost. calculating ineffective labour. Labour payoff rate (job/overhead cost) This is the cost per person of laying off the Company‟s own labour from either :- The idle labour pool (overhead cost) A job in progress (job cost) Annual cost of idle labour (overhead cost) This is the cost of keeping someone idle for a year, and takes into account the redeployment of Subcontract premium (job cost) the person in other areas. Subcontractors are 100% productive as soon as they are taken on, and require no training. However, using them incurs an additional cost above the normal labour cost.
  • 65. Bonus For Early Completion Glossary The client pays a bonus for early completion of a job. Early completion of a job means completing at least one period before the end of the planned duration e.g., if the planned duration is 4 periods, it must be completed in 3 periods or less to obtain the client bonus. The bonus varies depending upon the size of the job, and is expressed as a percentage of the tender value (bid entered) for the job; details are given in the Industry Information. The bonus is shown in the Job Details for the last period of the job. The early completion bonus varies according to the size of the job.
  • 66. Retention Glossary Retention is a held came from a number of jobs progressedachieved on 7. job in a period that is retained by the The retention % of the measured value (turnover) during period a client until the job is completed. Retention affects the cashflow of the company. The Retention Analysis for jobs won and The Industry Information showed retention to be 1% of measured value i.e., Financial Analysis shows that in period 7 In the example shown, the progressed provides comprehensive information If 1% ofjob is not completed to a satisfactory the company‟s retention figures wereheld and repaid, alongsome of the 15,429,190, or 154,292. level determined by the construction contract, with the about all retentions :- the retention may not be repaid. outstanding net retention to be repaid.  208,422 repaid from completed jobs Any retentions held are repaid in two equal instalments :- from work completed from jobs progress during the  154,292 held period  In the period when the job is completed The net retention of 54,130 helped the cashflow.  2 periods after the job completes Details of the % retained are shown in the Industry Information. Keep Clicking Anywhere on the screen to advance Quit
  • 67. Percentage Of A Job Completed Glossary The % of a job completed on the Job Details does not always equate to the measured value recovered on a job in relation to the original bid value. with a bid of 11,540,390 A job was won We will take a closer look at this anomaly. The job has just completed its 1st period, and the total value to date is 4,450,044. This equates to 38.6% of the bid i.e., (4,450,044 / 11,540,390) * 100 However, the % complete shown is lower at 38.3%, so why is there a difference ? The % complete is derived from the actual amount of the job completed to date. However, the company‟s measurement effort has secured an extra 0.3% of value over the 1st period, which is incorporated in the total value. Keep Clicking Anywhere on the screen to advance Quit
  • 68. Forward Workload And Margin Glossary The forward workload (or potential turnover) on a job is forward workload and margin values at the end of period 8 The the remaining value to be recovered from the present time until the job has forward workload and margin values determining the amount of progress. the company The been completed. When were formed from are shown in the Financial 6 jobs in Analysis. work that cannot undertake based upon the size of the capital base, the forward workload at the end of the previous period is the The forward margin is the Taking job 172 remaining profitstarting point shown, at the end of period 8 the company‟s :- anticipated as an example :- In the example for any calculations. on a job.  49.8% of the job was left to complete at the end of period 8, giving a remaining forward  Forward Workload was 30,171,560 Both are calculated at the end of a of 2,464,075 (49.8%the company‟s decisions have been processed. to the workload period, after all ofForwardvalue any bids won during period 9 are added The value of of 4,947,942)‟  the bid Margin was 1,409,828  The forward margin figure comes initial the forward workload less the remaining cost. used to from forward workload, and the cumulative figure is determine how much work the company can undertake. The ? Can be used to drill-down to job-level detail. ----------------------------------------------------------------------------------------------------------------------------- Forward workload and margin are important because :- Key Point  They are two of the key The remaining cost is based upon the anticipated true costprogress taking into account performance indicators upon which a company‟s of the job, is measured. build cost, design cost , site cost and project manager costs. In the case of design costs the quality of the design produced by the chosen design consultant  The forward workload providesinto Forward workloadaffectmargin form 2 of theprocess for determining whether is taken the starting pointand on the build costs. key performance indicators. account, and the during the bidding or not the client will allow the company to bid for a job based upon capital base limitations. Both indicators increased during period 8, which can be further verified by We will take a closer look at how both are calculated, andAnalysis (Performance All Periods). referring to the Financial used. The forward workload and margin values at the end of period 8 were considerably higher than at the end of period 7, and this rise was reflected in the increased in the KPI weightings. Keep Clicking Anywhere on the screen to advance The for ward workload at the end of period 8 is shown in the Financial Analysis. Quit