Better Estimates
Jane Prusakova
@jprusakova
2Viasat Proprietary
Every developer and every line manager everywhere
3Viasat Proprietary
›More accurate
›More confident
›Less effort to deliver
Defining better
4Viasat Proprietary
› Estimates happen early in the project life cycle
– Little is known about the project – including scope, requirements, technical details and
resources.
– With software development every project is different. Often there is little experience in the
domain, technology and resource management.
– Anticipated work and risk gets estimated. Unanticipated work is typically left out from the
estimating effort.
Facts about estimates
5Viasat Proprietary
Put more effort into learning
the scope, requirements,
technical details and
resources.
What we do
Little is known about the
project – including scope,
requirements, technical
details and resources
Increase time and effort for creating estimates.
6Viasat Proprietary
Gain experience in the
domain, technology and
resource management. Seek
help from experts.
What we do
Every project is different.
Often there is little experience
in the domain, technology and
resource management
Time and effort that may go more directly toward getting the project done. Pushes
out estimate delivery timeline, but also improves accuracy.
7Viasat Proprietary
Put more effort into
discovering the work needed
for the project.
What we do
Anticipated work and risk
gets estimated. Unanticipated
work is typically left out from
the estimating effort.
Takes time and effort, produces valuable knowledge.
Results are hard to convert to a date or time line.
8Viasat Proprietary
Software projects report 1994 - 2004
• 16% … 29%
Successful
• 53% … 53%
Challenged
• 31% …18%
Aborted
9Viasat Proprietary
Software projects report 1994 - 2004
• 16% … 29%
Successful
• 53% … 53%
Challenged
• 31% …18%
Aborted
›Success is defined as “delivered as
estimated”
›Anything less than successful can be due
to poor execution – or bad estimate
10Viasat Proprietary
› Sydney Opera house was estimated to take 6 years and
$7mln to build. It was completed after 16 years and
$102mln.
› Denver International Airport was estimated to take
– 4 years and $2.6bln.
– It started operating after 5.5years, having spent $4.8bln, with
reduced scope. Baggage handling was never implemented
as originally designed.
› Home Redecorating/Remodeling for kitchens and
bathrooms
– Redecorating projects were over budget 35% of the time
– Remodeling projects were over budget 53% of the time
What others do
11Viasat Proprietary
› Past effort is consistently underestimated
› Future effort is estimated optimistically
– Consistently
– Despite having good information about past performance of same tasks
– Estimating larger efforts with deadline farther out in the future exacerbates the effect of too-optimistic predictions
› Work by others is estimated more realistically
– Applies to both past effort and future work
Studies looked at filing taxes, completing a college thesis, writing a book.
Behavioral science: planning fallacy
12Viasat Proprietary
Random events are skewed to introduce additional cost and delay
Not evenly balanced between positive and negative results
Larger efforts take longer to react to unexpected events
Increasing the cost of delay as unexpected events arise
Consequences of disruption are non-linear, i.e. small delays compound into larger schedule slips over life of larger
projects
Error effect in estimates: more on planning fallacy
13Viasat Proprietary
› Estimate other people’s work and let others estimate yours
– to avoid optimistic bias
› Consider past estimates, use logged time for work already done, and calculate actual
effort involved
– Keep records of on-going work. Consult those records when working on future estimates
– Calculate appropriate multipliers and apply to future estimates
› Learn to live with low-confidence estimates on larger efforts
– Improve ROI by limiting time & effort spent on early estimates
› Focus estimation effort on smaller and more familiar projects for higher-confidence
estimates
What can we learn from science and history?
14Viasat Proprietary
The Mythical Man-Month: Essays on Software Engineering
by Frederick Phillips Brooks
Originally published in 1975
Later editions come with additional essays
15Viasat Proprietary
`
16Viasat Proprietary
Programmers are optimists
› In the upper left of Fig. 1.1 is a program.
› It is complete in itself, ready to be run by the
author on the system on which it was
developed. That is the thing commonly
produced in garages, and that is the object
the individual programmer uses in
estimating productivity.
› In the bottom left is a programming product.
› This is a program that can be run, tested,
repaired, and extended by anybody. It is
usable in many operating environments, for
many sets of data. It must be written in a
generalized fashion. Must be thoroughly
tested, so that it can be depended upon.
Finally, it requires its thorough documentation,
so that anyone may use it, fix it, and extend it.
A
17Viasat Proprietary
Programmers are optimists (contd.)
› Top right: programming system component
› every input and output conforms in syntax and
semantics with precisely defined interfaces.
The program must also be designed so that it
uses only a prescribed budget of resources.
Finally, the program must be tested with other
system components, in all expected
combinations. This testing must be extensive,
for the number of cases grows
combinatorially. Subtle bugs arise from
unexpected interactions of debugged
components.
› Bottom right: programming system product
› Many components working together. Cost
may rise further with more components,
tighter dependencies, and moving
dependencies.
18Viasat Proprietary
›Estimates inform business decisions
– Is this project feasible?
– How long until we realize any benefit, a sizeable benefit, all the expected benefit from
success?
– What will we have to give up in order to make this project happen?
– What is worth giving up for this project?
– What do we lose in case of failure? What do we lose in case of time overruns?
Better estimates: purpose
19Viasat Proprietary
› There is typically a need for projected delivery dates in order to coordinate with other teams working in
the same problem space
› There is also a need to allocate resources over time based on expected progress of the project
› In addition, estimate is often used as a measuring stick for project success (i.e. CHAOS reporting
metrics)
› The goal of estimates that get created should be to satisfy a tangible business need.
Can we live with no estimates?
20Viasat Proprietary
› Estimate often
› Record actual spent
– Calendar time
– Effort
› Work from past history when creating future estimates
– Check your optimism
› Communicate learning
– Share more than the # of hours estimated
Better approach to estimating
Better Estimates
Jane Prusakova
@jprusakova
22Viasat Proprietary
› Estimating is discovering and sharing useful information about a body of work
– Usually focused on work not done
– Occasionally about work that has been done, but no records are available
› Estimates are assumed to be a fictional number of man-hours
Estimating != estimates

More Related Content

PPTX
Room to Breathe: The BA's role in project estimation
PDF
Improving Focus and Predictability on Projects with Critical Chain Project Ma...
PPTX
Risk management
PDF
My pitch
PDF
Measurement magic in world of DevOps
PPTX
Agile Technology Delivery Process Mr
PDF
Twelve Risks to Enterprise Software Projects—And What to Do about Them
PDF
Relationship Business-Projects-Operations
Room to Breathe: The BA's role in project estimation
Improving Focus and Predictability on Projects with Critical Chain Project Ma...
Risk management
My pitch
Measurement magic in world of DevOps
Agile Technology Delivery Process Mr
Twelve Risks to Enterprise Software Projects—And What to Do about Them
Relationship Business-Projects-Operations

What's hot (19)

PPTX
10 tips to create accurate project estimates
PPT
Deadly Sins Estimation
PDF
Critical chain-concepts
PDF
Why projects are causing your organisation staff salary costs to go up
PPTX
File 1 four extra slides 2
PPT
Learning_Unit_1
PDF
Twelve Risks to Enterprise Software Projects-And What to Do About Them
PPTX
Project presentation - Filing Cabinet Project
PPTX
Project Management Powerpoint
PPTX
Critical chain and buffer management
PDF
Being prepared for the Unexpected
PDF
4 ways to manage your it budget it-toolkits
DOCX
Comparing projects hoover and shape cutting (1)
PPT
Agile estimates - Insights about the basic
KEY
Project Estimation:Survival Guide
PPT
Project Planning
PDF
2009 Resource Planning Summit Presentation Charles Howell
PDF
Why Is Managing Software So Hard?
PPTX
Epic Estimation - Agile or High Risk Guesswork
10 tips to create accurate project estimates
Deadly Sins Estimation
Critical chain-concepts
Why projects are causing your organisation staff salary costs to go up
File 1 four extra slides 2
Learning_Unit_1
Twelve Risks to Enterprise Software Projects-And What to Do About Them
Project presentation - Filing Cabinet Project
Project Management Powerpoint
Critical chain and buffer management
Being prepared for the Unexpected
4 ways to manage your it budget it-toolkits
Comparing projects hoover and shape cutting (1)
Agile estimates - Insights about the basic
Project Estimation:Survival Guide
Project Planning
2009 Resource Planning Summit Presentation Charles Howell
Why Is Managing Software So Hard?
Epic Estimation - Agile or High Risk Guesswork
Ad

Similar to Estimating software development (20)

PPTX
Mythbusting Software Estimation - By Tood Little
PDF
Agile Network India | Meetup | Software estimation for developers | Sachin Di...
PPTX
Estimation Protips - NCDevCon 2014
PDF
Software/Application Development Estimation
PDF
Drupalcon la estimation john_nollin
PPTX
Estimation - web software development estimation DrupalCon and DrupalCamp pre...
PDF
Software Estimation
PPTX
2015 drupalcampcebu estimation_jrf
PDF
Estimates or #NoEstimates by Enes Pelko
PPTX
#NoEstimates - Stop lying to yourself and your customers, and stop estimating
PDF
Estimations
PDF
Dark Art of Software Estimation 360iDev2014
PDF
To Estimate or Not to Estimate, Is that the Question? (2017 Better Software C...
PDF
Maximising Capital Investments - is guesswork eroding your bottomline?
PDF
The Power of #No
PDF
#NoEstimates
PPTX
Software estimation is crap
PPTX
Estimations: hit the target. Tips & Technics
PDF
Who and why uses estimates
PPTX
When Will This Be Done?
Mythbusting Software Estimation - By Tood Little
Agile Network India | Meetup | Software estimation for developers | Sachin Di...
Estimation Protips - NCDevCon 2014
Software/Application Development Estimation
Drupalcon la estimation john_nollin
Estimation - web software development estimation DrupalCon and DrupalCamp pre...
Software Estimation
2015 drupalcampcebu estimation_jrf
Estimates or #NoEstimates by Enes Pelko
#NoEstimates - Stop lying to yourself and your customers, and stop estimating
Estimations
Dark Art of Software Estimation 360iDev2014
To Estimate or Not to Estimate, Is that the Question? (2017 Better Software C...
Maximising Capital Investments - is guesswork eroding your bottomline?
The Power of #No
#NoEstimates
Software estimation is crap
Estimations: hit the target. Tips & Technics
Who and why uses estimates
When Will This Be Done?
Ad

More from Jane Prusakova (20)

PPTX
Software architecture houstontechfest2020
PPTX
Better remote teams
PPTX
Thoughts on building software architecture
PPTX
Improving IT Performance
PPTX
Agile Software Development
PPTX
Questions of Ethics in Software Development
PPTX
Just startcoding
PPTX
Just start coding
PPTX
Good code
PPTX
Managing remote teams.
PPTX
Gender-neutral Recruiting
PPTX
Privacy In The Digital Age
PPTX
Interview: a Learning Conversation
PPTX
Effective Code Review
PPTX
Effective Code Review
PPTX
Lets talk about good code
PPTX
Motivating Knowledge Workers
PPTX
What is good code?
PPTX
Pragmatic Agile: distributed teams
PPTX
A case for remote teams
Software architecture houstontechfest2020
Better remote teams
Thoughts on building software architecture
Improving IT Performance
Agile Software Development
Questions of Ethics in Software Development
Just startcoding
Just start coding
Good code
Managing remote teams.
Gender-neutral Recruiting
Privacy In The Digital Age
Interview: a Learning Conversation
Effective Code Review
Effective Code Review
Lets talk about good code
Motivating Knowledge Workers
What is good code?
Pragmatic Agile: distributed teams
A case for remote teams

Recently uploaded (20)

PPTX
additive manufacturing of ss316l using mig welding
PDF
PPT on Performance Review to get promotions
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
Welding lecture in detail for understanding
PPTX
Lecture Notes Electrical Wiring System Components
DOCX
573137875-Attendance-Management-System-original
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
Structs to JSON How Go Powers REST APIs.pdf
PPTX
Sustainable Sites - Green Building Construction
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
Well-logging-methods_new................
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
Digital Logic Computer Design lecture notes
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
additive manufacturing of ss316l using mig welding
PPT on Performance Review to get promotions
Operating System & Kernel Study Guide-1 - converted.pdf
Welding lecture in detail for understanding
Lecture Notes Electrical Wiring System Components
573137875-Attendance-Management-System-original
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Structs to JSON How Go Powers REST APIs.pdf
Sustainable Sites - Green Building Construction
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
CYBER-CRIMES AND SECURITY A guide to understanding
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Well-logging-methods_new................
Lesson 3_Tessellation.pptx finite Mathematics
UNIT 4 Total Quality Management .pptx
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Digital Logic Computer Design lecture notes
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd

Estimating software development

  • 2. 2Viasat Proprietary Every developer and every line manager everywhere
  • 3. 3Viasat Proprietary ›More accurate ›More confident ›Less effort to deliver Defining better
  • 4. 4Viasat Proprietary › Estimates happen early in the project life cycle – Little is known about the project – including scope, requirements, technical details and resources. – With software development every project is different. Often there is little experience in the domain, technology and resource management. – Anticipated work and risk gets estimated. Unanticipated work is typically left out from the estimating effort. Facts about estimates
  • 5. 5Viasat Proprietary Put more effort into learning the scope, requirements, technical details and resources. What we do Little is known about the project – including scope, requirements, technical details and resources Increase time and effort for creating estimates.
  • 6. 6Viasat Proprietary Gain experience in the domain, technology and resource management. Seek help from experts. What we do Every project is different. Often there is little experience in the domain, technology and resource management Time and effort that may go more directly toward getting the project done. Pushes out estimate delivery timeline, but also improves accuracy.
  • 7. 7Viasat Proprietary Put more effort into discovering the work needed for the project. What we do Anticipated work and risk gets estimated. Unanticipated work is typically left out from the estimating effort. Takes time and effort, produces valuable knowledge. Results are hard to convert to a date or time line.
  • 8. 8Viasat Proprietary Software projects report 1994 - 2004 • 16% … 29% Successful • 53% … 53% Challenged • 31% …18% Aborted
  • 9. 9Viasat Proprietary Software projects report 1994 - 2004 • 16% … 29% Successful • 53% … 53% Challenged • 31% …18% Aborted ›Success is defined as “delivered as estimated” ›Anything less than successful can be due to poor execution – or bad estimate
  • 10. 10Viasat Proprietary › Sydney Opera house was estimated to take 6 years and $7mln to build. It was completed after 16 years and $102mln. › Denver International Airport was estimated to take – 4 years and $2.6bln. – It started operating after 5.5years, having spent $4.8bln, with reduced scope. Baggage handling was never implemented as originally designed. › Home Redecorating/Remodeling for kitchens and bathrooms – Redecorating projects were over budget 35% of the time – Remodeling projects were over budget 53% of the time What others do
  • 11. 11Viasat Proprietary › Past effort is consistently underestimated › Future effort is estimated optimistically – Consistently – Despite having good information about past performance of same tasks – Estimating larger efforts with deadline farther out in the future exacerbates the effect of too-optimistic predictions › Work by others is estimated more realistically – Applies to both past effort and future work Studies looked at filing taxes, completing a college thesis, writing a book. Behavioral science: planning fallacy
  • 12. 12Viasat Proprietary Random events are skewed to introduce additional cost and delay Not evenly balanced between positive and negative results Larger efforts take longer to react to unexpected events Increasing the cost of delay as unexpected events arise Consequences of disruption are non-linear, i.e. small delays compound into larger schedule slips over life of larger projects Error effect in estimates: more on planning fallacy
  • 13. 13Viasat Proprietary › Estimate other people’s work and let others estimate yours – to avoid optimistic bias › Consider past estimates, use logged time for work already done, and calculate actual effort involved – Keep records of on-going work. Consult those records when working on future estimates – Calculate appropriate multipliers and apply to future estimates › Learn to live with low-confidence estimates on larger efforts – Improve ROI by limiting time & effort spent on early estimates › Focus estimation effort on smaller and more familiar projects for higher-confidence estimates What can we learn from science and history?
  • 14. 14Viasat Proprietary The Mythical Man-Month: Essays on Software Engineering by Frederick Phillips Brooks Originally published in 1975 Later editions come with additional essays
  • 16. 16Viasat Proprietary Programmers are optimists › In the upper left of Fig. 1.1 is a program. › It is complete in itself, ready to be run by the author on the system on which it was developed. That is the thing commonly produced in garages, and that is the object the individual programmer uses in estimating productivity. › In the bottom left is a programming product. › This is a program that can be run, tested, repaired, and extended by anybody. It is usable in many operating environments, for many sets of data. It must be written in a generalized fashion. Must be thoroughly tested, so that it can be depended upon. Finally, it requires its thorough documentation, so that anyone may use it, fix it, and extend it. A
  • 17. 17Viasat Proprietary Programmers are optimists (contd.) › Top right: programming system component › every input and output conforms in syntax and semantics with precisely defined interfaces. The program must also be designed so that it uses only a prescribed budget of resources. Finally, the program must be tested with other system components, in all expected combinations. This testing must be extensive, for the number of cases grows combinatorially. Subtle bugs arise from unexpected interactions of debugged components. › Bottom right: programming system product › Many components working together. Cost may rise further with more components, tighter dependencies, and moving dependencies.
  • 18. 18Viasat Proprietary ›Estimates inform business decisions – Is this project feasible? – How long until we realize any benefit, a sizeable benefit, all the expected benefit from success? – What will we have to give up in order to make this project happen? – What is worth giving up for this project? – What do we lose in case of failure? What do we lose in case of time overruns? Better estimates: purpose
  • 19. 19Viasat Proprietary › There is typically a need for projected delivery dates in order to coordinate with other teams working in the same problem space › There is also a need to allocate resources over time based on expected progress of the project › In addition, estimate is often used as a measuring stick for project success (i.e. CHAOS reporting metrics) › The goal of estimates that get created should be to satisfy a tangible business need. Can we live with no estimates?
  • 20. 20Viasat Proprietary › Estimate often › Record actual spent – Calendar time – Effort › Work from past history when creating future estimates – Check your optimism › Communicate learning – Share more than the # of hours estimated Better approach to estimating
  • 22. 22Viasat Proprietary › Estimating is discovering and sharing useful information about a body of work – Usually focused on work not done – Occasionally about work that has been done, but no records are available › Estimates are assumed to be a fictional number of man-hours Estimating != estimates