Feb 2022 local.gov.uk/pas
Welcome!
Future Proofing the
Plan-Making Process
Martin Hutchings & Shelly Rouse
local.gov.uk/pas
Today
What do we mean –
“future-proof the
plan making process”?
Focus for today:
Presentation, Q & A,
Debate
Agenda:
• Welcome/Background
• PAS Support
• Evidence bases – Mary Elkington
• Duty to Cooperate – Andrew Seaman
• Project Management – Nicki Faulkner
• Panel Q & A - what’s next for Plan making?
local.gov.uk/pas
Gather
Evidence
Consider
Issues &
Options
Consultation
(Reg 18)
Review
Comments
Representati
on (Reg 19)
Examination
in Public
Adopted
Local Plan
PAS Gateway Review 2021
Submission
(Reg 22)
LDS
Path
to 2023
?
?
?
?
?
?
?
?
In March 2020, the Government set a clear deadline of December 2023
for all authorities to have up-to-date Local Plans in place. WMS Chris Pincher 19th Jan 2021
local.gov.uk/pas
Gather
Evidence
Consider
Issues &
Options
Consultat
ion (Reg
18)
Review
Comment
s
Represen
tation
(Reg 19)
Examinat
ion in
Public
Adopted
Local
Plan
Future Proofing (Part 1)
Submis
sion
(Reg 22)
‘Up to Date’ ‘In Place’
Project
Management
Evidence
Base
Duty to
Cooperate
local.gov.uk/pas
Planning Reform - The ‘Known Unknowns’:
Neighbourhood Plans
Future Proofing (Part 2)
local.gov.uk/pas
Evidence
Base
Mary Elkington, Figura Planning
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
INTRODUCTION
Figura Planning Ltd
“Our aim as a consultancy is to support
policies and developments that deliver in the public interest”
Plan Making IS in the Public Interest.
Evidence review team
Simon Thornley & Mary Elkington with our associate John Baker (Point
Consultancy)
We ❤ plans. Embrace and share the excitement.
For a policy team getting to and through examination should be
the best, the most exciting thing about the job.
For elected members having it done takes away
a lot of uncertainty & gives them political cover
mary.elkington@figuraplanning.co.uk
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
APPROACH TO EVIDENCE REVIEWS
Preparation
 Reviewed various toolkits and checklists
 Cross-referenced with dozens of recent sound LP evidence bases
 Reviewed MIQs and outcomes from recent exams to highlight evidence issues
Assessment
 Specifics of review depends on stage of plan making
 Reviewing organised via a matrix of required and optional evidence
 Detailed review of each document
Report: Gaps Unnecessary evidence Quality Issues
Timeliness/Need for
updates
Consistency with
emerging plan
Consistency between
evidence
ACTION PLAN or RECOMMENDATIONS
Future Proofing the Plan Making Process
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
Housing
Overall housing need calculation
HMNA: Segmentation/profile
Allocation Strategy
Site Availability – Land Availability Assessment
Brownfield / Urban Capacity
Housing targets - identified Neighbourhood Areas
Small housing sites evidence
Infrastructure and Transport
Infrastructure Delivery Plan
Transport Assessments – Scenario Testing
Local Transport Plan
Education infrastructure capacity
Medical infrastructure capacity
Drainage, Water, Flooding
SFRA
Water Cycle Study
Coastal (if coastal LPA)
Economy
Local Business Needs
Economic Development Needs Assessment
Economic/Business/Employment Land Assessments
Retail, Leisure and town centre uses needs assessment
Town Centre Hierarchy & Town Centre Assessments.
Primary shopping area & other town centre policies
Other Topics
Renewables/Carbon/Climate
Heritage
Biodiversity
Air Quality
GI/Open Space/Sport-Recreation
Hazardous Substances
Site Specific Evidence
Noise and pollution
Overarching /legal requirements
Duty to cooperate
Sustainability Appraisal
Appropriate Assessment (HRA)
Public Sector Equalities Duty
Sustainability Appraisal
Strategic Objectives
Spatial Strategy
Plan Period Land Supply Trajectory
Five year housing land supply
Plan Viability
Large Allocations
Parameters Plan
Viability/deliverability
Key policy requirements
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
Housing
Overall housing need calculation
HMNA: Segmentation/profile
Allocation Strategy
Site / Land Availability Assessment
Brownfield / Urban Capacity
Housing targets - Neighbourhood Areas
Small housing sites evidence
Infrastructure and Transport
Infrastructure Delivery Plan
Transport Assessments – Scenario Testing
Local Transport Plan
Education infrastructure capacity
Medical infrastructure capacity
Drainage, Water, Flooding
SFRA
Water Cycle Study
Coastal (if coastal LPA)
Economy
Local Business Needs
Economic Development Needs Assessment
Economic/Business/Employment Land Assessments
Retail, Leisure and town centre uses needs assessment
Town Centre Hierarchy & Town Centre Assessments.
Primary shopping area & other town centre policies
Other Topics
Renewables/Carbon/Climate
Heritage
Biodiversity
Air Quality
GI/Open Space/Sport-Recreation
Hazardous Substances
Site Specific Evidence
Noise and pollution
Overarching /legal requirements
Duty to cooperate
Sustainability Appraisal
Appropriate Assessment (HRA)
Public Sector Equalities Duty
Sustainability Appraisal
Strategic Objectives
Spatial Strategy
Plan Period Land Supply Trajectory
Five year housing land supply
Plan Viability
Large Allocations
Parameters Plan
Viability/deliverability
Key policy requirements
62. …the size, type and tenure of housing
needed for different groups in the community
should be assessed and reflected in
planning policies (including… affordable
housing, families with children, older people,
students, people with disabilities, service
families, travellers, people who rent homes
and people wishing to commission or build
their own homes
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
Housing
Overall housing need calculation
HMNA: Segmentation/profile
Allocation Strategy
Site / Land Availability Assessment
Brownfield / Urban Capacity
Housing targets - Neighbourhood Areas
Small housing sites evidence
Drainage, Water, Flood
SFRA
Water Cycle Study
Coastal (if coastal LPA)
Economy
Local Business Needs
Economic Development Needs Assessment
Economic/Business/Employment Land Assessments
Retail, Leisure and town centre uses needs assessment
Town Centre Hierarchy & Town Centre Assessments.
Primary shopping area & other town centre policies
Other Topics
Renewables/Carbon/Climate
Heritage
Biodiversity
Air Quality
GI/Open Space/Sport-Recreation
Hazardous Substances
Site Specific Evidence
Noise and pollution
Overarching /legal requirements
Duty to cooperate
Sustainability Appraisal
Appropriate Assessment (HRA)
Public Sector Equalities Duty
Sustainability Appraisal
Strategic Objectives
Spatial Strategy
Plan Period Land Supply Trajectory
Five year housing land supply
Plan Viability
Large Allocations
Parameters Plan
Viability/deliverability
policy requirements
Chapter 8 of NPPF is your friend:
Mixed-use, accessibility &
transport; community facilities etc
Infrastructure and Transport
Infrastructure Delivery Plan
Transport Assessments – Scenario Testing
Local Transport Plan
Education infrastructure capacity
Medical infrastructure capacity
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
Housing
Overall housing need calculation
HMNA: Segmentation/profile
Allocation Strategy
Site / Land Availability Assessment
Brownfield / Urban Capacity
Housing targets - Neighbourhood Areas
Small housing sites evidence
Infrastructure and Transport
Infrastructure Delivery Plan
Transport Assessments – Scenario Testing
Local Transport Plan
Education infrastructure capacity
Medical infrastructure capacity
Drainage, Water, Flooding
SFRA
Water Cycle Study
Coastal (if coastal LPA)
Economy
Local Business Needs
Economic Development Needs Assessment
Economic/Business/Employment Land Assessments
Retail, Leisure and town centre uses needs assessment
Town Centre Hierarchy & Town Centre Assessments.
Primary shopping area & other town centre policies
Other Topics
Renewables/Carbon/Climate
Heritage
Biodiversity
Air Quality
GI/Open Space/Sport-Recreation
Hazardous Substances
Site Specific Evidence
Noise and pollution
Overarching /legal requirements
Duty to cooperate
Sustainability Appraisal
Appropriate Assessment (HRA)
Public Sector Equalities Duty
Sustainability Appraisal
Strategic Objectives
Spatial Strategy
Plan Period Land Supply Trajectory
Five year housing land supply
Plan Viability
Large Allocations
Parameters Plan
Viability/deliverability
Key policy requirements
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
GENERAL INSIGHTS: TIMELINESS
Don’t blow the budget too early
 Reg 18s flexible & light touch evidence can be fine at reg 18 as long as you get the
critical things out front (strategic objectives, greenbelt, water (WCS Scope), Initial
HRA, approach to allocations…)
 plan viability does not have to be in place at Reg 18 unless DM detail is at heart of
strategy
Reg 18: focus on evidence which drives the spatial strategy
Reg 19: legal requirements, key policy evidence, targeted
evidence to respond to issues raised at Reg 18
Getting the briefs right
 Consider the detail you need and how you will be relying on it
 Are there topics or areas you can exclude from the study?
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
GENERAL INSIGHTS: ROBUSTNESS
Ignoring greenbelt not a strategy
 if political decision is you won’t touch GB, you still
need to
 assess whether exceptional circs apply (need
land supply & Duty 2 Coop principles established)
 consider the 5 purposes of GB
 document the decision rationale
Issues with LAAs
 Conflating SEA with SHELAA assessments
 Passive call for sites – are you passively letting
landowners drive or are you actively reaching out
in areas less constrained or optimal for transport
 NPPG “suitability” does not mean POLICY ON is a starting place
Make sure definitions stack up & are clear in policies; what do you mean by
“large site” vs “strategic site” and aim for consistency across evidence
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
FUTURE PROOFING…
Keep an eye on Inspectors' comments & other exams (PINS link)
Read the inspectors reports from other LPAs
Read MIQs from similar councils
Remember, embrace plan making ❤!
Evidence:
a) Briefs should address specific questions: don’t just commission because
you need a ___ report.
b) Flexible to account for emerging strategies and guidance & timetable
changes
c) Keep overlap to a minimum
d) Clarify any inconsistencies
e) Don’t fear addenda and further evidence – if needed you can produce
Future
Proofing
the
Plan
Making
Process
|
Jan
2022
HORIZON
Decarbonisation
 Pace of change in energy decarbonisation technology is far faster than local plan
timescales. (eg EV charging) : consider flexible wording:
“utilise the most energy and water efficient
technologies to achieve zero carbon” …Manchester Joint Local Plan
BNG
 Ensure strategy in place for strategic sites (esp
Nitrate areas)
 Ensure approach doesn’t disadvantage SMEs
 Will be Factor in: SA/AA/SFRA/WCS/LAA/Viability
Mystic Mary’s Bonus 🔮
 Census 2021 – prepare to educate (objectors,
councillors…) “snapshot in time”
 Agriculture likely to step up agenda
(cf BNG, changes to agri support)
 Devo-levelling shifting discussions on duty to cooperate/strategic plans?
local.gov.uk/pas
Duty to
Cooperate
Andrew Seaman, Intelligent Plans & Examinations (IPE)
Duty to Cooperate
18
• Andrew Seaman
• Lead Advisor – Intelligent Plans and
Examinations
PAS, IPE and the Duty
• IPE Ltd is a development plan based consultancy comprised of experienced
professionals, specifically with examination experience with the Planning
Inspectorate. We offer tailored support and training to local authorities in their
plan making endeavours.
• IPE has been pleased to work with the Planning Advisory Service for many
years in supplying expertise to local authorities on particular aspects of plan
making, including peer review, evidence requirements and the duty to
cooperate.
• IPE and PAS have been working in tandem during 2021 to provide specific
review, advice and support to identified local authorities who anticipate that
discharging the Duty to Cooperate is a risk factor in the production of their
plan.
www.intelligentplans.co.uk 19
The Duty
• S33A Planning and Compulsory Purchase Act 2004
Plan making authorities must cooperate with each other/prescribed bodies upon strategic
matters; in particular they must engage constructively, actively and on an ongoing basis
…
• NPPF (in particular paragraphs 24-27)
Effective and on-going joint working between strategic policy-making authorities and relevant bodies is
integral to the production of a positively prepared and justified strategy
• PPG (ID 61-009-20190315 et al)
Strategic policy-making authorities are required to cooperate with each other, and other bodies, when
preparing, or supporting the preparation of policies which address strategic matters … these authorities
should produce, maintain, and update one or more statement(s) of common ground, throughout the
plan-making process.
www.intelligentplans.co.uk 20
The Duty
The DtC can be considered as comprising two interlinked strands:
• Process : the practical means by which S33A has been addressed including the
identification of strategic matters, the relevant prescribed bodies, the
engagement activities etc
• Outcomes : the specific plan making provisions which arise from the process of
cooperation. For example agreement on housing land supply to meet
requirements, infrastructure needs etc
www.intelligentplans.co.uk 21
www.intelligentplans.co.uk 22
The Duty at Examination
• Discharge of the DtC underpins the delivery of sustainable development (see
S33A(4)
• The DtC is a critical matter at Examination. Failure to demonstrate how the
DtC has been applied to the plan making process is a failure of legal
compliance.
The duty to co-operate must be fulfilled when preparing the plan and any failure
in this regard cannot be rectified after the plan has been submitted for
examination. (Planning Inspectorate Procedural Guide)
www.intelligentplans.co.uk 23
The Duty at Examination
• Before submission, the LPA must do all it can to resolve any substantive concerns about
the soundness or legal compliance of the plan, including any raised by statutory
undertakers and government agencies. Particular attention should be given to the duty
to cooperate. Statements of Common Ground can be very helpful in this regard.
• In order to demonstrate compliance with the duty to co-operate … the most helpful
approach is for the LPA to submit a statement of compliance with the duty. The
statement of compliance should identify any relevant strategic matters and how they
have been resolved – or if they have not, why not. It should detail who the LPA has co-
operated with and on which strategic matter(s), the nature and timing of the co-
operation (e.g. by including meeting notes), and the outcomes of the co-operation,
including how it has influenced the plan.
www.intelligentplans.co.uk 24
The Duty in Preparation (process)
• Consider the DtC at the inception of the plan making process
Identify
Strategic
Matters
Identify
Prescribed
Bodies
Review liaison/
collaboration
mechanisms
Establish
MoU
Active
liaison
SoCG
Plan Preparation
Compliance
Statement
www.intelligentplans.co.uk 25
The Duty in Preparation (process)
• Consider a project plan to address the DtC in plan making
www.intelligentplans.co.uk 26
The Duty (process and outcomes)
• Maintain evidence. Audit trail of activities and outcomes (linked to phases of
plan preparation eg Issues/Options, Reg 18, Reg 19, submission).
• keep a clear audit trail of meetings, their outcomes, and decisions
made
• get decisions in writing from other authorities/bodies
• clarify/confirm understanding/ intentions in writing
• Memoranda of Understanding
• Statement(s) of Common Ground (including disagreements)
• Duty to Cooperate Compliance Statement
www.intelligentplans.co.uk 27
The Duty (outcomes)
• Failure to agree.
• Not an indicator of legal compliance failure
• Will likely be a priority issue of examination into ‘soundness’
• Risk mitigation should be considered
• Examine the evidential reasons for disagreements arising
• Consider and document options to address (eg MoU, LDS, further joint
working)
Examples of ‘failure’: St Albans DC, Wealden DC, Sevenoaks BC
The Duty and Planning Reform
• White Paper – Planning for the Future 2020
The Duty to Cooperate test would be removed (… further consideration will be given to the way
in which strategic cross-boundary issues…including the scale at which plans are best prepared in
areas with significant strategic challenges)
 No details of any alternative and no updates on consultation outcomes on the proposition –
industry suggestions of strategic planning advisory bodies, devolution to larger authorities/
joint plan making, greater number of combined authorities etc
• Commentary
 Regardless of the proposition, the White Paper maintains reference to the need for strategic
planning on cross boundary issues; no subsequent suggestion of a fundamental alternative
 No reason to suspend plan making in the absence of clarity on future strategic plan making;
 Liaison on strategic matters will remain a key consideration regardless of statutory process.
www.intelligentplans.co.uk 28
www.intelligentplans.co.uk 29
Thank you for listening.
Reference sources:
Planning and Compulsory Purchase Act 2004
NPPF – see Plan Making
PPG – see specific sections on cooperation
PAS – Doing your Duty Practice Update (2014)
Planning Inspectorate Procedural Guide for Local Plan Examinations (Oct 2021)
Planning for the Future White Paper August 2020
local.gov.uk/pas
Project
Management
Nicki Faulkner, DAC Planning
PAS Project
Management
Support
Future Proofing the Plan Making Process –
27 January 2022
Project Team
DAC Planning provides support to local authorities and
local communities in planning for a sustainable future.
Key services include:
• Support for Local Plan and Neighbourhood Plan
production;
• Infrastructure planning;
• Project management;
• Coordination and facilitation of complex strategic
growth plans;
• Capacity building;
• Research and evidence base gathering; and
• Facilitation of community and stakeholder
engagement.
Arup is a multi-disciplinary practice that offers planning
related consultancy skills and services across the
country. We have a strong track record of working in
partnership with local authorities including:
• Supporting Local Plan production;
• Project management;
• Strategic growth plans and site assessments
particularly in the context of Green Belt;
• Infrastructure planning;
• Capacity building; and
• Governance and delivery advice.
Project
Background
• Follow-on support from Gateway Reviews which DAC
Planning/Arup undertook on behalf of PAS
• Provide assessment of the suitability and effectiveness of a
Council’s project plan, the LDS and available resources and
identify any risks and potential efficiencies for effective
production and delivery of the Local Plan
• So far, completed support for 15 local authorities across the
country with support on-going for 3 more
• Broad approach:
• Inception meeting;
• Desk-based review of documentation and project plan;
• Workshop session(s) with officers to discuss key risks; and
• Production of an advice note.
• Approach flexed to meet specific needs of each Council e.g.
additional workshops to work through project plan template
• Advice note highlights key risks and provides suggested mitigation
and recommendations, including areas for further support (from
PAS or others)
PAS Project Management Support
Key Risks
Identified
Achievability
of project
plan
Approach
to DtC
Volume of
consultation
responses to
analyse
Lack of (or
out-of-
date)
project plan
Managing
changes in
personnel
Time spent
resolving
objections
Time
pressures
beyond the
Local Plan
Linkages
between
elements of
plan
production
Assumptions
around time
needed for
examination
Challenges
with
governance
and Member
engagement
• Scoping is a key stage to:
• Inform Project Initiation Document and
project plan
• Identify key risks and how they can be
managed
• Value in undertaking this at outset of Local
Plan and/or if there is a significant change in
circumstances
• Take a holistic approach to project scoping
• Look beyond evidence base production
to consider the Duty to Cooperate,
Governance arrangements, Member
engagement, consultation and
engagement
• Consider using Local Plan Route Mapper
and Toolkit
• Use outputs from scoping to secure
corporate buy-in, articulate challenges and
manage risks to plan-making
Scope the Local Plan
1
Lessons
Learnt
Lessons
Learnt
• Importance of having a project plan!
• Live document to actively manage Plan production:
• Identify key milestones
• Produce high level and detailed plans
• Assess resources
• To be a useful tool, it needs to be realistic:
• Consider all facets of plan-making – not just evidence base
– and other tasks (AMR etc)
• Estimate time requirements for key tasks and map against
team resources/available budget
• Articulate interdependencies between different elements
• Build in contingency time and expect the unexpected
• Include governance and other lead-in times
• Use it to help manage expectations and articulate priorities
Use a Project Plan
2
• Significant issue across many authorities we spoke to!
• Be realistic and creative about approach to resourcing
• Understand resourcing peaks in preparing the Plan e.g. in
the lead-up to, and following consultation
• Think about what roles really need a policy officer and where
you can draw on wider planning or other expertise
• Consider options to boost capacity
• Prioritisation of tasks within policy team
• Wider resources within the Council
• Secondments
• Neighbouring authorities and county councils –
particularly for specialist resources
• Potential to outsource resource intensive tasks
Be Creative with Resources
3
Lessons
Learnt
• Don’t be afraid to challenge the norm and consider new
ways of doing things
• Key areas where this could reap significant benefits included:
• Streamlining governance arrangements/lead-in times
• Accelerating procurement timetable/required steps
• Reducing the length and/or number of consultation
periods (including updating the SCI)
• Manage political pressures and expectations –using the
PID/project plan/Route Mapper and Toolkit can help to
evidence value of an alternative approach
• Having a second opinion from a critical friend (including from
PAS) can be valuable and support decision making around
key risks, alternative approaches and opportunities to
streamline workstreams
Be Bold
4
Lessons
Learnt
Conclusion
• Project management is become ever more
important to delivery of sound Local Plans
• Planning White Paper proposes a statutory 30-
month timetable for preparing Local Plans
• Benefits from having a strong project
management system in place:
• Drive the Local Plan forward within a
context of resource constraints using an
evidenced and bold approach, rigorously
scoped out and planned
• Facilitate the transition and adaptation
required in the event of planning reform
Looking to the Future
local.gov.uk/pas
Refreshment
Break
local.gov.uk/pas
Planning Reform - The ‘Known Unknowns’:
Neighbourhood Plans
Panel Q & A / Discussion
local.gov.uk/pas
Thank You
& enjoy the
rest of your
day

More Related Content

PPTX
HNA Slides Show and Tell 14.10.21
PPTX
Councillor briefing nppf hiowlga as delivered
PPTX
Pas topic paper housing march20
PPTX
Keep on planning presentation final
PPTX
PAS Biodiversity Net Gain consultation overview - 10 February 2022
PPTX
How to keep going in Presumption
PPTX
HDTAP 2020 21 workshop
PPTX
Pas topic paper housing august19 draft3
HNA Slides Show and Tell 14.10.21
Councillor briefing nppf hiowlga as delivered
Pas topic paper housing march20
Keep on planning presentation final
PAS Biodiversity Net Gain consultation overview - 10 February 2022
How to keep going in Presumption
HDTAP 2020 21 workshop
Pas topic paper housing august19 draft3

What's hot (20)

PPTX
Pas hdt support april 19 as delivered
PPTX
Waste planning and the Duty to Co-operate
PPTX
PAS Biodiversity Net Gain and the Environment Bill - what does it mean for LP...
PPTX
Housing delivery test generic slides
PPTX
Presumption: How to keep making effective decisions
PPTX
Catriona riddell strategic planning 1st & 7th & 14th
PPTX
Gdpr and planning july 2019
PPTX
Councillor Briefing: Recent changes in planning
PPT
Councillor Briefing: Decision making, committees and probity
PPTX
PAS Biodiversity Net Gain London Borough Workshop 15 July 2021
PPT
Mosaic, Public Sector Forums, Efficiency Through E-Planning
PPT
Councillor Briefing: Local Plans and Plan making
PPTX
Pas hdt cohort 2 march 2020
PPT
Planning Aid England - Neighbourhood Planning - community group experiences
PPTX
Edna and sheila slideshare composite
PPT
Making defensible-planning-decisions-june2019
PPT
Approaching decisions on minerals and waste applications (May 2014)
PPT
Further alterations to the London Plan and beyond: wider South East perspective
PPTX
Neighbourhood Planning East Devon experience
PPT
The Arun Approach
Pas hdt support april 19 as delivered
Waste planning and the Duty to Co-operate
PAS Biodiversity Net Gain and the Environment Bill - what does it mean for LP...
Housing delivery test generic slides
Presumption: How to keep making effective decisions
Catriona riddell strategic planning 1st & 7th & 14th
Gdpr and planning july 2019
Councillor Briefing: Recent changes in planning
Councillor Briefing: Decision making, committees and probity
PAS Biodiversity Net Gain London Borough Workshop 15 July 2021
Mosaic, Public Sector Forums, Efficiency Through E-Planning
Councillor Briefing: Local Plans and Plan making
Pas hdt cohort 2 march 2020
Planning Aid England - Neighbourhood Planning - community group experiences
Edna and sheila slideshare composite
Making defensible-planning-decisions-june2019
Approaching decisions on minerals and waste applications (May 2014)
Further alterations to the London Plan and beyond: wider South East perspective
Neighbourhood Planning East Devon experience
The Arun Approach
Ad

Similar to Future proof event presentation event feb 2022 v2 (20)

PPTX
Presentation_Value of Local Plans Cllr and Corp Leadership Teams New Plan Sys...
PPTX
Local plans-and-plan-making cllr pres june2019
PDF
Public sector planning club, June 2018, Nottingham
PPT
Plan making - getting your plan in place (July 2013)
PPTX
Day 1 Seminar_The Plan-making Score_web.pptx
PDF
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
PDF
Derek stebbing local plans expert group
PPTX
Planning Aid England - The experiences of local groups
PPTX
PAS 2025 Conference Main Room Master Deck Web.pptx
PDF
Plan Making Reforms Implementation Consultation Presentation Aug 2023
PPTX
Leadership Essentials: Delivering Your Local Plan
PPTX
Shine Webinar, National Planning, 25 April
PPTX
OPDC revised draft Local Plan presentation - Employment
PPTX
NPPF Roadshow 2024 In-Person Presentation
PPT
The National Planning Policy Framework: Steve Miller DipTP MRTPI Head of Plan...
PPTX
Atlas Presentation: Birmingham
PPTX
Going beyond boundaries: Doing interdisciplinary research in the rural urban ...
PPTX
Ibda presentation
PPT
New Town Development Strategies Jan 2015 - Day 2
PDF
GroWNC Workgroup Launch Presentation
Presentation_Value of Local Plans Cllr and Corp Leadership Teams New Plan Sys...
Local plans-and-plan-making cllr pres june2019
Public sector planning club, June 2018, Nottingham
Plan making - getting your plan in place (July 2013)
Day 1 Seminar_The Plan-making Score_web.pptx
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Derek stebbing local plans expert group
Planning Aid England - The experiences of local groups
PAS 2025 Conference Main Room Master Deck Web.pptx
Plan Making Reforms Implementation Consultation Presentation Aug 2023
Leadership Essentials: Delivering Your Local Plan
Shine Webinar, National Planning, 25 April
OPDC revised draft Local Plan presentation - Employment
NPPF Roadshow 2024 In-Person Presentation
The National Planning Policy Framework: Steve Miller DipTP MRTPI Head of Plan...
Atlas Presentation: Birmingham
Going beyond boundaries: Doing interdisciplinary research in the rural urban ...
Ibda presentation
New Town Development Strategies Jan 2015 - Day 2
GroWNC Workgroup Launch Presentation
Ad

More from PAS_Team (20)

PPTX
Training Local Plan Examinations 2025 PCPA - Copy (1).pptx
PPTX
PAS nature emergency event for councillors
PPTX
MHCLG Presentation Green Belt PPG_PAS_18MAR25.pptx
PPTX
Dec 24 NPPF Webinar 19 March Golden Rules.pptx
PPTX
Day 2 Seminar_Innovation and Bold Leadership_web.pptx
PPTX
NPPF Dec 24 - Housing Numbers Webinar PAS FINAL Version.pptx
PPTX
NPPF Deep Dive: Infrastructure September 2024
PPTX
NPPF Deep Dive: Green Belt September 2024
PPTX
NPPF Deep Dive: Housing Numbers, Delivery, and Land Supply
PPTX
PAS Developer Contributions Deep Dive Online Slides
PPTX
PAS NPPF Consultation Local Plan and Strategic Plg Workshop SLIDES 16 09 24.pptx
PPTX
PAS PSDF Mop Up Workshop Presentation 2024 .pptx
PDF
231121 SP slides - PAS workshop November 2023.pdf
PPTX
So you want to apply for the Planning Skills Delivery Fund PAS Events August ...
PPTX
PAS BNG in Local Plans slides June 2023
PDF
Guildford BC BNG Policy June 2023.pdf
PDF
BNG at Salford City Council_June 2023.pdf
PPTX
PAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptx
PPTX
Leeds Beckett Lecture Career Advice.pptx
PPTX
Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...
Training Local Plan Examinations 2025 PCPA - Copy (1).pptx
PAS nature emergency event for councillors
MHCLG Presentation Green Belt PPG_PAS_18MAR25.pptx
Dec 24 NPPF Webinar 19 March Golden Rules.pptx
Day 2 Seminar_Innovation and Bold Leadership_web.pptx
NPPF Dec 24 - Housing Numbers Webinar PAS FINAL Version.pptx
NPPF Deep Dive: Infrastructure September 2024
NPPF Deep Dive: Green Belt September 2024
NPPF Deep Dive: Housing Numbers, Delivery, and Land Supply
PAS Developer Contributions Deep Dive Online Slides
PAS NPPF Consultation Local Plan and Strategic Plg Workshop SLIDES 16 09 24.pptx
PAS PSDF Mop Up Workshop Presentation 2024 .pptx
231121 SP slides - PAS workshop November 2023.pdf
So you want to apply for the Planning Skills Delivery Fund PAS Events August ...
PAS BNG in Local Plans slides June 2023
Guildford BC BNG Policy June 2023.pdf
BNG at Salford City Council_June 2023.pdf
PAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptx
Leeds Beckett Lecture Career Advice.pptx
Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...

Recently uploaded (20)

PPTX
Workshop-Session-1-LGU-WFP-Formulation.pptx
PDF
4_Key Concepts Structure and Governance plus UN.pdf okay
PPTX
Parliamentary procedure in meeting that can be use
PPT
The Central Civil Services (Leave Travel Concession) Rules, 1988, govern the ...
PPTX
Empowering Teens with Essential Life Skills 🚀
PPTX
True Fruits_ reportcccccccccccccccc.pptx
PPTX
ANALYSIS OF THE PROCLAMATION OF THE PHILIPPHINE INDEPENDENCE.pptx
PDF
PPT Item # 9 - FY 2025-26 Proposed Budget.pdf
PPTX
Presentatio koos kokos koko ossssn5.pptx
PPTX
cpgram enivaran cpgram enivaran cpgram enivaran
PDF
Redefining Diplomacy: Françoise Joly on Navigating a Multipolar Order
PPTX
The DFARS - Part 251 - Use of Government Sources By Contractors
PPTX
Core Humanitarian Standard Presentation by Abraham Lebeza
PDF
Building Bridges (of Hope) over Our Troubled Waters_PART 1
PDF
Item # 5 - 5307 Broadway St final review
PDF
PPT Items # 6&7 - 900 Cambridge Oval Right-of-Way
PPTX
Part II LGU Accreditation of CSOs and Selection of Reps to LSBs ver2.pptx
PDF
Concept_Note_-_GoAP_Primary_Sector_-_The_Great_Rural_Reset_-_Updated_18_June_...
PPTX
International Tracking Project Unloading Guidance Manual V1 (1) 1.pptx
PPTX
DFARS Part 253 - Forms - Defense Contracting Regulations
Workshop-Session-1-LGU-WFP-Formulation.pptx
4_Key Concepts Structure and Governance plus UN.pdf okay
Parliamentary procedure in meeting that can be use
The Central Civil Services (Leave Travel Concession) Rules, 1988, govern the ...
Empowering Teens with Essential Life Skills 🚀
True Fruits_ reportcccccccccccccccc.pptx
ANALYSIS OF THE PROCLAMATION OF THE PHILIPPHINE INDEPENDENCE.pptx
PPT Item # 9 - FY 2025-26 Proposed Budget.pdf
Presentatio koos kokos koko ossssn5.pptx
cpgram enivaran cpgram enivaran cpgram enivaran
Redefining Diplomacy: Françoise Joly on Navigating a Multipolar Order
The DFARS - Part 251 - Use of Government Sources By Contractors
Core Humanitarian Standard Presentation by Abraham Lebeza
Building Bridges (of Hope) over Our Troubled Waters_PART 1
Item # 5 - 5307 Broadway St final review
PPT Items # 6&7 - 900 Cambridge Oval Right-of-Way
Part II LGU Accreditation of CSOs and Selection of Reps to LSBs ver2.pptx
Concept_Note_-_GoAP_Primary_Sector_-_The_Great_Rural_Reset_-_Updated_18_June_...
International Tracking Project Unloading Guidance Manual V1 (1) 1.pptx
DFARS Part 253 - Forms - Defense Contracting Regulations

Future proof event presentation event feb 2022 v2

  • 1. Feb 2022 local.gov.uk/pas Welcome! Future Proofing the Plan-Making Process Martin Hutchings & Shelly Rouse
  • 2. local.gov.uk/pas Today What do we mean – “future-proof the plan making process”? Focus for today: Presentation, Q & A, Debate Agenda: • Welcome/Background • PAS Support • Evidence bases – Mary Elkington • Duty to Cooperate – Andrew Seaman • Project Management – Nicki Faulkner • Panel Q & A - what’s next for Plan making?
  • 3. local.gov.uk/pas Gather Evidence Consider Issues & Options Consultation (Reg 18) Review Comments Representati on (Reg 19) Examination in Public Adopted Local Plan PAS Gateway Review 2021 Submission (Reg 22) LDS Path to 2023 ? ? ? ? ? ? ? ? In March 2020, the Government set a clear deadline of December 2023 for all authorities to have up-to-date Local Plans in place. WMS Chris Pincher 19th Jan 2021
  • 4. local.gov.uk/pas Gather Evidence Consider Issues & Options Consultat ion (Reg 18) Review Comment s Represen tation (Reg 19) Examinat ion in Public Adopted Local Plan Future Proofing (Part 1) Submis sion (Reg 22) ‘Up to Date’ ‘In Place’ Project Management Evidence Base Duty to Cooperate
  • 5. local.gov.uk/pas Planning Reform - The ‘Known Unknowns’: Neighbourhood Plans Future Proofing (Part 2)
  • 7. Future Proofing the Plan Making Process | Jan 2022 INTRODUCTION Figura Planning Ltd “Our aim as a consultancy is to support policies and developments that deliver in the public interest” Plan Making IS in the Public Interest. Evidence review team Simon Thornley & Mary Elkington with our associate John Baker (Point Consultancy) We ❤ plans. Embrace and share the excitement. For a policy team getting to and through examination should be the best, the most exciting thing about the job. For elected members having it done takes away a lot of uncertainty & gives them political cover mary.elkington@figuraplanning.co.uk
  • 8. Future Proofing the Plan Making Process | Jan 2022 APPROACH TO EVIDENCE REVIEWS Preparation  Reviewed various toolkits and checklists  Cross-referenced with dozens of recent sound LP evidence bases  Reviewed MIQs and outcomes from recent exams to highlight evidence issues Assessment  Specifics of review depends on stage of plan making  Reviewing organised via a matrix of required and optional evidence  Detailed review of each document Report: Gaps Unnecessary evidence Quality Issues Timeliness/Need for updates Consistency with emerging plan Consistency between evidence ACTION PLAN or RECOMMENDATIONS Future Proofing the Plan Making Process
  • 9. Future Proofing the Plan Making Process | Jan 2022 Housing Overall housing need calculation HMNA: Segmentation/profile Allocation Strategy Site Availability – Land Availability Assessment Brownfield / Urban Capacity Housing targets - identified Neighbourhood Areas Small housing sites evidence Infrastructure and Transport Infrastructure Delivery Plan Transport Assessments – Scenario Testing Local Transport Plan Education infrastructure capacity Medical infrastructure capacity Drainage, Water, Flooding SFRA Water Cycle Study Coastal (if coastal LPA) Economy Local Business Needs Economic Development Needs Assessment Economic/Business/Employment Land Assessments Retail, Leisure and town centre uses needs assessment Town Centre Hierarchy & Town Centre Assessments. Primary shopping area & other town centre policies Other Topics Renewables/Carbon/Climate Heritage Biodiversity Air Quality GI/Open Space/Sport-Recreation Hazardous Substances Site Specific Evidence Noise and pollution Overarching /legal requirements Duty to cooperate Sustainability Appraisal Appropriate Assessment (HRA) Public Sector Equalities Duty Sustainability Appraisal Strategic Objectives Spatial Strategy Plan Period Land Supply Trajectory Five year housing land supply Plan Viability Large Allocations Parameters Plan Viability/deliverability Key policy requirements
  • 10. Future Proofing the Plan Making Process | Jan 2022 Housing Overall housing need calculation HMNA: Segmentation/profile Allocation Strategy Site / Land Availability Assessment Brownfield / Urban Capacity Housing targets - Neighbourhood Areas Small housing sites evidence Infrastructure and Transport Infrastructure Delivery Plan Transport Assessments – Scenario Testing Local Transport Plan Education infrastructure capacity Medical infrastructure capacity Drainage, Water, Flooding SFRA Water Cycle Study Coastal (if coastal LPA) Economy Local Business Needs Economic Development Needs Assessment Economic/Business/Employment Land Assessments Retail, Leisure and town centre uses needs assessment Town Centre Hierarchy & Town Centre Assessments. Primary shopping area & other town centre policies Other Topics Renewables/Carbon/Climate Heritage Biodiversity Air Quality GI/Open Space/Sport-Recreation Hazardous Substances Site Specific Evidence Noise and pollution Overarching /legal requirements Duty to cooperate Sustainability Appraisal Appropriate Assessment (HRA) Public Sector Equalities Duty Sustainability Appraisal Strategic Objectives Spatial Strategy Plan Period Land Supply Trajectory Five year housing land supply Plan Viability Large Allocations Parameters Plan Viability/deliverability Key policy requirements 62. …the size, type and tenure of housing needed for different groups in the community should be assessed and reflected in planning policies (including… affordable housing, families with children, older people, students, people with disabilities, service families, travellers, people who rent homes and people wishing to commission or build their own homes
  • 11. Future Proofing the Plan Making Process | Jan 2022 Housing Overall housing need calculation HMNA: Segmentation/profile Allocation Strategy Site / Land Availability Assessment Brownfield / Urban Capacity Housing targets - Neighbourhood Areas Small housing sites evidence Drainage, Water, Flood SFRA Water Cycle Study Coastal (if coastal LPA) Economy Local Business Needs Economic Development Needs Assessment Economic/Business/Employment Land Assessments Retail, Leisure and town centre uses needs assessment Town Centre Hierarchy & Town Centre Assessments. Primary shopping area & other town centre policies Other Topics Renewables/Carbon/Climate Heritage Biodiversity Air Quality GI/Open Space/Sport-Recreation Hazardous Substances Site Specific Evidence Noise and pollution Overarching /legal requirements Duty to cooperate Sustainability Appraisal Appropriate Assessment (HRA) Public Sector Equalities Duty Sustainability Appraisal Strategic Objectives Spatial Strategy Plan Period Land Supply Trajectory Five year housing land supply Plan Viability Large Allocations Parameters Plan Viability/deliverability policy requirements Chapter 8 of NPPF is your friend: Mixed-use, accessibility & transport; community facilities etc Infrastructure and Transport Infrastructure Delivery Plan Transport Assessments – Scenario Testing Local Transport Plan Education infrastructure capacity Medical infrastructure capacity
  • 12. Future Proofing the Plan Making Process | Jan 2022 Housing Overall housing need calculation HMNA: Segmentation/profile Allocation Strategy Site / Land Availability Assessment Brownfield / Urban Capacity Housing targets - Neighbourhood Areas Small housing sites evidence Infrastructure and Transport Infrastructure Delivery Plan Transport Assessments – Scenario Testing Local Transport Plan Education infrastructure capacity Medical infrastructure capacity Drainage, Water, Flooding SFRA Water Cycle Study Coastal (if coastal LPA) Economy Local Business Needs Economic Development Needs Assessment Economic/Business/Employment Land Assessments Retail, Leisure and town centre uses needs assessment Town Centre Hierarchy & Town Centre Assessments. Primary shopping area & other town centre policies Other Topics Renewables/Carbon/Climate Heritage Biodiversity Air Quality GI/Open Space/Sport-Recreation Hazardous Substances Site Specific Evidence Noise and pollution Overarching /legal requirements Duty to cooperate Sustainability Appraisal Appropriate Assessment (HRA) Public Sector Equalities Duty Sustainability Appraisal Strategic Objectives Spatial Strategy Plan Period Land Supply Trajectory Five year housing land supply Plan Viability Large Allocations Parameters Plan Viability/deliverability Key policy requirements
  • 13. Future Proofing the Plan Making Process | Jan 2022 GENERAL INSIGHTS: TIMELINESS Don’t blow the budget too early  Reg 18s flexible & light touch evidence can be fine at reg 18 as long as you get the critical things out front (strategic objectives, greenbelt, water (WCS Scope), Initial HRA, approach to allocations…)  plan viability does not have to be in place at Reg 18 unless DM detail is at heart of strategy Reg 18: focus on evidence which drives the spatial strategy Reg 19: legal requirements, key policy evidence, targeted evidence to respond to issues raised at Reg 18 Getting the briefs right  Consider the detail you need and how you will be relying on it  Are there topics or areas you can exclude from the study?
  • 14. Future Proofing the Plan Making Process | Jan 2022 GENERAL INSIGHTS: ROBUSTNESS Ignoring greenbelt not a strategy  if political decision is you won’t touch GB, you still need to  assess whether exceptional circs apply (need land supply & Duty 2 Coop principles established)  consider the 5 purposes of GB  document the decision rationale Issues with LAAs  Conflating SEA with SHELAA assessments  Passive call for sites – are you passively letting landowners drive or are you actively reaching out in areas less constrained or optimal for transport  NPPG “suitability” does not mean POLICY ON is a starting place Make sure definitions stack up & are clear in policies; what do you mean by “large site” vs “strategic site” and aim for consistency across evidence
  • 15. Future Proofing the Plan Making Process | Jan 2022 FUTURE PROOFING… Keep an eye on Inspectors' comments & other exams (PINS link) Read the inspectors reports from other LPAs Read MIQs from similar councils Remember, embrace plan making ❤! Evidence: a) Briefs should address specific questions: don’t just commission because you need a ___ report. b) Flexible to account for emerging strategies and guidance & timetable changes c) Keep overlap to a minimum d) Clarify any inconsistencies e) Don’t fear addenda and further evidence – if needed you can produce
  • 16. Future Proofing the Plan Making Process | Jan 2022 HORIZON Decarbonisation  Pace of change in energy decarbonisation technology is far faster than local plan timescales. (eg EV charging) : consider flexible wording: “utilise the most energy and water efficient technologies to achieve zero carbon” …Manchester Joint Local Plan BNG  Ensure strategy in place for strategic sites (esp Nitrate areas)  Ensure approach doesn’t disadvantage SMEs  Will be Factor in: SA/AA/SFRA/WCS/LAA/Viability Mystic Mary’s Bonus 🔮  Census 2021 – prepare to educate (objectors, councillors…) “snapshot in time”  Agriculture likely to step up agenda (cf BNG, changes to agri support)  Devo-levelling shifting discussions on duty to cooperate/strategic plans?
  • 17. local.gov.uk/pas Duty to Cooperate Andrew Seaman, Intelligent Plans & Examinations (IPE)
  • 18. Duty to Cooperate 18 • Andrew Seaman • Lead Advisor – Intelligent Plans and Examinations
  • 19. PAS, IPE and the Duty • IPE Ltd is a development plan based consultancy comprised of experienced professionals, specifically with examination experience with the Planning Inspectorate. We offer tailored support and training to local authorities in their plan making endeavours. • IPE has been pleased to work with the Planning Advisory Service for many years in supplying expertise to local authorities on particular aspects of plan making, including peer review, evidence requirements and the duty to cooperate. • IPE and PAS have been working in tandem during 2021 to provide specific review, advice and support to identified local authorities who anticipate that discharging the Duty to Cooperate is a risk factor in the production of their plan. www.intelligentplans.co.uk 19
  • 20. The Duty • S33A Planning and Compulsory Purchase Act 2004 Plan making authorities must cooperate with each other/prescribed bodies upon strategic matters; in particular they must engage constructively, actively and on an ongoing basis … • NPPF (in particular paragraphs 24-27) Effective and on-going joint working between strategic policy-making authorities and relevant bodies is integral to the production of a positively prepared and justified strategy • PPG (ID 61-009-20190315 et al) Strategic policy-making authorities are required to cooperate with each other, and other bodies, when preparing, or supporting the preparation of policies which address strategic matters … these authorities should produce, maintain, and update one or more statement(s) of common ground, throughout the plan-making process. www.intelligentplans.co.uk 20
  • 21. The Duty The DtC can be considered as comprising two interlinked strands: • Process : the practical means by which S33A has been addressed including the identification of strategic matters, the relevant prescribed bodies, the engagement activities etc • Outcomes : the specific plan making provisions which arise from the process of cooperation. For example agreement on housing land supply to meet requirements, infrastructure needs etc www.intelligentplans.co.uk 21
  • 22. www.intelligentplans.co.uk 22 The Duty at Examination • Discharge of the DtC underpins the delivery of sustainable development (see S33A(4) • The DtC is a critical matter at Examination. Failure to demonstrate how the DtC has been applied to the plan making process is a failure of legal compliance. The duty to co-operate must be fulfilled when preparing the plan and any failure in this regard cannot be rectified after the plan has been submitted for examination. (Planning Inspectorate Procedural Guide)
  • 23. www.intelligentplans.co.uk 23 The Duty at Examination • Before submission, the LPA must do all it can to resolve any substantive concerns about the soundness or legal compliance of the plan, including any raised by statutory undertakers and government agencies. Particular attention should be given to the duty to cooperate. Statements of Common Ground can be very helpful in this regard. • In order to demonstrate compliance with the duty to co-operate … the most helpful approach is for the LPA to submit a statement of compliance with the duty. The statement of compliance should identify any relevant strategic matters and how they have been resolved – or if they have not, why not. It should detail who the LPA has co- operated with and on which strategic matter(s), the nature and timing of the co- operation (e.g. by including meeting notes), and the outcomes of the co-operation, including how it has influenced the plan.
  • 24. www.intelligentplans.co.uk 24 The Duty in Preparation (process) • Consider the DtC at the inception of the plan making process Identify Strategic Matters Identify Prescribed Bodies Review liaison/ collaboration mechanisms Establish MoU Active liaison SoCG Plan Preparation Compliance Statement
  • 25. www.intelligentplans.co.uk 25 The Duty in Preparation (process) • Consider a project plan to address the DtC in plan making
  • 26. www.intelligentplans.co.uk 26 The Duty (process and outcomes) • Maintain evidence. Audit trail of activities and outcomes (linked to phases of plan preparation eg Issues/Options, Reg 18, Reg 19, submission). • keep a clear audit trail of meetings, their outcomes, and decisions made • get decisions in writing from other authorities/bodies • clarify/confirm understanding/ intentions in writing • Memoranda of Understanding • Statement(s) of Common Ground (including disagreements) • Duty to Cooperate Compliance Statement
  • 27. www.intelligentplans.co.uk 27 The Duty (outcomes) • Failure to agree. • Not an indicator of legal compliance failure • Will likely be a priority issue of examination into ‘soundness’ • Risk mitigation should be considered • Examine the evidential reasons for disagreements arising • Consider and document options to address (eg MoU, LDS, further joint working) Examples of ‘failure’: St Albans DC, Wealden DC, Sevenoaks BC
  • 28. The Duty and Planning Reform • White Paper – Planning for the Future 2020 The Duty to Cooperate test would be removed (… further consideration will be given to the way in which strategic cross-boundary issues…including the scale at which plans are best prepared in areas with significant strategic challenges)  No details of any alternative and no updates on consultation outcomes on the proposition – industry suggestions of strategic planning advisory bodies, devolution to larger authorities/ joint plan making, greater number of combined authorities etc • Commentary  Regardless of the proposition, the White Paper maintains reference to the need for strategic planning on cross boundary issues; no subsequent suggestion of a fundamental alternative  No reason to suspend plan making in the absence of clarity on future strategic plan making;  Liaison on strategic matters will remain a key consideration regardless of statutory process. www.intelligentplans.co.uk 28
  • 29. www.intelligentplans.co.uk 29 Thank you for listening. Reference sources: Planning and Compulsory Purchase Act 2004 NPPF – see Plan Making PPG – see specific sections on cooperation PAS – Doing your Duty Practice Update (2014) Planning Inspectorate Procedural Guide for Local Plan Examinations (Oct 2021) Planning for the Future White Paper August 2020
  • 31. PAS Project Management Support Future Proofing the Plan Making Process – 27 January 2022
  • 32. Project Team DAC Planning provides support to local authorities and local communities in planning for a sustainable future. Key services include: • Support for Local Plan and Neighbourhood Plan production; • Infrastructure planning; • Project management; • Coordination and facilitation of complex strategic growth plans; • Capacity building; • Research and evidence base gathering; and • Facilitation of community and stakeholder engagement. Arup is a multi-disciplinary practice that offers planning related consultancy skills and services across the country. We have a strong track record of working in partnership with local authorities including: • Supporting Local Plan production; • Project management; • Strategic growth plans and site assessments particularly in the context of Green Belt; • Infrastructure planning; • Capacity building; and • Governance and delivery advice.
  • 33. Project Background • Follow-on support from Gateway Reviews which DAC Planning/Arup undertook on behalf of PAS • Provide assessment of the suitability and effectiveness of a Council’s project plan, the LDS and available resources and identify any risks and potential efficiencies for effective production and delivery of the Local Plan • So far, completed support for 15 local authorities across the country with support on-going for 3 more • Broad approach: • Inception meeting; • Desk-based review of documentation and project plan; • Workshop session(s) with officers to discuss key risks; and • Production of an advice note. • Approach flexed to meet specific needs of each Council e.g. additional workshops to work through project plan template • Advice note highlights key risks and provides suggested mitigation and recommendations, including areas for further support (from PAS or others) PAS Project Management Support
  • 34. Key Risks Identified Achievability of project plan Approach to DtC Volume of consultation responses to analyse Lack of (or out-of- date) project plan Managing changes in personnel Time spent resolving objections Time pressures beyond the Local Plan Linkages between elements of plan production Assumptions around time needed for examination Challenges with governance and Member engagement
  • 35. • Scoping is a key stage to: • Inform Project Initiation Document and project plan • Identify key risks and how they can be managed • Value in undertaking this at outset of Local Plan and/or if there is a significant change in circumstances • Take a holistic approach to project scoping • Look beyond evidence base production to consider the Duty to Cooperate, Governance arrangements, Member engagement, consultation and engagement • Consider using Local Plan Route Mapper and Toolkit • Use outputs from scoping to secure corporate buy-in, articulate challenges and manage risks to plan-making Scope the Local Plan 1 Lessons Learnt
  • 36. Lessons Learnt • Importance of having a project plan! • Live document to actively manage Plan production: • Identify key milestones • Produce high level and detailed plans • Assess resources • To be a useful tool, it needs to be realistic: • Consider all facets of plan-making – not just evidence base – and other tasks (AMR etc) • Estimate time requirements for key tasks and map against team resources/available budget • Articulate interdependencies between different elements • Build in contingency time and expect the unexpected • Include governance and other lead-in times • Use it to help manage expectations and articulate priorities Use a Project Plan 2
  • 37. • Significant issue across many authorities we spoke to! • Be realistic and creative about approach to resourcing • Understand resourcing peaks in preparing the Plan e.g. in the lead-up to, and following consultation • Think about what roles really need a policy officer and where you can draw on wider planning or other expertise • Consider options to boost capacity • Prioritisation of tasks within policy team • Wider resources within the Council • Secondments • Neighbouring authorities and county councils – particularly for specialist resources • Potential to outsource resource intensive tasks Be Creative with Resources 3 Lessons Learnt
  • 38. • Don’t be afraid to challenge the norm and consider new ways of doing things • Key areas where this could reap significant benefits included: • Streamlining governance arrangements/lead-in times • Accelerating procurement timetable/required steps • Reducing the length and/or number of consultation periods (including updating the SCI) • Manage political pressures and expectations –using the PID/project plan/Route Mapper and Toolkit can help to evidence value of an alternative approach • Having a second opinion from a critical friend (including from PAS) can be valuable and support decision making around key risks, alternative approaches and opportunities to streamline workstreams Be Bold 4 Lessons Learnt
  • 39. Conclusion • Project management is become ever more important to delivery of sound Local Plans • Planning White Paper proposes a statutory 30- month timetable for preparing Local Plans • Benefits from having a strong project management system in place: • Drive the Local Plan forward within a context of resource constraints using an evidenced and bold approach, rigorously scoped out and planned • Facilitate the transition and adaptation required in the event of planning reform Looking to the Future
  • 41. local.gov.uk/pas Planning Reform - The ‘Known Unknowns’: Neighbourhood Plans Panel Q & A / Discussion
  • 42. local.gov.uk/pas Thank You & enjoy the rest of your day

Editor's Notes

  • #9: No two areas or plans are alike; an the review will depend in part on the stage of plan making This is your document and is meant to help – the draft report sets out recommended actions which can be agreed as an action plan, or recommendations Examples of recommendations could be very specific further work in relation to advisory development briefs or parameters plans is needed for plan viability “Appropriate Assessment needs to ensure in-combination effects consider the neighbouring authorities plans” “you’re reusing the SEA objectives from the scoping for the last local plan – you need evidence that stat consultees agree with this” To general: There is no narrative in relation to how the spatial strategy was arrived at
  • #10: Introducing the Assessment Matrix – ish The basics are not going to change… whatever shape a development plan takes you will have to be able to articulate objectives and spatial strategy AND how the spatial strategy follows from your social, physical and economic geography.
  • #11: Housing SHMNAs have changed somewhat as the standard method has bedded in Key thing SHMNA should do, and key to plan effectiveness, is segmentation as per NPPF 62 If you have policies seeking a mix of housing type and tenure you have to have something robust to hook it to.
  • #12: Strategic Allocations are key Some Local Plans go full-on with policy text listing 30 or more requirements; some list principles and cross reference to other policies In terms of evidence – you’ll have the fundamentals thought out – but consider the key impact issues – Chapter 8 of NPPF is your friend – not saying you don’t need any more evidence, but your justification is built-in. But a level of masterplanning is needed to ensure adequate services, density etc.
  • #13: Employment / economy Permitted Development (here to stay) means rethinking past ways of approaching employment evidence Proportionate is key here… unless you’re overarching objective is to focus on specific sectors general, light touch is probably OK. Let reps give you something to respond to and ask Ec Dev colleagues early on whats needed .
  • #14: Multiple reg 18s are becoming common; multiple reg 19s not unheard of
  • #15: Some very clear cases on greenebelt, but need substantiate the decision. SHLAA – our views – not just PPG – sutiability… but our view is focus on availability e developable deliverable NOT being passive on shlaa; placemaking should motivate you; political view: why asking for more vs why just taking what developers offer?
  • #16: Exams – particularly in your region
  • #17: Devo bill – Planning reform is dead! Long live Planning Reform
  • #36: Case study – Recommended scoping resources and evidence base documents in relation to key tasks such as Duty to Cooperate engagement to identify resource demands and realistic timescales, and inform procuring consultancy support
  • #37: Case study – Recommended producing a detailed plan programme for Regulation 19 Publication to predict timescales, allocate resources and coordinate workstreams in order to meet ambitious targets
  • #38: Case study – Recommended streamlining Local Plan production to achieve an ambitious timetable by: Identifying stages where the plan programme can be outsourced to consultants; Assigning Officers to complete workstreams in parallel such as processing Regulation 18 representations and progressing Duty to Cooperate discussions
  • #39: Case study – Recommended reducing timescales for plan production by holding 6 week Regulation 19 Publication, instead of 8 weeks used for Regulation 18 Consultation and evidencing this approach with a robust and detailed project plan